Citation : 2023 Latest Caselaw 897 Jhar
Judgement Date : 24 February, 2023
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Arbitration Appeal No. 05 of 2017
M/s A. B. Singh ... ... Appellant
Versus
M/s Central Coalfields Limited ... ... Respondent
---
CORAM: HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY
---
For the Appellant : Mr. Attanu Banerjee, Advocate
: Mr. Satish Kumar, Advocate
For the Respondent : Mr. A. K. Das, Advocate
---
10/24.02.2023
1. Heard the learned counsel for the parties.
Arguments of the appellant
2. Learned counsel for the appellant has submitted that petition filed under Section 34 of the Arbitration and Conciliation Act was hopelessly barred by limitation and it was not accompanied by any petition for condonation of delay under Section 34(3) of the Act. The learned counsel submits that a petition under Section 14 of the Limitation Act was filed stating that the respondent was pursuing his remedy before the civil court at Ranchi, although the jurisdiction was before the court at Bokaro.
3. While giving the dates, the learned counsel submits that the award is dated 23.12.2006 and the petition for setting aside was filed on 12.03.2007. 3 months for filing the petition under section 34 was scheduled to expire on 24.03.2007. Therefore, it was initially filed within the period of limitation and upon counting the days only 12 days further was available to the respondent. The learned counsel has further submitted that the petition was held to be not maintainable at Ranchi vide order dated 15.12.2007 on account of lack of territorial jurisdiction. The respondent filed miscellaneous appeal before this Court in Misc. Appeal No. 77/2008 which was ultimately dismissed on 09.12.2009. Thereafter, the respondent filed a petition on 04.01.2010 under Order VII Rule 10(A) of C.P.C. to fix the date for return of plaint which was rejected on 16.01.2010 as not maintainable. The petition under section 34 was taken back and was filed before the competent court on 21.01.2010
and thereafter, a petition under Section 14 of the Limitation Act was filed. The learned counsel submits that admittedly, no petition under section 34(3) was filed.
4. The learned counsel submits that the petition under Section 14 does not properly explain the timeline to be excluded. However, he has submitted that two points are also required to be considered; firstly, there was no requirement to file a petition under Order VII Rule 10(A) for return of the plaint as there was already an order to take back the plaint and accordingly petition under Order VII Rule 10(A) was held to be not maintainable. Secondly, the time spent in connection with Section 14 of the Limitation Act was also required to be explained in the petition, which was not done. The learned counsel has also submitted that upon perusal of the order dated 15.12.2007 itself, it was mentioned that the plaint was being returned for presentation in proper court, but the respondent did not take the plaint and challenge the order before the appellate court. The learned counsel submits that the conduct of the respondent indicates that they had not pursued their matter in good faith.
5. The learned counsel has also referred to the order passed by the learned court below dealing with the petition filed under Section 14 of the Limitation Act and has submitted that the learned court below has not dealt with the timeline and has not specifically mentioned as to which period was to be excluded in terms of Section 14.
6. The learned counsel submits that thereafter, the learned court below passed the impugned order on merits on the point of jurisdiction of the learned arbitrator and while passing the impugned order, the learned court below has not even referred to the findings of learned Arbitrator or to hold that the findings of the learned arbitrator was hit by any of the permissible grounds for interference under section 34 of the Arbitration and Conciliation Act, 1996.
7. The learned counsel submits that the order passed by this Court under Section 11 (6) has interpreted the provision of clause 95 of the arbitration agreement. The learned counsel has also submitted that the impugned order is not in consonance with the provisions of Section 34(2) of the Act.
8. The learned counsel has also referred to Section 4 of the Arbitration and Conciliation Act, 1996 to submit that the respondent
having not raised certain points regarding the jurisdiction at the relevant point of time has waived his right to raise such points at a later stage. The learned counsel has submitted that provision of Section 4 is to be read with Section 16 of the Act, 1996.
9. The learned counsel has relied upon the judgments passed by the Hon'ble Supreme Court reported in (2020) 18 SCC 277 (Quippo Construction Equipment Limtied vs. Janardan Nirman Private Limited) and (2014) 11 SCC 366 paragraph 16 to 19.
Arguments of the respondent
10. Learned counsel for the respondent, on the other hand, has opposed the prayer of the appellant and has submitted that the petition under Section 14 of the Limitation Act was rightly entertained and considered by the learned court below and the delay was condoned by a separate order. The learned counsel while referring to the dates has submitted that it is not in dispute that the award was passed on 23.12.2006 and the petition for setting aside was filed on 12.03.2007. The learned counsel, from the records of this case, could not point out any date mentioned in any of the petitions filed before the learned court below by the respondent regarding the date of receiving the award and therefore, it is not in dispute that the limitation is to be counted immediately after 23.12.2006 i.e., the date of award. Admittedly, the timeline for filing petition under Section 34 i.e., three months was scheduled to expire on 24.03.2007 and just before 12 days of the expiry of the period, the petition under Section 34 was filed. It is further not in dispute that the plaint was to be returned in terms of order dated 15.12.2007 against which the respondent had moved before the appellant authority in the High Court and the appeal was also dismissed on 09.12.2009. The learned counsel submits that after the decision in the miscellaneous appeal passed by this Court, the respondent had applied for certified copy immediately and he could get the certificate copy of the order passed in the miscellaneous appeal only on 21.12.2009. Thereafter, a petition under Order VII Rule 10(2) (A) was filed on 04.01.2010 which was rejected as not maintainable on 16.01.2010. Thereafter, the respondent took back the plaint on 18.01.2010 and presented the same before the learned Sub-Judge, Tenughat on
21.01.2010. The learned counsel submits that the entire timeline stands fully explained and therefore, the petition under Section 14 was rightly allowed by the learned court below and if particular dates have not been mentioned in Section 14 application, the same is not fatal to the merit of the petition under Section 14 of the Limitation Act. The learned counsel has also submitted that since Section 14 application was sufficient for excluding the period of delay, therefore, no petition under Section 34(3) was required to be filed and consequently, no petition under Section 34(3) for condonation of delay was ever filed by the respondent before the learned court below.
11. On the merits of the case, the learned counsel for the respondent has submitted that the point of jurisdiction was raised before the learned Arbitrator by stating that the arbitration proceeding is not maintainable and is liable to be dismissed. He has also submitted that the said point was elaborated by the respondent before the learned Arbitrator in the oral arguments which has been recorded by the learned Arbitrator, but the learned Arbitrator has not considered the fact that the learned Arbitrator had no jurisdiction to act as an arbitrator in the case.
12. The learned counsel has further submitted that a plea was also raised before the learned Arbitrator that there was no work order issued to the appellant for the period in dispute and there was no agreement much less any arbitration agreement for the period involved in the present case. Further, the learned counsel submits that clause 95 of the terms and conditions of the agreement, which was relied upon by the learned counsel for the appellant, was also not an arbitration clause. This aspect of the matter has also not been considered by the learned Arbitrator.
13. The learned counsel submits that since the jurisdictional issue was involved, the learned court below has rightly held that the learned Arbitrator had no jurisdiction to enter into the reference.
14. During the course of arguments and from perusal of the award, it appears from paragraph (VI) dealing with analysis of the submissions of the parties, the learned Arbitrator has recorded that he had given his ruling that the arbitrator had full jurisdiction to arbitrate upon the present dispute and then the learned Arbitrator dwelled upon his ruling further and elaborate his view points and ultimately, held as follows: -
"In this case, the issue of jurisdiction was not raised in the counter statement of the respondent. Considering all these points, I reiterate my earlier ruling and do not find the submission of the learned respondent tenable".
15. The learned counsel has relied upon the judgment passed by the Hon'ble Supreme Court in the case reported in 2022 SCC Online SC 690 (Mahanadi Coalfields Ltd. and Another vs. IVRCL AMR Joint Venture) and has referred to paragraph 9 thereof to submit that the Hon'ble Supreme Court has elaborately dealt with the basic ingredients which are required to be present in an arbitration clause. The learned counsel submits that the Hon'ble Supreme Court has also held that mere use of the word "arbitration" or non-use of the word "arbitration" may not be material It is the intention of the parties which is to be seen while interpreting the arbitrating clause. The learned counsel has placed clause 95 of the arbitration agreement and has submitted that the said clause cannot be termed as an arbitration clause at all.
16. At this stage of the dictation of the order, it has been suddenly pointed out by the learned counsel for the appellant that against the order condoning delay, a writ petition being W.P. (C) No. 4760/2011 was filed and the said writ petition is pending before this Court. At this it has been reported by the learned court master that there is a batch of four writ petitions in which W.P. (C) No. 4760/2011 is one of them and all the writ petitions are of this bench as per roster.
17. In view of the aforesaid last submission, post this case for further hearing on 01.03.2023 along with batch cases of writ petitions being W.P. (C) No. 4735/2011; W.P. (C) No. 4738/2011; 4745/2011 and W.P. (C) No. 4760/2011.
(Anubha Rawat Choudhary, J.) Mukul
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!