Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

J&K Tourism Development ... vs Indu Dhar Aima And Others
2021 Latest Caselaw 457 j&K

Citation : 2021 Latest Caselaw 457 j&K
Judgement Date : 9 April, 2021

Jammu & Kashmir High Court
J&K Tourism Development ... vs Indu Dhar Aima And Others on 9 April, 2021
        IN THE HIGH COURT OF JAMMU AND KASHMIR
                       AT JAMMU

                                             Reserved on: 01.04.2021
                                             Pronounced on: 09.04.2021

                                AA No. 44/2006


J&K Tourism Development Corporation & anr                ...Petitioner(s)

             Through: - Mr. M. K. Bhardwaj, Sr. Advocate with Mr. B. S.
                          Bali, Advocate.

                          Vs.

Indu Dhar Aima and others                             ...Respondent(s)

             Through: - Mr. U. K. Jalali, Sr. Advocate with M/s
                          Anuj Sawhney & Poonam Koul, Advocates.

CORAM:
      HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE.

                          JUDGEMENT

1. This is an application by the petitioners filed under Section 34 of the

Jammu and Kashmir Arbitration & Conciliation Act, 1997 [for short „the

Act of 1997‟ hereafter] for setting aside the award dated 01.09.2006 passed

by Shri A. N. Saraf, retired District & Sessions Judge, sole arbitrator,

awarding a sum of ₹ 13.39 lacs on account of escalation costs along with

9% per annum interest from 27.04.2002 till its realization.

2. With a view to appreciating the grounds of challenge taken by the

petitioners to assail the impugned award, it is necessary to notice material

background facts.

3. In the year 1991, the petitioners awarded the contract of

„construction work of Tourist Bungalow Sanasar‟ in favour of the 2 AA no. 44/2006

predecessor-in-interest of the respondents, late Shri J. N. Dhar ( for short „

the contractor‟ hereafter) vide allotment letter dated 09.10.1991. A formal

agreement bearing No. 45 dated 31.12.1991 was executed between the

petitioners and the contractor, laying down terms and conditions of the

contract. As per clause 6 of the terms and conditions of the contract, the

time period for completion of the work was stipulated as 9 working

months. While the original work in terms of the aforesaid contract

agreement was under execution, the work of Phase II was also allotted to

the contractor at the cost of ₹ 29,57,695.10 NP. The 2nd phase of the work

was to be executed by the contractor on the same terms and conditions on

which the original contract had been allotted to him.

4. To put it in black and white, a supplementary agreement between the

parties was executed on 07.07.1997 though both the works had been

completed by the contractor and handed over to the petitioners on

04.02.1995. As per the Engineer in-charge, there was a delay of one year

and three months in completing the works and the delay was on account of

reasons beyond the control of the contractor. It is because of these

recommendations of the Engineer in-charge of the work that no penalty

was imposed on the contractor. There is no dispute that the contractor was

paid the amount of the work for both the phases i.e. ₹ 24,57,304.90 for

Phase-I and ₹ 29,57,695.10 for Phase-II i.e. total sum of ₹ 54,13,203/-. The

contractor, who was supposed to complete each work within nine working

months could complete it much thereafter due to stoppage of work on

account of paucity of funds. He thus invoked Clause 43 of the original

agreement and laid a claim of ₹ 13.39 lacs along with interest on account of

escalation costs. The matter was placed before the Board of Directors in its 3 AA no. 44/2006

meeting held on 24.09.1998 in the office chambers of Hon‟ble the Chief

Minister, J&K State, ex-officio Chairman, J&K Tourism Development

Corporation, in which the proposal of the Managing Director for entering

into negotiations with the contractor for payment of escalation costs of ₹

13.39 lacs, claimed by the contractor, was approved and the Managing

Director was directed to work out the modus operandi of release of

payment and inform the Board accordingly.

5. It appears that no further progress was made in the negotiations and,

accordingly, the contractor invoked Clause 53 of the contract agreement

and sought appointment of Arbitrator to adjudicate the dispute arising out

of the contract entered into between the petitioners and the contractor. The

application was allowed and the matter was referred to the Arbitration of

Shri A. N. Saraf, retired District & Sessions Judge, as sole Arbitrator. The

Arbitrator entered the reference immediately on receipt of order dated

24.12.2004 passed by this Court under Section 11(4) of the Act of 1997

and the parties were directed to file their claims. On 02.07.2005, as many

as five issues, enumerated at page 2 of the award, were framed and the

parties were called upon to lead their evidence on affidavits. The

Arbitrator, after evaluating the evidence led before him, oral as well as

documentary, held the contractor entitled to recover the sum of ₹ 13.39 lacs

along with interest at the rate of 9% per annum to be calculated with effect

from 27.04.2002 i.e. the date of application filed before this Court for

appointment of arbitrator till its realization. The Arbitrator, while returning

findings on issue No.3, however, opined that no doubt the petitioners had

not been able to show the period during which the work remained stopped

but it was clear that the work, which was required to be completed within 4 AA no. 44/2006

nine working months, actually took 40 months to complete. He, therefore,

concluded that the circumstances did point out that there was delay in the

execution of the work and the delay was not attributable to the contractor.

The Arbitrator relied upon the decision of the Board of Directors taken in

the meeting held on 24.09.1998 and also the observations of the Engineer

in-charge with regard to the reasons for delayed execution of the works.

6. The petitioners are aggrieved of the award impugned and have

assailed the same primarily on the ground that it suffers from patent

illegality. Mr. M. K. Bhardwaj, learned senior counsel along with Mr. B. S.

Bali, would submit that the Arbitrator has reached his conclusions on the

basis of presumptions and conjectures while there was absolutely no

evidence to support such conclusion. He would submit that the findings of

the Arbitrator and the conclusions arrived at by him suffer from grave

perversity and, therefore, a ground for setting aside the award. He would

further submit that the interpretation put by the learned Arbitrator on the

decision of the Board of Directors, permitting negotiations with the

contractor as admission of the claim of escalation of the contractor, is

totally illogical and impregnate with complete perversity. He would frankly

submit that other than the aforesaid ground the petitioners have not assailed

the impugned award either on the ground that the Arbitrator has

misconducted himself or misconducted the proceedings. He would also not

find any fault with the manner and the procedure adopted by the Arbitrator

during the adjudication of the dispute.

7. Learned counsel for the petitioners have relied upon the judgments

of Supreme Court rendered in the cases of Tamilnadu Electricity Board

v. Bridge Tunnel Constructions, AIR 1997 SC 1376 and M/s 5 AA no. 44/2006

Rashtriya Chemicals & Fertilizers Limited v. M/s Chowgule Brothers

and others, AIR 2010 SC 3543 to substantiate their submissions that if

the award of the Arbitral Tribunal suffers from error apparent on record, it

is open to challenge under Section 34 of the Act.

8. Per contra, Mr. U. K. Jalali, learned senior counsel appearing

for the respondents, submits that in a reasoned award passed by the

Arbitrator under the Act of 1997, it is not open to the Court to go into the

merits nor it can probe the mental process of the Arbitrator and speculate as

to what impelled the Arbitrator to arrive at its conclusions. It is submitted

that once the award of the Arbitrator is supported by reasons, the Court,

while hearing an application under Section 34 of the Act, would not go into

the sufficiency or plausibility of the reasons unless such reasons are

without any evidence and suffer from perversity/patent illegality. He

would, therefore, submit that the Arbitrator, taking overall view of the

matter, particularly the decision of the Board of Directors taken on

24.09.1998 and the observations of the Engineer in-Charge, that the delay

in execution of the work was on account of paucity of funds and other

reasons not attributed to the contractor, found the claim of escalation

lodged by the contractor justified and accordingly passed the award. He

would urge that in the absence of any challenge by the petitioners to the

mode and manner in which the escalation charges have been calculated by

the contractor and accepted by the Arbitrator, it does not lie in the mouth of

the petitioners to now dispute the same in the instant application.

9. Having heard learned counsel for the parties and perused the record,

I do not find any patent illegality or perversity in the impugned award.

6 AA no. 44/2006

10. Undoubtedly, there is some ambiguity in the claims preferred and the

award passed by the learned Arbitrator and this ambiguity is with regard to

the actual period for which the work must have remained stopped either on

the directions of the petitioners or otherwise due to paucity of funds for the

project. Undoubtedly, in terms of the original agreement executed in the

year 1991 the First phase of construction of Dak Bunglow at Sanasar was

allotted to the contractor to be completed within a period of nine working

months. The agreement executed between the parties does not define

„working months‟. There is also no dispute that while the first phase of

work was under execution of the contractor, the petitioners allotted him

second phase of the work also to be executed on the same terms and

conditions. This necessarily increased the bulk of work and contributed to

the delay. As is admitted by the Engineer in-Charge, the delay was for two

reasons; one that there was addition of work of second phase; and, second

that there was some delay due to financial crunch faced by the corporation

during the year 1994-95. In view of the aforesaid observations of the

Engineer In-charge of the work and his decision not to impose any penalty

on the contractor, and more particularly when these observations of the

Engineer In-charge were part of the record and were never refuted by the

petitioners, no more evidence was required to be produced before the

Arbitrator to prove that there was indeed a delay of one year and three

months in completion of the work. That being the position, there should be

no denying the fact that in terms of the Clause 43 of the contract agreement

the contractor was entitled to escalation price to be worked out as per

clause 43 itself.

7 AA no. 44/2006

11. It is also interesting to note that the claim of the contractor for ₹

13.39 lacs towards escalation cost was never refuted by the petitioners on

the ground that it had not been worked out and quantified as per the

applicable formula. What was denied by the petitioners was their liability

to pay the escalation price under the agreement on the ground that there

was no order of stoppage of work from their side. The Arbitrator has taken

into consideration all the aspects and has concluded that on account of

delay not attributed to the contractor, the contractor was entitled to recover

the escalation cost. This view of the Arbitrator cannot be said to be either

based on no evidence or perverse.

12. The award passed by the Arbitrator under the Act of 1997 can only

be set aside on the grounds mentioned in Section 34 and on no other

grounds. The Court, while hearing an application under Section 34 of the

Act does not sit in appeal against the Arbitral award and interfere with it on

its merits. It is trite that an Arbitrator is a Judge appointed by the parties

and, as such, an award passed by him is unlikely to be interfered with.

Section 34 provides that an Arbitral award may be set aside by a Court on

the following grounds:-

      i)      Incapacity of a party;
      (ii)    the arbitration agreement not being valid ;

(iii) party making the application not given proper notice of arbitral proceedings ;

(iv) nature of dispute not falling within the terms of submission to arbitration:

(v) arbitral procedure not being in accordance with the agreement ;

13. In addition to the aforesaid grounds Section 34 (2) (b) mentions two

more grounds, which are left with the Court itself to decide. These are:

8 AA no. 44/2006

(i) dispute is not capable of settlement by arbitral process; and (ii)

the award is in conflict with the public policy of India.

14. The scope of interference with the award under Section 34 of the Act

is far less than it was under Section 30 or 33 of the Act of 1940. As a

matter of fact, the new Act based on UNICITRAL model was brought into

being with a view to curtailing judicial intervention. Apart from the

grounds mentioned in Section 34 (1) of the Act, the award could also be set

aside if it is contrary to the fundamental policy of Indian law or the interest

of India or justice or morality or it is patently illegal. The award could also

be set aside if it is unfair and unreasonable as to shock the conscience of

Court as it is against public policy. [See Venture Global Engineering v.

Satyam Computers Services Limited, (2008) 4 SCC 190]

15. The scope of public policy as a ground for setting aside the award

was discussed for the first time in the case of Renusagar Power Company

Ltd. v. General Electric Co. 1994 Supp (1) SCC 644. The Supreme Court

held that this defence must be invoked only in exceptional circumstances

where there is, "contravention of the fundamental policy of Indian law,

public interest of India and justice and morality". The scope of expression,

„the public policy‟ as a ground for setting aside the award was widened by

the Supreme Court in the case of Oil & Natural Gas Corpn. Ltd. vs

Western Geco International Ltd, AIR 2015 SC 363, where the

fundamental policy of Indian law was expounded to include the juristic

principles of judicial approach, natural justice and the Wednesbury‟s

principle of reasonableness. The Wednesbury‟s principle out rightly rejects

perverse or irrational defence which cannot satisfy the test of reasonability.

The scope of perversity was further extended in the case of Associate 9 AA no. 44/2006

Builders v. Delhi Development Authority, AIR 2015 SCF 620, wherein

it was held by the Supreme Court that a decision would be perverse if it is

based on no evidence or evidence which is unreliable and no reasonable

person would depend on it. This was the position of law with respect of

perversity and patent illegality obtaining at the time when the award in the

instant case was passed by the learned Arbitrator.

16. When the instant award is examined and the grounds of challenge

urged by the learned counsel for the petitioners are analyzed in the light of

legal position adumbrated herein above, it is difficult to say that the

impugned award could be placed in the category of the awards which suffer

from perversity or patent illegality and, therefore, against the public policy

of India.

17. It is true that the reasoning of the Arbitrator to support his findings,

that there was delay in execution of the work not attributed to the

contractor but attributable to the petitioners, is not very sound but, looking

to the totality of the circumstances and un-assailed observations by the

Engineer in-charge that there was delay of one year and three months in

execution of the work and that the delay was due to no fault of the

contractor, there was no reason or justification to deny compensation to the

contractor on account of escalation in terms of Clause 43 of the agreement.

18. It is true that the decision of the Board of Directors is not very clear

on the point as to whether the Board had, in principal, accepted the claim of

the contractor and directed the parties to negotiate on the modes operandi

of releasing the payment or the parties were relegated to negotiations even

with respect to admissibility of the claim. The Arbitrator has bonafidely

interpreted the decision of the Board of Directors and has come to the 10 AA no. 44/2006

conclusion that the Board of Directors has, in principal, accepted the claim

of escalation lodged by the contractor. I see no reason to sit in appeal over

this finding of fact returned by the Arbitrator by entering into the process

of reasoning of the Arbitrator, for that is not the scope of limited inquiry

envisaged under Section 34 of the Act of 1997.

19. For the foregoing reasons, I find no merit in this application and the

same is, accordingly, dismissed.

(Sanjeev Kumar) Judge

JAMMU 09.04.2021 Anil Raina, Addl. Reg/Secy Whether the order is speaking: Yes Whether the order is reportable: Yes

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter