Citation : 2024 Latest Caselaw 9863 Jhar
Judgement Date : 4 October, 2024
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P.(S) No.1170 of 2021
-------
Gopal Ram Rajak, aged about 63 years, S/o- Late Bechan Ram Rajak, Resident of Behind D.A.V Kapildev School, Upkar Nagar, Kadru, Ashok Nagar, P.O & P.S.- Argora, District- Ranchi. Jharkhand. ... Petitioner Versus
1. The State of Jharkhand.
2. The Secretary, Water Resources Department, Government of Jharkhand, Nepal House, Post Office & Police Station- Doranda, District- Ranchi, Jharkhand.
3. Under Secretary, Water Resources Department, Government of Jharkhand, having its office at Nepal House, P.O. & P.S. Doranda, District- Ranchi, Jharkhand.
4. Accountant General, Ranchi, Jharkhand, P.O & P.S.-
Doranda, District- Ranchi, Jharkhand.
.......Respondents
-------
CORAM : HON'BLE MR. JUSTICE DEEPAK ROSHAN
-------
For the Petitioner : Mr. Saurabh Shekhar, Adv. For the Respondents: Mr. Shashnak Shekhar, AC to AAG-V
-------
CAV ON:05.09.2024 Pronounced On:-04/10/2024
Heard learned counsel for the parties.
2. The instant writ application has been preferred
by the petitioner praying therein for quashing of the
order as contained in Memo No.5663 dated 31.12.2018
(Annexure-6), passed by the respondent no.3; whereby
order has been issued against this petitioner that 5% of
deduction will be done from the pensionable amount for
the period of 5 years.
3. Brief facts of the case as it appears from the
pleadings is that the petitioner has been working as
Executive Engineer in the Western Kosi Bank Division,
Kunauli, Birpur, of the River Kosi. During this time for
the period between 15.06.2002 to 15.10.2002, the flood
on the river Kosi was at its peak, and therefore, the flood
relief operations were being undertaken by the
Government. The Department was the responsible wing
of the Government. For this purposes, one M/s.
Sambhavi construction was engaged to perform flood
relief work. The work was completed however, the
payment could not be made for which the contractor
went before High Court, and on the directions of the
Hon'ble Court, one committee was constituted. The
committee came to a conclusion that payment to the
contractor is due, and therefore payment was released
in favor of the contractor.
4. In relation to this operation, the allegations
were framed against the petitioner, who at that point of
time was posted as Executive Engineer in the place of
incidents. The decision was taken to initiate
departmental proceedings against the petitioner. The
petitioner in the mean time had come to Jharkhand
after bifurcation of the Cadre in the year 2004. The
decision to initiate departmental proceeding was taken
by the Government of Jharkhand vide resolution dated
01.07.2009, and along with this resolution one
Prapatra- "KA" was also served upon the petitioner. The
allegations leveled against the petitioner in the Prapatra-
KA were two folds, which are as follows:-
(i) In the year 2002-03 for the purposes of flood relief work payment was made to M/s. Shambhavi construction and amount of Rs. 13.114 Lakhs was made to the contractor. For this unauthorized payment the petitioner is liable.
(ii) The petitioner delayed in forwarding form 24 proposals beyond 3 days, which is against the said norms and regulations of the Department. The form 24 proposal is a description of the work along with registration proposals, and due to the delay in forwarding the same the allegations were framed against the petitioner.
The petitioner submitted his reply dated
08/08/2009 denying the charges. The petitioner in his
reply stating that the allegation no. 1 is unfounded, as
because the payment was made on the basis of
judgment of Hon'ble Court and thereafter on the basis of
Departmental Committee Report.
Further, the enquiry was concluded and
enquiry report was submitted and in the Enquiry
Report, the petitioner was exonerated of charge no.1 but
however, in relation to charge no. 2 it was said that the
petitioner himself has admitted that he has delayed in
forwarding the form 24 proposals part 36, as is a norm
in the departmental procedure. Thereafter, the
respondent asked for reply to second show cause notice,
dated 19/11/2017 and with the second show cause
notice the copy of enquiry report was provided to the
petitioner.
It is the case of the petitioner that the Enquiry
Officer had already disclosed his mind that he is ready
to pass order of punishment against the petitioner in a
very mechanical manner. The conduct of respondents
has prejudicial to the petitioner, as it violates the basic
principle of natural justice.
The petitioner immediately preferred reply
dated 21/4/2017 to the second show cause, in which he
had stated that delay in submission of form 24 proposal
is not attributable to him; rather it was because of the
delay on part of Junior Engineer and Assistant
Engineer. The petitioner received form 24 proposal from
these authorities on 22.09.2002, and immediately he
forwarded the same to higher authority.
During the pendency of the Departmental
Proceedings, the petitioner retired on 31st August, 2017,
and therefore, on 10.11.2017 decision was taken by the
department to complete the regular departmental
proceedings initiated under Rule 55 of the Civil Services
(Classification Control and Appeal) Rules 1930 into a
proceeding under Rule 43B of the Pension Rule.
Thereafter the respondents passed the order of
punishment against the petitioner vide order dated
31.12.2018, under the provisions of 43B of Pension
Rule; whereby punishment of withholding of 5% of
pensionable amount for the period of 5 years was
imposed against the petitioner. Hence, this writ
application.
5. Mr. Saurabh Shekhar, learned counsel for the
petitioner assailing the impugned order made following
submissions:-
(i) The punishment has been imposed under
provision of Rule 43(b) of the pension Rule, however the
same is not in consonance with the said provision,
inasmuch as, 43(b) of the Pension Rules can be passed
only in relation to the allegation of pecuniary loss or in
case of grave misconduct and surprisingly; neither in the
order of punishment, there is any reference of pecuniary
loss to the State Government; nor there is any reference
to grave misconduct.
(ii) His next limb of the argument is that an error
has been committed in providing the second show cause
to the petitioner with an opinion and view that
punishment order is to be passed against him; which is
against the settled proposition of law.
(iii) His next limb of argument is that the
punishment is beyond the charge, inasmuch as, so far as
charge no.2 is concerned for which he has been
punished, there is a reference of fact that he has delayed
in forwarding Form 24 proposal part 36 as is the norm in
the departmental proceeding. However, as per the
charge-sheet it has been held that by delaying 3 days;
bad intent of the petitioner had surfaced i.e. "
गलत त ".
However, the punishment has been given for
negligence or indifference from work and for non-
following the official procedure. As aforesaid the charge
was only for bad intention in making delay in forwarding
the Form 24 as such the punishment has been given
beyond the charge.
(iv) The 4th limb of argument of the petitioner is
that as per 43(b) of Pension Rules, there has to be a
finding that the act of the petitioner has led to the
pecuniary loss to the Government. However, there is no
finding at all that what loss the Government has
incurred due to the act of the petitioner. Accordingly, the
impugned order deserves to be quashed and set aside
and the consequential benefit may be extended to the
petitioner.
6. Learned counsel for the respondents submits
that the payment to M/s. Sambhavi construction- the
contractor was only delayed due to this petitioner and for
the act of this petitioner, the respondent-authority has
incurred loss and the State was made to pay heavy
amount to the contractor. Had there been no delay on
the part of this petitioner, there would not have been any
loss of the State exchequer.
7. He further submits that there is no any
procedural irregularity and the order passed by the
disciplinary authority is in accordance with law and the
petitioner should be happy that it is only 5% of the
pension has been deducted only till 5 years though the
amount for which the State has incurred loss was much
and much higher.
8. Having heard learned counsel for the parties
and after going through the documents annexed with the
respective affidavits and the averments made therein, it
appears that the petitioner was exonerated from the
charge no.1, however in relation to charge no.2 it has
been said that the petitioner himself admitted that he
has delayed in forwarding the Form 24 proposal in part
36 as is a norm in the departmental proceeding.
9. One limb of argument of the learned counsel
for the petitioner is that as per Rule 43(b) of the Pension
Rules there has to be pecuniary loss to the Government
or any misconduct but there is no finding with regard to
loss incurred by the Government due to act of this
petitioner as it is an admitted fact that the petitioner was
responsible for delaying in forwarding Form 24 proposal
beyond 3 days.
From bare perusal of the impugned order there
is no any reference that the State has actually incurred
loss due to this delay of three days because admittedly
the other officers were also responsible for payment to
the contractor. As such on this score alone the impugned
order is fit to be quashed and set aside.
10. So far as the argument with regard to
punishment is beyond the charge is concerned; if
perused the charge no.2 which is at annexure-1 series, it
appears that the allegation against the petitioner with
respect to charge no.2 is that by not sending the Form
24 proposal within time was his bad intent. For brevity
charge no.2 is quoted herein below:-
"2. ल ग गत त गत ल ग त त त ग त -:
ग ग -
गलत त "
However, after going through the order of
punishment, it appears that in paragraph-7 there is a
finding of negligence or indifference in work in doing
official work and non-compliance of the official procedure.
So, there is no finding with regard to bad intent of this
petitioner and the punishment has been given for other
reasons i.e. with respect to indifference in doing official
work, negligence and non-compliance of the official
procedure; as such, the same is not sustainable in the
eye of law. The law is now well settled that the
punishment must be in accordance with charge, which is
absent in the instant case. Accordingly, on this ground
also, the impugned order dated 31.12.2018 is fit to be
quashed and set aside.
11. As a result, the instant writ application stands
allowed. The respondents are hereby directed to
calculate the arrear of pension, if the same has been
deducted, and pay the same within a period of 12 weeks
from the date of receipt/production of a copy of this
order.
12. Consequently, the instant writ application is
hereby allowed. Pending I.As., if any, is also closed.
(Deepak Roshan, J.)
Fahim/-
Jharkhand High Court, Ranch.
Dated:04/10/2024 AFR/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!