Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Mecon Limited vs M/S City Construction Corp. Durgapur ...
2025 Latest Caselaw 3551 Jhar

Citation : 2025 Latest Caselaw 3551 Jhar
Judgement Date : 28 March, 2025

Jharkhand High Court

M/S Mecon Limited vs M/S City Construction Corp. Durgapur ... on 28 March, 2025

Author: Sujit Narayan Prasad
Bench: Sujit Narayan Prasad
     IN THE HIGH COURT OF JHARKHAND AT RANCHI
                        -----

Arbitration Application No. 26 of 2023

------

M/s MECON Limited, having its head office at Vivekanand Path, P.O. & P.S-Doranda, Dist.- Ranchi, Jharkhand through its General Manager (Contracts & Legal), Shri Debabrata Acharya, Aged about 57 years, son of Late Tapan Kumar Acharya, resident of MECON Colony, Shyamali, P.O. & P.S. -Doranda, District - Ranchi, Jharkhand-834005. .... Petitioner Versus M/s City Construction Corp. Durgapur having its registered address at R.K. Pally, Main Gate, Durgapur, P.O. & P.S-Durgapur, District-Burdwan, West Bengal-

    713203.            ...     ....     ...                   Respondent
                             ---------

CORAM: HON'BLE MR. JUSTICE SUJIT NARAYAN PRASAD .....

For the Petitioner : Mr. Shresth Gautam, Advocate For the Respondent : Mr. Saptarshi Bhattacharjee, Adv.

[Through V.C.] Mr. Vibhor Mayank, Advocate .....

C.A.V. on 21/03/2025 Pronounced on 28/03/2025

Prayer:

1. The instant application has been filed by the

petitioner invoking the jurisdiction conferred under

Section 11(6) of the Arbitration and Conciliation Act,

1996 [hereinafter referred to as ‗Act, 1996'] for

appointment of arbitrator for resolution of dispute

between the parties.

-1- Arbitration Application No. 26 of 2023 Brief facts of the case:

2. Brief facts of the case, as per the pleadings made in

the application, which is required for adjudication of lis

reads as under:

3. The petitioner-MECON, is a ‗miniratna central public

sector enterprises of Govt. of India under the Ministry of

Steel' and is engaged in the business of consultancy and

execution of construction and industrial projects

throughout the country.

4. Tender bearing Tender Enquiry No. 11.51.027U/Civil

Works/Pkg. No. 001/008R dated 01.09.2021 was floated

by the petitioner inviting bids for execution of works

pertaining to ‗Civil Works for installation of 4th Stove in

Blast Furnace No. 4 of SAIL, Durgapur Steel Plant,

Durgapur'.

5. Pursuant thereto, the respondent applied the

aforesaid tender and after going through the tender

process emerged as L-1, as such was declared the

successful bidder. Accordingly, work order being Work

Order No. 11.51.027U/Civil Works/Pkg. No. 001/9807

dated 04.10.2021 was issued by the petitioner in favour

of respondent.

6. It is stated that in the ‗work order', it is clearly

stipulated that time is the essence of the contract,

therefore, the contractor-respondent was directed to

abide by the time schedule and execute the entire works

within a period of 08 (eight) months from the date of

issuance of ‗work order'.

7. After issuance of work order, the petitioner vide email

dated 06.10.2021 duly furnished the drawings to the

respondent-contractor in order to ensure that work be

executed in a timely and prompt manner.

8. It is stated that in spite of timely issuance of

drawings and other requisites instructions to the

respondent-contractor, the progress of the works was

very slow since inception. In that view of the matter, the

petitioner, vide e-mail dated 06.11.2021, duly intimated

the respondent-contractor to deploy adequate manpower

at the time and made a request to execute the work on

‗high priority jobs'.

9. The petitioner again vide email dated 09.11.2021

intimated the respondent-contractor that there have been

various failures on its end, which include non-

procurement of construction materials, non-procurement

of tools and tackles required to execute the work and

non-submission of labour license by the respondent.

10. Thereafter, the petitioner, vide email dated

15.11.2021 and 16.11.2021, send reminders and

requested to expedite the works but the respondent-

contractor did not meet the targets as agreed upon

between the parties.

11. In such circumstance, on 18.11.2021, the petitioner

issued a ‗Notice of Negligence' communicating that

delayed execution of works by the respondent is severely

jeopardizing the completion schedule but in spite of that

even after passage of 50 days no visible progress was

done in the work assigned to the respondent, which fact

was communicated to the respondent vide email dated

26.11.2021.

12. Consequently, a meeting was held on 26.11.2021 in

MECON Site Office, Durgapur between the parties

wherein revised dates for execution of works were

stipulated and agreed upon by the parties. But again, the

respondent failed to meet the revised timeline, which was

communicated to the respondent vide email dated

30.11.2021.

13. But instead of expediting the work, the respondent

withdrew manpower and machinery from the work site,

which the petitioner communicated to the respondent

vide letter dated 03.12.2021 stating that for such action,

the respondent shall be liable for suitable action as per

the provisions of work order.

14. But in spite of repeated requests and reminders by

the petitioner, the respondent did not execute the works

and virtually abandoned the work, which constrained the

petitioner to issue ‗Negligence & Risk Purchase Notice'

dated 04.12.2021 by which the respondent was

requested to immediately mobilize manpower and

machinery at the work site and initiate execution of civil

works and further if the respondent fails to discharge the

execute the work as per work order, the petitioner shall

left with no option but to complete the left work by a

third entity at the risk and cost of the respondent.

15. Accordingly, the petitioner carried out inspection of

work site and found that no manpower was deployed at

the side and no work was carried out by the respondent,

which was communicated by the MECON, Durgapur side

office to the petitioner vide email dated 06.12.2021.

16. In the meantime, the respondent vide letter dated

01.12.2021 communicated to the petitioner that work

fronts were purportedly not being made available to the

respondent and further claimed of escalation of item

rates, to which the petitioner replied vide email dated

10.12.2021 that the work order was fixed unit rate

contract having no provision for escalation and allegation

of the respondent with regard to the unavailability of

work site was also negated by the petitioner.

17. It is stated that seeing no improvement in the rate of

progress/execution of works by the respondent, the

petitioner terminated the work order vide letter dated

17.12.2021.

18. Upon issuance of the termination order, the

respondent was requested to return the reinforcement

bars taken from the stores along with all gate passes

issued to the workers of the respondents vide emails

dated 18.12.2021 and 29.12.2021.

19. Thereafter, the petitioner got the balance work under

the work order executed by a third entity at a total basic

price of Rs. 3,89,68,536/- as against the ‗Initial Total

Contract Price' of Rs. 3,07,80,708/- plus overhead.

20. Consequently, the petitioner vide letter dated

07.04.2022 raised its claim upon the respondent to the

tune of Rs.81,87,828/- but the respondent did not pay it

till date.

21. It has been stated that as per Clause 36.2 of the

work order since the dispute arose between the parties,

the petitioner vide letter dated 13.09.2022 requested the

respondent for conciliation of disputes that had accrued

between the parties, but the respondent failed to take any

action.

22. The petitioner herein, upon receiving no response

from the respondent side, issued a notice invoking

arbitration under clause 36.2.1 vide letter dated

16.06.2023 proposing panel of three names from which

the respondent was requested to nominate for

appointment of sole arbitrator for resolution of disputes

between the parties but the respondent did not take any

steps.

23. In the backdrop of aforesaid facts, the petitioner has

invoked the jurisdiction conferred under Section 11(6)

‗Act, 1996' for appointment of arbitrator for resolution of

dispute between the parties.

Submission advanced on behalf of petitioner:

24. Learned counsel for the petitioner has submitted that

in pursuance to ‗Notice Inviting Tender' [NIT], inviting

bids for execution of works pertaining to ‗Civil Works for

installation of 4th Stove in Blast Furnace No. 4 of SAIL,

Durgapur Steel Plant, Durgapur'. The respondent after

going through the tender process emerged as L-1, as

such was declared successful and accordingly work order

being Work Order No. 11.51.027U/Civil Works/Pkg. No.

001/9807 dated 04.10.2021 was issued by the petitioner

in favour of respondent.

25. Submission has been made that immediately after

issuance of work order, the petitioner vide email dated

06.10.2021 duly furnished the drawings to the

respondent-contractor in order to ensure that work be

executed in a timely and prompt manner.

26. Learned counsel for the petitioner has submitted that

the work order contains certain conditions particularly

the time period in which the entire work was to be

completed i.e., within a period of eight months from the

date of issuance of work order, as per clause 4.0

―Completion period‖ wherein it has specifically been

stated that ‗Entire works as detailed in the Technical

Specification shall be completed within 08 (eight) months

from the date of work order.' Further, as per Clause No.

36.0 in case of any dispute or difference in between the

parties on any provisions of the contract, there is

provision of invocation of arbitration clause.

27. It is case of the petitioner that since inception the

progress of the works was very slow, therefore, the

petitioner vide e-mail dated 06.11.2021 duly intimated

the respondent-contractor to deploy adequate manpower

at the time and made a request to execute the work on

‗high priority jobs'.

28. Further submission has been made that the

petitioner time and again, repeatedly sent several

reminder requesting the respondent-contractor to

expedite the works but the respondent-contractor did not

meet the targets as agreed upon between the parties.

Therefore, vide letter dated 18.11.2021, the petitioner

issued a ‗Notice of Negligence' communicating that

delayed execution of works by the respondent is severely

jeopardizing the completion schedule but in spite of that

even after passage of 50 days no visible progress was

done in the work assigned to the respondent. Thereafter,

a meeting was convened on 26.11.2021 in MECON Site

Office, Durgapur between the parties wherein revised

dates for execution of works were stipulated and agreed

by the parties. But again, the respondent failed to meet

the revised timeline, and instead of expediting the work,

the respondent withdrew manpower and machinery from

the work site.

29. It has further been submitted that in such

circumstance, the petitioner issued ‗Negligence & Risk

Purchase Notice' dated 04.12.2021 by which the

respondent was requested to immediately mobilize

manpower and machinery at the work site and initiate

execution of civil works and further if the respondent fails

to discharge the execute the work as per work order, the

petitioner shall left with no option but to complete the left

work by a third entity at the risk and cost of the

respondent.

30. Submission has been made the considering that fact

no improvement in the rate of progress/execution of

works by the respondent, the petitioner terminated the

work order vide letter dated 17.12.2021.

31. Thereafter, the petitioner got the balance work under

the work order executed by a third entity at a total basic

price of Rs. 3,89,68,536 as against the ‗Initial Total

Contract Price' of Rs. 3,07,80,708/- plus overhead.

Consequently, the petitioner vide letter dated 07.04.2022

raised its claim upon the respondent to the tune of

Rs.81,87,828/- but the respondent did not pay it till

date.

32. Submission has been made that in accordance with

the provisions of Clause 36.2.1, the petitioner vide letter

dated 13.09.2022 requested the respondent for

conciliation of the disputes but the respondent failed to

take any action, therefore, the petitioner issued notice

invoking arbitration clause 36.2.1 vide letter dated

16.06.2023 proposing panel of three names from which

the respondent was requested to nominate for

appointment of sole arbitrator for resolution of disputes

between the parties but the respondent did not take any

steps, therefore, the petitioner is before this Court under

the provisions of Section 11(6) ‗Act, 1996' for

appointment of arbitrator for resolution of dispute

between the parties.

Submission on behalf of respondent

33. Counter affidavit has been file on behalf of

respondent wherein the issue of maintainability of the

arbitration application has been raised besides raising

the issue on merit.

34. Mr. Saptarshi Bhattacherjee, learned counsel for the

respondent, who appeared through Virtual Mode, being

assisted by Mr. Vibhor Mayank, learned counsel for the

respondent, raising the issue of the maintainability of the

arbitration application, has submitted that the instant

application has been filed without following the due

procedure of law as the petitioner at no point of time has

followed the mechanism as prescribed under reference.

35. Further submission has been made that the work

order under reference, was never signed and accepted by

the respondent, as such there exists no agreement by the

parties to submit any dispute to arbitration which may

arise between them.

36. On the merit of the issue, submission has been made

that this Court has no jurisdiction to decide on any

purported issuance of drawings, deployment of man

power, mobilization thereof and/or any execution of

works, which emanated out of a purported work order

dated 04.10.2021 and further this Court has no

jurisdiction to hear any purported issue pertaining to

procurement of construction materials, non-procurement

of tools and tackles required to execute any purported

work or works with regard to test pile boring etc., as

alleged by the petitioner.

37. Therefore, submission has been made that purported

notice of negligence dated 18.11.2021 is bad in law and

is outside the purview of Arbitration.

38. Further submission has been made that failure to

adhere to timelines, progress of work, withdrawal of man

power, abandonment of work site is not amenable under

the provisions of Arbitration and Conciliation Act, 1996,

therefore, the purported ‗negligence and risk purchase

notice' dated 04.12.2021 is bad in law and outside the

purview of Act, 1996.

39. Learned counsel has submitted that absence of any

arbitration clause is evident from email communication

dated 04.10.2021 and 09.11.2021 issued by the

petitioner.

40. Further submission has been made that the alleged

‗termination order' dated 17.12.2021 is bad in law and

the consequential demand of additional cost of

Rs.81,87,828/- plus overhead is also not tenable in law.

41. At paragraph 8 of the counter affidavit, it has been

denied that the petitioner has approached the respondent

for any form of conciliation and it has been denied at

paragraph 9 that there exists any valid arbitration clause

between the parties.

42. Therefore, submission has been made that the

instant application is fit to be dismissed in limine.

Analysis

43. We have heard learned counsel for the parties, gone

through the material available on record and rival

submissions advanced on behalf of parties.

44. The fact, which is not in dispute is that a ‗Notice

Inviting Tender' [NIT], inviting bids for execution of works

pertaining to ‗Civil Works for installation of 4th Stove in

Blast Furnace No. 4 of SAIL, Durgapur Steel Plant,

Durgapur', was floated, upon which the respondent

participated in the tender process and after going

through the tender process emerged as L-1 tenderer, as

such was declared successful. Accordingly work order

being Work Order No. 11.51.027U/Civil Works/Pkg. No.

001/9807 dated 04.10.2021 was issued by the petitioner

in favour of respondent.

45. The work order contains certain conditions. Clause

1.0 under the caption ‗Scope of Work', it is specifically

stated that ‗Your scope of work shall be strictly as per

Technical Specification (enclosed as Annexure-I).'

46. Further 2.0 speaks about the contract price which

says that the contract price for the total scope of work

enumerated in this Work Order is indicated in the Price

Schedule (Annexure -II) and the contract price shall be

firm and not subject to any increase/decrease

whatsoever for impositions of any fresh taxes and cesses,

if any, or statutory variation/removal of any existing

taxes and cess etc. within the contractual period.

47. Clause 4.0 is under the caption ‗Completion period'.

Clause 4.1 emphatically says that Completion Schedule/

Time is one of the most important aspects of the work

order and Contractor shall complete the entire work as

per the scope of work detailed in the technical

specification. Further laying emphasis, it has been

stipulated therein that the ‗Entire works as detailed in

the Technical Specification shall be completed within 08

(eight) months. For ready reference, Clause 4 of the work

order is quoted as under:

4.0 COMPLETION PERIOD 4.1 Completion Schedule/ Time is one of the most important aspects of the work order and is firm & binding Contractor shall complete the entire work as per the scope of work detailed in the technical specification and clause 1.0 above in all respects as the following schedule: Entire works as detailed in the Technical Specification shall be completed within 08 (eight) months from the date of work order. 4.2 In order to achieve completion schedule as stated above, contractor shall submit to MECON within 2 (two) weeks from work order, a detailed work programme time schedule in the form of a Bar Chart/ PERT Network to complete the entire scope of work, for approval by MECON. The Contractor shall have to comply with PERT/Bar Chart, as approved by MECON, for completion of the entire work.

4.3 The delivery period as mentioned above shall be suitably extended if the Contractor is delayed or impeded in the performance of any of its obligations under this order by reasons of any of the following:

i) Delay in issue of drawings/documents by MECON/SAIL-

DSP/CET (Consultant) Delay in issue drawings/ documents to the contractor from the schedule as stipulated in the Technical Specification.

ii) Any occurrence of Force Majeure as provided in clause no. 35.0.

iⅲ) Any suspension order given by MECON under clause no. 22.0.

iv) Delay in handing over of front to carry out civil works as certified by site engineer.

The delivery period under the above condition shall be extended by such period as shall be fair and reasonable in all the circumstances and as shall fairly reflect the delay or impediment sustained by the contractor for the reasons attributable to MECON. Except where otherwise specifically provided in the order, the Contractor shall submit to MECON their claim for an extension of the delivery period together with particulars of the event or circumstances justifying such extension as soon as reasonably practicable after the commencement of such an event or circumstances. The Contractor shall at all times use its reasonable efforts to minimize any delay in the performance of its obligation under the order."

48. Clause 11.0 of the work order deals with ‗submission

of progress report, which says that the contractor shall

furnish progress report as 1st and 15th of every month

showing the progress of each activity. For ready

reference, clause 11 of the work order is quoted as under:

"11.0 SUBMISSION OF PROGRESS REPORT The CONTRACTOR shall furnish progress report as 1" & 15 of every month showing the progress of each activity as per the

bar chart agreed between MECON and CONTRACTOR. If requested by MECON, CONTRACTOR shall also furnish three (3) prints each to the MECON of progress photographs of the work done at Site.‖

49. Clause 15.1 of the work order speaks about

Inspection of the work, wherein it has been stated that

Construction/Contract work shall be inspected by

petitioner-MECON to ensure that the plans and

specification are being properly executed. The petitioner-

MECON shall have access and right to inspect the work

or any part thereof at any stage. If by the above

inspection, the petitioner rejects any work, the

Contractor shall make good such rejections either by

modifications or repairs as may be necessary, to the

entire satisfaction of petitioner-MECON. For ready

reference, the Clause 15.1 is quoted as under:

15.0 ACCEPTANCE 15.1 INSPECTION The Construction/ Contract work shall be inspected by MECON/SAIL-DSP/CET to ensure that the plans and specification are being properly executed. MECON/SAIL-

DSP/CET shall have access and right to inspect the work or any part thereof at any stage. If by the above inspection, MECON/ SAIL-DSP/CET reject any work, the Contractor shall make good such rejections either by modifications or repairs as may be necessary, to the entire satisfaction of MECON. Such repair modifications include re-execution of such of those works of other Contractor's and/ or agencies, which might have got damaged or affected by re-work done to the contractor's work. All supply items shall be inspected by MECON/SAIL-DSP CET, if required, before despatch to site. Contractor shall send

inspection call after readiness of materials along with copies of Internal Test report/ Test Certificates etc.

50. Clause 16 speaks about completion certificate, which

says that within 10 days of the completion of the entire

scope of work, the contractor shall give notice of such

completion to MECON and MECON shall inspect the

work and after satisfying itself with tests as required,

shall issue completion certificate to the contractor.

51. Clause 18 speaks about the responsibility for

performance of contract, which says that the Contractor

shall be responsible for the due and faithful performance

of the Work Order in all respects according to the intent

and meaning of the drawings, specifications and all other

documents referred to in this Work Order. For ready

reference clause 18.1 is quoted as under:

18.0 RESPONSIBILITY FOR PERFORMANCE OF CONTRACT 18.1The Contractor shall be responsible for the due and faithful performance of the Work Order in all respects according to the intent and meaning of the drawings, specifications and all other documents referred to in this Work Order. Any approval which MECON/SAIL-DSP/ CET may have given in respect of the order shall not bind MECON/SAIL DSP/ CET and notwithstanding any approval or acceptance given by MECON/SAIL DSP/CET. It shall be lawful for MECON to reject the work at site, if it is found that the materials used by the Contractor are not in conformity with the terms and conditions of the Work Order in all respects.

52. Further, the work order also contains an arbitration

clause under Clause 36. Clause 36.1.1 says that in the

event of any dispute or difference relating to

interpretation and application of the provisions of

Contract between the Contractor& MECON, such dispute

or difference shall be taken by either party for resolution

through Administrative Mechanism for Resolution of

CPSEs Disputes (AMRCD) as mentioned in DPE OM

no:4(1)/2013-DPE(GM)/FTS-1835 dated 22.05.2018.

Clause 36.2.1 says that any disputes, differences,

whatsoever, arising between the parties out of or relating

to the contraction meaning, scope, operation or effect of

this Order shall be settled between MECON and the

Contractor amicably. If, however, the MECON and the

Contractor are not able to resolve their disputes /

differences amicably as aforesaid, the said disputes /

differences shall be settled by Arbitration in accordance

with the Rules of Arbitration and the award made in

pursuance thereof shall be binding on the parties.

Conciliation shall be resorted to prior to invoking

Arbitration. For ready reference, Clause 36, the

Arbitration clause is quoted as under:

"36.0 ARBITRATION 36.1 For PSUs 36.1.1 In the event of any dispute or difference relating to interpretation and application of the provisions of Contract between the Contractor & MECON, such dispute or difference shall be taken by either party for resolution through Administrative Mechanism for Resolution of CPSEs Disputes (AMRCD) as mentioned in DPE OM no:4(1)/2013-DPE(GM)/FTS-

1835 dated 22.05.2018. The place of arbitration shall be New

Delhi and the language to be used in Arbitration proceeding shall be English.

36.1.2 During the pendency of the Arbitration proceedings both the parties shall continue to perform their contractual obligations, 36.2 For other than PSUs 36.2.1 Any disputes, differences, whatsoever, arising between the parties out of or relating to the contraction meaning, scope, operation or effect of this Order shall be settled between MECON and the Contractor amicably. If, however, the MECON and the Contractor are not able to resolve their disputes / differences amicably as aforesaid, the said disputes / differences shall be settled by Arbitration in accordance with the Rules of Arbitration and the award made in pursuance thereof shall be binding on the parties. Conciliation shall be resorted to prior to invoking Arbitration. Work under this Order shall be continued by the Contractor during the Arbitration proceedings unless otherwise directed in writing by MECON or unless matter is such that the work cannot possibly be continued until the decision of the arbitrator is obtained. 36.2.2 The arbitration shall be governed and regulated in all respect according to Laws of India.

36.2.3 The Arbitration proceedings shall be regulated and governed by Indian Arbitration and Conciliation Act 1996, or such modification thereof. The seat & venue of Arbitration proceeding shall be Ranchi.

36.2.4 This order including the Arbitration proceeding shall be governed by and interpreted in accordance with the laws of India and shall be subject to the exclusive jurisdiction of the courts of Ranchi."

53. It is evident from Clause 36 of the work order that it

provides for dispute redressal mechanism stating

specifically therein that the disputes / differences shall

be settled by Arbitration in accordance with the Rules of

Arbitration and the award made in pursuance thereof

shall be binding on the parties. Conciliation shall be

resorted to prior to invoking Arbitration.

54. As per pleading available on record, it is evident that

the respondent-contractor has accepted the work order

and started the contractual work but the work having not

been concluded as per the time schedule, and there was

no improvement in the rate of progress/execution of

works by the respondent, the petitioner-MECON

terminated the work order vide letter dated 17.12.2021.

Thereafter, the petitioner got the balance work under the

work order executed by a third entity at a total basic

price of Rs. 3,89,68,536/- as against the ‗Initial Total

Contract Price' of Rs. 3,07,80,708/- plus overhead.

Consequently, the petitioner vide letter dated 07.04.2022

raised its claim upon the respondent to the tune of

Rs.81,87,828/- but the respondent did not pay it till

date.

55. It is submitted that thereafter as per provisions of

Clause 36.2.1, the petitioner vide letter dated 13.09.2022

requested the respondent for conciliation of the disputes

but the respondent failed to take any action, therefore,

the respondent issued notice invoking arbitration clause

36.2.1 vide letter dated 16.06.2023 proposing panel of

three names from which the respondent was requested to

nominate for appointment of sole arbitrator for resolution

of disputes between the parties but the respondent did

not take any steps.

56. Hence, the present petition invoking the jurisdiction

of this Court conferred under Section 11(6) of the Act,

1996, for appointment of arbitrator for resolution of

dispute between the parties.

57. The respondent has raised the issue that the

condition stipulated in the work order cannot be

construed to be concluded contract, as such the

arbitration clause even if it is available therein as Clause

No. 36.0, cannot maintain the present application under

Section 11 (6) of the Arbitration and Conciliation Act,

1996 in absence of any formal contract between the

parties.

58. Argument on merit of the issue has also been made.

59. This Court needs to refer herein so far merit of the

case is concerned the same is not required to be taken

into consideration at this stage by this Court reason

being that this Court is exercising the power conferred

under Section 11(6) of the Act, 1996 wherein the

jurisdiction lies to the Court to appoint arbitrator only

and any other issues on merit is to be considered in

course of adjudication by the arbitrator, if appointed.

60. Herein, the issue has been raised that the work order

cannot be said to be concluded contract and as such the

instant application is not maintainable.

61. This Court, therefore, first is to consider the issue as

to:

"Whether the work order containing certain conditions

including arbitration clause can be said to be

concluded contract in a case where the work order

has been issued by the petitioner in terms of the

decision taken by the tender committee in pursuance

to the „Notice Inviting Tender‟ and the said work order

has been accepted by the respondent-contractor by

commencement of the work, as referred in the said

work order?"

62. This Court, in order to answer the issue, needs to

again go the factual aspect of the instant case.

63. The petitioner-MECON, for executing the work,

invited bids for execution of works pertaining to ‗Civil

Works for installation of 4th Stove in Blast Furnace No. 4

of SAIL, Durgapur Steel Plant, Durgapur', whereupon the

respondent-contractor offered his candidature and

participated in the tender process. The respondent-

contractor, after going through the tender process

emerged as L-1 tenderer, and as such was declared

successful. Accordingly work order being Work Order No.

11.51.027U/Civil Works/Pkg. No. 001/9807 dated

04.10.2021 was issued by the petitioner in favour of

respondent.

64. The said work order has been accepted by the

respondent since the respondent has commenced the

work in pursuance to the said work order. The said work

order contains certain conditions including the

arbitration clause at Clause No. 36 i.e., the dispute

redressal mechanism. Clause 36.2 of the work order

contains specific provision that in case of any dispute

between the parties, the same shall be referred to for

arbitration.

65. Further, Clause 36.2.1 of the work order speaks that

any disputes, differences, whatsoever, arising between

the parties shall be settled between parties amicably. If,

however, the parties are not able to resolve their

disputes/differences amicably as aforesaid, the said

disputes/differences shall be settled by Arbitration in

accordance with the Rules of Arbitration and the award

made in pursuance thereof shall be binding on the

parties. However, conciliation shall be resorted to prior to

invoking Arbitration.

66. Fact about commencement of work has not been

disputed by the respondent, since there is no averment to

that effect that work has not been commenced by the

respondent-contractor.

67. The question, therefore, would be that in such

circumstances where the work order issued by the

petitioner has not been disputed rather it is being

admitted as would appear from the conduct of the

respondent-contractor that the work has commenced in

pursuance to the said work order.

68. The moment the respondent has accepted the work

order by commencement of the work in pursuance to the

said work order dated 04.10.2021, according to the

considered view of this Court it is not available for the

respondent to take the ground that the same cannot be

treated in the nature of concluded contract reason being

that the document if being accepted it is to be accepted

by the party in entirety and not in piecemeal.

69. It is settled principle of law that there cannot be

‗approbate and reprobate' meaning thereby the part of

the document cannot be allowed to be accepted and part

thereof cannot be allowed to be refused. Reference in this

regard be made to the judgment rendered in the case of

R.N. Gosain vs. Yashpal Dhir reported in (1992) 4 SCC

683 wherein at paragraph 10 which reads hereunder:

"10. Law does not permit a person to both approbate and reprobate. This principle is based on the doctrine of

election which postulates that no party can accept and reject the same instrument and that "a person cannot say at one time that a transaction is valid and thereby obtain some advantage, to which he could only be entitled on the footing that it is valid, and then turn round and say it is void for the purpose of securing some other advantage". [See : Verschures Creameries Ltd. v. Hull and Netherlands Steamship Co. Ltd, Scrutton, L.J.] According to Halsbury‟s order (for example for the payment of costs) a party may be precluded from saying that it is invalid and asking to set it aside". (para 1508)"

70. In State of Punjab and Ors. vs. Krishan Niwas,

AIR 1997 Supreme Court 2349 the Hon'ble Apex Court

at paragraph-4 has laid down that once the employee has

accepted the correctness of the order and then acted

upon it, the same cannot be questioned by the concerned

71. It needs to refer herein that the Arbitration and

Conciliation Act, 1996 defines arbitration agreement. As

per Section 2(b) of the Act, 1996, the arbitration

agreement will be said to be agreement as referred in

Section 7 of the Act, 1996. Reference of Section 2(b) along

with Section 7 of the Act, 1996 needs to refer herein

which reads as under:

Section 2(b) "arbitration agreement" means an agreement referred to in section 7;

Section 7. Arbitration agreement.--(1) In this Part, "arbitration agreement" means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.

(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.

(3) An arbitration agreement shall be in writing. (4) An arbitration agreement is in writing if it is contained in--

(a) a document signed by the parties;

(b) an exchange of letters, telex, telegrams or other means of telecommunication [including communication through electronic means] which provide a record of the agreement; or

(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.

(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract.

72. It is evident from Section 7 of the Act, 1996 wherein

certain criteria have been given considering the same to

be an agreement within the meaning of Section 2(b) of the

Act, 1996. The ‗Arbitration Agreement' has been defined

under Chapter II of Section 7, which means an agreement

by the parties to submit to arbitration all or certain

disputes which have arisen or which may arise between

them in respect of a defined legal relationship, whether

contractual or not; meaning the agreement will be said to

be an agreement which if is in respect of legal

relationship, whether contractual or not.

73. Sub-section (2) of Section 7 thereof stipulated that

an arbitration agreement may be in the form of an

arbitration clause in a contract or in the form of a

separate agreement. Sub-Section (3) thereof provides that

an arbitration agreement shall be in writing. Sub-section

(4) thereof provides that an arbitration agreement is in

writing if it is contained in-- (a) a document signed by the

parties; (b) an exchange of letters, telex, telegrams or

other means of telecommunication [including

communication through electronic means] which provide

a record of the agreement; or (c) an exchange of

statements of claim and defence in which the existence of

the agreement is alleged by one party and not denied by

the other.

74. Sub-Section (5) of Section 7 stipulates that the

reference in a contract to a document containing an

arbitration clause constitutes an arbitration agreement if

the contract is in writing and the reference is such as to

make that arbitration clause part of the contract.

75. It is evident from perusal of Section 7 sub-section

4(b) along with the word ―legal relationship‖ as provided

under Section 7(1) that the legal relationship also

establishes by way of exchange of letters, telex, telegrams

or other means of telecommunication [including

communication through electronic means] which provide

a record of the agreement.

76. This Court, therefore, requires to consider what is

the meaning of word ‗legal relationship'

77. For that, this Court is again delving into the factual

aspect of the present case, from which it would be

evident that the work order is issued on the basis of the

decision taken by the tender committee which was

constituted in pursuance to the ‗Notice Inviting Tender',

in which the respondent was declared successful.

78. It is the respondent who has offered its candidature

for consideration so that the work order be allotted to

him, if he is found to be eligible in terms of the condition

of NIT. The respondent after going through the tender

process has emerged L-1 and has been declared

successful and thereafter the decision has been taken by

issuing the work order in favour of respondent. The

issuance of the work order, after being successful in the

tender process, will be said to have creation of legal

relationship between the petitioner-MECON and

respondent-contractor.

79. This Court is coming to such conclusion, that is of

relationship between the petitioner-MECON and

respondent-contractor is relationship, for the reason that

process of entering into the relationship will be legal one

when the work order has been issued in favour of the

respondent after conclusion of process of tender and

thereafter the respondent while accepting the terms and

conditions of the work order has commenced the

proposed work also.

80. The matter would have been different, if the

respondent would not have commenced the work in

pursuance to the work order and at the outright work

order was not accepted by the respondent but that is not

the fact herein and if that would have been the situation

then it could have been understood that no legal

relationship has ever existed between the parties.

81. But herein the fact is otherwise since the

respondents have accepted the work order meaning

thereby the work order has been accepted by the

respondent in entirety including the terms and conditions

stipulated therein, in particular clause 36.0 which is the

Arbitration Clause mentioned in the work order.

82. Section 7 sub-section 4(b) stipulates that an

arbitration agreement is in writing if it is contained in

exchange of letters, telex, telegrams or other means of

telecommunication [including communication through

electronic means] which provide a record of the

agreement if the same will be read along with the

definition of ‗legal relationship, the ground which has

been taken on behalf of respondent that the condition

stipulated having not been signed by the respondent will

not be said to be concluded contract, is having no force,

reason being that in case of exchange of letters the

bilateral relationship might be there but in a case of

telex, telegrams or other means of telecommunication,

which provide the record of agreement, there is no

requirement of signature of the other side, exactly the

case herein.

83. The moment the work order has been accepted by

commencement of work by the respondent it is not

available for the respondent to take the ground there is

no signature on the work order, hence, the agreement

cannot be said to be concluded agreement.

84. The moment the respondent has offered its

candidature for allotment of work order in pursuance to

Notice Inviting Tender and in furtherance thereto

decision has been taken on his application on

consideration by the petitioner after declaring the

respondent to be successful bidder and work order has

been issued thereafter then the same will in the same

transaction and it will be the contract in between the

petitioner and the respondent by virtue of issuance of

work order incorporating certain condition including

Clause No. 36 of arbitration.

85. The issue fell for consideration before the Hon'ble

Apex Court in the case of Govind Rubber Limited Vs.

Louis Drefus Commodities Asia Private Limited

[(2015) 13 SCC 477], wherein it has been held that a

commercial agreement has to be construed according to

sense and meaning as collected in a first place from the

terms used and understood in the plain, ordinary and

popular sense in order to effectuate the immediate

intention of the parties. An agreement even if not signed

by the parties can be spelt out from correspondence

exchanged between the parties. However, it is the duty of

the Court to construe correspondence with a view to

arrive at the conclusion whether there was any meeting

of mind between the parties which could create a binding

contract between them and further it has been held that

in order to constitute an agreement, it need not be signed

by all the parties. For ready reference, the relevant

paragraphs of the judgment are quoted as under:

"12. There may not be any dispute with regard to the settled proposition of law that an agreement even if not signed by the parties can be spelt out from correspondence exchanged between the parties. However, it is the duty of the court to construe correspondence with a view to arrive at the conclusion whether there was any meeting of mind between the parties which could create a binding contract between them. It is necessary for the court to find out from the correspondence as to whether the parties were ad idem to the terms of contract.

13. It is equally well settled that while construing an arbitration agreement or arbitration clause, the courts have to adopt a pragmatic and not a technical approach. In Rukmanibai Gupta v. Collector [(1980) 4 SCC 556] , this Court held that:

(SCC p. 560, para 6)

"6. Arbitration agreement is not required to be in any particular form. What is required to be ascertained is whether the parties have agreed that if disputes arise between them in respect of the subject-matter of contract such dispute shall be referred to arbitration, then such an arrangement would spell out an arbitration agreement."

14. So far as the first contention made by the learned counsel for the appellant that since the appellant did not sign the agreement, it cannot be said to be a party to the agreement, we would like to refer Section 7 of the Arbitration and Conciliation Act, which reads as under:

7.Arbitration agreement.--(1) In this Part, „arbitration agreement‟ means an agreement by the parties to submit to arbitration all or certain disputes which have arisen or which may arise between them in respect of a defined legal relationship, whether contractual or not.

(2) An arbitration agreement may be in the form of an arbitration clause in a contract or in the form of a separate agreement.

(3) An arbitration agreement shall be in writing. (4) An arbitration agreement is in writing if it is contained in--

(a) a document signed by the parties;

(b) an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement; or

(c) an exchange of statements of claim and defence in which the existence of the agreement is alleged by one party and not denied by the other.

(5) The reference in a contract to a document containing an arbitration clause constitutes an arbitration agreement if the contract is in writing and the reference is such as to make that arbitration clause part of the contract."

15. A perusal of the aforesaid provisions would show that in order to constitute an arbitration agreement, it need not be signed by all the parties. Section 7(3) of the Act provides that the arbitration agreement shall be in writing, which is a mandatory requirement. Section 7(4) states that the arbitration agreement shall be in writing, if it is a document signed by all the parties. But a perusal of clauses (b) and (c) of Section 7(4) would show that a written document which may not be signed by the parties even then it can be arbitration agreement. Section 7(4)(b) provides that an arbitration agreement can be culled out from an exchange of letters, telex, telegrams or other means of telecommunication which provide a record of the agreement.

16. On reading the provisions it can safely be concluded that an arbitration agreement even though in writing need not be signed by the parties if the record of agreement is provided by exchange of letters, telex, telegrams or other means of telecommunication. Section 7(4)(c) provides that there can be an arbitration agreement in the exchange of statements of claims and defence in which the existence of the agreement is alleged by one party and not denied by the other. If it can be prima facie shown that the parties are at ad idem, then the mere fact of one party not signing the agreement cannot absolve him from the liability under the agreement. In the present day of e-commerce, in cases of internet purchases, tele purchases, ticket booking on internet and in standard forms of contract, terms and conditions are agreed upon. In such agreements, if the identity of the parties is established, and there is a record of agreement it becomes an arbitration agreement if there is an arbitration clause showing ad idem between the parties. Therefore, signature is not a formal requirement under Section 7(4)(b) or 7(4)(c) or under Section 7(5) of the Act.

86. Therefore, this Court, taking into consideration the

discussion made hereinabove and law laid down by

Hon'ble Apex Court in the case of Govind Rubber

Limited Vs. Louis Drefus Commodities Asia Private

Limited (supra), is of the view that what has been

argued on behalf of respondent by taking the ground that

arbitration clause as contained in the work order cannot

be construed to be an agreement since it is not a

concluded one, is not sustainable for the reasons

aforesaid, accordingly the same is rejected.

87. The issue formulated by this Court on the basis of

pleading made by the parties is answered against the

respondent and it is hereby held that the work order

issued by the petitioner in favour of the respondent, who

had already commenced the proposed work based upon

the said work order, is concluded contract.

88. This Court, after having discussed the issue is in

detail, as hereinabove, is of the view that it is a case

where the application filed under Section 11 (6) of the

Act, 1996 is held to be maintainable.

89. Now, the second question which arises for

consideration is as to:

Whether the mechanism, as provided under Clause 36

of the work order has properly been followed before

taking recourse of provision of Section 11(6) of the Act,

1996 or not?

90. It is evident from clause 36.2.1 of the work order that

any disputes, differences, whatsoever, arising between

the parties out of or relating to the contraction meaning,

scope, operation or effect of this Order shall be settled

between MECON and the Contractor amicably. If,

however, the MECON and the Contractor are not able to

resolve their disputes / differences amicably as aforesaid,

the said disputes / differences shall be settled by

Arbitration in accordance with the Rules of Arbitration

and the award made in pursuance thereof shall be

binding on the parties. Conciliation shall be resorted to

prior to invoking Arbitration.

91. Clause 36.2 of the work order is specific that in case

of any dispute between the parties, the same shall be

referred to for arbitration.

92. This Court in the backdrop of aforesaid clause has

again delve into the factual aspect and found therefrom

that at clause 4.0, which speaks about completion

schedule/time, wherein it has specifically been

mentioned that Completion Schedule/ Time is one of the

most important aspects of the work order and further the

entire works as detailed in the Technical Specification

shall be completed within 08 (eight) months from the date

of work order.

93. But, as per pleading made in the writ petition, when

the respondent-contractor failed to expedite the progress

of the work in question and did not meet the targets, as

agreed upon between the parties, sent several reminder

letters and vide letter dated 18.11.2021 as also ‗Notice of

Negligence', as would be evident from Annexure 8 to the

instant application. Consequently, a joint meeting was

also convened on 26.11.2021 whereby revised dates for

execution of works were agreed upon by the parties, as

would be evident from minutes of meeting dated

26.11.2021, annexed a Annexure 10 to the instant

application.

94. It is the case of the petitioner that even thereafter,

the respondent did not adhere to the time schedule and

honor the commitment given by the respondent, as such

several request/warning letters were given for completion

of work, annexed as Annexure 12 to the application.

Thereafter, it is stated that inspection was done by the

petitioner of the site and it was found that no work is

being carried out by the respondent, as such the

petitioner terminated the work order, which was

communicated to the respondent vide letter of

termination order dated 17.12.2021 [Annexure 17 to the

instant application] and got the balance work executed by

a third entity third entity at a total basic price of Rs.

3,89,68,536 as against the ‗Initial Total Contract Price' of

Rs. 3,07,80,708/- plus overhead.

95. Consequently, the petitioner vide letter dated

07.04.2022 raised its claim upon the respondent to the

tune of Rs.81,87,828/- and a claim letter dated

07.04.2022 has been sent by the petitioner to the

respondent, as would be evident from Annexure 19 to the

instant application.

96. It appears that the petitioner vide letter dated

13.09.2022 requested the respondent contractor for

conciliation of the disputes that has accrued between the

parties as per Clause 36.2.1 of the work order but the

respondent did not act in furtherance of the notice for

conciliation issued under Clause 36.2.1 of the work order

and no communication has been received by the

respondent in this regard also.

97. The fact about making communication for the

purpose of resolution of dispute through conciliation has

not been disputed by the respondent in the counter

affidavit rather the issue of work order being not treated

as concluded agreement has mainly been raised, which

this Court has answered hereinabove.

98. It is settled position of law that the condition

stipulated in the work order/agreement is to be followed

by both the parties and in case of non-observance of the

conditions stipulated therein, which contains the

arbitration clause, the party aggrieved shall have the

right to take recourse of Arbitration and Conciliation Act,

1996.

99. This Court, therefore, is of the view the recourse as

available under Section 11(6) of the Arbitration and

Conciliation Act, 1996 has been taken after exhausting

the alternative dispute redressal mechanism i.e., the

process of conciliation, as available under Clause 362.1.

100. Accordingly, the question, as formulated by the

Court is answered.

101. This Court, from the discussions made

hereinabove, deems it fit and proper to exercise the power

conferred under Section 11(6) of the Act, 1996 and

requires to pass order accordingly.

102. Accordingly, the instant Arbitration Application

stands allowed.

103. However, for making suggestion of the name of

the arbitrator by the parties, the matter is posted on

28.03.2025.

104. List this case on 28.03.2025 under appropriate

heading.

(Sujit Narayan Prasad, J.)

Later on 28.03.2025

1. This Court in course of argument has sought

for name of the arbitrator by way of suggestion from the

parties, upon which both the parties have suggested the

name of Hon'ble Mr. Justice Amitav Kumar Gupta

(Retd.), High Court of Jharkhand to act as an Arbitrator.

2. Accordingly, this Arbitration Application stands

disposed of by appointing Hon'ble Mr. Justice Amitav

Kumar Gupta, Former Judge, High Court of Jharkhand,

Ranchi, as Arbitrator for resolution of dispute.

3. Needless to say that the parties will be at liberty to

raise all the legal issues for its consideration by the

learned Arbitrator, in accordance with law.

4. Learned Registrar General of this Court is directed to

send a copy of the entire records of this case along with

entire order sheet with this order to the learned

Arbitrator forthwith.

5. The instant arbitration application is allowed and

accordingly, disposed of.

(Sujit Narayan Prasad, J.)

Alankar / A.F.R.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter