Wednesday, 20, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Aquatech vs The Jammu And Kashmir Sports Council & ...
2026 Latest Caselaw 21 J&K

Citation : 2026 Latest Caselaw 21 J&K
Judgement Date : 20 January, 2026

[Cites 0, Cited by 0]

Jammu & Kashmir High Court

M/S Aquatech vs The Jammu And Kashmir Sports Council & ... on 20 January, 2026

Author: Rahul Bharti
Bench: Rahul Bharti
 HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                 AT JAMMU

                             WP(C) No. 1781/2020

                                     Date of Pronouncement :       19.01.2026
                                                 Uploaded on :      20.01.2026


M/S Aquatech
                                                                   .....Petitioner

                        Through:   Mr. Rahul Pant, Sr. Advocate with
                                   Mr. Anirudh Sharma, Advocate

                  Vs

The Jammu and Kashmir Sports Council & Ors.
                                                                 .....Respondents



                       Through: Ms. Anshuja Tak, Advocate

CORAM:        HON'BLE MR. JUSTICE RAHUL BHARTI, JUDGE
                       JUDGMENT (ORAL)

01. The institution of this writ petition by the petitioner

acting through its partner-Gurmit Singh is with an en

objective to claim the writ reliefs as prayed for, which are

reproduced as under :-

"

I. Mandamus commanding the respondents to release the Earnest money in the shape of CDR No. 913040003156730(1547), dated 16th of January, 2013 for an amount of Rs. 3,80,000/- issued by the Axis Bank, Jalandhar dated 16th of January, 2013;

II. Mandamus commanding the respondents to release the two (2) Bank Guarantees bearing No. 01550100000243 dated 26th of February, 2013 for an amount of Rs. 8,89,447.50 and the Bank Guarantee bearing No. 01550100000246 dated 3rd of June, 2013 for the same amount issued by the Axis Bank, Jalandhar and

submitted by the petitioner as security deposit for the execution of the contract ;

III. Mandamus commanding the respondents to release the balance payment of Rs. 15,12,126/- as also the security deducted from the running account bills of the petitioner ;

IV. Mandamus commanding the respondents to release the due payments of the petitioner along with interest @ 12% from the date the payments became due to the petitioner and ;

V. Any other writ, order or direction which this Hon'ble Court may deem fit and proper in the facts and circumstances of the case, may also be granted in favour of the petitioner and against the respondents along with cost."

02. Upon the filing of the writ petition, this Court came to put

the respondents on notice in terms of an order dated

05.11.2020 inviting their reply/objections to the writ

petition. Despite repeated opportunities, reply eventually

came on record on 28.09.2022 filed on behalf of the

respondents No. 1 to 3 by Advocate Ms. Anshuja Tak.

03. The institution of the writ petition by the petitioner is

resting on a cause of action that NIT No. 37 of 2012-13

dated 02.01.2013 for the purpose of construction/up-

gradation/supply and installation of civil and electro-

mechanical works for the commission of existing

swimming pool at the M.A. Stadium of Jammu including

design proposals for complete job, testing and

commissioning at the estimated cost of Rs. 190.00 lacs

was responded to by the petitioner in which the petitioner

came to qualify the technical as well as financial bid

evaluation stage as being the lowest bidder and then

being called upon by the respondent No. 2-Executive

Engineer, J&K Sports Council, Construction Division,

Sports House, M.A. Stadium, Jammu of the respondent

No. 1-J&K Sports Council to furnish performance

guarantee to 10 % of the tender cost amounting to Rs.

17,78,895/- and also to mobilize resources for execution

of the contract for which Letter of Intent dated

20.02.2013 was issued without any corresponding formal

allotment order which later came to be issued on

07.03.2013 wherefrom completion period of four months

was to be reckoned.

04. The petitioner is said to have deposited an amount of Rs.

3,80,000/- as earnest money along with furnishing of

bank guarantee amount equivalent to the 5% of the

contract value.

05. Despite all handicaps which are said to have been

created from the end of the respondents related to

execution of the contract work, the petitioner is said to

have carried out the execution as per the drawings

submitted by it notwithstanding absence of approval to

the said drawings coming from the respondents' end.

06. The petitioner, as per the averments made in the writ

petition, is said to have completed first stage of the

contract work which was approximately 35% of the total

civil work on the basis whereof the petitioner generated a

running account bill for Rs. 52,09,697.50, in response

whereto nothing was heard or responded to from the end

of the respondents despite reminders one after another

submitted by the petitioner.

07. Instead, it is submitted that the petitioner was subjected

to a threatening posture from the end of the respondents,

who initially issued communications and ultimately

proceeded to issue a final notice dated 20.07.2013,

calling upon the petitioner to resume the work and

complete the same without any further delay

08. The petitioner from its end is said to have responded to

the said final notice by its reply dated 29.07.2013 with

the situation resulting in termination of the petitioner's

contractual engagement by issuance of letter dated

30.07.2013 issued by the respondent No. 1.

09. The petitioner is said to have approached this Court with

a writ petition OWP No. 1191/2013 during the pendency

of which a mutual agreement was arrived at for

resumption of the work which facilitated disposal of the

writ petition vide an order dated 29.11.2013 leading

resumption of work w.e.f 04.12.2013 by the petitioner

and concluding the work by 31.03.2014 against which

the petitioner is said to have received Rs. 1,62,76,824/-

leaving Rs. 15,12,126/- as unreleased payment along

with earnest money deposit of the petitioner and

performance guarantee of an amount of Rs. 8,89,447.50.

The last payment released in favour of the petitioner is

said to be on 23.03.2018 for Rs. 7,01,795/-.

10. The petitioner's grievance emanates that despite having

earned Work Completion Certificate dated 11.03.2016

issued by the respondent No. 2, the petitioner is being

subjected to suffer loss of his earnest money, bank

guarantee money thereby constraining it to come forward

with the present writ petition.

11. The respondents in their reply have come forward

admitting that the work has been completed by the

petitioner on 14.02.2018 but release of CDR for Rs.

3,80,000/- could not be effected because of being

misplaced whereas the balance payment for the amount

of work done by the petitioner was also in the process of

release due to some procedural requirements getting

delayed whereas two bank guarantees amounting to Rs.

8,89,447.50 each are said to have been forfeited even

prior to the filing of OWP No. 1191/2013.

12. Given the limited nature of the controversy remaining in

view of the admission made by the respondents that CDR

is intended to be released in favour of the petitioner and

the balance work payment also made to the petitioner,

the only controversy relates to the two bank guarantees

said to have been forfeited even prior to the institution of

the writ petition OWP No. 1191/2013.

13. Once the petitioner is said to have carried out the

completion of the contract work then whether the

respondent No. 1 was still entitled to forfeit the said two

guarantees is an issue on which the respondent No. 1

ought to have first afforded an opportunity of hearing to

the petitioner seeking its response and then pass a

reasoned order as to how come in the face of carrying out

the project to its completion, the petitioner was still to

suffer loss of two bank guarantees.

14. Accordingly, this writ petition is disposed of with a

direction relatable to the grievance of the petitioner with

respect to the two bank guarantees. The respondent No.

1 is directed to consider the matter afresh relatable to the

said two bank guarantees of the petitioner in the light of

the completion of the contract work by the petitioner.

15. The petitioner is directed to approach the respondent No.

1 with a detailed representation and upon making of

which the respondent No. 1 to take a final decision within

a period of three months. In case, the petitioner would

still be left aggrieved then the disposal of the writ petition

not to prejudice the right of the petitioner to come up

with a fresh writ petition.

16. The detailed order is following the order dated

28.02.2023 vide which the writ petition was ordered to be

disposed of as is hereby being done.

(RAHUL BHARTI) JUDGE JAMMU 19.01.2026 SUNIL Whether the order is speaking ? : Yes/No Whether the order is reportable ? : Yes/No

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter