Citation : 2021 Latest Caselaw 1327 j&K
Judgement Date : 22 October, 2021
HIGH COURT OF JAMMU AND KASHMIR AND LADAKH
AT JAMMU
Reserved on : 23.09.2021
Pronounced on: 22.10.2021
OWP No. 303/2016
Puran Singh .....Appellant/Petitioner(s)
Through :- Mr. Ashok Sharma, Advocate
v/s
Union of India and others .....Respondent(s)
Through :- Mr. Vishal Sharma, ASGI
Coram: HON'BLE MR. JUSTICE RAJNESH OSWAL, JUDGE
JUDGMENT
1. The petitioner, pursuant to the auction notice bearing No.
Misc/GEN/1/Trees/DEO dated 01.05.2014 for 89 trees situated at 31
RR Military Station, Udhampur issued by the respondent No. 3,
participated in the auction and emerged as the highest bidder on
15.05.2014 for offering a price of Rs. 7,25,500/-. As per the
condition of the auction notice, besides depositing earnest money of
Rs. 25,000/-, the petitioner also deposited 25% of the highest bid
money immediately at the fall of hammer. The petitioner claims to
have waited for acceptance of his offer and it was only after 18
months, the respondents accepted the bid of the petitioner.
2. It is further stated by the petitioner that as the bid was accepted after
more than 18 months, so in the intervening period the price of wood
had come down about 50% of the total amount of the bid. The
petitioner claims that the market rate of the wood at the time of
auction was Rs. 750 per quintal i.e. in the month of May, 2014. The
petitioner has further stated that he continued to approach the
respondent No. 3 number of times and finally on 03.12.2015
requested the respondent No. 3 to pay back his 25% of the amount
already deposited by him on 15.05.2014 but the same was not paid
by respondent No. 3 deliberately and in turn re-auction notice was
issued on 18.02.2016 causing pecuniary loss to the petitioner.
Thereafter, the petitioner claims to have issued the legal notice dated
06.02.2016 to respondent No. 3 requesting him for refund of his
money but the respondent No. 3 forfeited 25% of the amount i.e. Rs.
1,81,375/- deposited by the petitioner at the time of bid vide notice
issued by the respondents on 29.01.2016.
3. The petitioner has challenged the forfeiture of the sum of Rs.
1,81,375/- on the ground that the respondent No. 3 intentionally and
willfully despite numerous requests of the petitioner did not grant
permission to the petitioner to remove the trees and further caused
delay of 18 months in communicating the approval of bid and it has
resulted in huge loss to the petitioner, as the price of the auctioned
wood was reduced to 50 % of the total market value as it existed at
the time of bid. It is further stated that the petitioner has been
condemned unheard and without affording opportunity of being
heard, the amount has been forfeited. The petitioner has prayed for
quashing of order of forfeiture of the amount of Rs. 1,81,375/- and
further prayed for issuance of appropriate directions to the
respondents to refund the above mentioned amount.
4. The petitioner has placed on record the copy of the auction notice
dated 01.05.2014, the receipt regarding the amount deposited by the
petitioner with the respondent as advance money, letter dated
03.12.2015 and legal notice dated 06.02.2016 and subsequent auction
notice dated 18.02.2016 issued by the Defence Estates Officer,
Udhampur Circle, respondent No. 3 herein. During the pendency of
the present writ petition, the petitioner has also placed on record the
receipt regarding the bid money deposited by the successful bidder
pursuant to re-auction conducted by the respondents and perusal of
the said receipt reveals that the tress have been auctioned for a sum
of Rs. 3,05,000/-.
5. Response stands filed by the respondents in which it is admitted that
the petitioner after emerging as successful bidder has deposited a
sum of Rs. 1,81, 375/-. It is further submitted by the respondents that
after the payment was received by the respondents, the case was
forwarded to respondent No. 2 for approval vide office letter dated
21.05.2014 (Annexure-II to the objections filed by the Respondents).
The Competent Authority raised certain observations vide letter
dated 23.06.2014 (annexure-III to the objections filed by the
Respondents) and the matter was again taken up with the Army
Authority vide letter dated 30.06.2014 for rectification of the
observations. It is further stated that it took some time to rectify the
observations as different agencies i.e. Sericulture Department, State
Government and local authorities were involved in the said process
and after rectification, the Competent Authority accorded the
approval for removal of trees vide order dated 23.10.2015
(Annexure-IV). After the approval, the petitioner was asked to
deposit the balance amount i.e. 75% of bid money and 10% security
deposit within seven days vide letter dated 06.11.2015 (Annexure-
V). Thereafter, the petitioner made a representation on 03.12.2015
that he was not interested in the contract as the rates of the wood had
come down and the decision to accept the bid after 18 months was
not justified. The said representation was sent to the Competent
Authority vide letter dated 08.12.2015 (Annexure-VII). However, the
Competent Authority directed to give final chance to the contractor
to deposit the balance amount and further it was mentioned in the
notice that if he failed to deposit the amount, the amount already
deposited by him shall be forfeited but the petitioner did not respond
to the said notice and thereafter fresh auction notice was issued and
the permission letter was given to new contractor, namely, Mulkh
Raj for removal of 89 trees. It is further stated by the respondents
that as per terms and conditions of the auction notice, in case of
failure to cut/ remove the trees within the stipulated time, the
contractor is liable for penalty at the discretion of the Defence
Estates Officer (DEO) and further DEO has reserved the right to
cancel the contract and forfeit the advance amount. It is further
mentioned in the auction notice that in case of breach of any term
and condition of the auction notice, the contractor shall be liable for
penalty including forfeiture of his security.
6. Mr. Ashok Sharma, learned counsel for the petitioner vehemently
submitted that the respondents consumed 18 months in approving the
bid of the petitioner and by that time, the rates of the wood had
substantially come down and the respondents have acted in a very
unfair and unreasonable manner.
7. Per contra, Mr. Vishal Sharma, learned ASGI, has vehemently
argued that the respondents were well within their right to either
approve or refuse the bid of the contractor and it was stipulated in the
auction notice that acceptance of the bid was to be made by the
Competent Authority. As the number of agencies were involved for
clearing the observations made by the Competent Authority so
Competent Authority took some time to grant the approval for the
bid.
8. Heard and perused the record.
9. As per the terms and conditions of the auction notice, the petitioner
was required to deposit 75% of the balance money plus 10% as
security money and TCS as applicable, on the acceptance of the bid
by the Competent Authority. The Competent Authority had reserved
the right to reject/accept any bid/highest bid without assigning any
reason thereof and decision of the Defence Estates Officer,
Udhampur Circle was held to be final. So the bid made by the
petitioner/contractor was required to be approved by the Competent
Authority. The bid admittedly was made on 15.05.2014 and as per
response filed by the respondents it was approved by the Competent
Authority on 23.10.2015 i.e. it took 17 months and 8 days for the
Competent Authority to grant the approval of the bid made by the
petitioner. It is evident from the terms and conditions of the auction
notice that no period has been stipulated in the auction notice for
approval of the bid by the Competent Authority. Even the perusal of
the letter dated 18.12.2015 (Annexure-V to the objections filed by
the respondents) addressed by the respondent No. 3 to respondent
No. 2 reveals that the respondent No. 2 has himself observed that no
time limit to accept the bid has been mentioned therein besides there
is no mechanism to deal with cases wherein inordinate delay has
occurred to communicate approval of the bid. So, there is admission
on the part of the respondents that there was inordinate delay in
communicating the approval of the bid. Now in such scenario when
the respondents have themselves admitted that there is no mechanism
to deal with the cases where there is inordinate delay in
communicating the approval of the bid, it is to be seen as to whether
the respondents have acted in a reasonable manner or not. It is apt to
take note of section 6 of the Jammu and Kashmir Contract Act, 1977
(1920 A. D.) which reads as under:
"6. Revocation how made.- A proposal is revoked-
(1) by the communication of notice of revocation by the proposer to the other party;
(2) by the lapse of the time prescribed in such proposal for its acceptance, or, if no time is so prescribed, by the lapse of a reasonable time, without communication of the acceptance;
(3) by the failure of the acceptor to fulfill a condition precedent to acceptance; or (4) by the death or insanity of the proposer, if the fact of his death or insanity comes to the knowledge of the acceptor before acceptance."
10. A perusal of sub section 2 of section 6 of the Act reveals that a
proposal is revoked by the lapse of time prescribed in such proposal
for its acceptance and where no time is so prescribed, by the lapse of
a reasonable time, without communication of the acceptance
meaning thereby when the proposal is not accepted within the
reasonable time. In the instant case, this is an admitted fact that no
period was provided for acceptance of the bid by the Competent
Authority so it is required to be considered as to whether the offer
made by the petitioner stood revoked by the lapse of time as the
same was not accepted by the Competent Authority within the
reasonable time. The expression "reasonable time" may vary from
case to case. In certain circumstances even a delay of few days may
be fatal and in certain other circumstances, the delay of few months
may not be fatal.
11. The contention of the petitioner is that the respondents did not accept
the bid within the reasonable time and they took 17 months and 8
days during which the rates of the wood had substantially come
down and this contention of the petitioner is substantiated by the
amount of bid offered and accepted by the respondents in the re-
auction conducted on 06.03.2016 where 89 trees those were the
subject matter of the earlier auction notice, were re-auctioned for a
sum of Rs. 3,05,000/- so there is substantial difference of Rs.
4,20,500/-. The time consumed by the respondents for granting the
approval of the bid of the petitioner can by no means be termed as a
reasonable time for acceptance of the bid particularly when the
respondents have themselves admitted that there is no mechanism to
deal with the cases where inordinate delay has occasioned in
communicating the acceptance. The use of word "inordinate delay"
by the respondents themselves in the Annexure-V (supra) is self
explanatory that means usually or disproportionately large or
excessive. The respondents should have obtained the requisite
clearances for the purposes of cutting the trees in question before
putting the same for auction and the respondents cannot be permitted
to forfeit the amount solely on the ground that no time was
prescribed for acceptance of the bid by the Competent Authority. If
such contention of the respondents is accepted, then there cannot be
any time limit for acceptance of proposal and that shall be violative
of Contract Act (supra) The bid should have been accepted within a
reasonable time and if the respondents did not accept the same within
the reasonable time, then the offer stood revoked, notwithstanding its
acceptance beyond the reasonable time.
12. The State and its authorities/instrumentalities while dealing with its
citizens must act with fairness as well as in reasonable and
transparent manner. While the relationship between the parties after
the contract has come in to existence, is governed by the terms and
conditions of the contract and it does not matter if one of the
contracting party is State but at pre contract stage, the State and its
instrumentalities must act in a transparent, fair and reasonable
manner. Any action of the State which is not informed by fairness
and reason is constitutionally invalid on the touchstone of article 14
of the constitution of India.
13. In Shrilekha Vidyarthi (Kumari) v. State of U.P, reported in
(1991) 1 SCC 212, Apex Court has observed as under
"21. The Preamble of the Constitution of India resolves to secure to all its citizens Justice, social, economic and political; and Equality of status and opportunity. Every State action must be aimed at achieving this goal. Part IV of the Constitution contains
„Directives Principles of State Policy‟ which are fundamental in the governance of the country and are aimed at securing social and economic freedoms by appropriate State action which is complementary to individual fundamental rights guaranteed in Part III for protection against excesses of State action, to realise the vision in the Preamble. This being the philosophy of the Constitution, can it be said that it contemplates exclusion of Article 14 -- non-arbitrariness which is basic to rule of law -- from State actions in contractual field when all actions of the State are meant for public good and expected to be fair and just? We have no doubt that the Constitution does not envisage or permit unfairness or unreasonableness in State actions in any sphere of its activity contrary to the professed ideals in the Preamble. In our opinion, it would be alien to the constitutional scheme to accept the argument of exclusion of Article 14 in contractual matters. The scope and permissible grounds of judicial review in such matters and the relief which may be available are different matters but that does not justify the view of its total exclusion. This is more so when the modern trend is also to examine the unreasonableness of a term in such contracts where the bargaining power is unequal so that these are not negotiated contracts but standard form contracts between unequals.
22. There is an obvious difference in the contracts between private parties and contracts to which the State is a party. Private parties are concerned only with their personal interest whereas the State while exercising its powers and discharging its functions, acts indubitably, as is expected of it, for public good and in public interest. The impact of every State action is also on public interest. This factor alone is sufficient to import at least the minimal requirements of public law obligations and impress with this character the contracts made by the State or its instrumentality. It is a different matter that the scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes. However, to the extent, challenge is made on the ground of violation of Article 14 by alleging that the impugned act is arbitrary, unfair or unreasonable, the fact that the dispute also falls within the domain of contractual obligations would not relieve the State of its obligation to comply
with the basic requirements of Article 14. To this extent, the obligation is of a public character invariably in every case irrespective of there being any other right or obligation in addition thereto. An additional contractual obligation cannot divest the claimant of the guarantee under Article 14 of non-arbitrariness at the hands of the State in any of its actions.
24. The State cannot be attributed the split personality of Dr Jekyll and Mr Hyde in the contractual field so as to impress on it all the characteristics of the State at the threshold while making a contract requiring it to fulfil the obligation of Article 14 of the Constitution and thereafter permitting it to cast off its garb of State to adorn the new robe of a private body during the subsistence of the contract enabling it to act arbitrarily subject only to the contractual obligations and remedies flowing from it. It is really the nature of its personality as State which is significant and must characterize all its actions, in whatever field, and not the nature of function, contractual or otherwise, which is decisive of the nature of scrutiny permitted for examining the validity of its act. The requirement of Article 14 being the duty to act fairly, justly and reasonably, there is nothing which militates against the concept of requiring the State always to so act, even in contractual matters. There is a basic difference between the acts of the State which must invariably be in pubic interest and those of a private individual, engaged in similar activities, being primarily for personal gain, which may or may not promote public interest. Viewed in this manner, in which we find no conceptual difficulty or anachronism, we find no reason why the requirement of Article 14 should not extend even in the sphere of contractual matters for regulating the conduct of the State activity.
14. In ABL International Ltd. v. Export Credit Guarantee Corpn. of
India Ltd., reported in (2004) 3 SCC 553, the Apex Court has held
as under:
"28. However, while entertaining an objection as to the maintainability of a writ petition under Article 226 of the Constitution of India, the court should bear in mind the fact that the power to issue prerogative writs under Article 226 of the Constitution is plenary in nature and is not limited by any other
provisions of the Constitution. The High Court having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. The Court has imposed upon itself certain restrictions in the exercise of this power. (See Whirlpool Corpn. v. Registrar of Trade Marks [(1998) 8 SCC 1] .) And this plenary right of the High Court to issue a prerogative writ will not normally be exercised by the Court to the exclusion of other available remedies unless such action of the State or its instrumentality is arbitrary and unreasonable so as to violate the constitutional mandate of Article 14 or for other valid and legitimate reasons, for which the Court thinks it necessary to exercise the said jurisdiction."
15. Thus in view of the inordinate delay in acceptance of offer and
communication thereof, this court is of the considered opinion that
the action of the respondents in forfeiting the amount paid by the
petitioner is unfair, unjust and arbitrary.
16. In view of what has been discussed above, the present petition is
allowed and the forfeiture of sum of Rs. 1,81,375/ by the respondents
is held to be bad in law and the respondents are directed to refund the
sum of Rs. 1,81,375/ along with interest @ 5% per annum from
01.02.2016 within a period of three months from today.
(RAJNESH OSWAL) JUDGE
JAMMU 22.10.2021 Rakesh Whether the order is speaking: Yes Whether the order reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!