Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Abdul Rehman Ahanger vs Ut Of J&K & Others
2024 Latest Caselaw 252 j&K/2

Citation : 2024 Latest Caselaw 252 j&K/2
Judgement Date : 15 March, 2024

Jammu & Kashmir High Court - Srinagar Bench

Abdul Rehman Ahanger vs Ut Of J&K & Others on 15 March, 2024

Author: Rajnesh Oswal

Bench: Rajnesh Oswal

      IN THE HIGH COURT OF JAMMU & KASHMIR AND
                  LADAKHAT SRINAGAR
                                                  Reserved on: 06.03.2024
                                                  Pronounced on: 15.03.2024

                           WP(C) No.1711/2022

ABDUL REHMAN AHANGER                           ...PETITIONER(S)
      Through: - Ms. Asma Rashid, Advocate.
Vs.

UT OF J&K & OTHERS                             ...RESPONDENT(S)
      Through: -     Mr. Raies-ud-din Ganai, Dy. AG.


CORAM:HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE

                                  JUDGMENT

1) The petitioner along with his two brothers had approached the

respondents for grant of building permission for construction of a

commercial complex at Batabagh Narapora Road Sopore. After the

requisite No Objection Certificates were issued by the concerned

departments, the respondent-Municipal Council, Sopore, granted

permission in favour of the petitioner and his two brothers for raising the

construction vide order dated 28.01.2016. The petitioner further claims

to have deposited the building permission fee on 31.12.2015 for an

amount of Rs.1,60,600/. The petitioner further states that when the

building permission was granted, he was not in a position to raise

construction of three storeyed building like his other two brothers due to

financial constraints and he raised construction of only single storey

building. The petitioner further claims to have obtained loan from the

financial institution and his friends and relatives for the purpose of

raising further construction of two more stories but could not raise the

construction due to Covid-19 Pandemic. The petitioner, as such,

submitted an application in the month of April, 2021 before the

respondent-Municipal Council which was forwarded to the concerned

departments for their No Objection certificates. The petitioner was also

directed to deposit the building permission fee and the same was

deposited in the Municipal Council Office, Sopore, through a cheque

amounting to Rs.1,14,050/. The concerned departments also granted No

Objection Certificates for raising the construction. It is further stated that

the petitioner has acquired a right of deemed permission as his building

permission case was not decided by the respondents. The petitioner,

accordingly, started the construction as a matter of right but the

respondents started interference in the completion of construction of the

building. The petitioner claims to have made applications with the

respondents for grant of revised permission for raising two more floors

but the same were not considered, as such, the petitioner through the

medium of present writ petition has sought directions upon the

respondents thereby restraining them from causing any sort of

interference with the construction being raised over the ground floor of

the building situated at Batabagh Narapora Road, Sopore.

2) The respondents have filed their response stating therein that the

petitioner had filed an application seeking building permission in his

favour for three storied commercial building at site Neharpora, Damna,

Sopore in the year 2016, which was accorded by the respondent-Council

vide order dated 28.01.2016. After sometime, the petitioner again

approached the respondents for accord of building permission for

construction of further two stories over the already existing ground floor

on the ground that he could not construct the building as per the earlier

site plan due to financial stringency. The case of the petitioner was

again referred to the concerned departments for their No Objection

Certificates. R&B Department Division Sopore submitted its report vide

communication dated 24.06.2021 with the remarks that the ground floor

of the shop line is at a distance of only 17 feet instead of 25 feet from the

centre of Neharpora main road, as such, is violating the prevailing

Ribbon Development Act, therefore, the case of the petitioner was not

accorded approval. The petitioner again approached the respondents for

approval and his case was again referred to the concerned departments,

however, the R&B Department Division again raised the same objection

that the building has been constructed at the distance of 17 feet from the

centre of the road instead of 25 feet.

3) Learned counsel for the petitioner submitted that once the

construction on the ground floor has been raised by the petitioner, the

respondents cannot deny permission to him for raising construction of

2nd and 3rd floors on the ground that the structure at ground floor is at a

distance of 17 feet from the centre of the road instead of 25 feet. She

further submitted that the petitioner is ready to furnish an undertaking

that if at any time the building comes under road widening process, he

will not claim any compensation for the said structure.

4) Per contra, Mr. Raies-ud-din Ganai, Dy. AG, submitted that the

petitioner cannot raise the construction in violation of Ribbon

Development Act. He further submitted that the respondents are not

possessing the whole of the record in respect of the building permission

granted in favour of the petitioner.

5)    Heard and perused the record.


6)    This is an admitted fact that the petitioner was permitted to raise

construction by the respondents and also that the petitioner has raised

the construction on ground floor only. It is admitted by the respondents

that the petitioner had applied before them for raising construction of

2nd and 3rd floors but due to the report submitted by the Executive

Engineer, R&B Division, Sopore, the application of the petitioner for

raising construction of 2nd and 3rd floors could not be accepted. The

petitioner has placed on record the building permission granted to him

and his brother for raising construction of two three storeyed

commercial buildings and one single storeyed commercial building

vide order dated 28.01.2016. The respondents have not been able to

produce the record in respect of the building permission granted in

favour of the petitioner and his brother, so as to ascertain as to whether

there was any stipulation for keeping a particular distance from the

centre of the road or not.

7) Be that as it may, the petitioner has already raised construction of

the ground floor and no one ever raised any objection to the same. The

petitioner has also placed on record the photographs demonstrating the

building line existing on spot. The communication of Executive

Engineer dated 24.06.2021 bears the mention of the fact that the

petitioner has furnished an undertaking that he will not claim any

compensation for the said structure, if the structure comes under the

road widening programme. The petitioner has placed on record the

application dated 20.06.2022 for grant of revised building permission

whereas the present writ petition has been filed on 04.08.2022. In view

of above, as the petitioner has already raised the construction of the

ground floor and objection in respect of violation of Ribbon

Development Act was never raised, this court deems it proper to direct

the respondents to consider the application of the petitioner for grant of

revised building permission as per rules notwithstanding the objection

raised by the Executive Engineer, R&B Division, Sopore, in respect of

the distance of the ground floor from the centre of the road. The

petitioner shall also file an undertaking with the respondents that in the

event the structure sought to be raised by him comes under road

widening, he will not claim any compensation for the same. The

application submitted by the petitioner shall be decided with in the

period of 30 days from the date, the copy of this order is made available

to the concerned respondents.

8)      Disposed of as above.



                                                    (Rajnesh Oswal)
                                                         Judge
SRINAGAR
15.03.2024
"Bhat Altaf-Secy"
                Whether the order is reportable:    YES/NO





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter