Citation : 2023 Latest Caselaw 4199 Guj
Judgement Date : 8 June, 2023
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/FIRST APPEAL NO. 2671 of 1996
FOR APPROVAL AND SIGNATURE:
HONOURABLE MR. JUSTICE BHARGAV D. KARIA
==========================================================
1 Whether Reporters of Local Papers may be allowed
to see the judgment ?
2 To be referred to the Reporter or not ?
3 Whether their Lordships wish to see the fair copy
of the judgment ?
4 Whether this case involves a substantial question
of law as to the interpretation of the Constitution
of India or any order made thereunder ?
==========================================================
CHAIRMAN,GEB & 2 other(s)
Versus
JAGJIT TEXTILE DY. & PRIN.WORKTHRO' MANGALLAL G.PARTNER
==========================================================
Appearance:
MR PREMAL R JOSHI(1327) for the Appellant(s) No. 1,2,3
ADITYA R PARIKH(8769) for the Defendant(s) No. 1
==========================================================
CORAM:HONOURABLE MR. JUSTICE BHARGAV D. KARIA
Date : 08/06/2023
ORAL JUDGMENT
1.Heard learned advocate Mr. Premal R.Joshi for
the appellants and larned advocate Mr. Aditya
R. Parikh for the respondent.
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
2.The appellants have preferred this appeal
being aggrieved and dissatisfied with the
judgment and order dated 11.04.1996 passed by
the Civil Judge(SD), Gondal in Special Civil
Suit No.169/1993.
3.The respondent - original plaintiff was
having Textile and Dying Printing Industry at
Jetpur for printing Sarees. The appellant-
Gujarat Electricity Board (GEB) supplied
industrial electric connection of 120 H.P
under Consumer No. 33201/00035/3 of the
respondent plaintiff.
4.On 27.08.1993 an inspection was carried out
by the officers of the GEB at the factory of
the respondent plaintiff. It is the case of
the GEB that during the course of inspection,
it was observed that there was tampering of
the meter and therefore, meter was removed
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
and sent to Dhoraji laboratory for testing
purpose. Thereafter bill for theft of
electricity of Rs.3,80,548.47 ps. was issued
on 28.08.1993 which is produced at Exh.39.
5.The respondent plaintiff therefore, filed
Special Civil Suit No.169/1993 before the
Court of Civil Judge (Senior Division) at
Gondal challenging the issuance of the said
bill.
6.The appellant GEB filed written statement at
Exh.30 denying the averments made in the
plaint and further contended that meter of
the respondent plaintiff was checked and it
was found moving slow at 74.74% and some
solution was found on the seal of Metal Meter
Box. Two seals on the Metal Meter Box were
also found to be tampered with and therefore,
it was case of theft of electricity and meter
was removed from the factory of the
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
respondent plaintiff. In the testing report
submitted by Dhoraji laboratory, it was found
that ends of CT wire were turned and there
was also some change in Y phase of CT and
thereby meter was tampered with. It was
further contended that aforesaid proceeding
of testing and removal of meter was made in
presence of one Nishitbhai Maganbhai Patel
who was power of attorney holder of
respondent firm.
7.After considering the rival contentions of
the parties, the learned Judge framed the
following issues:
"1. Whether the plaintiff proves that though it did not commit power theft, Checking Officer of the defendant while checking its meter on 27.08.93 falsely alleged power theft and falsely issued supplementary bill of Rs.3,80,548.47 ps. and disconnected plaintiff's electric connection?
2.Whether defendants prove that plaintiff had committed theft of
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
electricity?
3.Whether plaintiff is entitled to get the declaration that impugned bill is illegal, arbitrary, null, void and not enforceable?
4. Whether the plaintiff is entitled for permanent injunction restraining defendants from disconnecting plaintiff's electric connection?
5. What order and what decree?"
8.Learned Judge by answering issue nos. 1, 3
and 4 in the affirmative and issue no. 2 in
the negative allowed the suit filed by the
respondent plaintiff by decreeing the suit
declaring that bill at Exh.39 of
Rs.3,80,548.47 is illegal and not recoverable
by the appellant - GEB - original defendant
and further directed not to disconnect the
electric connection provided by the appellant
GEB.
9.Learned advocate Mr. Premal Joshi for the
appellant-GEB submitted that the learned
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
Judge has committed an error by not
considering the test report submitted by
Dhoraji laboratory at Exh.67 wherein it is
categorically found during the testing of the
meter that there was tampering by changing
wires in CT. He also invited the attention of
the Court to the diagram drawn in the said
laboratory report to submit that learned
Judge has ignored this vital evidence.
10. Learned advocate Mr. Joshi also referred
to and relied upon Exh.65 which is an
inspection report wherein it is observed
during the course of inspection that seals
applied on meter were containing some
solution and even the paper seals were
different than the usual seals applied by
GEB. It was submitted that the learned Judge
without considering such vital evidence has
come to the erroneous conclusion that because
four seals were found to be okay on the Metal
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
box meter in the laboratory test report but
findings given by laboratory test report that
there was tampering of the meter was ignored.
11. It was submitted that the findings
arrived at by the learned Judge with regard
to not providing an opportunity to the
authorised person of the respondent firm is
not true inasmuch as Nishitbhai Patel who has
signed the inspection report as well as the
laboratory test report as witness, was power
of attorney holder of respondent no.1 firm
and therefore, such findings arrived at by
the learned Judge are contrary to the
evidence on record.
12. It was further submitted that facts
emerging from record that there was no change
in consumption of electricity after change of
meter cannot be criteria for holding that
there was no theft of electricity. It was
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
submitted that there is a finding given by
the testing laboratory that the meter was
running slow because of tampering and change
of wire inside meter which proves that there
was theft of electricity and the bill issued
by GEB applying ABCD formula was just and
proper and learned Judge ought to have
dismissed the suit.
13. On the other hand, learned advocate Mr.
Aditya Parikh appearing for the respondent
consumer submitted that the impugned judgment
and order is passed on the basis of evidence
to the effect that there were four seals on
the meter and the same were found to be okay
which was also admitted by the witness of
GEB, Jamnadasbhai Ramjibhai, Deputy Executive
Engineer at Exh.70.
14. It was submitted that testing
laboratory report is falsified by GEB's own
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
witness and therefore, the learned Judge has
rightly come to the conclusion that there is
no fault on part of the respondent plaintiff
for alleged theft of electricity.
15. It was further submitted that learned
Judge has rightly come to the conclusion that
Nishitkumar Maganlal PW-1 who was power of
attorney holder of respondent firm was not
authorised as consumer and therefore, the
entire exercise undertaken by GEB for
inspection and testing of the meter is liable
to be quashed and set aside.
16. Having heard the learned advocates for
the respective parties and having considered
the oral and documentary evidence before the
Court below, it is not in dispute that the
evidence of Jamnadas Ramjibhai at Exh.70 is
required to be considered going to the root
of the matter to the effect that four seals
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
on the meter were found to be in order which
is also stated in the laboratory report at
Exh.67.
17. Learned Judge has considered in detail
the various events which have taken place
during the course of inspection and after
considering the inspection report at Exh.65,
statement of representative of consumer
Nishitkumar at Exh.66 and report of Dhoraji
laboratory at Exh. 67 vis-a-vis the evidence
of Jamnadas Ramjibhai at Exh,70 has rightly
come to the conclusion that when the seals on
the meter were found to be in order then the
respondent plaintiff cannot be saddled with
liability of the slow moving meter on the
allegation of theft of electricity. Learned
Judge has also relied upon the undisputed
fact that in order to change the ends of CT
wires, it is necessary to open the terminal
block of the meter and in order to open
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
terminal block of the meter, it is necessary
to break the rosy colour plastic seal
no.24098. However such seal is found to be
okay in the laboratory test report at Exh.67,
therefore, it cannot be believed that the
respondent plaintiff had changed the ends of
CT wires to slow down the meter.
18. It was further observed and held in the
impugned order that after installation of the
new meter, amount of bill should be 75% more
as alleged, if the allegation of GEB is
believed, however, on the basis of comparison
of bills produced at Exh. 41 to 47 with
electricity bill at Exh. 48 to 62, clearly
shows there was no rise in the bill amount by
75% even after installation of new meter.
Considering such aspects and evidence on
record, the learned Judge has decreed the
suit by holding that the bills at Exh.39 of
Rs.3,80,548.47 is illegal and such amount is
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
not recoverable from the respondent
plaintiff.
19. Reliance was also placed on Circular No.
471 of GEB dated 18.10.1990 and Circular
No.470 with regard to wrong connection found
in sealed metal meter box and circular no.
473 which pertains to correctness and
slowness of the meter without mal practise.
Considering such circulars, it was rightly
held by the learned Judge that there is no
evidence led by the appellant-GEB with regard
to tampering with the meter as the seals on
the meter were found to be in order. On
perusal of all the three circulars,
reference is required to be made to Electric
Inspector but the same was not done.
20. The appellant GEB has thus failed to
prove its case of slow meter and theft of
electricity in view of the fact that in the
C/FA/2671/1996 JUDGMENT DATED: 08/06/2023
testing laboratory report it is categorically
stated that the four seals on the meter were
found to be okay.
21. In view of above findings of fact
arrived at by the learned Judge in the
impugned judgment and order on the basis of
oral and documentary evidence led by both the
sides, no interference is required to be made
by this Court in the impugned judgment and
order as the impugned order cannot be said to
be contrary to the evidence on record or
perverse in any manner whatsoever.
22. The appeal accordingly stands dismissed.
Record and proceedings, if any, be
returned to the concerned Court.
(BHARGAV D. KARIA, J) RAGHUNATH R NAIR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!