Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Hindustan Steel Works ... vs Bharat Construction Company
2023 Latest Caselaw 1172 Jhar

Citation : 2023 Latest Caselaw 1172 Jhar
Judgement Date : 17 March, 2023

Jharkhand High Court
M/S. Hindustan Steel Works ... vs Bharat Construction Company on 17 March, 2023
      IN THE HIGH COURT OF JHARKHAND AT RANCHI
                 (Commercial Appellate Jurisdiction)
             Commercial Appeal No. 15 of 2019
                            --------

M/s. Hindustan Steel Works Construction Limited & Ors.

... Appellants Versus Bharat Construction Company ...Respondent

CORAM: HON'BLE MR. JUSTICE SHREE CHANDRASHEKHAR HON'BLE MR. JUSTICE RATNAKER BHENGRA

For the Appellants : Mrs. J. Mazumdar, Advocate Mr. Parambir Singh Bajaj, Advocate For the Respondent : Mr. A. K. Das, Advocate

--------

Order No. 9/Dated: 17th March 2023

I.A No. 452 of 2021 This application has been filed under section 5 of the Limitation Act for condoning the delay of 65 days which initially occurred at the time of filing of the appeal labelled as First Appeal No. 352 of 2018 - appeal was filed on 7th September 2018.

It appears that the application under section 5 of the Limitation Act was filed on 21st January 2021.

In the application under section 5 of the Limitation Act, the appellant has stated as under:

"6. That it is humbly stated that for filing of the appeal permission had to be taken from the management.

7. That it is humbly stated that the file was moved in the office but since there was a reshuffling of the management so there was some delay in the filing of the said appeal.

8. That it is humbly stated that infact the new management who has taken over the charge of NBCC (India Ltd.) had to pursue the documents of the said case as it relates to company case and due to which there has been a delay in filing of the said appeal.

9. That it is humbly stated that due to the reshuffling of the management and matter relates to company case and the new management has taken opinion from their law department and this was also one of the reasons for the delay.

10. That it is humbly stated that infact the delay of 65 days is due to reshuffling of the management and it is a company matter and the company has to abide by its terms and could not file the said appeal in time.

11. That the appellants state that the council after drafting and finalizing the commercial appeal same was filed by 07.09.2018."

Mr. A. K. Das, the learned counsel for the sole respondent has submitted that delay beyond period of 60 days normally should not be condoned in the matters arising out of the 2 Commercial Appeal No. 15 of 2019

Commercial Courts Act, 2015.

The learned counsel for the respondent refers to the judgment in "Government of Maharashtra (Water Resources Department) Represented by Executive Engineer v. Borse Brothers Engineers and Contractors Private Limited" (2021) 6 SCC 460 to lay support to the aforesaid submission that I.A No. 452 of 2021 is liable to be dismissed.

In "Borse Brothers Engineers and Contractors Private Limited" the Hon'ble Supreme Court has held as under :

63. Given the aforesaid and the object of speedy disposal sought to be achieved both under the Arbitration Act and the Commercial Courts Act, for appeals filed under Section 37 of the Arbitration Act that are governed by Articles 116 and 117 of the Limitation Act or Section 13(1-A) of the Commercial Courts Act, a delay beyond 90 days, 30 days or 60 days, respectively, is to be condoned by way of exception and not by way of rule. In a fit case in which a party has otherwise acted bona fide and not in a negligent manner, a short delay beyond such period can, in the discretion of the court, be condoned, always bearing in mind that the other side of the picture is that the opposite party may have acquired both in equity and justice, what may now be lost by the first party's inaction, negligence or laches.

67. That apart, on the facts of this appeal, there is a long delay of 75 days beyond the period of 60 days provided by the Commercial Courts Act. Despite the fact that a certified copy of the District Court's judgment was obtained by the respondent on 27-4-2019, the appeal was filed only on 9-9-2019, the explanation for delay being:

"2. That, the certified copy of the order dated 1-4-2013 was received by the appellant on 27-4-2019. Thereafter the matter was placed before the CGM purchase MPPKVVCL for the compliance of the order. The same was then sent to the law officer, MPPKVVCL for opinion.

3. That after taking opinion for appeal, and approval of the authorities concerned, the officer-in-charge was appointed vide order dated 23-7-2019.

4. That, thereafter due to bulky records of the case and for procurement of the necessary documents some delay has been caused however, the appeal has been prepared and filed pursuant to the same and further delay.

5. That due to the aforesaid procedural approval and since the appellant is a public entity formed under the Energy Department of the State Government, the delay caused in filing the appeal is bona fide and which deserve[s] to be condoned."

It appears that in Commercial (Money Suit) Case No. 52 of 2008 the claim of the respondent has been allowed to the extent of Rs. 58,43,761/-. The appellant-company is a Central Government Undertaking which in the last few years has faced serious difficulties and turbulence in its working.

In view of "M. K. Prasad v. P. Arumugam (2001) 6 SCC 176 it is now well-settled proposition in law that while examining 3 Commercial Appeal No. 15 of 2019

the application under section 5 of the Limitation Act, the Court may look into the probable loss which may be caused to the aggrieved party and, therefore, delay occurred in filing the petition/appeal may be condoned by imposing appropriate cost.

Having regard to the aforesaid facts and circumstances in the case, we have formed a decision to grant an opportunity to the appellant to contest the matter on merits. Therefore, the delay occurred in preferring this commercial appeal needs to be condoned, by imposing cost of Rs.55000/- which shall be paid to the sole respondent within a period of four weeks.

I.A No. 452 of 2021 is allowed in the aforesaid terms. Commercial Appeal No. 15 of 2019 Post this matter on 20th April 2023 to be listed under the heading "Final Disposal".

Before the next date of hearing both parties shall file written submissions and produce compilation of judgments, if any.

(Shree Chandrashekhar, J.)

(Ratnaker Bhengra, J.) Amit/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter