Citation : 2023 Latest Caselaw 3331 Jhar
Judgement Date : 4 September, 2023
IN THE HIGH COURT OF JHARKHAND AT RANCHI
W.P. (C) No. 831 of 2022
---------
Ramesh Dutt Pathak .... Petitioner.
Versus
1. The State of Jharkhand through the Principal Secretary, Govt. of Jharkhand,
Rural Works Department, Dhurwa, Ranchi.
2. The Chief Engineer, Rural Works Special Area, Dhurwa, Ranchi.
3. The Superintending Engineer, Rural Works Special Circle, Ranchi.
4. The Executive Engineer, Rural Works Special Division, Simdega.
..... Respondents
---------
CORAM: SRI SANJAYA KUMAR MISHRA, C.J.
SRI ANANDA SEN, J.
---------
For the Petitioner: M/s Naresh Pd. Singh and Arvind Kumar Singh, Advocates.
For the State: Mr. Rahul Saboo, GP-II and Saurav Mahto, AC to GP-II.
---------
10/Dated: 04.09.2023:
Upon hearing the learned counsel for the parties, this Court passed
the following, (Per, Ananda Sen, J.)
ORDER
In this petition, filed under Article 226 of the Constitution of India, the petitioner has prayed for a direction upon the respondents to issue an order to release payment in lieu of the additional works executed by the petitioner and also to allot an amount of Rs.8,53,989.87 as requested by respondent No. 4 through his letter No. 474 Simdega dated 29.6.2021 (Annexure-8) so that the said outstanding admitted balance amount can be paid to the petitioner as full and final payment for the Construction of Block-cum-Circle Office Building for Thetahi Tangar Block in Simdega District and the duly sanctioned additional works related thereto and to pay the cost of litigation.
2. Counsel for the petitioner submits that admittedly the construction work was awarded to the petitioner and the petitioner completed the same, but the respondents have not paid the balance amount of Rs.8,53,989.87 for the reasons best known, they have withheld the same. It is the case of the petitioner that the Executive Engineer, Rural Development, Special Division, Simdega vide letter No. 474 dated 29.6.2021 has admitted the fact that the petitioner has completed the work and he is entitled for the amount, thus the amount of Rs.8,53,989.87 be allocated so that the petitioner can be paid the dues. Counsel for the petitioner further contended that when there is clear admission on the part of the respondents, they cannot sit tight over the matter and deny the legitimate claim. Counsel for the petitioner also submitted that the respondents have admitted a part of the claim but they are taking a plea that the extra work, which was done was
without any written order of the higher authority, but in fact, the Executive Engineer has directed to undertake the extra construction work, which the respondent-State has also admitted.
3. The respondents appeared and filed their counter affidavit. In their counter affidavit they have admitted that the work for construction of Block-cum- C.O building was allotted to the petitioner after tender a proper process. The respondents have further admitted that as per the agreement, the construction value was Rs.3,26,54,703/- out of which, Rs.3,22,53,000/- was paid and an amount of Rs.4,01,703/- is still unpaid which the petitioner is entitled to receive. In the counter affidavit, it has further been mentioned that so far as the extra work is concerned, there is provision that until and unless written order is received from the Incharge Engineer, the amount will not be paid. As there is no written order of the Incharge Engineer, though the estimate was prepared by the Executive Engineer, but as the same was not sanctioned, the petitioner is not entitled to receive the amount for extra work, which the petitioner has undertaken. Counsel for the respondents lastly submits that as there is disputed question of fact, this writ petition is not maintainable.
4. After hearing the parties, we find the fact that the petitioner was awarded the job to construct the Block-cum-C.O building, Simdega, is not disputed. Execution of the agreement is also not disputed. The respondents have also admitted in paragraph-12 of the counter affidavit that out of the contract value, the petitioner is still entitled to receive Rs.4,01,703/-. During course of argument also, learned counsel for the State admitted that the aforesaid amount is payable and will be paid to the petitioner. Thus the dispute is only in respect of the value of extra work, which has been executed by the petitioner. The record of this case suggests that the petitioner has undertaken extra work. This fact has also not been denied by the respondents, but the plea which they have taken is that the higher authority i.e. the Engineer Incharge has not approved the estimate and the amount of extra work. From Annexure-8 to the writ petition, which is letter of the Executive Engineer, Rural Development, Special Division, Simdega written to the Chief Engineer, it is clear that the petitioner was directed to undertake the extra work for which, supplementary agreement No. 74F2/2020-21 dated 1.7.2020 was also executed. The Executive Engineer also wrote to the higher authority that on several occasions, allotment is being sought for, but the same has not been made.
5. From the aforesaid counter affidavit and the documents, it is clear that the respondents have denied the payment only on the ground that the Incharge, Engineer has not approved the extra work. The respondents have not denied the fact that the extra construction work has been undertaken by the petitioner,
execution of supplementary agreement for extra construction is also admitted. It is true that the Hon'ble Supreme Court in several judgments has held that in a contractual matter, the Court should not interfere exercising jurisdiction under Article 226 of the Constitution of India. When there is disputed question of fact, a petition under Article 226 of the Constitution of India should not be entertained. Further, it has been held in several judgments that in case where there is alternative remedies, the petition under Article 226 of the Constitution should not be resorted to.
It is needless to refer several judgment on the aforesaid line but the respondents have referred to and relied upon the judgment delivered in the case of State of Kerala and Ors. Vs. M.K. Jose reported in (2015) 9 SCC 433. It is normal proposition that in contractual matter, the Court would show reluctance in interfering in contractual matter, specially in monetary claim.
6. The Hon'ble Supreme Court in the case of Joshi Technologies International INC. Vs. Union of India and Ors. reported in (2015) 7 SCC 728 has observed that there is no absolute bar of the maintainability of the writ petition, even in contractual matter or where there is disputed question of fact or even when there is monetary claim. The discretion lies with the High Court, but normally the Court should not exercise the jurisdiction. In a very recent judgment, the Hon'ble Supreme Court after taking into consideration several previous judgments, in the case of M.P. Power Management Co. Ltd. Vs. Sky Power Southeast Solar India (P) Ltd., reported in (2023) 2 SCC 703 in paragraph 82.6 has held as under:
"82.6. Without intending to be exhaustive, it may include the relief of seeking payment of amounts due to the aggrieved party from the State. The State can, indeed, be called upon to honour its obligations of making payment, unless it be that there is a serious and genuine dispute raised relating to the liability of the State to make the payment. Such dispute, ordinarily, would include the contention that the aggrieved party has not fulfilled its obligations and the Court finds that such a contention by the State is not a mere ruse or a pretence."
Further in Paragraph 82.9, the Hon'ble Supreme Court has held as under:-
"82.9. The need to deal with disputed questions of fact, cannot be made a smokescreen to guillotine a genuine claim raised in a writ petition, when actually the resolution of a disputed question of fact is unnecessary to grant relief to a writ applicant."
7. Thus, from the aforesaid two paragraphs, it is quite clear that a writ petition is maintainable in money claim and proper relief can be granted where there is no disputed question of fact or whether the disputed question of fact has got no relation with the prayer so made, or the dispute raised is ornamental or superfluous.
8. Considering the aforesaid judgment, if we apply the facts of this case, we find that the Execution of the extra work is admitted. The execution of additional/supplementary agreement for extra work is also admitted. It is also admitted that some amount arising out of original agreement also remains to be paid. The respondents have only one ground for non-payment i.e. the extra work was not approved by the Incharge Engineer. This ground cannot be a ground to deny the payment to the petitioner for the work, which the petitioner has actually completed. More so when for undertaking the extra work a supplementary agreement was also executed. The ground taken by the State in not making the payment is frivolous. Thus, this is a fit case where jurisdiction under Article 226 of the Constitution of India can be exercised by giving direction to the respondents to pay the amount to the petitioner as admitted in paragraph 12 of the counter and also to pay for the extra work, which the petitioner has undertaken, as per the supplementary agreement, as assessed in Annexure-8 of this petition.
9. In that view, the respondents are directed to make payment as directed aforesaid, within sixty days from the date of receipt of a copy of this order, failing which, the amount will carry interest @ 6% per annum from the date of entitlement till the actual payment.
10. Accordingly, this writ petition stands allowed.
(Sanjaya Kumar Mishra, C.J.)
Anu/-Cp2 (Ananda Sen, J.)
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!