Citation : 2021 Latest Caselaw 457 j&K
Judgement Date : 9 April, 2021
IN THE HIGH COURT OF JAMMU AND KASHMIR
AT JAMMU
Reserved on: 01.04.2021
Pronounced on: 09.04.2021
AA No. 44/2006
J&K Tourism Development Corporation & anr ...Petitioner(s)
Through: - Mr. M. K. Bhardwaj, Sr. Advocate with Mr. B. S.
Bali, Advocate.
Vs.
Indu Dhar Aima and others ...Respondent(s)
Through: - Mr. U. K. Jalali, Sr. Advocate with M/s
Anuj Sawhney & Poonam Koul, Advocates.
CORAM:
HON'BLE MR. JUSTICE SANJEEV KUMAR, JUDGE.
JUDGEMENT
1. This is an application by the petitioners filed under Section 34 of the
Jammu and Kashmir Arbitration & Conciliation Act, 1997 [for short „the
Act of 1997‟ hereafter] for setting aside the award dated 01.09.2006 passed
by Shri A. N. Saraf, retired District & Sessions Judge, sole arbitrator,
awarding a sum of ₹ 13.39 lacs on account of escalation costs along with
9% per annum interest from 27.04.2002 till its realization.
2. With a view to appreciating the grounds of challenge taken by the
petitioners to assail the impugned award, it is necessary to notice material
background facts.
3. In the year 1991, the petitioners awarded the contract of
„construction work of Tourist Bungalow Sanasar‟ in favour of the 2 AA no. 44/2006
predecessor-in-interest of the respondents, late Shri J. N. Dhar ( for short „
the contractor‟ hereafter) vide allotment letter dated 09.10.1991. A formal
agreement bearing No. 45 dated 31.12.1991 was executed between the
petitioners and the contractor, laying down terms and conditions of the
contract. As per clause 6 of the terms and conditions of the contract, the
time period for completion of the work was stipulated as 9 working
months. While the original work in terms of the aforesaid contract
agreement was under execution, the work of Phase II was also allotted to
the contractor at the cost of ₹ 29,57,695.10 NP. The 2nd phase of the work
was to be executed by the contractor on the same terms and conditions on
which the original contract had been allotted to him.
4. To put it in black and white, a supplementary agreement between the
parties was executed on 07.07.1997 though both the works had been
completed by the contractor and handed over to the petitioners on
04.02.1995. As per the Engineer in-charge, there was a delay of one year
and three months in completing the works and the delay was on account of
reasons beyond the control of the contractor. It is because of these
recommendations of the Engineer in-charge of the work that no penalty
was imposed on the contractor. There is no dispute that the contractor was
paid the amount of the work for both the phases i.e. ₹ 24,57,304.90 for
Phase-I and ₹ 29,57,695.10 for Phase-II i.e. total sum of ₹ 54,13,203/-. The
contractor, who was supposed to complete each work within nine working
months could complete it much thereafter due to stoppage of work on
account of paucity of funds. He thus invoked Clause 43 of the original
agreement and laid a claim of ₹ 13.39 lacs along with interest on account of
escalation costs. The matter was placed before the Board of Directors in its 3 AA no. 44/2006
meeting held on 24.09.1998 in the office chambers of Hon‟ble the Chief
Minister, J&K State, ex-officio Chairman, J&K Tourism Development
Corporation, in which the proposal of the Managing Director for entering
into negotiations with the contractor for payment of escalation costs of ₹
13.39 lacs, claimed by the contractor, was approved and the Managing
Director was directed to work out the modus operandi of release of
payment and inform the Board accordingly.
5. It appears that no further progress was made in the negotiations and,
accordingly, the contractor invoked Clause 53 of the contract agreement
and sought appointment of Arbitrator to adjudicate the dispute arising out
of the contract entered into between the petitioners and the contractor. The
application was allowed and the matter was referred to the Arbitration of
Shri A. N. Saraf, retired District & Sessions Judge, as sole Arbitrator. The
Arbitrator entered the reference immediately on receipt of order dated
24.12.2004 passed by this Court under Section 11(4) of the Act of 1997
and the parties were directed to file their claims. On 02.07.2005, as many
as five issues, enumerated at page 2 of the award, were framed and the
parties were called upon to lead their evidence on affidavits. The
Arbitrator, after evaluating the evidence led before him, oral as well as
documentary, held the contractor entitled to recover the sum of ₹ 13.39 lacs
along with interest at the rate of 9% per annum to be calculated with effect
from 27.04.2002 i.e. the date of application filed before this Court for
appointment of arbitrator till its realization. The Arbitrator, while returning
findings on issue No.3, however, opined that no doubt the petitioners had
not been able to show the period during which the work remained stopped
but it was clear that the work, which was required to be completed within 4 AA no. 44/2006
nine working months, actually took 40 months to complete. He, therefore,
concluded that the circumstances did point out that there was delay in the
execution of the work and the delay was not attributable to the contractor.
The Arbitrator relied upon the decision of the Board of Directors taken in
the meeting held on 24.09.1998 and also the observations of the Engineer
in-charge with regard to the reasons for delayed execution of the works.
6. The petitioners are aggrieved of the award impugned and have
assailed the same primarily on the ground that it suffers from patent
illegality. Mr. M. K. Bhardwaj, learned senior counsel along with Mr. B. S.
Bali, would submit that the Arbitrator has reached his conclusions on the
basis of presumptions and conjectures while there was absolutely no
evidence to support such conclusion. He would submit that the findings of
the Arbitrator and the conclusions arrived at by him suffer from grave
perversity and, therefore, a ground for setting aside the award. He would
further submit that the interpretation put by the learned Arbitrator on the
decision of the Board of Directors, permitting negotiations with the
contractor as admission of the claim of escalation of the contractor, is
totally illogical and impregnate with complete perversity. He would frankly
submit that other than the aforesaid ground the petitioners have not assailed
the impugned award either on the ground that the Arbitrator has
misconducted himself or misconducted the proceedings. He would also not
find any fault with the manner and the procedure adopted by the Arbitrator
during the adjudication of the dispute.
7. Learned counsel for the petitioners have relied upon the judgments
of Supreme Court rendered in the cases of Tamilnadu Electricity Board
v. Bridge Tunnel Constructions, AIR 1997 SC 1376 and M/s 5 AA no. 44/2006
Rashtriya Chemicals & Fertilizers Limited v. M/s Chowgule Brothers
and others, AIR 2010 SC 3543 to substantiate their submissions that if
the award of the Arbitral Tribunal suffers from error apparent on record, it
is open to challenge under Section 34 of the Act.
8. Per contra, Mr. U. K. Jalali, learned senior counsel appearing
for the respondents, submits that in a reasoned award passed by the
Arbitrator under the Act of 1997, it is not open to the Court to go into the
merits nor it can probe the mental process of the Arbitrator and speculate as
to what impelled the Arbitrator to arrive at its conclusions. It is submitted
that once the award of the Arbitrator is supported by reasons, the Court,
while hearing an application under Section 34 of the Act, would not go into
the sufficiency or plausibility of the reasons unless such reasons are
without any evidence and suffer from perversity/patent illegality. He
would, therefore, submit that the Arbitrator, taking overall view of the
matter, particularly the decision of the Board of Directors taken on
24.09.1998 and the observations of the Engineer in-Charge, that the delay
in execution of the work was on account of paucity of funds and other
reasons not attributed to the contractor, found the claim of escalation
lodged by the contractor justified and accordingly passed the award. He
would urge that in the absence of any challenge by the petitioners to the
mode and manner in which the escalation charges have been calculated by
the contractor and accepted by the Arbitrator, it does not lie in the mouth of
the petitioners to now dispute the same in the instant application.
9. Having heard learned counsel for the parties and perused the record,
I do not find any patent illegality or perversity in the impugned award.
6 AA no. 44/2006
10. Undoubtedly, there is some ambiguity in the claims preferred and the
award passed by the learned Arbitrator and this ambiguity is with regard to
the actual period for which the work must have remained stopped either on
the directions of the petitioners or otherwise due to paucity of funds for the
project. Undoubtedly, in terms of the original agreement executed in the
year 1991 the First phase of construction of Dak Bunglow at Sanasar was
allotted to the contractor to be completed within a period of nine working
months. The agreement executed between the parties does not define
„working months‟. There is also no dispute that while the first phase of
work was under execution of the contractor, the petitioners allotted him
second phase of the work also to be executed on the same terms and
conditions. This necessarily increased the bulk of work and contributed to
the delay. As is admitted by the Engineer in-Charge, the delay was for two
reasons; one that there was addition of work of second phase; and, second
that there was some delay due to financial crunch faced by the corporation
during the year 1994-95. In view of the aforesaid observations of the
Engineer In-charge of the work and his decision not to impose any penalty
on the contractor, and more particularly when these observations of the
Engineer In-charge were part of the record and were never refuted by the
petitioners, no more evidence was required to be produced before the
Arbitrator to prove that there was indeed a delay of one year and three
months in completion of the work. That being the position, there should be
no denying the fact that in terms of the Clause 43 of the contract agreement
the contractor was entitled to escalation price to be worked out as per
clause 43 itself.
7 AA no. 44/2006
11. It is also interesting to note that the claim of the contractor for ₹
13.39 lacs towards escalation cost was never refuted by the petitioners on
the ground that it had not been worked out and quantified as per the
applicable formula. What was denied by the petitioners was their liability
to pay the escalation price under the agreement on the ground that there
was no order of stoppage of work from their side. The Arbitrator has taken
into consideration all the aspects and has concluded that on account of
delay not attributed to the contractor, the contractor was entitled to recover
the escalation cost. This view of the Arbitrator cannot be said to be either
based on no evidence or perverse.
12. The award passed by the Arbitrator under the Act of 1997 can only
be set aside on the grounds mentioned in Section 34 and on no other
grounds. The Court, while hearing an application under Section 34 of the
Act does not sit in appeal against the Arbitral award and interfere with it on
its merits. It is trite that an Arbitrator is a Judge appointed by the parties
and, as such, an award passed by him is unlikely to be interfered with.
Section 34 provides that an Arbitral award may be set aside by a Court on
the following grounds:-
i) Incapacity of a party;
(ii) the arbitration agreement not being valid ;
(iii) party making the application not given proper notice of arbitral proceedings ;
(iv) nature of dispute not falling within the terms of submission to arbitration:
(v) arbitral procedure not being in accordance with the agreement ;
13. In addition to the aforesaid grounds Section 34 (2) (b) mentions two
more grounds, which are left with the Court itself to decide. These are:
8 AA no. 44/2006
(i) dispute is not capable of settlement by arbitral process; and (ii)
the award is in conflict with the public policy of India.
14. The scope of interference with the award under Section 34 of the Act
is far less than it was under Section 30 or 33 of the Act of 1940. As a
matter of fact, the new Act based on UNICITRAL model was brought into
being with a view to curtailing judicial intervention. Apart from the
grounds mentioned in Section 34 (1) of the Act, the award could also be set
aside if it is contrary to the fundamental policy of Indian law or the interest
of India or justice or morality or it is patently illegal. The award could also
be set aside if it is unfair and unreasonable as to shock the conscience of
Court as it is against public policy. [See Venture Global Engineering v.
Satyam Computers Services Limited, (2008) 4 SCC 190]
15. The scope of public policy as a ground for setting aside the award
was discussed for the first time in the case of Renusagar Power Company
Ltd. v. General Electric Co. 1994 Supp (1) SCC 644. The Supreme Court
held that this defence must be invoked only in exceptional circumstances
where there is, "contravention of the fundamental policy of Indian law,
public interest of India and justice and morality". The scope of expression,
„the public policy‟ as a ground for setting aside the award was widened by
the Supreme Court in the case of Oil & Natural Gas Corpn. Ltd. vs
Western Geco International Ltd, AIR 2015 SC 363, where the
fundamental policy of Indian law was expounded to include the juristic
principles of judicial approach, natural justice and the Wednesbury‟s
principle of reasonableness. The Wednesbury‟s principle out rightly rejects
perverse or irrational defence which cannot satisfy the test of reasonability.
The scope of perversity was further extended in the case of Associate 9 AA no. 44/2006
Builders v. Delhi Development Authority, AIR 2015 SCF 620, wherein
it was held by the Supreme Court that a decision would be perverse if it is
based on no evidence or evidence which is unreliable and no reasonable
person would depend on it. This was the position of law with respect of
perversity and patent illegality obtaining at the time when the award in the
instant case was passed by the learned Arbitrator.
16. When the instant award is examined and the grounds of challenge
urged by the learned counsel for the petitioners are analyzed in the light of
legal position adumbrated herein above, it is difficult to say that the
impugned award could be placed in the category of the awards which suffer
from perversity or patent illegality and, therefore, against the public policy
of India.
17. It is true that the reasoning of the Arbitrator to support his findings,
that there was delay in execution of the work not attributed to the
contractor but attributable to the petitioners, is not very sound but, looking
to the totality of the circumstances and un-assailed observations by the
Engineer in-charge that there was delay of one year and three months in
execution of the work and that the delay was due to no fault of the
contractor, there was no reason or justification to deny compensation to the
contractor on account of escalation in terms of Clause 43 of the agreement.
18. It is true that the decision of the Board of Directors is not very clear
on the point as to whether the Board had, in principal, accepted the claim of
the contractor and directed the parties to negotiate on the modes operandi
of releasing the payment or the parties were relegated to negotiations even
with respect to admissibility of the claim. The Arbitrator has bonafidely
interpreted the decision of the Board of Directors and has come to the 10 AA no. 44/2006
conclusion that the Board of Directors has, in principal, accepted the claim
of escalation lodged by the contractor. I see no reason to sit in appeal over
this finding of fact returned by the Arbitrator by entering into the process
of reasoning of the Arbitrator, for that is not the scope of limited inquiry
envisaged under Section 34 of the Act of 1997.
19. For the foregoing reasons, I find no merit in this application and the
same is, accordingly, dismissed.
(Sanjeev Kumar) Judge
JAMMU 09.04.2021 Anil Raina, Addl. Reg/Secy Whether the order is speaking: Yes Whether the order is reportable: Yes
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!