Citation : 2021 Latest Caselaw 281 j&K
Judgement Date : 10 March, 2021
Sr. No. 237
HIGH COURT OF JAMMU AND KASHMIR
AT JAMMU
WP(C) 45/2021
CM 243/2021
Reserved on 09.03.2021.
Pronounced on 10. 03.2021.
Naseema Rashid Wani and another ..... Petitioner (s)
Through :- Mr. R.K.Gupta Sr. Advocate with
Mr. Udhay Bhaskar, Advocate
V/s
Jammu Municipal Corporation and ors .....Respondent(s)
Through :- Mr. Rajnish Raina, Advocate.
Coram: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
HON'BLE MR. JUSTICE SANJAY DHAR, JUDGE
JUDGMENT
1 In this petition filed under Article 226 of Constitution of India, the
petitioners have sought quashing of the following:
(i) Notice No. JMC/CEO/785 dated 06.01.2021 issued by respondent No.1 purportedly under Section 248 of the Municipal Corporation Act, 2000 (for short 'the Act') whereby the petitioners have been called upon to show cause within a period of 48 hours as to why the building permission granted to them on 05.08.2017 may not be cancelled; and
(ii) Order No. JMC/CEO/561-67 dated 08.01.2021 issued by respondent No.1 whereby the building permission granted to the petitioners has been cancelled and sealing of the premises has been ordered.
2 Impugned order dated 08.01.2021 (supra) is assailed by the
petitioners, inter alia, on the ground that the same is in violation of the
principles of natural justice, in that, the impugned show cause notice was never
served upon the petitioners, nor were they given any opportunity of being
heard.
3 Mr. R.K.Gupta, learned senior counsel representing the petitioners
submits that the impugned orders are predicated primarily on the premise that
as per the report of Additional Deputy Commissioner, Jammu dated
04.01.2021, the petitioners have raised construction on the land which includes
the State land admeasuring 3 marlas under khasra No. 94 situate at Sidhra,
Jammu. However, neither the Additional Deputy Commissioner, Jammu, who
purports to have conducted the demarcation ever associated the petitioners in
the said process, nor the report of demarcation was ever put to the petitioners
by respondent No.1 for objections. Learned senior counsel has also raised the
issue of jurisdiction of respondent No.1 under the provisions of the Act to issue
the show cause notice and cancel the permission granted four years back, more
so, when the same has already been acted upon and construction raised in
accordance therewith.
4 Mr. Raina, learned counsel, appearing for the respondents has
opposed the maintainability of the petition on the ground that the petitioners
were well aware about the show cause notice which in their absence was pasted
on the conspicuous part of the 'offending structure'. He argues that apart from
encroaching upon the State land admeasuring 3 marlas, the petitioners have
also committed various violations and, therefore, invited action under the
provisions of Control of Building Operations Act. They were, thus, put on
show cause notice to which the petitioners also submitted their reply. It is on
consideration of the objections of the petitioners, the impugned order for
cancellation of the permission and sealing of the premises was made.
5 Having heard learned counsel for the parties and perused the
record, it is seen that the impugned show cause notice was issued on
06.01.2021 and as per the report of the process server of the respondents, the
same was pasted on the subject premises on 06.01.2021 itself. The impugned
order of cancellation of the building permission and sealing of the premises
was made on 08.01.2021.
6 Even if we were to agree with the stand of the respondents that
the show cause notice was, indeed, pasted on 06.01.2021 itself, yet, it remains
to be seen as to whether one day's time to the petitioners to respond to the
show cause notice could, by any stretch of reasoning, be termed as reasonable
and fair opportunity to the petitioners to submit their explanation/reply. The
answer to this question has to be no and emphatic no.
7 We may not agree with the learned counsel for the petitioners that
the petitioners were not aware of pasting of the notice till 08.01.2021, yet we
are of the considered view that giving a day's time to the petitioners to respond
to the show cause notice was only an eye wash and does not comply with the
principles of natural justice. The petitioners have been deprived of reasonable
opportunity to respond to the show cause notice. That renders the impugned
order cancellation of building permission and sealing of the premises bad in the
eye of law.
8 In view of the aforesaid, the writ petition is allowed and the
impugned order dated 08.01.2021 (supra) issued by respondent No. 1 whereby
the building permission granted to the petitioners has been cancelled and the
premises have been ordered to be sealed, is quashed. The parties are, thus,
relegated to the position as it was obtaining on 06.01.2021 when the show
cause notice was issued by respondent No.1 to the petitioners. The petitioners
shall be at liberty to file objections to the show cause notice taking all the
available pleas including those taken in this petition within a period of one
week from today. Respondent No.1, on receipt of such objections, shall
consider and dispose of the same within a period of one week thereafter by
passing a speaking order, copy whereof shall be conveyed to the petitioners
forthwith. In case, an adverse order is passed against the petitioners, the same
shall not be given effect to for a period of one week so as to enable the
petitioners to avail appropriate remedy available to them in law. It is further
provided that till a decision as aforesaid is taken by respondent No.1, the
petitioners shall not raise any fresh construction on the spot.
Disposed of in the above terms.
The record is returned to Mr. Raina in the open Court.
(SANJAY DHAR) (SANJEEV KUMAR)
JUDGE JUDGE
Jammu
10.03.2021
Sanjeev
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!