Citation : 2023 Latest Caselaw 1567 Jhar
Judgement Date : 12 April, 2023
IN THE HIGH COURT OF JHARKHAND AT RANCHI
Arbitration Appeal No. 10 of 2008
M/s Bharat Coking Coal Limited having its Head Quarter at Koyla
Bhawan, P.O. Koyla Nagar, P.S. Saraidhela, District-Dhanbad
... ... Appellant
Versus
New Satnam Transport Company, a partnership firm with Sri Tirath
Singh, son of Sri Santokh Singh and Smt. Pritpal Kaur, wife of Sri
Gurupal Singh, as partners both residents of Katras Road, Matkuria,
P.O. P.S. and District-Dhanbad ... ... Respondent
---
CORAM: HON'BLE MRS. JUSTICE ANUBHA RAWAT CHOUDHARY
---
For the Appellant : Mr. Anoop Kr. Mehta, Advocate
: Mr. Manish Kumar, Advocate
For the Respondent : Mr. J.K. Pasari, Advocate
---
16/12.04.2023 Heard learned counsel for the parties.
2. This appeal is directed against the judgment dated 31.01.2008 (decree sealed and signed on 08.02.2008) passed by the learned Sub Judge VI, Dhanbad in Title (Arb.) Suit No. 31 of 1995 rejecting the objection filed under Section 30 of the Arbitration Act, 1940 for setting aside the Award dated 12.04.2006. The sole Arbitrator was appointed vide order dated 27.05.2005 in Title (Arbitration) Sut No. 31 of 1995 passed by the learned Sub-ordinate Judge VII th, Court, Dhanbad.
Foundational facts and background of the case.
3. The foundational facts are that by a Notice dated 08.06.1991 the Appellant ( hereinafter referred to as BCCL) invited persons willing to undertake the work of sand transportation in any mine in BCCL to do the job at the rate decided by BCCL bunker wise/source wise for various areas of BCCL including from different river Ghat/stock to Kustore (East/South) bunkers of Kustore Colliery under Kustore Area for the year 1991-92.
4. By Letter of Intent dated 22.07.1991, issued by BCCL, the rate was communicated to be rate of 88-89 plus 15% and the formal contract was awarded to the claimant by work order dated 10 th of October, 1991. It has been the specific case of the claimant that vide letter dated 06.11.1991, the claimant recorded his protest to the rate and kept the issue of rate fixation alive and while the work was going on, the claimant once again vide a letter dated 22nd January, 1992 communicated that the rate for the year 1991-92 was yet to be finalized which was causing financial hardship to him. Numerous letters right from 16th September, 1991 to 15th of
December, 1994 were issued by the claimant wherein the claimant repeatedly demanded the finalization of rate of sand transport.
5. So far as the BCCL is concerned, their specific case was that work order dated 10th of October, 1991 was binding. Clause-14 prohibited granting of any escalation on account of rate increase in the price of Diesel/POL/Tyres or any other items required for work or on account of increased rate/levies etc. during the contract period and therefore no arbitrable dispute could be raised by the contractor on account of the aforesaid heads. It was also raised that the work order provided that only such disputes as relatable to transportation of sand namely quantity, quality etc. were referable for arbitration.
6. When the dispute arose between the parties the claimant approached the Civil, Court, Dhanbad under Section 8 & 20 of the Arbitration Act, 1940 on the strength of clause-19 of the work order, BCCL opposed the same but the application of the claimant was allowed against which BCCL filed appeal. The appeal was dismissed which was challenged by BCCL before Hon'ble Supreme Court of India by filing SLP being SLP (Civil) No. 6592 of 1997 which was disposed of on contest on 05.02.1999. Order passed by the Hon'ble Supreme Court is quoted as under: -
"We have heard learned counsel for the parties. In our view, no case for our consideration survives in this Special Leave Petition against the order of reference to arbitration as number of disputes are raised by the respondent. Learned counsel for the petitioners vehemently placed for our consideration two submissions namely-
(i) Under Clause 14 of the agreement no escalation of the rate was payable on account of increase in prices of diesel/POL/Tyres or any other items required for the work or on account of increased statutory taxes/levies during the contract period: and
(ii) 15% escalation was already agreed and the respondent had accepted without any demur. Therefore, no arbitrable dispute survives.
Learned counsel for the respondent submitted that the claims put forward by the respondent include number of items apart from the item mentioned in Clause 14 of the Agreement and 15 per cent escalated amount which the respondent had received was subject to the contention raised by it in its representation against 15 per cent escalation. All these questions, in our view are required to be thrashed out before the Arbitrator and it cannot be said that all these disputes are therefore not arbitrable. It is obvious that it will be open to the petitioners to submit before the Arbitrator whether any of the
disputes is really arbitrable or not and whether the respondent was fully satisfied with the amount that it received. All these questions are left open. Subject to the aforesaid observations, the Special Leave Petition is disposed of."
7. On 23.04.1999 one Arbitrator was appointed who, vide award dated 24.03.2001, awarded a sum of Rs. 2,05,570/- with interest @ 8% thereon if not paid within four months. The awarded amount was paid by BCCL by cheque dated 10.07.2001 which was accepted and acknowledged by the claimant vide letter dated 23.07.2001. Initially On 22.06.2001, the objection was filed by the claimant under Section 34 of the Arbitration and Conciliation Act, 1996 and on 08.08.2001, the claimant contractor filed another objection under Section 30 and 33 of the Arbitration Act of 1940. BCCL contested the objection. The Civil Court, Dhanbad was pleased to set aside the award dated 24.03.2001 and directed appointment of new Arbitrator. The High Court upheld the order by Civil Court by judgment and order dated 19.11.2003. The BCCL filed Special Leave Petition on 25.02.2004 which too was dismissed by the Hon'ble Supreme Court. Consequently, fresh arbitration commenced leading to the award passed in the present case.
8. Before the learned Arbitrator, it was contended by BCCL that the rates of transportation given and relatable to the year 1989-90 and 1990-91 had nothing to do with the work order under consideration, as the work order under consideration was distinct and separate from those related to 1989-90 and 1990-91. It was contended that in the year 1988, tender for the sand transportation was invited for three years for the period 1988-89, 1989-90 and 1990-91, but the rates were finalized for the year 1988-1989 only. Since the rates for the remaining period could not be finalized, a separate agreement was entered into and the issue of payable rates for those two years namely 1989-90 and 1990-91 was referred to arbitration. In respect of the work order for the period 1991-92 i.e. the work order which was in dispute in the present arbitration proceedings, it was their case that while issuing the notice, the escalation element was duly considered by adding 15% over and above the rate of 1988-89 and the notice was given wide publicity out of which the contract between the parties was born. By accepting the Letter of Intent and continuing with the work thereafter, the claimant had accepted the counter offer by BCCL. BCCL also denied that
the revision of rates was ever assured to the claimant. It was also their case before the learned Arbitrator that unilateral and uncalled for correspondences by the claimant did not create any right or arbitrable dispute. BCCL further contended that admittedly the claimant had been paid for the work of sand transportation for the period 1991-92 at old rate of 1988-89 plus 15% escalation as per the condition of the notice and work order, hence the demand of the claimant of 60% enhancement of the rate for the base year 1988-89 was wholly misconceived. It was contended that the arbitrator being a creature of the agreement was not at liberty to travel beyond the conditions of agreement which included a bar on payment of escalation in view of the fixed rate, i.e. rate of 1988-89 plus 15%. However, BCCL did not raise any objection so far as computation was concerned.
9. The perusal of the award reveals that BCCL did not question the authenticity of the fact of receiving the letters/documents annexed with the statement of claim but kept their right to interpret the same at the time of hearing.
10. A supplementary claim was also made by the claimants for future interest and refund of earnest money and the total claim was for an amount of Rs. 1,66,37,137.37 and it was also brought on record that the claimant had already received an amount of Rs. 2,05,570.00 by cheque dated 10.07.2001.
11. The issues and the decision in terms of the award is as under: -
Issues framed Finding in the award 1) Whether the claim On the face of the record, the contents of the Statement of could forward by the
Claims in particular the claimant has included items apart claimant include the number of items apart from the items mentioned in Clause- 14 of the Agreement from the items (the work order dated 10th October, 1991).
mentioned in Clause-14 of the agreement.
2). Whether the items of On the face of the record, the items of claims forwarded by claims made by the the claimant are over and above the claim of 15% escalated claimant is over and above the claim of 15% amount which the claimant has already received.
escalated amount which the claimant has already received; 3). Whether the For the sake of convenience and the issues being allied to disputes raised by
each other, the issue Nos. 3, 4 and 6 has been dealt with the claimant in consideration of the analogously and following finding has been arrived at: contractual condition
are arbitrable; "On examination it is found that the Clause -14 is not a clause putting the items mentioned therein in the category of
4) Whether any of the EXCEPTED MATTERS. It is one thing to urge that the disputes as raised by the claimant for their claimant would not get any reimbursement of the escalated application U/S 20 amount on account of their being Clause- 14 in existence before the Court is really arbitrable or whereas it is a different thing to urge that the disputes not;
relating to the items mentioned in Clause -14 are not arbitrable. The Arbitration Clause being Clause- 19 is
5) Whether the claimant is fully absolutely free from any restriction and does not satisfied with the contemplate of any EXCEPTED MATTERS. I hold that all amount that it received;
the disputes raised by the claimants are arbitrable."
6) Whether in view With regard to issue no. 5 following findings has been of the inclusion recorded by the learned Arbitrator:
of Clause-14 in the work order "The claimant is not satisfied with the payment received for the related work, inclusive of 15% of escalation in respect of Diesel/POL/Tyre the claimant is entitled to get etc. is patent from the pleadings itself. The question is labour escalation, whether his accepting the payment of the final bill amounts POL escalation, material escalation to legal satisfaction closing the door on arbitration. and escalation in Beginning from the letter dated 22-7-1991, at least till 20-9- Government Taxes etc.
1994 the claimant had written innumerable letters putting on record that the rate for the year 1991-92 was yet to be finalized. The legal effect of such correspondences cannot be brushed aside as has been sought to be done by BCCL by espousing that the correspondences were uninvited and unwarranted and the rates for the year mentioned stood finalized once for all with the issuance of the work order dated 10-10-1991. The correspondences by the claimant might be uninvited yet BCCL was under 'duty to speak'. In a running contract in which the parties were actively involved and one of the parties was continuously writing about the purport and scope of the contract against the alleged understanding thereof by the other party, the latter was under an obligation to record the negative. Where there is a 'duty to speak', not to speak or to maintain silence amounts to consent.
Here, the silence of BCCL amounted to consent that the rates were to be finalized. Had BCCL something else in mind, it was always open to it to issue a STOP Work order or to assert that the rate of 1988-89 along with 15% escalation thereon was final for the year 1991-92. Hence, it is concluded that the claimant cannot be said to be legally satisfied with the amount received."
7) Whether the Money due to a person withheld by the holder without claimant is entitled to justified reason and without a contract to the contrary is of for the payment of the interest; if so, at what course refundable/reimbursable/payable with interest - this rate from which date?
is a basic tenet of the world of Commerce. Hence, the claimant is entitled to interest.
8) Whether the The claimant is entitled to extra rate claimed on account of claimant is entitled to route diversion made by the District Administration. The any extra rate claimed on account of alleged fact of Route diversion was also never denied or proved to route diversion said to the contrary by BCCL.
be made by the District Administration.
12. The following is the comparative table of the claimed amount and the awarded amount :-
Claimed Amount Awarded Amount (A) Claims for rate difference in respect of sand transportation from different River Ghat/Stock to Kustore (East)/(South) Bunker of Kustore Colliery under Kustore Area, BCCL for the period from 22-7-
1991 to 31-3-1992, the arithmetic of which is :
(i) in respect of Muraidih Ghat the work Against claim (A)(i) the amount of done was for Rs. 37,64,884.00, Increase in Rs. 6,08,028.76 only was Awarded.
percentage was 30% and the difference of amount/payable claim was Rs. 11,29,465.00
(ii) in respect of Kapasara/ Domarkunda Against claim (A)(ii) the amount of Ghat the work done was for Rs. Rs. 11,51,577.68 only was Awarded. 71,30,512.00, increase in percentage was 30% and the difference of amount/payable claim was Rs. 21,39,154.00
(iii) in respect of Bhowra Ghat the work Against claim (A)(iii) the amount of done was for Rs. 46,962.00, increase in Rs. 7584.36 only was Awarded. percentage was 30% and the difference of amount/payable claim was Rs. 14,087.00
(iv) in respect of Stock to Bunker the work done was for Rs. 2652.00, increase in Against claim (A)(iv) the amount of percentage was 40% and the difference of Rs. 428.29 only was Awarded. amount/payable claim was Rs. 1,061.00 (B) Additional rate payable/claim due to Since against the claim of Rs. 4,89,434.00 diversion of route by the District the claimant had received a sum of Rs.
Administration was 10% of Base rate plus 2,05,570.00 under Award of Sri S. escalation (Muraidihi/Barja Ghat). The Chattopadhyay dated 24-3-2001, the claim was to the tune of Rs. 4,89,434.00 learned Arbitrator held that there is no justifiable reason or evidence to justify the reopening of the claim. Hence, NIL Award was given.
(C) Interest @24% per annum from 1-4- The claimant was awarded simple interest 1992 to 31-5-1999 over money blocked @13% per annum computable from was claimed which amounted to Rs. 1-4-1992 till the date of actual satisfaction 64,89,904.00. of the Award i.e. till the date of actual payment on the sum of Rs. 17,67,619.00.
Supplementary claim no. (i) for further interest of Rs. 59,61,656.00 being interest @24% per annum for the period from 1-6-
1999 to 31-12-2005.
The interest @24% was claimed from the due date till realization of the claim or the date of decree, whichever is earlier.
(D) Expenses incurred in Court In the absence of any proof regarding proceedings up-to Hon'ble Supreme Court expenses in Court, the learned Arbitrator was claimed to the tune of Rs. 3,00,000.00 given NIL award. The claimant claimed further 24% per annum of Rs. 1,05,63,105.00 payable from respective due date till realization of claim or date of decree whichever is earlier.
Supplementary claim (ii) was made for The learned Arbitrator held that BCCL refund of Rs. 50,000.00 (Earnest money shall return the sum of Rs. 50,000.00 lying deposit) and Rs. 62,376.37 (security deposited with it on account of earnest deposit). money and Rs. 62,376.37 on account of security deposit without any interest.
13. BCCL filed objection to the award and primarily raised the ground that -
-the learned Arbitrator failed to appreciate that while accepting the counter offer rate of the Respondent of 15% rate escalation over the rate of 1988-89, by sending and uncalled for correspondences which did not create any right in favour of the claimant to get the rate escalation and such correspondences could not make the claim on a/c of rate escalation arbitrable dispute, for adjudication;
-The learned Arbitrator committed error of law in holding on the basis of letters of the claimant beginning from 22/7/91 till 20/9/94 that that the
rate of the year 1991-92 was not yet finalised and the legal effect of these letters cannot be brushed aside while holding that correspondences by the claimant might be uninvited yet respondent was under duty to speak against that without appreciating these letters do not form part of contract.
- the formerly appointed Arbitrator made the award for a sum of Rs. 2,05,570/- in favour of the Claimant and the claimant accepted the said award without any demour vide Cheque dated 17/07/01 and thereby the claimant was not entitled to any further amount out of the subsequent arbitration and in making the award under challenge learned Arbitrator committed legal misconduct; the learned Arbitrator committed legal conduct in interpreting clause of the work order 19 in isolation ignoring specific prohibitory clause 14 of the work order prohibiting any escalation of any nature under the contract.
-The award made by the learned Arbitrator is otherwise perverse and against the provisions of law out of jurisdictional error committed by the Ld. Arbitrator having gone beyond the contract.
-The interest allowed is highly excessive @13% per annum and that too with effect from 1992 against the provisions of interest Act.
-The contractual conditions does not provide for payment of interest and the learned Arbitrator should not have allowed the interest with effect from 1/4/92 when the learned Arbitrator has been appointed by the learned Court vide order dt.- 27/5/05 more so when the Respondent has accepted the payment of the awarded amount under the earlier award in respect of the constructing work without any protest in estopping the claimant from making any further claim in respect of the related work.
-The award is out and out perverse and from the fact of it is illegal and thereby fit to be set aside.
14. The learned court below refused to interfere with the award and made it the rule of the court by the impugned judgement. Submission on behalf of the appellant-BCCL
15. The learned counsel for the appellant has submitted that the impugned order by which the award passed by the learned Arbitrator under the provision of Arbitration Act, 1940 has been made the rule of the court, is under challenge. The learned counsel submits that the learned Arbitrator has travelled beyond the contract of the parties and had committed jurisdictional error while pronouncing the award.
16. He submits that it is not in dispute that the amount as per the rate as mentioned in the work order was already paid to the respondent i.e., the rate of the year 1988-89 plus 15% and the claim of the respondent was over and above the said rate which in turn was on the basis of certain communications issued by the respondent. Learned counsel has also submitted that under clause 14 of the work order, no escalation was payable. He submits that once the rate was fixed through the work order
which was never modified by any modification of contract between the parties, there was no scope for directing any additional payment over and above the rate which was fixed and paid by the appellant to the claimant. The learned counsel submits that mere silence on the part of the appellant to the communication issued by the respondent that the rate was not yet final, was not sufficient to grant any additional amount over and above the rate fixed on the basis of work order. He submits that even the learned Arbitrator did not record any finding that the rates stood modified. The learned Arbitrator only recorded that the silence of the appellant to the communication made by the claimant only amounted to the fact that the rates were not finalized. Learned counsel has further submitted that the awarded rate of interest is excessive. He submits that the learned Arbitrator has awarded interest @ 13% for the pre-reference period, pendente lite as well as future interest till payment.
17. The learned counsel has further referred to Section 29 of the Arbitration Act, 1940 to submit that it was the jurisdiction of the court concerned to award interest for the period post decree and therefore, the learned Arbitrator could not have awarded interest till payment. Submission on behalf of the claimant-respondent
18. Learned counsel for the claimant, on the other hand, has opposed the prayer of the appellant. He submits that this Court is exercising power under appellate jurisdiction to the order by which the award was made the rule of the court. The learned counsel submits that the scope of interference in the award is per se very restricted and is all the more constricted at the appellate stage. The learned counsel has relied upon a judgment passed by the Hon'ble Supreme Court in the case of M/s Ravindra Kumar Gupta & Company Vs. Union of India reported in (2010) 1 SCC 409. Learned counsel has further submitted that the scope of interference in the matter of arbitral award is very limited even under the 1940 Act. He has relied upon the judgment passed by the Hon'ble Supreme Court reported in (2003) 7 SCC 396 (State of U.P. Vs. Allied Constructions). He has further relied upon the judgment passed by Hon'ble Supreme Court reported in (2007) 9 SCC 503 (BOC India Ltd. Vs. Bhagwati Oxygen Ltd.) para 27 and 28 to submit that even when the Arbitrator has taken a plausible view, there is no scope for interference.
19. The learned counsel has vehemently submitted that interpretation of contract between the parties is in the exclusive jurisdiction of the learned Arbitrator and there is no scope for referring to the clauses of agreement between the parties and come to a different finding.
20. On the point of interest, the learned counsel for the respondent has relied upon judgment passed by Hon'ble Supreme Court reported in (2018) 9 SCC 266 (Reliance Cellulose Products Ltd. Vs. Oil and Natural Gas Corporation ltd.) (para 24) to submit that the Hon'ble Supreme Court has clearly held that the learned Arbitrator under the 1940 Act had the power to grant interest for all the three periods; pre reference, pendente lite and future interest. The learned counsel submits that the Arbitrator having granted interest at the flat rate of 13% for pre reference, pendente lite and future interest till payment has not committed any illegality. He has also submitted that the said judgment has also been relied upon and followed by this Court in Arbitration Appeal No.7 of 2003 vide judgment dated 01.11.2018, para 14 and 15 thereof.
21. The learned counsel for the claimant, on the merit of the case, has submitted that there was a clear communication from the side of the claimant that the rate which will be finalized for the period 1990-1991, would be the rate for the contract period of 1991-1992 involved in the present case. The learned counsel submits that the Arbitrator has considered the said communication and has awarded a lump sum award and there is no scope for entering into the mental process of the Arbitrator once the calculation of the amount for which the award has been granted, has not been mentioned in the award. He submits that the claim was much higher and the learned Arbitrator has reduced the amount substantially though has not given any calculation. During the course of the Arbitration, the learned counsel has also submitted that with regard to other contractors, the rate for the period 1989-1990 and 1990-1991 was revised and therefore, the claimant was also entitled to such revision. The learned counsel for the claimant has submitted that the claim was calculated on the basis of such award passed in relation to third parties. However, from perusal of the award, no specific reference of any such award has been mentioned. The learned counsel does not dispute that so far as the amount of the rate of 1988-89 plus 15% is concerned, the same was already paid to the claimant and the claim was over and above the rate of 1988-89 + 15 %.
Rejoinder argument on behalf of the appellant
22. In response, learned counsel for the appellant has referred to the judgment passed by Hon'ble Supreme Court reported in (2022) 3 SCC 739 (Atlanta Ltd. v. Union of India) [para 21 (h)] to submit that though there is limited scope in the matter of interpretation of contract as has been done by the learned Arbitrator, but still the award can be interfered with if it is found to be beyond the terms of the agreement. He submits that the rate is an important element of the agreement between the parties. Finding of this Court
23. Before proceedings to decide the case on merits, it is important to take into consideration the law laid down by the Hon'ble Supreme Court in the matter of interference with arbitral award under the Arbitration Act, 1940.
24. In the judgement passed in the case of B.V. Radha Krishna v. Sponge Iron India Ltd., reported in (1997) 4 SCC 693 the Hon'ble Supreme court has referred to earlier judgement passed in the case of "State of Rajasthan Vs. Puri Construction Co. Ltd." in para 11 and has referred to para 12, 26 to 28 of the judgement which are as follows: -
"On the scope and ambit of the power of interference by the court with an award made by an arbitrator in a valid reference to arbitration, various decisions have been made from time to time by Law Courts of India including this Court and also by the Privy Council and the English Courts. Both the parties have referred to such decisions in support of their respective contentions. The factual contentions of the respective parties are proposed to be scrutinised and then the facts are proposed to be tested within the conspectus of judicial decisions governing the issues involved."
"The arbitrator is the final arbiter for the dispute between the parties and it is not open to challenge the award on the ground that the arbitrator has drawn his own conclusion or has failed to appreciate the facts. In Sudarsan Trading Co. v. Govt. of Kerala it has been held by this Court that there is a distinction between disputes as to the jurisdiction of the arbitrator and the disputes as to in what way that jurisdiction should be exercised. There may be a conflict as to the power of the arbitrator to grant a particular remedy. One has to determine the distinction between an error within the jurisdiction and an error in excess of the jurisdiction. Court cannot substitute its own evaluation of the conclusion of law or fact to come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. (emphasis supplied) Whether a particular amount was liable to be paid is a decision within the competency of the arbitrator. By
purporting to construe the contract the court cannot take upon itself the burden of saying that this was contrary to the contract and as such beyond jurisdiction. If on a view taken of a contract, the decision of the arbitrator on certain amounts awarded is a possible view though perhaps not the only correct view, the award cannot be examined by the court. Where the reasons have been given by the arbitrator in making the award the court cannot examine the reasonableness of the reasons. If the parties have selected their own forum, the deciding forum must be conceded the power of appraisement of evidence. The arbitrator is the sole judge of the quality as well as the quantity of evidence and it will not be for the court to take upon itself the task of being a judge on the evidence before the arbitrator.
In Municipal Corpn. of Delhi v. Jagan Nath Ashok Kumar, it has been held by this Court that appraisement of evidence by the arbitrator is ordinarily never a matter which the court questions and considers. It may be possible that on the same evidence the court may arrive at a different conclusion than the one arrived at by the arbitrator but that by itself is no ground for setting aside the award. It has also been held in the said decision that it is difficult to give an exact definition of the word 'reasonable'. Reason varies in its conclusions according to the idiosyncrasies of the individual and the time and circumstances in which he thinks. In cases not covered by authority the verdict of a jury or the decision of a Judge sitting as a jury usually determines what is 'reasonable' in each particular case. The word reasonable has in law prima facie meaning of reasonable in regard to those circumstances of which the actor, called on to act reasonably knows or ought to know. An arbitrator acting as a Judge has to exercise a discretion informed by tradition, methodized by analogy, disciplined by system and subordinated to the primordial necessity of order in the social life. Therefore, where reasons germane and relevant for the arbitrator to hold in the manner he did, have been indicated, it cannot be said that the reasons are unreasonable.
In this case, claims before the arbitrators arise from the contract between the parties. It is well settled that if a question of law is referred to arbitrator and the arbitrator comes to a conclusion, it is not open to challenge the award on the ground that an alternative view of law is possible. In this connection, reference may be made to the decisions of this Court in Alopi Parshad and Sons Ltd. v. Union of India and Kapoor Nilokheri Coop. Dairy Farm Society. In Indian Oil Corpn. Ltd. v. Indian Carbon Ltd., this Court has held that the court does not sit in appeal over the award and review the reasons. The court can set aside the award only if it is apparent from the award that there is no evidence to support the conclusions or if the award is based upon any legal proposition which is erroneous."
25. In the case of "Hindustan Construction Co. Ltd. v. Governor of Orissa" reported in (1995) 3 SCC 8, the Hon'ble Supreme Court observed on the scope of interference by the Court as follows:
"... It is well known that the court while considering the question whether the award should be set aside, does not examine that question as an appellate court. While exercising the said power, the court cannot reappreciate all the materials on the record for the purpose of recording a finding whether in the facts and circumstances of a particular case the award in question could have been made. Such award can be set aside on any of the grounds specified in Section 30 of the Act...."
26. In the judgement passed by the Hon'ble Supreme Court in the case of Harish Chandra and Company v. State of Uttar Pradesh, (2016) 9 SCC 478, it has been clearly held that one cannot dispute the legal proposition that an award can be set aside only on the grounds specified in clauses (a), (b) and (c) of Section 30 of the 1940 Act and on no other grounds. It has also been held that the grounds such as inadequacy of reasons in support of an award, error committed by the arbitrator on facts, alternate and/or more plausible view could be taken than what is taken by the arbitrator, improper appreciation of evidence done by the arbitrator in recording any finding, etc. are not the grounds on which any award much less a reasoned award can be set aside. In other words, none of these grounds can be made the foundation for setting aside the award because they do not fall within the four corners of any of the three sub-clauses of Section 30 of the 1940 Act.
27. In BOC India Ltd. v. Bhagwati Oxygen Ltd., (2007) 9 SCC 503 dealing with regards to award governed by the provisions of Arbitration Act, 1940, it has been held that in the case of a reasoned award, the court can interfere if the award is based upon a proposition of law which is unsound in law and that the erroneous proposition of law must be established to have vitiated the decision. It has also been held that such error of law must appear from the award itself or from any document or note incorporated in it or appended to it and it was not permissible to travel and consider materials not incorporated or appended to the award.
28. In the judgement passed by the Hon'ble Supreme Court in the case of Atlanta Ltd. v. Union of India, (2022) 3 SCC 739, the scope of
interference in arbitral award under the Arbitration Act, 1940 has been summarized as under:-
" 17. The consistent view taken in several judicial pronouncements is that the Court does not sit in appeal over an award passed by an arbitrator and the only grounds on which it can be challenged are those that have been specified in Sections 30 and 33 of the Arbitration Act, namely, when there is an error on the face of the award or when the learned arbitrator has misconducted himself or the proceedings. In this context, we may usefully refer to Kwality Mfg. Corpn. v. Central Warehousing Corpn., where it has been observed as follows : (SCC pp. 146-47, para 10) "10. At the outset, it should be noted that the scope of interference by courts in regard to arbitral awards is limited. A court considering an application under Section 30 or 33 of the Act, does not sit in appeal over the findings and decision of the arbitrator. Nor can it reassess or reappreciate evidence or examine the sufficiency or otherwise of the evidence. The award of the arbitrator is final and the only grounds on which it can be challenged are those mentioned in Sections 30 and 33 of the Act. Therefore, on the contentions urged, the only question that arose for consideration before the High Court was, whether there was any error apparent on the face of the award and whether the arbitrator misconducted himself or the proceedings."
(emphasis supplied)
18. In Assam SEB v. Buildworth (P) Ltd., where the learned arbitrator has taken a particular view on the construction of the provisions of the contract, the Court had held as below : (SCC p. 154, para 13) "13. The arbitrator has taken the view that the provision for price escalation would not bind the claimant beyond the scheduled date of completion. This view of the arbitrator is based on a construction of the provisions of the contract, the correspondence between the parties and the conduct of the Board in allowing the completion of the contract even beyond the formal extended date of 6-9-1983 up to 31-1-1986. Matters relating to the construction of a contract lie within the province of the Arbitral Tribunal. Moreover, in the present case, the view which has been adopted by the arbitrator is based on evidentiary material which was relevant to the decision. There is no error apparent on the face of the record which could have warranted the interference of the court within the parameters available under the Arbitration Act, 1940. The arbitrator has neither misconducted himself in the proceedings nor is the award otherwise invalid." (emphasis supplied)
19. It is also a well-settled principle of law that challenge cannot be laid to the award only on the ground that the arbitrator has drawn his own conclusion or failed to appreciate the relevant facts. Nor can the Court substitute its own view on the conclusion of law or facts as against those drawn by the arbitrator, as if it is sitting in appeal. This aspect has been highlighted in State of Rajasthan v. Puri Construction Co. Ltd., where it has been observed thus : (SCC pp. 500-501, para 26) "26. The arbitrator is the final arbiter for the dispute between the parties and it is not open to challenge the award on the ground that the arbitrator has drawn his own conclusion or has failed to appreciate the facts. In Sudarsan Trading Co. v. State of Kerala it has been held by this Court that there is a distinction between disputes as to the jurisdiction of the arbitrator and the disputes as to in what way that jurisdiction should be exercised. There may be a conflict as to the power of the arbitrator to grant a particular remedy. One has to determine the distinction between an error within the jurisdiction and an error in excess of the jurisdiction.
Court cannot substitute its own evaluation of the conclusion of law or fact to come to the conclusion that the arbitrator had acted contrary to the bargain between the parties. Whether a particular amount was liable to be paid is a decision within the competency of the arbitrator. By purporting to construe the contract the court cannot take upon itself the burden of saying that this was contrary to the contract and as such beyond jurisdiction. If on a view taken of a contract, the decision of the arbitrator on certain amounts awarded is a possible view though perhaps not the only correct view, the award cannot be examined by the court. Where the reasons have been given by the arbitrator in making the award the court cannot examine the reasonableness of the reasons. If the parties have selected their own forum, the deciding forum must be conceded the power of appraisement of evidence. The arbitrator is the sole judge of the quality as well as the quantity of evidence and it will not be for the court to take upon itself the task of being a Judge on the evidence before the arbitrator." (emphasis in original and supplied)
20. As long as the arbitrator has taken a possible view, which may be a plausible view, simply because a different view from that taken in the award, is possible based on the same evidence, would also not be a ground to interfere in the award. In Arosan Enterprises Ltd. v. Union of India, this Court has held as follows : (SCC p. 475, para 36) "36. Be it noted that by reason of a long catena of cases, it is now a well- settled principle of law that reappraisal of evidence by the court is not permissible and as a matter of fact exercise of power by the court to reappraise the evidence is unknown to proceedings under Section 30 of the Arbitration Act. In the event of there being no reasons in the award, question of interference of the court would not arise at all. In the event, however, there are reasons, the interference would still be not available within the jurisdiction of the court unless of course, there exist a total perversity in the award or the judgment is based on a wrong proposition of law. In the event however two views are possible on a question of law as well, the court would not be justified in interfering with the award." (Also refer MCD v. Jagan Nath Ashok Kumar.)
21. In Rajasthan State Mines & Minerals, relied on by the respondent Union of India, on a conspectus of the case law relating to an award made under the Arbitration Act, 1940 and the scope of interference by courts in such an arbitral award, the legal position was summarised by the Court in the following words : (SCC pp. 309-11, para 44) "44. From the resume of the aforesaid decisions, it can be stated that:
(a) It is not open to the court to speculate, where no reasons are given by the arbitrator, as to what impelled the arbitrator to arrive at his conclusion.
(b) It is not open to the court to admit to probe the mental process by which the arbitrator has reached his conclusion where it is not disclosed by the terms of the award.
(c) If the arbitrator has committed a mere error of fact or law in reaching his conclusion on the disputed question submitted for his adjudication then the Court cannot interfere.
(d) If no specific question of law is referred, the decision of the arbitrator on that question is not final, however much it may be within his jurisdiction and indeed essential for him to decide the question incidentally. In a case where a specific question of law touching upon the jurisdiction of the arbitrator was referred for the decision of the arbitrator by the parties, then the finding of the arbitrator on the said question between the parties may be binding.
(e) In a case of a non-speaking award, the jurisdiction of the court is limited. The award can be set aside if the arbitrator acts beyond his jurisdiction.
(f) To find out whether the arbitrator has travelled beyond his
jurisdiction, it would be necessary to consider the agreement between the parties containing the arbitration clause. The arbitrator acting beyond his jurisdiction is a different ground from the error apparent on the face of the award.
(g) In order to determine whether the arbitrator has acted in excess of his jurisdiction what has to be seen is whether the claimant could raise a particular claim before the arbitrator. If there is a specific term in the contract or the law which does not permit or give the arbitrator the power to decide the dispute raised by the claimant or there is a specific bar in the contract to the raising of the particular claim then the award passed by the arbitrator in respect thereof would be in excess of jurisdiction.
(h) The award made by the arbitrator disregarding the terms of the reference or the arbitration agreement or the terms of the contract would be a jurisdictional error which requires ultimately to be decided by the Court. He cannot award an amount which is ruled out or prohibited by the terms of the agreement. Because of specific bar stipulated by the parties in the agreement, that claim could not be raised. Even if it is raised and referred to arbitration because of a wider arbitration clause such claim amount cannot be awarded as the agreement is binding between the parties and the arbitrator has to adjudicate as per the agreement.......... ...
(i) The arbitrator could not act arbitrarily, irrationally, capriciously or independently of the contract. A deliberate departure or conscious disregard of the contract not only manifests the disregard of his authority or misconduct on his part but it may tantamount to mala fide action.
(j) The arbitrator is not a conciliator and cannot ignore the law or misapply it in order to do what he thinks just and reasonable; the arbitrator is a tribunal selected by the parties to decide the disputes according to law."
22. In a recent ruling in NTPC, decided by a three-Judge Bench of this Court, drawing strength from the decision in Kwality Mfg. Corpn., it has been held thus : (NTPC case, SCC para 13) "13. From the above pronouncements, and from a catena of other judgments of this Court, it is clear that for the objector/appellant in order to succeed in their challenge against an arbitral award, they must show that the award of the arbitrator suffered from perversity or an error of law or that the arbitrator has otherwise misconducted himself. Merely showing that there is another reasonable interpretation or possible view on the basis of the material on the record is insufficient to allow for the interference by the Court (see State of U.P. v. Allied Constructions; Ravindra Kumar Gupta & Co. v. Union of India and Oswal Woollen Mills Ltd. v. Oswal Agro Mills Ltd.)." (emphasis supplied)"
29. Upon perusal of the impugned award, this Court finds that the learned Arbitrator has dealt with both the points which have been specifically referred to in the submissions made by the appellant in the earlier round of litigation in S.L.P. (Civil) No. 6592 of 1997 disposed of on 05.02.1999 and has returned findings by considering the materials on record. The learned Arbitrator, after considering materials on record, clearly recorded that all the disputes raised by the claimant were arbitrable. The learned Arbitrator also considered the point as to whether accepting the payment of final bill amounted to closing the door on arbitration and recorded a finding by considering the correspondences that the claimant
cannot be said to be legally satisfied with the amount received. The learned Arbitrator further held that the claimant was entitled to extra rate claimed on account of route diversion made by the district administration after having decided the jurisdictional issues/preliminary issues. In connection with the claim as raised by the claimant, the learned Arbitrator straightaway proceeded to pronounce the award and partly allowed the claim as mentioned in the chart above. The learned Arbitrator recorded that the claimant could be entitled to interest which is the basic tenet of the world of commerce and accordingly, awarded simple interest @13% per annum computed from 01.04.1992 till the date of actual satisfaction of the Award i.e. till the date of actual payment of sum of Rs. 17,67,619.00.
30. This court finds that it cannot be said that the award was based on an erroneous proposition of law appearing on the face of the award in order to vitiate the award. This court finds that the learned arbitrator has considered all aspects of the matter including the terms of the contract and all the materials on record and the statement of claim and has come to conclusions based on fact. This court finds that the learned arbitrator has acted within his jurisdiction while interpreting the contract and applying the same to the facts and circumstances of the case based on materials on record. The award cannot be said to be an award which is contrary to the contract entered into by the parties. It is also not the case of the appellant that the learned arbitrator has failed to consider material documents produced by the parties for arriving at a right decision. On the other hand, this court is of the considered view that the learned arbitrator has duly considered the statement of claim, the terms and conditions of the contract and the material documents produced by the parties, which were available on record, and came to the conclusions in favour of the claimant with regard to all the issues including the issue regarding interpretation of the clause 14 of the contract and also consequence of receipt of payment pursuant to the earlier award. The view taken by the learned arbitrator is certainly a plausible view on interpretation of contract and the transactions between the parties in the light of the materials placed before the learned arbitrator. The learned arbitrator has given lump sum award with regards to quantification of the claim under each head and partly allowed the claim.
31. On perusal of the impugned judgment, this court finds that the learned court below has exercised its powers within the contours of the
aforesaid legal proposition in the limited scope of intervention in an arbitral award while refusing to set aside the award and has committed no error in law calling for any interference in appellate jurisdiction of this court except on the point of interest, which will be considered later. This court finds that neither the learned arbitrator has committed any legal misconduct nor committed any factual or legal error apparent on the face of the record while recording the findings on jurisdictional issues or on the interpretation of contract as placed by the parties before the learned arbitrator. This court also finds that the learned court below has considered the stand taken by the appellant and did not find any substance in the objections raised by the appellant. The reasoning of the arbitrator cannot be said to be perverse to the extent that no man with ordinary prudence could take such view. None of the findings recorded in the award can be said to be against any provision of law or in contravention of any of the clauses of the agreement so as to constitute a case of legal misconduct on the part of the arbitrator within the meaning of Section 30 of the Act for setting aside an award.
On the point of interest
32. In the judgement passed by the Hon'ble Supreme Court in the case of Hindustan Construction Co. Ltd. v. State of J & K, (1992) 4 SCC 217, it has been held by referring to the earlier judgement passed by the Hon'ble Supreme Court in the case of Secretary, Irrigation Department, Govt. of Orissa v. G.C. Roy reported in (1992) 1 SCC 508 stating that though the said decision deals with the power of the arbitrator to award interest pendente lite, the principle of the decision makes it clear that the arbitrator is competent to award interest for the period commencing with the date of award to the date of decree or date of realization, whichever is earlier.
33. Again, in the judgement passed in Bhagawati Oxygen Ltd. v. Hindustan Copper Ltd., (2005) 6 SCC 462, it has been held as follows: -
"40. As to post-award interest, the point is covered by the decision of this Court in Hindustan Construction Co. Ltd. v. State of J&K. It was held there that an arbitrator is competent to award interest for the period from the date of the award to the date of decree or date of realisation, whichever is earlier."
34. In the case of Bhagawati Oxygen Ltd. v. Hindustan Copper Ltd., (2005) 6 SCC 462, the learned arbitrator had awarded interest at the universal rate of eighteen percent for all the three stages and the concerned
High Court had reduced the rate of interest @6%. The Hon'ble Supreme Court restored the rate of interest by observing that the rate could not be interfered with as it was based on the ground of loan so advanced by respondent to the appellant at that rate.
35. From the perusal of the award, it is apparent that the claimant had prayed for further interest @24% per annum on the total claim payable from respective due date till realization of claim or date of decree, whichever was earlier. However, the learned Arbitrator has passed award of simple interest @ 13% per annum payable from 01.04.1992 till the date of actual satisfaction of the Award i.e. till the actual payment. The learned Arbitrator has not restricted the payment of interest till the date of realization of the claim or till the date of decree, whichever was earlier. Consequently, the learned Arbitrator has awarded interest even for post decree period. The decree in the present case was signed on 08.02.2008. Although a point was argued before the learned court below that the interest allowed was highly excessive @13% with effect from 1992 but the learned court below has recorded that the learned Arbitrator has not caused any jurisdictional error in the award and that the interest allowed by the learned Arbitrator was also in accordance with law.
36. Section 29 of the Arbitration Act, 1940 clearly stipulates that in so far as an Award is for payment of money, the Court may in the decree, order interest from the date of decree at such rate as the court deems reasonable, to be paid on the principal sum as adjudged by the Award and confirmed by the decree. Section 29 of the Arbitration Act, 1940 is quoted as under:
"29. Interest on awards.- Where and in so far is an award is for the payment of money the Court may in the decree order interest, from the date of the decree at such rate as the Court deems reasonable, to be paid on the principal sum as adjudged by the award and confirmed by the decree."
37. In the judgement passed in the case of Hindustan Construction Co. Ltd. (Supra) and also in the case of Secretary, Irrigation Department, Govt. of Orissa v. G.C. Roy (Supra) followed in judgement passed in the case of Bhagwati Oxygen Ltd. (Supra), it has clearly been held that the Arbitrator is competent to award interest for the period from the date of Award to the date of decree or the date of realization, whichever is earlier. Even in judgement passed by this Court in Arbitration Appeal No. 7 of
2003 decided on 01.11.2018, a coordinate bench of this court has held that under Section 29 of 1940 Act, the Court has the discretion to award interest at a reasonable rate from the date of decree to be paid on the principal sum as adjudged by the Award and confirmed by the decree.
38. The award of learned Arbitrator, to the extent it awards interest till payment i.e. even for period beyond the date of decree, cannot be sustained in the eyes of law being perverse and contrary to the provisions of law and contrary to the aforesaid judicial pronouncements. The learned Arbitrator had no jurisdiction to award interest beyond the date of decree. This Court is of the considered view that the learned court below ought to have interfered with the award of interest by the learned arbitrator to the extent it related to period beyond the date of decree till realization. The judgement passed by the learned court below calls for interference to this extent. Accordingly, the Award of interest in the present case as awarded by the learned Arbitrator, is confined till the date of signing of the decree i.e. 08.02.2008.
39. There is no material on record to show as to what was the prevalent rate of interest at the time when the award was passed. Admittedly there is no contractual rate of interest. Accordingly, for the period from the date of decree till payment, rate of interest is reduced to 9% per annum on the awarded amount of Rs. 17,67,619.00.
40. This arbitration appeal is accordingly disposed of.
41. Office is directed to prepare a decree.
42. Let the Lower Court Records be immediately transmitted to the court concerned.
43. Pending interlocutory applications are closed.
44. Interim order stands vacated.
45. Let this judgement be immediately communicated to the court concerned through FAX/e-mail.
(Anubha Rawat Choudhary, J.) Saurav/Pankaj
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!