Citation : 2021 Latest Caselaw 916 j&K/2
Judgement Date : 17 August, 2021
HIGH COURT OF JAMMU & KASHMIR AND LADAKH
AT SRINAGAR
WP(C) No. 693/2021 c/w
WP(C) No. 694/2021
Reserved On: 13th of August, 2021.
Pronounced On: 17th of August, 2021.
(i.) WP(C) No. 693/2021; CM No. 2048/2021:
M/S Shalimar Constructions
... Petitioner(s)
Through:
Mr M. A. Qayoom, Advocate with
Mr Mian Muzaffar, Advocate.
Versus
SKUAT (K) Shalimar, Srinagar & Ors.
... Respondent(s)
Through: -
Mr M. Y. Bhat, Senior Advocate with Mr R. A. Bhat, Advocate for R-1 to 9; and Mr N. A. Ronga, Advocate for R-10 to 13.
(ii) WP(C) No. 694/2021; 2049/2021:
M/S Fayaz Ahmad Bhat ... Petitioner(s) Through:
Mr M. A. Qayoom, Advocate with Mr Mian Muzaffar, Advocate.
Versus
SKUAT (K) Shalimar, Srinagar & Ors.
... Respondent(s) Through: -
Mr M. Y. Bhat, Senior Advocate with Mr R. A. Bhat, Advocate for R-1 to 9; and Mr N. A. Ronga, Advocate for R-10 to 13.
CORAM:
Hon'ble Mr Justice Ali Mohammad Magrey, Judge.
(JUDGMENT)
01. Both these Petitions involve similar questions of facts and the
law and are, thus, for the sake of convenience, decided by this common
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
Judgment. For purpose of reference, the facts of WP(C) No. 693/2021 are
relied upon.
02. The case of the Petitioner is that it had submitted the tender
documents for the works with respect to which tenders were invited by the
official Respondents in terms of E-Tender notices dated 28th of November,
2020; 8th of December, 2020; and 19th of December, 2020, strictly in
accordance with the terms and conditions of the tender notices. Thereafter, the
official Respondents, as stated, entertained the tender documents of the
Petitioner-firm and, after opening of the tender documents, found the
Petitioner-firm to be the lowest bidder. However, instead of issuing allotment
orders in favour of the Petitioner-firm, the official Respondents, in terms of
communications/ notices dated 21st of January, 2021, informed the Petitioner-
firm that before allotment order is issued in its favour, it is required to deposit
additional security at 5% and 4% of the advertised cost in the shape of
CDR/FDR/BG pledged to the Assistant Controller, Estates, as per the terms
and conditions of E-NIT under reference. The aforesaid notices dated 21st of
January, 2021 are stated to have followed by letter dated 5th of February, 2021,
wherein the official Respondents informed the Petitioner-firm that in addition
to 10% bill deposit, 20% more bill deposit shall be deducted from every
running bill and that the Petitioner-firm should deposit 5% additional security
deposit as per NIT. The Petitioner-firm is also claimed to have been asked to
file an Affidavit for completion of the project including all low rate items
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
without deviation and not to request for bill deposit till completion of the
work. The Petitioner-firm was also told that the project needs to be completed
as per allotted time period and that in case of delay, 1% penalty per month
shall be imposed. Besides, it was also told that labour management plan is to
be maintained by the construction agency. The aforesaid letter dated 5 th of
February, 2021 was replied by the Petitioner-firm on 17th of February, 2021,
wherein the Petitioner-firm stated that routine bill deposit of 10% was a norm
and acceptable to it, but, the additional bill deposit of 20% amounted to direct
violation of NIT and PWD Code of Works, thus not acceptable to the
Petitioner-firm. The Petitioner-firm also stated that the additional bill security
of 5% was not acceptable to it because as per the NIT, the Petitioner-firm had
not to deposit the additional bill security of 5% and, instead, it was 5% for
work at serial No. 1 and 4% for works at serial Nos. 2, 3 and 4. The Petitioner-
firm is also stated to have referred to various circulars on the subject issued
by the Government, wherein it has been circulated that the Contractors should
not be asked for additional bill security for abnormally low bids. This reply
submitted by the Petitioner-firm on 17th of February, 2021, however, was not
considered by the official Respondents and, instead, the Works Committee of
the SKAUST-K, Shalimar, Srinagar, in its meeting held on 24th of February,
2021, decided to put the works to fresh tender on various terms and conditions.
Accordingly, fresh tenders were issued on 27th of February, 2021 and 16th of
March, 2021. It is pleaded that since the official Respondents decided to put
the works to fresh tender in respect of which the Petitioner-firm was found to
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
be the lowest tenderer and proceeded to issue the fresh tender notices on 27th
of February, 2021 and 16th of March, 2021, therefore, not only the decisions
dated 2nd of February, 2021 and 24th of February, 2021, but also the fresh E-
Tender notices issued on 27th of February, 2021 and 16th of March, 2021, as
well as any decision taken thereafter towards the allotment of works to
Respondents 10 to 13, have caused great prejudice to the rights and interests
of the Petitioner-firm, constraining it to file the instant Petition.
03. Objections stand filed on behalf of Respondents 1 to 9. It is stated
that since the Petitioner-firm did not accept/comply all the conditions as
reflected in letter No. Au/Estates/2020-21/2093-94 and letter No.
Au/Estates/2021-21/209-96, both dated 5th of February, 2021, and taking into
consideration the fact that the execution of the Projects once allowed on very
low/unworkable offered rates (in finishing items) of the lowest bidders will
leave the Projects incomplete resulting in non-achievement of set targets and
would entail disputes and litigation causing severe loss to public exchequer,
the Works Committee of the University met again on 24th of February, 2021,
wherein the Estates Officer (Member Secretary) apprised the members of the
Works Committee that the recommendations of previous meeting held on 2nd
of February, 2021 on the issue of unreasonable rates, as decided and recorded
in the minutes of meeting, were conveyed to the lowest tenderers/contractors
viz. M/s Shalimar Constructions/ Petitioner in WP(C) No. 693/2021; and M/s
Fayaz Ahmad/ Petitioner in WP(C) No. 694/2021, but they have declined to
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
accept the additional terms and conditions vide their response dated 17th of
February, 2021 and 7th of February, 2021, respectively. It is pleaded that
during the course of proceedings, it was realized that the lowest bidders are,
thus consuming precious time of the University, resultantly, the Committee
felt it necessary that expeditious steps are taken to ensure execution of above
referred works during the current financial year so that funds may not get
lapsed unreasonably. It was, as stated, after thorough deliberations on the
matter that some decisions were unanimously agreed upon, which decisions
of the Works Committee were conveyed to the Petitioners, but they did not
agree to the same, thus forcing the Works Committee to decide for
cancellation of the NITs referred to above in the interest of public exchequer
in general and the University in particular. It is contended that the Works
Committee, in these circumstances, recommended re-tendering of all the
concerned works, which recommendations were duly approved by the
Competent Authority as per norms. The re-tendering notices are, accordingly,
stated to have been issued. In this factual discourse, the Respondents 1 to 9
have urged that they not only had justifiable, but compelling reasons to cancel
the earlier tendering process and re-tender the works, therefore, no
interference is warranted in the said process from this Court.
04. The Respondents 10 to 13 have adopted the Objections filed on
behalf of the Respondents 1 to 9.
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
05. Mr M. A. Qayoom, the learned Counsel, representing the
Petitioner in both the Petitions, while reiterating the claim made in the Writ
Petitions in support of the pleadings, submitted that immediately after the
Respondents 1 to 9 issued fresh tender notices dated 27th of February, 2021
and 16th of March, 2021, the Petitioner-firms filed suit for Declaration and
Injunction before the Court of learned Principal District Judge, Srinagar, for
declaring those tender notices null and void, besides seeking a direction not
to allot the work to any person other than the Plaintiffs/ Petitioners herein. It
is pleaded that the Civil Court entertained the suits and, besides issuing
summons/notices in the main suit as well as in the application for grant of
interim relief, it directed the Respondents to produce the scanned copies of
the record relating to the tender notices before the Court on 18 th of March,
2021, whereafter, the Respondents caused their appearance in the Court, but
did not produce the record relating to the tender notices before the Court,
which prompted the Petitioner-firms to file a Contempt Petition before the
Court, however, while the matter was pending consideration before the Court,
the official Respondents opened the tender documents on 30th of March, 2021
and, after finding the Respondents 10 to 13 as L1, they decided to allot the
work to them. It is averred that the non-compliance of the order of the Court
and the opening of the tender documents during the pendency of the
proceedings before the Court, in itself, makes it axiomatic as to how the
official Respondents have arbitrarily and capriciously dealt with the matter
and, in order to defeat the claim of the Petitioner-firms and with a view to give
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
undue benefit to Respondents 10 to 13, they, firstly, took decision dated 2nd of
February, 2021 and, thereafter, in terms of decision dated 24th of February,
2021, cancelled the previous bids and issued fresh tender notices. The
impugned decisions dated 2nd of February, 2021 and 24th of February, 2021 as
well as the subsequently issued fresh tender notices, as per the learned
Counsel, are, thus violative of all the safeguards enshrined in Articles 14 and
21 of the Constitution of India, as such, liable to be set aside.
06. Learned counsel for the Petitioner-Firms further submitted that
otherwise also the decision taken by the official Respondents on 2nd of
February, 2021 is contrary to NITs issued for the execution of works on 28th
of November, 2020; 8th of December, 2020; and 29th of December, 2020. It is
argued that this aspect of the matter had also been highlighted by the
Petitioner-firms in their reply, wherein attention of the official Respondents
had also been invited to different circulars and orders occupying the field,
however, without considering the said reply so submitted by the Petitioner-
firms, the official Respondents, in the meeting held on 24th of February, 2021,
decided to issue fresh tender notices. In that view of the matter, the learned
Counsel pleads that not only the said decision dated 24th of February, 2021,
but also the fresh tender notices are arbitrary in nature, aimed at defeating the
claim of the Petitioner-firms, therefore, liable to be set at naught.
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
07. It is next contended by the learned Counsel for the Petitioner-
firms that after the Petitioner-firms were found as L1 for the works advertised
by the official Respondents in terms of tender notices dated 28th of November,
2020; 8th of December, 2020; and 29th of December, 2020, the Petitioner-firms
had a legitimate expectation of allotment of work in their favour and that this
fact was the relevant factor requiring due consideration in a fair decision
making process, however, the official Respondents have failed to give due
weightage to it, rendering the decision arbitrary and liable to be set aside.
08. Mr Qayoom further proceeded to contend that before taking the
decisions dated 2nd of February, 2021 and 24th of February, 2021, as also
before issuing the fresh tender notices, the official Respondents were obliged
in law to provide an opportunity of being heard to the Petitioner-firms so that
they could explain their position in tune with their reply dated 17th of
February, 2021, more particularly when they were found as L1 in the earlier
tendering process, however, no opportunity of being heard was provided to
the Petitioner-firms to explain their position nor were they given any reason(s)
for not considering the reply so submitted by the Petitioner-firms before
taking the impugned decisions and/or issuing the fresh tender notices. The
impugned decisions dated 2nd of February, 2021 and 24th of February, 2021,
coupled with the fresh tender notices, as per the learned Counsel, are, thus
violative of principles of natural justice, equity and fair play, as such, liable to
be set aside.
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
09. The next contention of Mr Qayoom is that the decision taken by
the official Respondents on 24th of February, 2021 in putting the works to
fresh tenders is not only arbitrary, but also smacks of bias as well inasmuch
the Respondents 1 to 9, in order to accommodate Respondents 10 to 13, have
altered the terms and conditions of the tender notices dated 28th of November,
2020; 8th of December, 2020; and 29th of December, 2020 and have waived
almost all the terms and conditions to favour Respondents 10 to 13.
10. It was also argued by the learned Counsel representing the
Petitioner-firms that the official Respondents, by accepting the bid of
Respondents 10 to 13, have caused a loss of Rs. 92,75,097.67 to the public
exchequer, which aspect of the matter also throws considerable light on the
arbitrary and malafide attitude adopted by the Respondents 1 to 9 in taking
decisions dated 2nd of February, 2021 and 24th of February, 2021 as well as
issuing fresh tender notices, thereby rendering the entire process non-est in
the eyes of law.
11. Per Contra, Mr M. Y. Bhat, the learned Senior Counsel,
appearing for Respondents 1 to 9, submitted that no cause of action has
accrued to the Petitioner-firms in filing the Writ Petitions inasmuch as none
of their rights stands violated by the action of the official Respondents. It is
submitted that merely submitting the lowest tender does not vest the bidder
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
with any right to get the allotment of work and that once the Petitioner-firms
themselves refused to accept the terms and conditions of the contract,
therefore, no claim can be made by them regarding the allotment of works in
their favour. It is pleaded that the Petitioner-firms cannot force the official
Respondents to make allotment on their own terms and conditions and as per
their own whims and caprice. The learned Senior Counsel argued that the
tenderer has the right to cancel the process or even allot the contract to some
other person as the choice of entering into a contract is a subjective choice,
based on variety of aspects. It is contended that the contract between the
parties was not concluded in absence of agreement of the Petitioner-Firms qua
fulfilling all the terms and conditions of the contract. In support of his
arguments, Mr Bhat has referred to and relied upon the law laid down by the
Hon'ble Supreme Court in a recent Judgment rendered in case titled 'M/s
Padia Timber Company (P) Ltd. v. The Board of Trustees of
Vishakhapatnam Port Trust: AIR 2021 SC 341'.
12. Mr N. A. Ronga, the learned Counsel representing the
Respondents 10 to 13, has adopted the arguments advanced by Mr Bhat,
learned Senior Counsel appearing for Respondents 1 to 9.
13. In rebuttal, Mr Qayoom vociferously made an endeavour to
convince the Court that the decision of altering the conditions of contract, as
reflected in the minutes of the meeting of the Works Committee held on 2nd
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
of February, 2021, was not approved by the Vice-Chancellor, SKUAST in
respect of item No.1 regarding deduction of 20% more bill deposit from every
running bill, 5% additional security deposit as per NIT and 1% penalty per
month beyond the allotted time period. To support this argument, Mr Qayoom
has invited the attention of the Court to the observations of the Vice Chairman,
SKUAST on the minutes of the meeting of the Works Committee held on 2nd
of February, 2021 and submitted that, instead of complying with the
observations of the Vice Chancellor, the official Respondents issued
communication to the Petitioner-firms asking them to adhere to the additional
conditions as incorporated in letter dated 5th of February, 2021. It is further
submitted that this communication was replied by the Petitioner-firms
disagreeing to accept the condition of additional bill deposit being in direct
violation of the terms and conditions of the NIT, however, the Petitioner-
firms, notwithstanding such objection, agreed to 5% additional security
deposit, besides completing the work within the stipulated period of time and
not asking for payments till completion of work, but despite that, the official
Respondents rejected the claim of the Petitioner-firms and decided to put the
works to fresh tendering. Mr Qayoom pleaded that this decision of the official
Respondents was malafide in nature, aimed at ensuring rejection of the
completed contract in favour of the Petitioner-firms and for awarding undue
benefit to the Respondents 10 to 13, thereby rendering the entire action of the
official Respondents in violation of the law laid down by the Hon'ble Supreme
Court in various judicial pronouncements. In this behalf the learned Counsel
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
has referred to and relied upon Paragraphs 8 to 10 of the Judgment rendered
by the Apex Court in case titled 'Maa Binda Express Carrier & Anr v.
Northeast Frontier Railway & Ors: AIR 2014 Supreme Court 390'. It is also
urged that the official Respondents have not, at all, included those conditions
in the fresh tender notices which were additionally imposed on the Petitioner-
firms after completing the contract. It is pleaded that the contract between the
parties was completed upon issuance of communication dated 21st of January,
2021 by the official Respondents in view of mandate of Sections 4 and 5 of
the Contract Act, 1872 inasmuch as all the conditions of the tender notices
were adhered to by the Petitioner-firms and that the subsequent conditions
cannot render the completed contract void. In this behalf, reliance in placed
on the law laid down by the Supreme Court at Paragraph No. 15 of the
Judgment rendered in case titled 'Jawahar Lal Barman v. the Union of
India: AIR 1962 Supreme Court 378'.
14. As regards the Judgment cited by Mr Bhat, the learned Senior
Counsel representing the official Respondents, i.e., AIR 2021 SC 342, Mr
Qayoom submitted that same is distinguishable, having been passed on
different set of facts, as such, not applicable to the instant case.
15. Heard the learned counsel for the parties, perused the pleadings
on record and considered the matter. I have also gone through the relevant
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
records made available by the learned Senior Counsel representing the official
Respondents.
16. Admittedly, the Petitioner-firms emerged as L1 in the earlier
tendering process flouted by the official Respondents for the works in
question, however, the Works Committee, in its meeting held on 2nd of
February, 2021, after observing that the rates quoted by the lowest tenderers
regarding several items were unreasonable as per the BoQ and in order to
safeguard the projects, recommended incorporation of certain additional
conditions like more bill deposit, additional security deposit, Affidavit from
the Contractor concerned, penalty on delay per month, etcetera, prior to
issuance of the final allotment order(s) in favour of the lowest bidders. This
incorporation of additional conditions on part of the official Respondents did
not find favour with the Petitioner-firms, who did not accept the same on the
ground that these are in direct conflict with the tender notices. It was on the
basis of such position that the Works Committee, in its meeting held on 24th
of February, 2021, while observing that the lowest bidders are consuming time
and that expeditious steps are required to be taken by the University to ensure
execution of works in question during the current financial year,
recommended cancellation of the earlier tendering process and initiation of
fresh one. Given this position, the question that arises for consideration is
whether the action of the official Respondents in cancelling the earlier
tendering process and putting the works in question to fresh tenders can be
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
said to be irrational or arbitrary in nature. In this behalf, what requires to be
stated is that as per settled legal position, the tender issuing authority, i.e., the
University herein this case, is the best judge of its interests/ needs and that it
is always open to the said authority to suitably modify or change the eligibility
criteria so as to best serve its purposes. Whenever a change is introduced in
the eligibility criteria, either by introducing some new condition(s) or
restricting or altogether doing away with certain previous concessions, it
might hurt the interests of someone or the other, but, for that reason, the
change(s) made in the eligibility criteria cannot be labelled as malafide or
arbitrary. The Works Committee, after examining that the cost offer of all the
respective lowest bidders for the works were unreasonable in several items as
per the BoQ and in order to safeguard its interests, decided to incorporate
certain additional conditions prior to issuance of the allotment order(s) in
favour of the lowest bidders which conditions were not accepted by the lowest
bidders/ Petitioner-firms, thereby constraining the official Respondents to
cancel the earlier tendering process and initiate the process afresh. In such
circumstances, the official Respondents can hardly be faulted for protecting
itself against entering into such a contract with the Petitioner-firms.
17. Besides, the Courts are expected to exercise judicial restraint in
interfering with the administrative action, particularly in the matter of tender
or contract. Ordinarily, the soundness of the decision taken by the tender
issuing authority ought not to be questioned, but the decision-making process
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
can certainly be subject to judicial review. The soundness of the decision may
be questioned, firstly, if the decision made is so arbitrary and irrational that
the Court can say that the decision is such that no responsible authority acting
reasonably and in accordance with relevant law could have reached or;
second, if the process adopted or decision made by the authority is malafide
or intended to favour someone or; third, if the public interest is affected. In
the case on hand, when the Petitioner-firms did not accept all the terms and
conditions prescribed by the official Respondents prior to issuance of final
allotment order(s) in their favour, in such eventuality, the decision of the
official Respondents in cancelling the earlier tendering process and putting
the works to fresh tender cannot be said to be one where they have acted in a
manner in which no responsible authority acting reasonably and in accordance
with the relevant law would have acted. Furthermore, a bare perusal of the
pleadings on record, does not indicate that the decision made by the authority
is malafide or intended to favour someone. In fact, the decision of the official
Respondents was the result of non-acceptance of all the terms and conditions
of the contract on part of the Petitioner-firms. Likewise, the third ground of
public interest is also not affected in the present case because while it may be
in public interest to have greater competition, it is also in public interest that
all the tender conditions are complied with as prescribed by the tender issuing
authority and that there is no uncertainty in that area.
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
18. Law on the subject of scope of judicial review in the matters of
Contract is no more res integra.
19. In case titled 'Tata Cellular V. Union of India: (1994) 6
Supreme Court Cases 651', at Paragraph No.94, Hon'ble the Supreme Court
of the country, while dealing with the issue similar to the one subject matter
of the instant Petitions, evolved the following principles:
1. "The modern trend points to judicial restraint in administrative action;
2. The Court does not sit as a court of appeal but merely reviews the manner in which the decision was made;
3. The Court does not have the expertise to correct the administrative decision. If a review of the administrative decision is permitted it will be substituting its own decision, without the necessary expe4rtise which itself may be fallible;
4. The terms of the invitation to tender cannot be open to judicial scrutiny because the invitation to tender is in the realm of contract. Normally speaking, the decision to accept the tender or award the contract is reached by process of negotiations through several tiers. More often than not, such decisions are made qualitatively by experts;
5. The Government must have freedom of contract. In other words, a fair play in the joints is a necessary concomitant for an administrative body functioning in an administrative sphere or quasi-administrative sphere. However, the decision must not only be tested by the application of Wednesbury principle of reasonableness (including its other facts pointed out above) but must be free from arbitrariness not affected by bias or actuated by mala fides; and
6. Quashing decisions may impose heavy administrative burden on the administration and lead to increased and unbudgeted expenditure."
20. In case titled 'Sterling Computers Limited V. M&N
Publications Ltd: (1993) 1 SCC 445', the Apex Court, at Paragraph No.12,
has laid down as under:
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
"In contracts having commercial element, some more discretion has to be conceded to the authorities so that they may enter into contracts with persons, keeping an eye on the augmentation of the revenue. But even in such matters they have to follow the norms recognized by courts while dealing with public property. It is not possible for courts to question and adjudicate every decision taken by an authority, because many of the Government Undertakings which in due course have acquired the monopolist position in matters of sale and purchase of products and with so many ventures in hand, they can come out with a plea that it is not always possible to act like a quasi-judicial authority while awarding contracts. Under some special circumstances a discretion has to be conceded to the authorities who have to enter into contract giving them liberty to assess the overall situation for purpose of taking a decision as to whom the contract be awarded and at what terms. If the decisions have been taken in bona fide manner although not strictly following the norms laid down by the courts, such decisions are upheld on the principle laid down by Justice Holmes, that courts while judging the constitutional validity of executive decisions must grant certain measure of freedom of 'play in the joints' to the executive."
21. Again, the Apex Court, in case titled 'Directorate of Education
& Ors. V. Educomp Datamatics Ltd. And Ors: (2004) 4 SCC 19', while
applying the principles enunciated in Tata Cellular's case (supra), at
Paragraph No.12, observed, thus:
"12. It has been held in these decisions that the terms of the invitation to tender are not open to judicial scrutiny, the same being in the realm of contract. That the Government must have a free hand in setting the terms of the tender. It must have reasonable play in its joints as a necessary concomitant for an administrative body in an administrative sphere. The Courts would interfere with the administrative policy decision only if it is arbitrary, discriminatory, malafide or actuated by bias. It is entitled to pragmatic adjustments which may be called for by the particular circumstances. The Courts cannot strike down the terms of the tender prescribed by the Government because it feels that some other terms in the tender would have been fair, wise or logical. The Courts can interfere only if the policy decision is arbitrary, discretionary or malafide."
On an appreciation of the law laid down above, what comes to
limelight is that the modern trend points to judicial restraint in administrative
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
action and that the Court does not sit as a 'Court of Appeal', but merely
reviews the manner in which the decision was made. It has also been declared
that Court does not have the expertise to correct the administrative decision
and that if a review of the administrative decision is permitted, it will be
substituting its own decision, without the necessary expertise which itself may
be fallible. Furthermore, fair play in the joints is a necessary concomitant for
an administrative body functioning in an administrative sphere or quasi-
administrative sphere and quashing administrative decisions may impose
heavy administrative burden on the administration and lead to increased and
unbudgeted expenditure.
22. It is, thus settled that public authorities must be left with the same
liberty as they have in framing the policies, even while entering into contracts
because many contracts amount to implementation or projection of policies of
the Government. But it cannot be overlooked that unlike policies, contracts
are legally binding commitments and they commit the authority which may
be held to be a State within the meaning of Article 12 of the Constitution of
India in many cases for years. It is for this reason that the Courts have
impressed that even in contractual matters the public authority should not have
unfettered discretion. In contracts having commercial element, some more
discretion has to be conceded to the authorities so that they may enter into
contracts with persons keeping an eye on the augmentation of the revenue.
But, even in such matters, they have to follow the norms recognized by Courts
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
while dealing with public property. It is not possible for the Courts to question
and adjudicate every decision taken by an authority because many of the
Government Undertakings, which in due course have acquired the monopolist
position in matters of sale and purchase of products and with so many ventures
in hand, they can come out with a plea that it is not always possible to act like
a quasi-judicial authority while awarding contracts. Under some special
circumstances, a discretion has to be conceded to the authorities who have to
enter into contract by giving them liberty to assess the overall situation for
purpose of taking a decision as to whom the contract be awarded and at what
terms. If the decisions have been taken in bonafide manner, although not
strictly following the norms laid down by the Courts, such decisions are
upheld on the principle laid down by Justice Holmes that Courts, while
judging the constitutional validity of executive decisions, must grant certain
measure of freedom of 'play in the joints' to the executive.
Looking at the instant case in the above perspective, the
Petitioner-firms have not been able to establish before the Court that the
decision taken by the official Respondents in cancelling the earlier tendering
process and putting the works in question to fresh tenders is an arbitrary
exercise of power or that the same was/ is malafide in nature. In 'Jagdish
Mandal v. State of Orissa: (2007) 14 SCC 517', at Paragraph No.22, the
Hon'ble Supreme Court held, thus:
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
"22. .... Therefore, a Court before interfering in tender or contractual matters in exercise of power of judicial review, should pose to itself the following questions:
(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone;
OR
Whether the process adopted or decision made is so arbitrary and irrational that the court can say: "the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached";
(ii) Whether public interest is affected.
If the answers are in the negative, there should be no interference under Article 226."
From a bare perusal of the pleadings placed on record as well as
after going through the relevant records placed before the Court by the official
Respondents, it is more than apparent that the decision taken by the official
Respondents in cancelling the earlier tendering process and putting the works
in question to fresh tenders was certainly not irrational in any manner
whatsoever or intended to favour anyone. This decision, apart from being
lawful and sound, appears to have been taken by the official Respondents in
view of non-acceptance of all the terms and conditions of contract on part of
the lowest bidders/ Petitioner-firms.
23. For all that has been said and done hereinabove, I do not find any
merit in both these Petitions. These entail dismissal and are, accordingly,
dismissed. Interim directions, if any, subsisting as on date, shall stand vacated.
WP(C) No. 693/2021 c/w WP(C) No. 694/2021
24. Pending miscellaneous applications, if any, shall also stand
disposed of, accordingly.
25. No order as to costs.
26. Registry to place a copy of this Judgment on each file.
27. The relevant record as produced by Mr Bhat, the learned Senior
Counsel representing the official Respondents, is returned to him in the open
Court.
(Ali Mohammad Magrey) Judge SRINAGAR August 17th, 2021 "TAHIR"
i. Whether the Judgment is reportable? Yes/ No.
ii. Whether the Judgment is speaking? Yes/ No.
TAHIR MANZOOR BHAT
2021.08.17 11:38
I attest to the accuracy and
integrity of this document
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!