Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chief Engineer Pmgsy Jkrrda vs M/S C&Z Associates (Joint Ventures)
2025 Latest Caselaw 149 J&K

Citation : 2025 Latest Caselaw 149 J&K
Judgement Date : 16 May, 2025

Jammu & Kashmir High Court

The Chief Engineer Pmgsy Jkrrda vs M/S C&Z Associates (Joint Ventures) on 16 May, 2025

Author: Rajnesh Oswal
Bench: Rajnesh Oswal
      HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                       AT JAMMU
                  (Through Virtual Mode)

                                                  Reserved on: 28.04.2025
                                                Pronounced on: 16.05.2025
CJ Court

                             LPA No. 73/2025
                           [WP(C) No. 3169/2019]

The Chief Engineer PMGSY JKRRDA               ...Petitioner(s)/Appellant(s)
Jammu and others
                 Through: Mr. Ravinder Gupta, AAG

                                  v/s
M/s C&Z Associates (Joint Ventures)                        .... Respondent(s)
through its partner Ashwani Thakur.
                    Through:    Mr. Rahul Sharma, Advocate


CORAM: HON'BLE THE CHIEF JUSTICE
       HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE.
                                JUDGMENT

1. The respondent-firm was allotted the contract for construction of

balance work of road from Khaog to Batodi, and it executed the work

to the satisfaction of the appellants and even the completion certificate

was also issued in its favour. During execution of the contract, the

respondent did additional work by way of Slip Clearance in the years

2013, 2014 and 2015 amounting to Rs. 45.96 lacs in total, regarding

which various inter se communications were made by officials of the

appellant-Department to arrange the funds against the additional work

done by the respondent in the years 2013, 2014 and 2015. The

respondent has placed on record the communications dated

30.10.2013 and 25.01.2017 to demonstrate that the funds were sought

by the officials of the appellants to clear the liability of the

respondent. When the said liability was not cleared by the appellants,

the respondent filed a writ petition for directing the appellants to

release the payment of Rs. 45.96 lacs in its favour against the admitted

work done liability by way of Slip Clearance in the years 2013, 2014

and 2015.

2. Appellants objected to the claim of the respondent by submitting that

in absence of work order, technical sanction, administrative approval

and also availability of the funds, the claim of the respondent cannot

be considered and even no tender has been issued for the additional

work allegedly executed by the respondent.

3. The learned Writ Court vide judgment dated 26.11.2024 allowed the

writ petition filed by the respondent and directed the appellants to pay

Rs. 45.96 lacs to respondent within a period of six weeks from receipt

of copy of the order.

4. Appellants have impugned the judgment dated 26.11.2024 through

this intra-court appeal on similar grounds, as were raised by them

while objecting to the writ petition like absence of work order,

technical sanction and administrative approval, and non-availability of

the funds, etc. Though the issue of delay has been raised in this appeal

but the same was never urged by the appellants before the learned writ

court, as such the same cannot be considered in the appeal.

5. Mr. Ravinder Gupta, learned A.A.G, has argued that in absence of

administrative approval and tendering process, no liability can be

fastened upon the appellants in respect of work executed by the

respondent.

6. Per contra, Mr. Rahul Sharma, learned counsel for the respondent has

argued that there is admission on the part of the appellants in respect

of execution of additional work by the respondent, which is duly

substantiated by the communications placed on record by the

respondent, whereby the funds were sought by the officials of the

appellants for release of the admitted liability of the respondent.

7. Heard learned counsel for the parties and perused the record.

8. Appellants have not denied the execution of work by the respondent.

The only ground on which the claim the respondent is being objected

to by the appellants is that the respondent has executed the work

without any approval/sanction of the competent authority and in

absence of tendering process.

9. This is an admitted fact that the respondent was allotted construction

of balance work of road from Khaog to Batodi and while the

respondent was in the process of executing the said work, additional

works were assigned to the respondent. The communications dated

30.10.2013 and 25.01.2017 bear testimony to the fact that amount of

Rs. 25.45 and Rs. 20.51 were sought by appellant No.3 from appellant

No.2. Appellants have not denied the execution of additional work. It

is difficult to believe that a Contractor would execute the work on his

own without being asked to do so by the officials of the appellants,

thereby putting his financial interest in peril. Since the appellants have

not denied the execution of additional work by the respondent but are

objecting to the claim of the respondent only on the ground of lack of

administrative approval and tendering process, the appellants are

under obligation to clear the liability of the respondent. In this context,

it would be appropriate to take note of the judgment passed in case

titled as "Union Territory of J&K & Ors. Vs. Sanjeev Kumar" 2021

Legal Eagle (J&K) 110, wherein a Coordinate Bench of this court

has observed that the petitioner who was allotted the contract by the

Housing Board cannot be expected to first verify as to whether the

contract that has been allotted to him was being executed within the

territorial jurisdiction of the Housing Board or not, nor was he

expected to refuse the execution of the work simply because the

subject matter of the work was not put to open tendering system.

10. We have examined the judgment passed by the writ court and we do

not find any reason to show indulgence. The present appeal is found to

be misconceived and the same is, accordingly, dismissed.

                                                     (RAJNESH OSWAL)                 (ARUN PALLI)
                                                        JUDGE                       CHIEF JUSTICE
                      Jammu
                      16.05.2025
                      Karam Chand/Secy.

                                              Whether the order is speaking: Yes/No
                                              Whether the order is reportable: Yes/No









 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter