Citation : 2023 Latest Caselaw 674 j&K/2
Judgement Date : 31 May, 2023
Sr.No. 02
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
WP (C) No. 3069/2022
Reserved on : 19.04.2023
Pronounced on : 31.05.2023
M/S Hussain Enterprises ... Petitioner(s)
Through :- Mr. Hakim Suhail Ishtiaq, Advocate
V/s
UT of Ladakh & Ors. ... Respondent(s)
Through :- Mr. T.M Shamsi, DSGI
Coram: HON'BLE MR. JUSTICE JAVED IQBAL WANI, JUDGE
JUDGMENT
31.05.2023
1. In the instant petition filed under Article 226 of the Constitution, the
petitioner firm herein seeks writ of mandamus against the respondents
herein for payment of an amount of Rs. 1,22,53,871.00/- (Rupees One
Crore Twenty Two Lacs Fifty-Three Thousand Eight Hundred Seventy
One only/-) along with interest @ as may be deemed appropriate by the
Court.
2. Facts as are discernible from the record, necessary for the decision of the
instant petition are that the respondents herein floated an E-Tender bearing
No. 386 of HE Div. Leh of 2021-22 dated 19.03.2022 for supply of 20mm
Dia Pre-Insulated MDPE pipe outer Dia PE8o PN 16 ISO 4427:2007.
3. The petitioner submitted a bid of Rs. 1,24,81,042.00/- (Rupees One Crore
Twenty-Four Lacs Eighty-One Thousand Forty-Two Only/-) and
consequently came to be declared as L1 by the respondents and
accordingly, a letter of acceptance was issued in his favour by Respondent
2 vide letter No. CE/PHE-I&FC/UTL/Supply/2022-23/271-73 dated
04.05.2022 with a clear direction to the petitioner to mobilize his resources
for supply of the material.
4. The petitioner claims that the items to be supplied to the respondents being
not readily available in the market and manufactured by the manufacturer
on orders upon placing an order only, the petitioner placed an order for
manufacture and supply of the items to the concerned manufacturer only,
when the respondents issued the letter of acceptance.
5. The petitioner claims to have entered into negotiations as well with the
respondents qua the rate quoted earlier by him in respect of the items to be
supplied to the respondents whereupon same were reduced.
6. The respondents/Respondent 3 states to have issued supply order bearing
No. CE/PHE-I&FC/UTL/Supply/2022-23/1117-20 dated 25.08.2022 in
favour of the petitioner and as per the time duration clause provided in the
said supply order, that the items have had to be supplied by the petitioner
to the respondents within 25 days.
7. The petitioner however, states to have informed the respondents
immediately upon issuance of the supply order that the order for
manufacturing of the items to be supplied had been placed by the petitioner
with the manufacturer only after the finalization of negotiated rates, as the
earlier order placed with the manufacturer by the petitioner had been
withdrawn and as such, sought more time for making the requisite supplies,
as also, as and when a substantial quantity of the items kept manufactured
by the manufacturer.
8. It is also being stated by the petitioner that items to be supplied to the
respondents have had been inspected by an expert firm engaged by the
respondents namely "Rites Limited".
9. It is being further stated that the petitioner upon receiving supplies of the
items from the manufacturer, supplied the same to the respondents
however, in the meantime received a communication No. PHE/CC-
JJM/2022-23/3592-94 dated 25.10.2022 from the respondents asking the
petitioner to supply the balance material within 07 days, in response to
which the petitioner claims to have addressed letter dated 26.10.2022 to the
respondents seeking grant of extension of one month for completing the
supply of items.
10. The petitioner claims to have supplied the entire quantity of the items to
the respondents in terms of supply order acknowledged by the respondents
and consequently had sought release of payments thereof.
11. The Respondent 3, however, is stated to have refused to release the
payments in favour of the petitioner in terms of invoice dated 10.12.2022
on the ground that in terms of the supply order, the petitioner had to supply
the items within 25 days ignoring the issuance of letter dated 25.10.2022
addressed by Respondent 3 to the petitioner as well as letter dated
26.10.2022 submitted by the petitioner in response thereto.
12. It is being stated that the petitioner did not commit any delay in making
supplies to the respondents deliberately or intentionally, but the said delay
occurred on account of delayed issuance of supply order and also on
account of the negotiations of rates held prior to the issuance of the same
and post issuance of letter of acceptance.
13. The respondents, though entered appearance before the court through their
counsel on 31.12.2022 and sought time to file objections to the petition
while availing one more opportunity thereafter on 27.02.2023 did not file
objections thereto. However, the appearing counsel for the respondents
during the consideration of the matter produced a copy of objections of the
respondents to the petition and the same were taken on record.
14. In the objections, the respondents have stressed that in terms of the supply
order dated 25.08.2022, the petitioner had to supply the items within 25
days in which the petitioner failed. It is further being averred in the
objections that the petitioner did not produce any inspection certificate of
the items from the 3rd party and that as such, in absence thereof, the
petitioner cannot raise any bill against the items supplied by him.
Heard learned counsel for the parties and perused the record.
15. Learned counsel for the petitioner while making submissions reiterated to
the contentions raised in the petition whereas the counsel for the
respondents controverted the same in tune with the stand taken in the
objections.
16. Having regard to the nature of the controversy involved in the petition, the
ground urged by the respondents for denying payment to the petitioner for
the items supplied by him in terms of the allotment order dated 25.08.2022
is twofold; firstly, that the time was the essence of the contract, as the
petitioner have had to supply the items within the period stipulated in the
supply order, in which the petitioner failed and secondly, that the items
supplied by the petitioner had not been inspected by any 3rd party certifying
the quality of the items.
17. In so far as first issue (supra) raised by the respondents is concerned, it is
pertinent to note that the respondents though have had stipulated period of
25 days in the supply order within which the petitioner had to make the
supplies, yet Respondent 3 in terms of communication dated 25.10.2022
extended the said stipulated period of 25 days by further 07 days, thus
diluted the strictness of the condition of 25 days incorporated in the supply
order, manifestly suggesting that the respondents did not acknowledge
time to be the essence of the contract.
In so far as non-submission of inspection certificates by 3rd party, in
respect of the items supplied by the petitioner to the respondents is
concerned, the perusal of the record of the petition would reveal that the
petitioner has submitted to the respondents such certificates of the 3rd party
indisputably nominated by the respondents and without there being any
role of the petitioner in the said process of inspection of the items.
18. The perusal of the objections and the record appended therewith would
reveal that Respondent 3 addressed a letter to Respondent 4 on 29.06.2022
about the non receipt of items from the petitioner and in respect thereof,
Respondent 2 had recommended an action as per norms against the
petitioner, yet the respondents have not denied the fact that the petitioner
was invited for negotiations on the original price quoted by him, which
finally resulted into issuance of supply order dated 25.08.2022, therefore,
the respondents cannot take the plea, that the petitioner failed to supply the
items post issuance of letter of intent dated 04.05.2022, when admittedly
supply order came to be issued thereafter on 25.08.2022.
19. Having regard to the aforesaid facts and circumstances in as much as the
respective pleadings of the parties as above, the rival contentions of the
appearing counsel for the parties, the petition is disposed of in the
following manner:-
"the petitioner shall submit his invoice/s and all other
relevant documents in support of its claim before
Respondent 2 along with a copy of this order within 15
days, whereafter upon receipt of the same, Respondent
2 shall verify the quantity of items claimed to have been
supplied by the petitioner as also adherence to all
requisites and formalities as per the terms and
conditions of the E-tender dated 19.03.2022 read with
supply order dated 25.08.2022 and upon verifying the
same, Respondent 2 shall release all payment in favour
of the petitioner for the net quantity supplied by the
petitioner within a period of four weeks in accordance
with law and if there is no other legal impediment
thereto."
The petition along with connected application(s), if any, is accordingly
disposed of.
(Javed Iqbal Wani) Judge
Jammu:
31.05.2023
Manan
Whether the order is speaking : Yes
Whether the order is reportable : No
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!