Citation : 2022 Latest Caselaw 8620 Guj
Judgement Date : 29 September, 2022
C/CA/2368/2022 ORDER DATED: 29/09/2022
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/CIVIL APPLICATION NO. 2368 of 2022
In F/FIRST APPEAL NO. 5717 of 2022
With
R/CIVIL APPLICATION NO. 2375 of 2022
==========================================================
NATHABHAI KHIMABHAI
Versus
STATE OF GUJARAT
==========================================================
Appearance:
MR NITIN M AMIN(126) for the Applicant(s) No. 1
MR SANJAY M AMIN(130) for the Applicant(s) No. 1
for the Respondent(s) No. 2,3
MS DHWANI TRIPATHI, ASST. GOVERNMENT PLEADER/PP for the
Respondent(s) No. 1
==========================================================
CORAM:HONOURABLE MS. JUSTICE SONIA GOKANI
and
HONOURABLE MS. JUSTICE NISHA M. THAKORE
Date : 29/09/2022
ORAL ORDER
(PER : HONOURABLE MS. JUSTICE SONIA GOKANI)
1. Rule. Learned Assistant Government Pleader waives
service of notice of rule for and on behalf of the respondent -
State.
2. The group of applicants, who are before this Court
seeking to condone the delay of 2488 and 2458 days
respectively, challenging the judgment and order dated
21.02.2013 passed by the learned Principal Senior Civil Judge
C/CA/2368/2022 ORDER DATED: 29/09/2022
in Land Reference Cases at Junagadh.
3. It emerges from the record that the possession of the
lands of the applicants had been taken over by the State in the
year 2000. Additional compensation had been given at the
rate of Rs.32.40 per square meters for irrigated land and
Rs.25.87 per square meters for Jirayat land and Rs.11.14 per
square meters for non-used/ uncultivated land. Additional
compensation was given at the rate of 12% per annum for the
period of 30 months and solatium at the rate of 30% on the
said amount. This has aggrieved the applicants, whose main
grievance is that the sale instances of the very village,
whereby the market value of the land had been fixed at Rs.75
has not been taken into consideration by the Reference Court.
3.1. It is further their say that they were without the land
and any compensation for the period of nearly 10 years and
therefore, could not have sufficient fund to file appeals.
Hence, the request is made to condone the delay of 2488 and
2458 days relying on the decision of the Apex Court
rendered in case of K. Subbarayadu and others vs. Special
Deputy Collector (Land Acquisition), reported in 2017 12
SCC 840. It was an appeal under the Land Acquisition Act,
C/CA/2368/2022 ORDER DATED: 29/09/2022
1894 before the Apex Court where the delay of 3671 days has
been condoned by the Apex Court by striking the balance that
for the delay which has been caused, no interest would be
chargeable.
4. This Court has heard the learned advocate, Mr.Nitin
Amin appearing for the applicants and learned Assistant
Government Pleader, Ms. Dhwani Tripathi for respondent-
State.
5. Learned advocate, Mr.Nitin Amin has relied on the
decision of the Apex Court in case of K. Subbarayadu and
others (supra) and has urged that the practical difficulty of the
appellants needs to be born in mind. He has further urged
that this Court in Civil Application No.01 of 2019 in First
Appeal No.8076 of 2019 has also condoned the huge delay in
bringing the heirs of the Land Reference Court on record. He
has further pointed out that sufficient cause as mentioned in
the provision as per the decision of the Apex Court rendered
in case of S.Ganeshraju (D) Thr. L.Rs.& Another vs.
Narasamma (D) Thr. L.Rs. & others,reported in 2012 (4)
Scale 152 shall need to be given a liberal meaning. There are
fair chances to succeed in the appeal and the plight of the
C/CA/2368/2022 ORDER DATED: 29/09/2022
agriculturist shall be considered sympathetically. He has
urged that he has already paid the price for his not having
approached this Court well within time, as per the said
decision of the Apex Court where he may not claim the
interest for the delayed period.
6. Learned Assistant Government Pleader, Ms. Dhwani
Tripathi has strongly objected to this on the ground that the
delay is huge and there is no sufficient explanation. She has
further urged that the phrases used are standard and do not
indicate anything in particulars with regard to the conditions
of the applicants, the Court may not condone the delay when
delay of each day needs to be explained by the party.
7. Having heard learned advocates on both the sides and
also having taken into consideration the explanation, this
Court noticed that the judgment and order of the Reference
Court dated 21.02.2013 where of course there is a some rise
in the amount of compensation. The applicants are before this
Court indicating that for the very village the sale instances of
Rs.75 per square meters for irrigated land. It is also matter of
record that the land has been acquired in the year 2000 and
the applicants being the agriculturist would have no other
C/CA/2368/2022 ORDER DATED: 29/09/2022
means to sustain themselves. In that circumstances, they have
pleaded their inability to pay the Court fees in each case.
8. Being alive to the decision of the Apex Court and also in
case of State of Nagaland vs. Lipok AO and others,
reported in 2005 3 SCC 752 which says that Section 5 of
the Limitation Act shall have to be liberally construed so as to
do substantial justice to the parties. The provision
contemplates that the court has to go into the position of
the person concerned and to find out if the delay can be said
to have been resulted from the cause which he had adduced
and whether the cause recorded in the peculiar circumstances
of the case is sufficient.
9. The Apex Court in case of K. Subbarayadu and others
(supra) was also dealing with Land Acquisition Cases where it
held that the acquisition of the land the lifeline of the
agriculturist is lost. There may be omissions on the part of the
claimants to adopt extra vigilance; but same need not be used
as a ground to depict them as not having bona-fide or to treat
the same as a negligent act. The Court ought to adopt a
pragmatic approach so far as the Land Acquisition matters are
concerned, for awarding just and reasonable compensation.
C/CA/2368/2022 ORDER DATED: 29/09/2022
10. Relying on the decision of the Apex Court rendered in
case of Dhiraj Singh (D) Thr. Lrs. vs. Haryana State
and Ors, reported in 2014 9 Scale 441 the Apex Court
struck the balance by denying the appellants' interest for the
period for which they did not approach the Court. Apt would
be to reproduce the findings and observations of the Apex
Court in this regard:
"12. In fact, in a matter arising out of the same notification, in Civil Appeal Nos.617-619 of 2012, this Court had rendered a judgment dated 17.1.2012 condoning the delay of 4644 days and enhancing the compensation to Rs.200/- per square yard. A perusal of the counter affidavit filed by the respondents makes it clear that the rate of Rs.200/- per sq. yard fixed in Horam's case (LPA No.920 of 1994) has been upheld by this Court by dismissing the special leave petition against the said judgment. A perusal of the said order makes it clear that it relied upon dismissal orders passed in various other special leave petitions whereby the aforesaid rate had been upheld.
13. Thus, in almost all cases, the rate of Rs.200/- per sq. yard has been applied by the High Court and this Court.
14. The appellants are identically situated and there is no reason to meet out a different trcatment to them. We also note that, while in these cases, the High Court had refused to condone the delay and dismissed the LPAs of the appellants, other LPAs were allowed by the High Court itself by condoning the delay of the same magnitude in the same circumstances."
C/CA/2368/2022 ORDER DATED: 29/09/2022
11. This Court also in Civil Application No.01 of 2019 in First
Appeal No.8076 of 2019 relying of the decision of the Apex
Court rendered in case of Banwari Lal vs. Balbir Singh,
reported in 2016 (1) SCC 607 and considering the peculiar
facts and circumstances allowed the application by condoning
the delay of 4175 days in bringing the heirs on the record.
12. As can be noted from the version given by the applicants
that they are agriculturist, who have lost their land in the year
2000 and their sale instance of the very village also has
provided them the cause to approach this Court. The delay is
also well explained of their not having the sufficient means.
It is quite understandable that the persons who have lost their
only means of bread and butter if needs to adduce the Court
fees which in an individual case of Rs.75,000/-, it is extremely
difficult for them to make an arrangement till the amount
given under the award is available to them. Delay having been
sufficiently explained, the Court is of the opinion that this is
the fit case for permitting the condonation of delay.
13. Resultantly, these applications are allowed, delay of
2488 and 2458 days is condoned with a specific rider and
direction that for the entire amount of delay which has been
C/CA/2368/2022 ORDER DATED: 29/09/2022
caused in filing the First Appeals, no interest shall be claimed
by the petitioners as agreed to oral submissions of the learned
advocate, Mr.Nitim Amin and also has been reflected in the
decision of the Apex Court in case of Dhiraj Singh (D) Thr.
Lrs.(supra) reiterated in case of K. Subbarayadu and others
(supra).
14. Rule is made absolute accordingly. First Appeals be
numbered and listed for admission in seriatim.
(SONIA GOKANI, J)
(NISHA M. THAKORE,J) Bhoomi
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!