Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Shalimar Constructions vs Skuat (K) Shalimar
2021 Latest Caselaw 916 j&K/2

Citation : 2021 Latest Caselaw 916 j&K/2
Judgement Date : 17 August, 2021

Jammu & Kashmir High Court - Srinagar Bench
M/S Shalimar Constructions vs Skuat (K) Shalimar on 17 August, 2021
      HIGH COURT OF JAMMU & KASHMIR AND LADAKH
                     AT SRINAGAR

                         WP(C) No. 693/2021 c/w
                          WP(C) No. 694/2021
                                                    Reserved On: 13th of August, 2021.
                                                  Pronounced On: 17th of August, 2021.
(i.) WP(C) No. 693/2021; CM No. 2048/2021:

M/S Shalimar Constructions
                                                                 ... Petitioner(s)
                                Through:
                      Mr M. A. Qayoom, Advocate with
                       Mr Mian Muzaffar, Advocate.

                                   Versus

SKUAT (K) Shalimar, Srinagar & Ors.
                                                               ... Respondent(s)

Through: -

Mr M. Y. Bhat, Senior Advocate with Mr R. A. Bhat, Advocate for R-1 to 9; and Mr N. A. Ronga, Advocate for R-10 to 13.

(ii) WP(C) No. 694/2021; 2049/2021:

M/S Fayaz Ahmad Bhat ... Petitioner(s) Through:

Mr M. A. Qayoom, Advocate with Mr Mian Muzaffar, Advocate.

Versus

SKUAT (K) Shalimar, Srinagar & Ors.

... Respondent(s) Through: -

Mr M. Y. Bhat, Senior Advocate with Mr R. A. Bhat, Advocate for R-1 to 9; and Mr N. A. Ronga, Advocate for R-10 to 13.

CORAM:

Hon'ble Mr Justice Ali Mohammad Magrey, Judge.

(JUDGMENT)

01. Both these Petitions involve similar questions of facts and the

law and are, thus, for the sake of convenience, decided by this common

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

Judgment. For purpose of reference, the facts of WP(C) No. 693/2021 are

relied upon.

02. The case of the Petitioner is that it had submitted the tender

documents for the works with respect to which tenders were invited by the

official Respondents in terms of E-Tender notices dated 28th of November,

2020; 8th of December, 2020; and 19th of December, 2020, strictly in

accordance with the terms and conditions of the tender notices. Thereafter, the

official Respondents, as stated, entertained the tender documents of the

Petitioner-firm and, after opening of the tender documents, found the

Petitioner-firm to be the lowest bidder. However, instead of issuing allotment

orders in favour of the Petitioner-firm, the official Respondents, in terms of

communications/ notices dated 21st of January, 2021, informed the Petitioner-

firm that before allotment order is issued in its favour, it is required to deposit

additional security at 5% and 4% of the advertised cost in the shape of

CDR/FDR/BG pledged to the Assistant Controller, Estates, as per the terms

and conditions of E-NIT under reference. The aforesaid notices dated 21st of

January, 2021 are stated to have followed by letter dated 5th of February, 2021,

wherein the official Respondents informed the Petitioner-firm that in addition

to 10% bill deposit, 20% more bill deposit shall be deducted from every

running bill and that the Petitioner-firm should deposit 5% additional security

deposit as per NIT. The Petitioner-firm is also claimed to have been asked to

file an Affidavit for completion of the project including all low rate items

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

without deviation and not to request for bill deposit till completion of the

work. The Petitioner-firm was also told that the project needs to be completed

as per allotted time period and that in case of delay, 1% penalty per month

shall be imposed. Besides, it was also told that labour management plan is to

be maintained by the construction agency. The aforesaid letter dated 5 th of

February, 2021 was replied by the Petitioner-firm on 17th of February, 2021,

wherein the Petitioner-firm stated that routine bill deposit of 10% was a norm

and acceptable to it, but, the additional bill deposit of 20% amounted to direct

violation of NIT and PWD Code of Works, thus not acceptable to the

Petitioner-firm. The Petitioner-firm also stated that the additional bill security

of 5% was not acceptable to it because as per the NIT, the Petitioner-firm had

not to deposit the additional bill security of 5% and, instead, it was 5% for

work at serial No. 1 and 4% for works at serial Nos. 2, 3 and 4. The Petitioner-

firm is also stated to have referred to various circulars on the subject issued

by the Government, wherein it has been circulated that the Contractors should

not be asked for additional bill security for abnormally low bids. This reply

submitted by the Petitioner-firm on 17th of February, 2021, however, was not

considered by the official Respondents and, instead, the Works Committee of

the SKAUST-K, Shalimar, Srinagar, in its meeting held on 24th of February,

2021, decided to put the works to fresh tender on various terms and conditions.

Accordingly, fresh tenders were issued on 27th of February, 2021 and 16th of

March, 2021. It is pleaded that since the official Respondents decided to put

the works to fresh tender in respect of which the Petitioner-firm was found to

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

be the lowest tenderer and proceeded to issue the fresh tender notices on 27th

of February, 2021 and 16th of March, 2021, therefore, not only the decisions

dated 2nd of February, 2021 and 24th of February, 2021, but also the fresh E-

Tender notices issued on 27th of February, 2021 and 16th of March, 2021, as

well as any decision taken thereafter towards the allotment of works to

Respondents 10 to 13, have caused great prejudice to the rights and interests

of the Petitioner-firm, constraining it to file the instant Petition.

03. Objections stand filed on behalf of Respondents 1 to 9. It is stated

that since the Petitioner-firm did not accept/comply all the conditions as

reflected in letter No. Au/Estates/2020-21/2093-94 and letter No.

Au/Estates/2021-21/209-96, both dated 5th of February, 2021, and taking into

consideration the fact that the execution of the Projects once allowed on very

low/unworkable offered rates (in finishing items) of the lowest bidders will

leave the Projects incomplete resulting in non-achievement of set targets and

would entail disputes and litigation causing severe loss to public exchequer,

the Works Committee of the University met again on 24th of February, 2021,

wherein the Estates Officer (Member Secretary) apprised the members of the

Works Committee that the recommendations of previous meeting held on 2nd

of February, 2021 on the issue of unreasonable rates, as decided and recorded

in the minutes of meeting, were conveyed to the lowest tenderers/contractors

viz. M/s Shalimar Constructions/ Petitioner in WP(C) No. 693/2021; and M/s

Fayaz Ahmad/ Petitioner in WP(C) No. 694/2021, but they have declined to

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

accept the additional terms and conditions vide their response dated 17th of

February, 2021 and 7th of February, 2021, respectively. It is pleaded that

during the course of proceedings, it was realized that the lowest bidders are,

thus consuming precious time of the University, resultantly, the Committee

felt it necessary that expeditious steps are taken to ensure execution of above

referred works during the current financial year so that funds may not get

lapsed unreasonably. It was, as stated, after thorough deliberations on the

matter that some decisions were unanimously agreed upon, which decisions

of the Works Committee were conveyed to the Petitioners, but they did not

agree to the same, thus forcing the Works Committee to decide for

cancellation of the NITs referred to above in the interest of public exchequer

in general and the University in particular. It is contended that the Works

Committee, in these circumstances, recommended re-tendering of all the

concerned works, which recommendations were duly approved by the

Competent Authority as per norms. The re-tendering notices are, accordingly,

stated to have been issued. In this factual discourse, the Respondents 1 to 9

have urged that they not only had justifiable, but compelling reasons to cancel

the earlier tendering process and re-tender the works, therefore, no

interference is warranted in the said process from this Court.

04. The Respondents 10 to 13 have adopted the Objections filed on

behalf of the Respondents 1 to 9.

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

05. Mr M. A. Qayoom, the learned Counsel, representing the

Petitioner in both the Petitions, while reiterating the claim made in the Writ

Petitions in support of the pleadings, submitted that immediately after the

Respondents 1 to 9 issued fresh tender notices dated 27th of February, 2021

and 16th of March, 2021, the Petitioner-firms filed suit for Declaration and

Injunction before the Court of learned Principal District Judge, Srinagar, for

declaring those tender notices null and void, besides seeking a direction not

to allot the work to any person other than the Plaintiffs/ Petitioners herein. It

is pleaded that the Civil Court entertained the suits and, besides issuing

summons/notices in the main suit as well as in the application for grant of

interim relief, it directed the Respondents to produce the scanned copies of

the record relating to the tender notices before the Court on 18 th of March,

2021, whereafter, the Respondents caused their appearance in the Court, but

did not produce the record relating to the tender notices before the Court,

which prompted the Petitioner-firms to file a Contempt Petition before the

Court, however, while the matter was pending consideration before the Court,

the official Respondents opened the tender documents on 30th of March, 2021

and, after finding the Respondents 10 to 13 as L1, they decided to allot the

work to them. It is averred that the non-compliance of the order of the Court

and the opening of the tender documents during the pendency of the

proceedings before the Court, in itself, makes it axiomatic as to how the

official Respondents have arbitrarily and capriciously dealt with the matter

and, in order to defeat the claim of the Petitioner-firms and with a view to give

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

undue benefit to Respondents 10 to 13, they, firstly, took decision dated 2nd of

February, 2021 and, thereafter, in terms of decision dated 24th of February,

2021, cancelled the previous bids and issued fresh tender notices. The

impugned decisions dated 2nd of February, 2021 and 24th of February, 2021 as

well as the subsequently issued fresh tender notices, as per the learned

Counsel, are, thus violative of all the safeguards enshrined in Articles 14 and

21 of the Constitution of India, as such, liable to be set aside.

06. Learned counsel for the Petitioner-Firms further submitted that

otherwise also the decision taken by the official Respondents on 2nd of

February, 2021 is contrary to NITs issued for the execution of works on 28th

of November, 2020; 8th of December, 2020; and 29th of December, 2020. It is

argued that this aspect of the matter had also been highlighted by the

Petitioner-firms in their reply, wherein attention of the official Respondents

had also been invited to different circulars and orders occupying the field,

however, without considering the said reply so submitted by the Petitioner-

firms, the official Respondents, in the meeting held on 24th of February, 2021,

decided to issue fresh tender notices. In that view of the matter, the learned

Counsel pleads that not only the said decision dated 24th of February, 2021,

but also the fresh tender notices are arbitrary in nature, aimed at defeating the

claim of the Petitioner-firms, therefore, liable to be set at naught.

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

07. It is next contended by the learned Counsel for the Petitioner-

firms that after the Petitioner-firms were found as L1 for the works advertised

by the official Respondents in terms of tender notices dated 28th of November,

2020; 8th of December, 2020; and 29th of December, 2020, the Petitioner-firms

had a legitimate expectation of allotment of work in their favour and that this

fact was the relevant factor requiring due consideration in a fair decision

making process, however, the official Respondents have failed to give due

weightage to it, rendering the decision arbitrary and liable to be set aside.

08. Mr Qayoom further proceeded to contend that before taking the

decisions dated 2nd of February, 2021 and 24th of February, 2021, as also

before issuing the fresh tender notices, the official Respondents were obliged

in law to provide an opportunity of being heard to the Petitioner-firms so that

they could explain their position in tune with their reply dated 17th of

February, 2021, more particularly when they were found as L1 in the earlier

tendering process, however, no opportunity of being heard was provided to

the Petitioner-firms to explain their position nor were they given any reason(s)

for not considering the reply so submitted by the Petitioner-firms before

taking the impugned decisions and/or issuing the fresh tender notices. The

impugned decisions dated 2nd of February, 2021 and 24th of February, 2021,

coupled with the fresh tender notices, as per the learned Counsel, are, thus

violative of principles of natural justice, equity and fair play, as such, liable to

be set aside.

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

09. The next contention of Mr Qayoom is that the decision taken by

the official Respondents on 24th of February, 2021 in putting the works to

fresh tenders is not only arbitrary, but also smacks of bias as well inasmuch

the Respondents 1 to 9, in order to accommodate Respondents 10 to 13, have

altered the terms and conditions of the tender notices dated 28th of November,

2020; 8th of December, 2020; and 29th of December, 2020 and have waived

almost all the terms and conditions to favour Respondents 10 to 13.

10. It was also argued by the learned Counsel representing the

Petitioner-firms that the official Respondents, by accepting the bid of

Respondents 10 to 13, have caused a loss of Rs. 92,75,097.67 to the public

exchequer, which aspect of the matter also throws considerable light on the

arbitrary and malafide attitude adopted by the Respondents 1 to 9 in taking

decisions dated 2nd of February, 2021 and 24th of February, 2021 as well as

issuing fresh tender notices, thereby rendering the entire process non-est in

the eyes of law.

11. Per Contra, Mr M. Y. Bhat, the learned Senior Counsel,

appearing for Respondents 1 to 9, submitted that no cause of action has

accrued to the Petitioner-firms in filing the Writ Petitions inasmuch as none

of their rights stands violated by the action of the official Respondents. It is

submitted that merely submitting the lowest tender does not vest the bidder

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

with any right to get the allotment of work and that once the Petitioner-firms

themselves refused to accept the terms and conditions of the contract,

therefore, no claim can be made by them regarding the allotment of works in

their favour. It is pleaded that the Petitioner-firms cannot force the official

Respondents to make allotment on their own terms and conditions and as per

their own whims and caprice. The learned Senior Counsel argued that the

tenderer has the right to cancel the process or even allot the contract to some

other person as the choice of entering into a contract is a subjective choice,

based on variety of aspects. It is contended that the contract between the

parties was not concluded in absence of agreement of the Petitioner-Firms qua

fulfilling all the terms and conditions of the contract. In support of his

arguments, Mr Bhat has referred to and relied upon the law laid down by the

Hon'ble Supreme Court in a recent Judgment rendered in case titled 'M/s

Padia Timber Company (P) Ltd. v. The Board of Trustees of

Vishakhapatnam Port Trust: AIR 2021 SC 341'.

12. Mr N. A. Ronga, the learned Counsel representing the

Respondents 10 to 13, has adopted the arguments advanced by Mr Bhat,

learned Senior Counsel appearing for Respondents 1 to 9.

13. In rebuttal, Mr Qayoom vociferously made an endeavour to

convince the Court that the decision of altering the conditions of contract, as

reflected in the minutes of the meeting of the Works Committee held on 2nd

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

of February, 2021, was not approved by the Vice-Chancellor, SKUAST in

respect of item No.1 regarding deduction of 20% more bill deposit from every

running bill, 5% additional security deposit as per NIT and 1% penalty per

month beyond the allotted time period. To support this argument, Mr Qayoom

has invited the attention of the Court to the observations of the Vice Chairman,

SKUAST on the minutes of the meeting of the Works Committee held on 2nd

of February, 2021 and submitted that, instead of complying with the

observations of the Vice Chancellor, the official Respondents issued

communication to the Petitioner-firms asking them to adhere to the additional

conditions as incorporated in letter dated 5th of February, 2021. It is further

submitted that this communication was replied by the Petitioner-firms

disagreeing to accept the condition of additional bill deposit being in direct

violation of the terms and conditions of the NIT, however, the Petitioner-

firms, notwithstanding such objection, agreed to 5% additional security

deposit, besides completing the work within the stipulated period of time and

not asking for payments till completion of work, but despite that, the official

Respondents rejected the claim of the Petitioner-firms and decided to put the

works to fresh tendering. Mr Qayoom pleaded that this decision of the official

Respondents was malafide in nature, aimed at ensuring rejection of the

completed contract in favour of the Petitioner-firms and for awarding undue

benefit to the Respondents 10 to 13, thereby rendering the entire action of the

official Respondents in violation of the law laid down by the Hon'ble Supreme

Court in various judicial pronouncements. In this behalf the learned Counsel

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

has referred to and relied upon Paragraphs 8 to 10 of the Judgment rendered

by the Apex Court in case titled 'Maa Binda Express Carrier & Anr v.

Northeast Frontier Railway & Ors: AIR 2014 Supreme Court 390'. It is also

urged that the official Respondents have not, at all, included those conditions

in the fresh tender notices which were additionally imposed on the Petitioner-

firms after completing the contract. It is pleaded that the contract between the

parties was completed upon issuance of communication dated 21st of January,

2021 by the official Respondents in view of mandate of Sections 4 and 5 of

the Contract Act, 1872 inasmuch as all the conditions of the tender notices

were adhered to by the Petitioner-firms and that the subsequent conditions

cannot render the completed contract void. In this behalf, reliance in placed

on the law laid down by the Supreme Court at Paragraph No. 15 of the

Judgment rendered in case titled 'Jawahar Lal Barman v. the Union of

India: AIR 1962 Supreme Court 378'.

14. As regards the Judgment cited by Mr Bhat, the learned Senior

Counsel representing the official Respondents, i.e., AIR 2021 SC 342, Mr

Qayoom submitted that same is distinguishable, having been passed on

different set of facts, as such, not applicable to the instant case.

15. Heard the learned counsel for the parties, perused the pleadings

on record and considered the matter. I have also gone through the relevant

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

records made available by the learned Senior Counsel representing the official

Respondents.

16. Admittedly, the Petitioner-firms emerged as L1 in the earlier

tendering process flouted by the official Respondents for the works in

question, however, the Works Committee, in its meeting held on 2nd of

February, 2021, after observing that the rates quoted by the lowest tenderers

regarding several items were unreasonable as per the BoQ and in order to

safeguard the projects, recommended incorporation of certain additional

conditions like more bill deposit, additional security deposit, Affidavit from

the Contractor concerned, penalty on delay per month, etcetera, prior to

issuance of the final allotment order(s) in favour of the lowest bidders. This

incorporation of additional conditions on part of the official Respondents did

not find favour with the Petitioner-firms, who did not accept the same on the

ground that these are in direct conflict with the tender notices. It was on the

basis of such position that the Works Committee, in its meeting held on 24th

of February, 2021, while observing that the lowest bidders are consuming time

and that expeditious steps are required to be taken by the University to ensure

execution of works in question during the current financial year,

recommended cancellation of the earlier tendering process and initiation of

fresh one. Given this position, the question that arises for consideration is

whether the action of the official Respondents in cancelling the earlier

tendering process and putting the works in question to fresh tenders can be

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

said to be irrational or arbitrary in nature. In this behalf, what requires to be

stated is that as per settled legal position, the tender issuing authority, i.e., the

University herein this case, is the best judge of its interests/ needs and that it

is always open to the said authority to suitably modify or change the eligibility

criteria so as to best serve its purposes. Whenever a change is introduced in

the eligibility criteria, either by introducing some new condition(s) or

restricting or altogether doing away with certain previous concessions, it

might hurt the interests of someone or the other, but, for that reason, the

change(s) made in the eligibility criteria cannot be labelled as malafide or

arbitrary. The Works Committee, after examining that the cost offer of all the

respective lowest bidders for the works were unreasonable in several items as

per the BoQ and in order to safeguard its interests, decided to incorporate

certain additional conditions prior to issuance of the allotment order(s) in

favour of the lowest bidders which conditions were not accepted by the lowest

bidders/ Petitioner-firms, thereby constraining the official Respondents to

cancel the earlier tendering process and initiate the process afresh. In such

circumstances, the official Respondents can hardly be faulted for protecting

itself against entering into such a contract with the Petitioner-firms.

17. Besides, the Courts are expected to exercise judicial restraint in

interfering with the administrative action, particularly in the matter of tender

or contract. Ordinarily, the soundness of the decision taken by the tender

issuing authority ought not to be questioned, but the decision-making process

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

can certainly be subject to judicial review. The soundness of the decision may

be questioned, firstly, if the decision made is so arbitrary and irrational that

the Court can say that the decision is such that no responsible authority acting

reasonably and in accordance with relevant law could have reached or;

second, if the process adopted or decision made by the authority is malafide

or intended to favour someone or; third, if the public interest is affected. In

the case on hand, when the Petitioner-firms did not accept all the terms and

conditions prescribed by the official Respondents prior to issuance of final

allotment order(s) in their favour, in such eventuality, the decision of the

official Respondents in cancelling the earlier tendering process and putting

the works to fresh tender cannot be said to be one where they have acted in a

manner in which no responsible authority acting reasonably and in accordance

with the relevant law would have acted. Furthermore, a bare perusal of the

pleadings on record, does not indicate that the decision made by the authority

is malafide or intended to favour someone. In fact, the decision of the official

Respondents was the result of non-acceptance of all the terms and conditions

of the contract on part of the Petitioner-firms. Likewise, the third ground of

public interest is also not affected in the present case because while it may be

in public interest to have greater competition, it is also in public interest that

all the tender conditions are complied with as prescribed by the tender issuing

authority and that there is no uncertainty in that area.

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

18. Law on the subject of scope of judicial review in the matters of

Contract is no more res integra.

19. In case titled 'Tata Cellular V. Union of India: (1994) 6

Supreme Court Cases 651', at Paragraph No.94, Hon'ble the Supreme Court

of the country, while dealing with the issue similar to the one subject matter

of the instant Petitions, evolved the following principles:

1. "The modern trend points to judicial restraint in administrative action;

2. The Court does not sit as a court of appeal but merely reviews the manner in which the decision was made;

3. The Court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expe4rtise which itself may be fallible;

4. The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts;

5. The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides; and

6. Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure."

20. In case titled 'Sterling Computers Limited V. M&N

Publications Ltd: (1993) 1 SCC 445', the Apex Court, at Paragraph No.12,

has laid down as under:

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

"In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognized by courts while dealing with public property. It is not possible for courts to question and adjudicate every decision taken by an authority, because many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of 'play in the joints' to the executive."

21. Again, the Apex Court, in case titled 'Directorate of Education

& Ors. V. Educomp Datamatics Ltd. And Ors: (2004) 4 SCC 19', while

applying the principles enunciated in Tata Cellular's case (supra), at

Paragraph No.12, observed, thus:

"12. It has been held in these decisions that the terms of the invitation to tender are not open to judicial scrutiny, the same being in the realm of contract. That the Government must have a free hand in setting the terms of the tender. It must have reasonable play in its joints as a necessary concomitant for an administrative body in an administrative sphere. The Courts would interfere with the administrative policy decision only if it is arbitrary, discriminatory, malafide or actuated by bias. It is entitled to pragmatic adjustments which may be called for by the particular circumstances. The Courts cannot strike down the terms of the tender prescribed by the Government because it feels that some other terms in the tender would have been fair, wise or logical. The Courts can interfere only if the policy decision is arbitrary, discretionary or malafide."

On an appreciation of the law laid down above, what comes to

limelight is that the modern trend points to judicial restraint in administrative

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

action and that the Court does not sit as a 'Court of Appeal', but merely

reviews the manner in which the decision was made. It has also been declared

that Court does not have the expertise to correct the administrative decision

and that if a review of the administrative decision is permitted, it will be

substituting its own decision, without the necessary expertise which itself may

be fallible. Furthermore, fair play in the joints is a necessary concomitant for

an administrative body functioning in an administrative sphere or quasi-

administrative sphere and quashing administrative decisions may impose

heavy administrative burden on the administration and lead to increased and

unbudgeted expenditure.

22. It is, thus settled that public authorities must be left with the same

liberty as they have in framing the policies, even while entering into contracts

because many contracts amount to implementation or projection of policies of

the Government. But it cannot be overlooked that unlike policies, contracts

are legally binding commitments and they commit the authority which may

be held to be a State within the meaning of Article 12 of the Constitution of

India in many cases for years. It is for this reason that the Courts have

impressed that even in contractual matters the public authority should not have

unfettered discretion. In contracts having commercial element, some more

discretion has to be conceded to the authorities so that they may enter into

contracts with persons keeping an eye on the augmentation of the revenue.

But, even in such matters, they have to follow the norms recognized by Courts

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

while dealing with public property. It is not possible for the Courts to question

and adjudicate every decision taken by an authority because many of the

Government Undertakings, which in due course have acquired the monopolist

position in matters of sale and purchase of products and with so many ventures

in hand, they can come out with a plea that it is not always possible to act like

a quasi-judicial authority while awarding contracts. Under some special

circumstances, a discretion has to be conceded to the authorities who have to

enter into contract by giving them liberty to assess the overall situation for

purpose of taking a decision as to whom the contract be awarded and at what

terms. If the decisions have been taken in bonafide manner, although not

strictly following the norms laid down by the Courts, such decisions are

upheld on the principle laid down by Justice Holmes that Courts, while

judging the constitutional validity of executive decisions, must grant certain

measure of freedom of 'play in the joints' to the executive.

Looking at the instant case in the above perspective, the

Petitioner-firms have not been able to establish before the Court that the

decision taken by the official Respondents in cancelling the earlier tendering

process and putting the works in question to fresh tenders is an arbitrary

exercise of power or that the same was/ is malafide in nature. In 'Jagdish

Mandal v. State of Orissa: (2007) 14 SCC 517', at Paragraph No.22, the

Hon'ble Supreme Court held, thus:

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

"22. .... Therefore, a Court before interfering in tender or contractual matters in exercise of power of judicial review, should pose to itself the following questions:

(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone;

OR

Whether the process adopted or decision made is so arbitrary and irrational that the court can say: "the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached";

(ii) Whether public interest is affected.

If the answers are in the negative, there should be no interference under Article 226."

From a bare perusal of the pleadings placed on record as well as

after going through the relevant records placed before the Court by the official

Respondents, it is more than apparent that the decision taken by the official

Respondents in cancelling the earlier tendering process and putting the works

in question to fresh tenders was certainly not irrational in any manner

whatsoever or intended to favour anyone. This decision, apart from being

lawful and sound, appears to have been taken by the official Respondents in

view of non-acceptance of all the terms and conditions of contract on part of

the lowest bidders/ Petitioner-firms.

23. For all that has been said and done hereinabove, I do not find any

merit in both these Petitions. These entail dismissal and are, accordingly,

dismissed. Interim directions, if any, subsisting as on date, shall stand vacated.

WP(C) No. 693/2021 c/w WP(C) No. 694/2021

24. Pending miscellaneous applications, if any, shall also stand

disposed of, accordingly.

25. No order as to costs.

26. Registry to place a copy of this Judgment on each file.

27. The relevant record as produced by Mr Bhat, the learned Senior

Counsel representing the official Respondents, is returned to him in the open

Court.

(Ali Mohammad Magrey) Judge SRINAGAR August 17th, 2021 "TAHIR"

                               i.    Whether the Judgment is reportable?           Yes/ No.
                               ii.   Whether the Judgment is speaking?             Yes/ No.




TAHIR MANZOOR BHAT
2021.08.17 11:38
I attest to the accuracy and
integrity of this document
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter