Citation : 2021 Latest Caselaw 618 j&K
Judgement Date : 16 June, 2021
IN THE HIGH COURT OF JAMMU AND KASHMIR
AT JAMMU
(THROUGH VIRTUAL MODE)
Reserved on: 01.06.2021
Pronounced on:16 .06.2021
WP(C) No.970/2020
CM Nos.2398/2020 & 2399 of 2020
MAHESH CHANDER SHARMA & ANR. ...PETITIONER(S)
Through: Mr. Rameshwar P. Sharma, Sr. Adv. with Mr.
Rohit Gupta, Advocate.
Vs.
UNION TERRITORY OF J&K & ORS. ....RESPONDENT(S)
Through: Mr. F. A. Natnoo, AAG.
CORAM: HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE
JUDGMENT
1) Petitioner No.1 is a consumer of electric energy supplied by the
respondents and is identified by consumer ID No.0101020005173 and
Installation No.GHB/1974. He claims to have executed a lease deed in
favour of petitioner No.2 qua the premises situated in Khasra No.360/361
Opposite Bakshi Nagar, Pulli Akhnoor Road, Jammu, where the subject
electric connection has been sanctioned by the respondents for a load of
5KV-90KV (commercial). As is apparent from the documents on record,
it is a three phase and four wire connection sanctioned by the respondents
in favour of the petitioners for the aforementioned commercial load.
CM Nos.2398 and 2399 of 2020
2) The petitioners are aggrieved and have assailed the monthly bill of
supply of electricity raised by the respondents for the month of January,
2020.
3) It is the contention of the petitioners that right from the year 2016,
when the sanction was accorded for revision of load of 05 KV to 90KV,
the petitioner No.1 has been regularly paying the electricity bills as raised
by the respondents every month and has not committed a single default in
clearing the electricity bills qua the connection in question. However, the
petitioner No.1 was astonished to see the bill for the month of January,
2020, with an opening balance of Rs.17,00,556.00 in addition to the
monthly bill of Rs.74,249.00. The petitioners claim that on receipt of this
highly excessive and inflated bill, the petitioners represented to the
respondents for rectification of the bill but no action in this regard was
taken. The petitioners were even threatened of disconnection of the
electricity supply if they failed to deposit the bill amount.
4) The petitioners have assailed this impugned bill issued by the
respondents for the month of January, 2020, on the ground that there has
never been any default in payment of the electricity bills which the
petitioners have been depositing regularly every month and, therefore, the
demand for the arrears amounting to more than Rs.17.00 lakhs included in
the monthly bill of January, 2020, is totally arbitrary, illegal and uncalled
for.
5) The impugned bill has also been assailed on the ground that the
respondents, before working out the excess charges of electricity supply
CM Nos.2398 and 2399 of 2020
and making a demand thereof never put the petitioners on notice and,
thus, violated the principles of natural justice. It is argued that the
petitioners were never made aware as to the basis of such exorbitant and
inflated bill indicating some past arrears running into lakhs.
6) Learned counsel for the petitioners, Mr. R. P. Sharma, placed
strong reliance on Section 126 of the Electricity Act, 2003 and submitted
that the procedure laid down in Section 126 with regard to assessment of
electricity charges payable by the petitioners has not been adhered to at all
and, therefore, the impugned bill, in so far it pertains to the arrears on
account of electricity charges, is not sustainable in law.
7) Per contra, learned counsel for the respondents took this Court to
the objections filed to the maintainability of the writ petition on behalf of
respondent No.1 to 5. He referred to Section 24 to 26 of the Electricity
Act and, in particular, placed reliance on Rule 16 of the Indian Electricity
Rules, 1956 to put across his argument that in the face of an alternative
and efficacious statutory remedy being available to the petitioners, the
resort to extraordinary jurisdiction of this Court was not permissible.
8) Learned counsel for the respondents would further point out that
the case of the petitioners is not one relatable to assessment made under
Section 126 of the Act but is only by way of correction of an error
committed by the respondents while working out the electricity charges
for the supply made to the petitioners.
9) The stand of the respondents is reflected in para 4 of the objections,
which, for facility of reference, is reproduced here-under:
CM Nos.2398 and 2399 of 2020
"....it is submitted that the petitioners are bound to pay the demand charges of Rs. 18,00,939/- (Rupees Eighteen lakhs nine hundred and thirty nine only) as it has been found during inspection that the billing being done to the petitioners was quite less since the Multiplying Factor being applied only @ 1, however, the (Multiplying Factor had been three times the Unit i.e. (multiplied by 3), but the excess charges have not been charged from January, 2016, but only previous 24 months have been charged keeping in view the departmental policy. The petitioners are bound to pay the charges for excess energy consumed by them since the same has cause huge loss to the public exchequer and the billed amount is perfectly legal and there is no flaw/arbitrariness in the said bill."
10) In short, the argument of learned counsel appearing for the
respondents is that the actual energy consumption of the petitioners for
the month of January, 2020, is only Rs.74,348.66, whereas the amount of
Rs.15,48,260/ has been imposed as short assessment made by the
respondents due to applying of wrong multiplying factor. It is pointed out
that it was during the inspection conducted by third party i.e. M/S Yadav
Measurements Pvt. Ltd. on the directions of the Government, it came to
light that since the petitioners had been sanctioned a three phase
connection, as such, the units were required to be calculated with a
Multiplying Factor of (3) whereas the respondents had been applying the
Multiplying Factor of (1). It is on account of this discrepancy pointed out
by the Inspection Agency, corrective measures were taken and bills for
last 24 months were reworked and recalculated. This happened in many
similarly situated cases. It is not the case of the petitioners that the
petitioners above have been chosen for differential treatment.
11) Having heard learned counsel for the parties and perused record, I
am of the view that the impugned bill, in so far it pertains to the arrears
CM Nos.2398 and 2399 of 2020
worked out by applying the multiplying factor (3) as per the report of
independent Inspection Agency, cannot sustain in law.
12) Admittedly, the petitioners are not at fault in any manner. It is not
the case of the respondents that the petitioners from the date of sanction of
the electricity connection in their favour, have ever defaulted in payment
of electricity bills raised by the respondents on month to month basis. The
error, which the respondents allege to have been committed by the
officials of the department, is also not in any manner attributed to the
petitioners. As a matter of fact, it is the case of the respondents that due to
a bona fide mistake or lack of knowledge, the respondent department had
been applying the multiplying factor (1) whereas the actual multiplying
factor applicable was (3). And it was so pointed out for the first time by
an independent Inspection Agency appointed by the Government to
inspect all important installations. This Court is not saying even for a
minute that the respondents are not within their right to correct the errors
of fact, if any, made by them. Going by the stand of the respondents, it is
evident that they have acted upon the inspection report submitted by an
independent agency appointed by the Government and have come to
know that in case of three phased connection, the units consumed at a
particular installation are required to be calculated with multiplying factor
(3).
13) Be that as it may, the question remains that was it not incumbent
upon the respondents to put petitioners to notice, supply them the report
of the Inspection Agency also the basis for revision of paid electricity
bills. If the answer to this question is in affirmative, then the impugned
CM Nos.2398 and 2399 of 2020
bill clearly gets vitiated being issued in violation of principles of natural
justice. Had the petitioners been heard in the matter, given an adequate
opportunity to rebut claim of the respondents, it is possible that they could
have legitimately contradicted the stand of the respondents and persuaded
them not to revise the bills simply on the basis of observations made by
the Inspection Agency. In the absence of report of Inspection Agency
made available to the petitioners and in the absence of making the
petitioners known of the formula applied for working out the impugned
bill, there was no occasion or opportunity for the petitioners to explain
their position or contradict the findings of the Inspection Agency and the
respondents. I, therefore, find the impugned bill in flagrant violation of
principle of audi alteram partem.
14) After the judgment of A. K. Kraipak v. Union of India. (1969) 2
SCC 262, a thin line of distinction between an administrative power and a
quasi judicial power is virtually obliterated. In paragraph 20 of A. K.
Kraipak (supra), the Supreme Court held thus:-
"20. The aim of the rules of natural justice is to secure justice or to put it negatively to prevent miscarriage of justice. These rules can operate only in areas not covered by any law validly made. In other words they do not supplant the law of the land but supplement it. The concept of natural justice has undergone a great deal of change in recent years. In the past it was thought that it included just two rules namely: (1) no one shall be a judge in his own case (Nemo debet esse judex propria causa) and (2) no decision shall be given against a party without affording him a reasonable hearing (audi alteram partem). Very soon thereafter a third rule was envisaged and that is that quasi- judicial enquiries must be held in good faith, without bias and not arbitrarily or unreasonably. But in the course of years many more subsidiary rules added to the rules of natural justice. Till very recently it was the opinion of the courts that unless the authority concerned was required by the law under which it functioned to act judicially there
CM Nos.2398 and 2399 of 2020
was no room for the application of the rules of natural justice. The validity of that limitation is now questioned. If the purpose of the rules of natural justice is to prevent miscarriage of justice, one fails to see why those rules should be made inapplicable to administrative enquiries. Often times it is not easy to draw the line that demarcates administrative enquiries from quasi-judicial enquiries. Enquiries which were considered administrative at one time are now being considered as quasi-judicial in character. Arriving at a just decision is the aim of both quasi-judicial enquiries as well as administrative enquiries. An unjust decision in an administrative enquiry may have far more reaching effect than a decision in a quasi-judicial enquiry. What particular rule of natural justice should apply to a given case must depend to a great extent on the facts and circumstances of that case, the framework of the law under which the enquiry is held and the constitution of the Tribunal or body of persons appointed for that purpose. Whenever a complaint is made before a court that some principle of natural justice had been contravened the court has to decide whether the observance of that rule was necessary for a just decision on the facts of that case."
15) The principles of natural justice have been designed to ensure
fairness in action by the State and public bodies and, therefore, an
important facet of Article 14 of the Constitution of India. One of the
principles of natural justice i.e. the principle of audi alteram partem has
been explained by the Supreme Court in numerous judgments handed
down by the Supreme Court from time to time. Mohinder Singh Gill v.
Election Commission of India, (1978) 1 SCC 405, Smt. Maneka
Gandhi v. Union of India, AIR 1978 SC 597 and Swadeshi Cotton
Mills v. Union of India, AIR 1981 SC 818, Union of India v. Tulsiram
Patel, (1985) 3 SCC 398 to cite the few.
16) In paragraph No.95 and 96 of Tulsiram Patel (supra), the Supreme
Court beautifully concertized law on the subject, which, for facility of
reference, are reproduced hereunder:-
CM Nos.2398 and 2399 of 2020
"95. The principles of natural justice have thus come to be recognized as being a part of the guarantee contained in Article 14 because of the new and dynamic interpretation given by this Court to the concept of equality which is the subject-matter of that Article. Shortly put, the syllogism runs thus violation of a rule of natural justice results in arbitrariness which is the same as discrimination; where discrimination is the result of state action, it is a violation of Article 14: therefore, a violation of a principle of natural justice by a State action is a violation of Article 14. Article 14, however, is not the sole repository of the principles of natural justice. What it does is to guarantee that any law or State action violating them will be struck down. The principles of natural justice, however, apply not only to legislation and State action but also where any tribunal, authority or body men, not coming within the definition of "State" in Article 12, is charged with the duty of deciding a matter. In such a case, the principles of natural justice require that it must decide such matter fairly and impartially.
The rule of natural justice with which we are concerned in these Appeals and Writ Petitions, namely, the audi alteram partem rule, in its fullest amplitude means that a person against whom an order to his prejudice may be passed should be informed of the allegations and charges against him, be given an opportunity of submitting his explanation thereto, have the right to know the evidence, both oral or documentary, by which the matter is proposed to be decided against him, and to inspect the documents which are relied upon for the purpose of being used against him, to have the witnesses who are to give evidence against him examined in his presence and have the right to cross-examine them, and to lead his own evidence, both oral and documentary, in his defence. The process of a fair hearing need not, however, conform to the judicial process in a court of law, because judicial adjudication of causes involves a number of technical rules of procedure and evidence which are unnecessary and
CM Nos.2398 and 2399 of 2020
not required for the purpose of a fair hearing within the meaning of audi alteram partem rule in a quasi-judicial or administrative inquiry. If we look at clause (2) of Article 311 in the light of what is stated above, it will be apparent that clause is merely an express statement of the audi alteram partem rule which is implicitly made part of the guarantee contained in Article 14 as a result of the interpretation placed upon that Article by recent decisions of this Court. Clauses (2) of Article 311 requires that before a government servant is dismissed, removed or reduced in rank, an inquiry must be held in which he is informed of the charges against him and given a reasonable opportunity of being heard in respect of those charges. The nature of the hearing to be given to a government servant under clauses (2) of Article 311 has been elaborately set out by this Court in Khem chand's case in the passages from the judgment extracted above. Though that case related to the original clause (2) of Article 311, the same applies to the present clause (2) of Article 311 except for the fact that now a government servant has no right to make any representation against the penalty proposed to be imposed upon him but, as pointed out earlier, in the case of Suresh Koshy George v. The University of Kerala and others, such an opportunity is not the requirement of the principles of natural justice and as held in Associated Cement Companies Ltd. v. T. C. Shrivastava and others neither the ordinary law of the land nor industrial law requires such an opportunity to be given. The Opportunity of showing cause against the proposed penalty was only the result of the interpretation placed by the Judicial Committee of the Privy Council in Lall's Case upon section 240(3) of the Government of India, 1935, which was accepted by this Court in Khem Chand's Case. If, therefore, an inquiry held against a government servant under clause (2) of Article 311 is unfair or biased or has been conducted in such a manner as not to give him a fair or reasonable opportunity to defend himself, undoubtedly, the principles of natural justice would be violated, but in such a
CM Nos.2398 and 2399 of 2020
case the order of dismissal, removal or reduction in rank would be held to be bad as contravening the express provisions of clause (2) of Article 311 and there will be no scope for having recourse to Article 14 for the purpose of invalidating it."
17) From the aforesaid enunciation of law, it is trite that the principles
of natural justice constitute basic element of fair hearing having their
roots in the innate sense of man for fair play and justice. The audi alteram
partem rule in its complete sense would mean that a person against whom
an order to his prejudice may be passed should be informed of the
allegation and charges against him, be given adequate opportunity of
submitting his explanation thereto both oral and documentary, and shall
have the right to know the material by which the matter is proposed to be
decided against him. Any action by the State or a public body which visits
a person with civil consequences is to be taken in compliance with the
principles of audi alteram partem. It is true that audi alteram partem rule
is not rigid and inflexible principle to be applied in all situations. As
rightly observed in Tulsiram Patel (supra) that they are not cast in a rigid
mould nor can they be put in a legal straight jacket. They do not apply in
the same manner to two situations, which are not alike. Their applicability
can be excluded by express words of statute or by necessary intendment.
Similarly, in the case of Smt. Maneka Gandhi (supra), it has been
observed that even where there is no specific provision for showing cause,
yet in a proposed action which affects the right of an individual, it is duty
of the authority to give reasonable opportunity of being heard. This duty
CM Nos.2398 and 2399 of 2020
is said to be implied to nature of functions to be performed by authorities
having power to take punitive or damaging action.
18) Delhi Transport Corporation v. DTC Mazdoor Congress, 1991
Supp. (1) SCC 600, is another Constitution Bench judgment, which
throws considerable light on the observance of principles of natural justice
in particular audi alteram partem rule. In the aforesaid case, it has been
held that the audi alteram partem rule, which, in essence, enforces the
equity clause of Article 14 of the Constitution, is applicable not only to
quasi judicial orders but to administrative orders affecting prejudicially
the party in question unless application of rule has been expressly
excluded by Act or regulation or rule. The rule of principles of natural
justice does not supplant but supplement the rules and regulations and it is
the demand of the rule of law, which permeates our constitution that the
rule is observed both substantially and procedurally. It is, thus, trite that
any action prejudicial to a citizen, which is taken by the State or public
authority without affording him an opportunity of being heard would be
unfair and arbitrary. An action which is unfair and arbitrary would fall
foul of rule of equality, which is soul and spirit of Article 14 of the
Constitution. It is only in exceptional cases like where there is no
prejudice caused to a person against whom an order is passed or the
compliance of principles of natural justice particularly the rule of audi
alteram partem, even if observed would not change the position and
would be a mere useless formality, its strict adherence is excluded.
19) Recently the Supreme Court in the case of State of U.P. v. Sudhir
Kumar Singh, 2020 SCC Online SC 847 elaborately dealt with the
CM Nos.2398 and 2399 of 2020
scope and applicability of audi alteram partem rule. Hon'ble the Supreme
Court after surveying the entire case law, in paragraph No.39 held thus:-
"39. An analysis of the aforesaid judgments thus reveals:
(1) Natural justice is a flexible tool in the hands of the judiciary to reach out in fit cases to remedy injustice. The breach of the audi alteram partem rule cannot by itself, without more, lead to the conclusion that prejudice is thereby caused.
(2) Where procedural and/or substantive provisions of law embody the principles of natural justice, their infraction per se does not lead to invalidity of the orders passed. Here again, prejudice must be caused to the litigant, except in the case of a mandatory provision of law which is conceived not only in individual interest, but also in public interest.
(3) No prejudice is caused to the person complaining of the breach of natural justice where such person does not dispute the case against him or it. This can happen by reason of estoppel, acquiescence, waiver and by way of non-challenge or non-denial or admission of facts, in cases in which the Court finds on facts that no real prejudice can therefore be said to have been caused to the person complaining of the breach of natural justice.
(4) In cases where facts can be stated to be admitted or indisputable, and only one conclusion is possible, the Court does not pass futile orders of setting aside or remand when there is, in fact, no prejudice caused. This conclusion must be drawn by the Court on an appraisal of the facts of a case, and not by the authority who denies natural justice to a person.
(5) The "prejudice" exception must be more than a mere apprehension or even a reasonable suspicion of a litigant. It should exist as a matter of fact, or be based upon a definite
CM Nos.2398 and 2399 of 2020
inference of likelihood of prejudice flowing from the non- observance of natural justice.
20) Applying the aforesaid principles to the instant case, it is
abundantly clear that the impugned bill has resulted in serious breach of
audi alteram partem rule in its entirety. The petitioners have been
condemned unheard and the impugned order has visited them with serious
civil consequences. Had the respondents put the petitioners on notice and
supplied them all the material relied upon for drawing the bill impugned,
the petitioners would have got an opportunity to explain, rebut or
contradict the same. A serious prejudice has been caused to the petitioners
by denying them an opportunity of being heard and by passing an ex-parte
order. As is apparent from reading of the averments made in the writ
petition, the petitioners have set up a fairly probable case in their defense
but have been disabled to put it up before the respondents because of
unilateral and behind the back action of the respondents. I have, therefore,
no doubt in my mind that in the instant case by not complying with the
audi alterlam partem rule, the respondents have caused serious prejudice
to the petitioners and have acted in a manner, which is unfair and arbitrary
and, therefore, violative of Article 14 of the Constitution.
21) In the instant case, the petitioners have been held liable to a huge
amount running into lakhs and they are not even aware of the basis
therefor. Plea of the respondents that there is an alternative remedy
available under the Act would pale in insignificance. It is now well settled
that if an order is in flagrant violation of principles of natural justice, the
same is amenable to challenge under Article 226 of the Constitution of
CM Nos.2398 and 2399 of 2020
India, availability of equally efficacious statutory remedy
notwithstanding. Reference in this regard is invited to para 15 of the
judgment of the Supreme Court in the case of Whirlpool Corporation
vs. Registrar Of Trade Marks, Mumbai & Ors.(1998) 8 SCC 1, which,
for facility of reference, is reproduced as under:
"Under Article 226 of the Constitution, the High Court, having regard to the facts of the case, has a discretion to entertain or not to entertain a writ petition. But the High Court has imposed upon itself certain restrictions one of which is that if an effective and efficacious remedy is available, the High Court would not normally exercise its jurisdiction. But the alternative remedy has been consistently held by this Court not to operate as a bar in at least three contingencies, namely, where the writ petition has been filed for the enforcement of any of the Fundamental Rights or where there has been a violation of the principle of natural justice or where the order or proceedings are wholly without jurisdiction or the vires of an Act is challenged. There is a plethora of case law on this point but to cut down this circle of forensic whirlpool, we would rely on some old decisions of the evolutionary era of the constitutional law as they still hold the field."
22) It is, thus, trite that normally where a statute itself prescribes a
remedy, resort must be had to that particular statutory remedy before
invoking the extraordinary writ jurisdiction of the High Court and the
High Court while exercising its writ jurisdiction under Article 226 of the
Constitution may decline to grant relief in the writ petition until such
CM Nos.2398 and 2399 of 2020
statutory remedy is exhausted. This rule of exhaustion of statutory remedy
is, however, a rule of policy, convenience and discretion and not a rule of
law nor does it bar jurisdiction of the High Court in granting relief in an
appropriate case and in exceptional circumstances. Violation of principles
of natural justice is one such appropriate case where exception is to be
taken to the general rule. This is what has been put succinctly by the
Supreme Court in Whirlpool Corporation (supra).
23) In the given facts and circumstances where the petitioners have
been slapped with a huge electricity bill running into lakhs without even
giving them an opportunity of being heard, relegating the petitioners to
the alternative remedy available under the Act would be a travesty of
justice.
24) Equally ill founded is the argument of learned counsel for the
petitioners that the respondents have not adhered to the provisions of
Section 126 of the Electricity Act for making assessment.
25) From a bare reading of Section 126 of the Act, it clearly transpires
that the Section applies to a case where a consumer is found to have
indulged in unauthorized use of electricity. In the instant case there is no
allegation of unauthorized use of electricity or theft of electricity supply
by the petitioners for which they need to be assessed under Section 126 of
the Act.
26) For the foregoing reasons, I find merit in this petition and,
accordingly, the same is allowed. The impugned bill in so far it pertains to
the demand of Rs.17,00,556.00, is quashed. The petitioners shall,
CM Nos.2398 and 2399 of 2020
however, deposit the monthly bill for the month of January, 2020, as also
for the subsequent months within a period of one month without any fail.
27) Notwithstanding that this Court has quashed the impugned bill to
the extent aforesaid, the respondents shall be free to proceed in the matter
for recovery of excess load charges, if any, after providing an adequate
opportunity of being heard to the petitioners and to present their case
before the respondents. Needless to say that providing of adequate
opportunity to the petitioners would mean supplying them all the requisite
documents including inspection report and the basis of applying the
multiplying factor of (3) to the case of the petitioners and then passing a
speaking order after taking into consideration the reply, if any, submitted
by the petitioners.
(Sanjeev Kumar) Judge Jammu 16.06.2021 "Bhat Altaf, PS"
Whether the order is speaking: Yes
Whether the order is reportable: Yes
Judgment pronounced today on 16.06.2021 in terms of Rules 138 (3) of
the Jammu and Kashmir High Court Rules, 1999.
(Javed Iqbal Wani) Judge
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!