Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Rabari Rana Madha vs State Of Gujarat
2022 Latest Caselaw 4111 Guj

Citation : 2022 Latest Caselaw 4111 Guj
Judgement Date : 12 April, 2022

Gujarat High Court
Rabari Rana Madha vs State Of Gujarat on 12 April, 2022
Bench: Nirzar S. Desai
    C/SCA/13857/2019                              ORDER DATED: 12/04/2022




           IN THE HIGH COURT OF GUJARAT AT AHMEDABAD

            R/SPECIAL CIVIL APPLICATION NO. 13857 of 2019
                                With
            R/SPECIAL CIVIL APPLICATION NO. 13859 of 2019
                                With
            R/SPECIAL CIVIL APPLICATION NO. 13861 of 2019
                                With
            R/SPECIAL CIVIL APPLICATION NO. 13862 of 2019
                                With
            R/SPECIAL CIVIL APPLICATION NO. 13863 of 2019
==========================================================
                         RABARI RANA MADHA
                                Versus
                          STATE OF GUJARAT
==========================================================
Appearance:
MR SP MAJMUDAR(3456) for the Petitioner(s) No. 1
MR. NISHIT P GANDHI(6946) for the Petitioner(s) No. 1
NOTICE SERVED for the Respondent(s) No. 2
NOTICE SERVED BY DS for the Respondent(s) No. 1
MR AKASH CHHAYA AGP for the Respondent - State
==========================================================

 CORAM:HONOURABLE MR. JUSTICE NIRZAR S. DESAI

                            Date : 12/04/2022

                             ORAL ORDER

1.1 By way of these petitions, the petitioners have challenged the order dated 15.12.2018 passed by the learned Principal Senior Civil Judge, Palanpur below Exh.1 in LAR (Execution Petition) No.65 of 2010 insofar as the learned Judge has not accepted the entire calculation of compensation to be awarded to the petitioners, which was produced by the petitioners below Mark-455/1 and further prayed for directions to the respondents to pay compensation to the petitioner as per calculation made by the petitioners in calculation-sheet produced by the petitioners before the learned Executing

C/SCA/13857/2019 ORDER DATED: 12/04/2022

Court.

1.2 Since all these petitions are preferred against different LAR Execution Applications and more or less though they were different, the orders passed in separate LAR Execution Petitions, considering the fact that the operative order, which is under challenge by way of each of the petitioner is same since it pertains to same land acquisition, all these matters are taken up together and are heard and being decided together, with the consent of the learned advocates for the parties.

1.3 The facts of this group of petitions are identical to that of a group of petitions being Special Civil Application No.6262 of 2019 and allied matters and hence for sake of convenience, Special Civil Application No.6262 of 2019 is treated to be a lead petition and facts of Special Civil Application No.6262 of 2019 are being taken into consideration as facts of all petitions preferred on the same subject matter.

2.1 It is the case of the petitioners that lands of the petitioners were covered under the acquisition proceedings for which award was passed and ultimately compensation was fixed by this Court in a group of First Appeal No.2091 of 1993 and allied matters. Those First Appeals were disposed of vide order dated 16.03.1996 wherein following interim directions were issued, more

C/SCA/13857/2019 ORDER DATED: 12/04/2022

particularly the direction reproduced in para:4 of the petition, which reads as under:

"(i) The Collector of the District shall form a team under his direct supervision and control where he can take assistance of officers working under him up to the level of Deputy Collector and preferably that of Prant Officer of the Prant, if there be any and visit the place physically, ascertain the position during the entire period right from the date of publication of notification under sec.4 i.e. 4.8.1986 till today and for that purpose 7/12 extracts of the relevant years, the land assessment record which is referred to as Anawari statement and if scarcity during the relevant period is declared, payment of scarcity subsidy, if any made, also be taken into consideration and likewise panchnamas that were drawn in respect of land under acquisition and which are brought on record in the aforesaid Civil Applications may also be taken into consideration. To facilitate the work of the learned Collector of the District, the State Authority or the Estate Officer, Deesa Airfield, are directed to supply the copies of panchnamas and produce the same before the Collector.

2.2 Pursuant to the aforesaid order passed in the group of First Appeals, the petitioners preferred Land Reference (Execution) No.65 of 2010 and allied matters before the learned District Judge, Banaskantha.

2.3 During the course of the aforesaid proceedings, LAR Execution applications, vide order dated 21.02.2018, learned Principal Senior Civil Judge, Palanpur passed an order and directed the parties to give their calculation in the form of statement latest by 31.03.2018 and pursuant to the aforesaid order dated 21.02.2018, the petitioners

C/SCA/13857/2019 ORDER DATED: 12/04/2022

gave calculation and so the respondents also gave the calculation. Both the parties gave calculation but the Reference Court believed the calculation given by the present petitioner except for the last column no.31. Ultimately vide order dated 31.03.2018 Execution Application preferred by the petitioners was disposed of by the learned Principal Senior Civil Judge, Palanpur by directing respondents to deposit the amount as per the calculation-sheet prepared by them.

2.4 According to the petitioners calculation submitted by respondents which was considered by the Reference Court was erroneous and, therefore, the petitioners preferred Special Civil Application No.10650 of 2018 before this Court. The aforesaid petition was disposed of vide order dated 06.10.2018 whereby co-ordinate bench of this Court, in paras:3 and 4, observed as under and disposed of the petitions.

"3. It appears that respondent no.2 - Acquiring Body have submitted calculation sheet at Mark- 436/1 with Exh.436 before the Executing Court and learned advocate Mr. Ankit Shah appearing for respondent no.2 made a statement at bar that respondent no.2 is going to deposit the amount as early as possible as per impugned order. As and when such amount is deposited by the respondent no.2, the petitioners are at liberty to withdraw the said amount as shown in the calculation sheet submitted by the respondent no.2 at Mark436/1 with Exh.436 by way of account payee cheque on proper verification.

4. The petitioners (Org.claimants) have ventilated

C/SCA/13857/2019 ORDER DATED: 12/04/2022

grievance that the amount already deposited and now to be deposited is less than the amount awarded to the respective petitioners and to demonstrate the said fact the petitioners have furnished calculation sheet with respect to Execution Petition Nos. 60 of 2010 before this Court along with affidavit at page no.77. So, considering the issue involved in the execution proceedings with regard to calculation of the amount and its entitlement under the head claimed by the respective petitioners (Org.claimants), it would meet the ends of justice if the Executing Court is directed to consider the calculation sheet that may be placed on record by the petitioners (Org.claimants) with respect to each claimant and also to provide opportunity to the respondents while deciding the legality and correctness of the calculation that may be placed by the petitioners (Org.claimants) before the Executing Court. The petitioners (Org.claimants) are directed to place their respective calculation sheets before the Executing Court in each execution petition on or before 22.10.2018. On filing of such calculation sheets by the petitioners (Org.claimants), the learned Executing Court shall decide such dispute of calculation in accordance with the provision of law and after hearing both the sides and decide the same as expeditiously as possible but not later than four weeks from the date of filing of the calculation sheets by the respective petitioners (Org.claimants). It is clarified that learned Executing Court shall decide the calculation that may be placed by the petitioners (Org.claimants) on record independently and uninfluenced by the observations recorded in the impugned order and for this limited purpose, the execution proceedings shall stand revived on record of learned Executing Court."

2.5 Pursuant to the aforesaid order dated 06.10.2018, fresh calculation-sheet given by the petitioner before the

C/SCA/13857/2019 ORDER DATED: 12/04/2022

learned Executing Court below Mark : 455/1 and ultimately Reference Court, vide order dated 15.12.2018, passed order below Exh.1 in LAR Execution Petition Nos.60 of 2010 to 68 of 2010. Operative part of the aforesaid order reads as under:-

"As per calculation sheet produced by applicant on record at Mark-455/1 the amount remaining unpaid as on 28.03.2000 is as per column no.27.

For the amount remaining unpaid from 29.03.2000 to 28.11.2018, the applicant is entitled to 15% interest on Net amount payable shown at column no.22 as per the award of District Court as per the calculation sheet Mark - 455/ 1 till realization.

Inspite of the order directing the opponents to pay the amount on or before 30.6.2018 opponents have not complied the same and therefore the opponents are directed to deposit the same amount within 30 days. Further if the opponents fail to deposit the above amount alongwith interest accrued till realization within 30 days, the applicants are at liberty to recover the said amount by application for issuance of Jangam Warrant in accordance with provisions of law.

Order of this petition is kept in the present Execution Petition No.60/2010.

A copy of this order be kept along with the

C/SCA/13857/2019 ORDER DATED: 12/04/2022

Execution Petition No.61/2010 to 68/2010.

Pronounced in open Court on the 15th day of the month of December, 2018."

2.6 According to the present petitioner while passing the aforesaid order, the Reference Court observed that amount shown at column no.28 of the calculation-sheet is incorrect.

2.7 Since to understand the controversy by referring to column which may lead to some confusion, the query was put to learned advocate Mr.Majmudar, at this stage, as to what is column no.28 which is believed to be incorrect by the Reference Court, Mr.Majmudar submitted that by calculating the amount at column no.28 the petitioner has claimed interest over the interest from the date of award till the amount was actually deposited on 28.03.2000.

2.8 The aforesaid order dated 15.12.2018 was challenged by both the sides by way of this group of petitions, the petitioner challenged the aforesaid orders and prayed for remaining amount which has remained unpaid though claimed by the petitioner and stated in column no.31 at page:51 of the petition. The aforesaid amount is an amount calculated by the petitioner towards interest over the interest from the date of award till 28.03.2000, the date on which the aforesaid amount was deposited in the Registry of the trial Court. Whereas the present Respondent No.2 i.e. Defense Estate Officer

C/SCA/13857/2019 ORDER DATED: 12/04/2022

challenged the order dated 15.12.2018 by preferring group of petitions being Civil Revision Application No.335 of 2021 and allied matters before this Court on the ground that it is not open to award interest on interest and Executing Court has placed reliance on the calculation-sheet below Mark 455/1.

2.9 The aforesaid group of petitions being Civil Revision Application No.335 of 2021 and allied matters was dismissed by the coordinate Bench of this Court vide order dated 30.11.2021. In the order dated 30.11.2021, in paras:10, 11, 12, 13 and 14, the Coordinate Bench of this Court, while dismissing the petitions, observed as under:

"10. Now, as per the direction issued by this Court in the aforesaid petitions, the claimants submitted revised calculation sheet at mark 455/1. The Executing Court has considered the aforesaid factual background of the case and thereafter recorded certain undisputed facts. It has been observed by the Executing Court that as per the award dated 1.5.1992 passed by the District court, the claimants are entitled to further amount of 6% severance charge. The High Court, in the First Appeals, has merely reduced the amount of compensation awarded by the District Court by observing that the claimants were entitled to Rs.6/- per sq.mtr for non-irrigated land and Rs.7/- per sq.mtr. for irrigated land. The rate of interest has not been disturbed by the High Court in the First Appeals. Thus, the Executing Court has considered the fact that the claimants are entitled to severance charges as per the award of the District Court.

11. It is also not in dispute that the applicant had

C/SCA/13857/2019 ORDER DATED: 12/04/2022

deposited the principal amount on 28.3.2000 before the District Court. However, the amount of interest @15% was not deposited. It is pertinent to note at this stage that though Special Leave Petition was dismissed by the Hon'ble Supreme Court on 5.1.1998, the principal amount was deposited by the applicant only on 28.3.2000. Thereafter, it is also not in dispute that further amount was deposited by the applicant on 28.11.2018.

12. Keeping in view the aforesaid factual aspects, the Executing Court has rightly observed that the claimant cannot claim interest over interest amount i.e. 15% as per column no.27 but the claimants are entitled to interest 15% as per column no.22. Thus, it is held that the claimants are entitled to interest from 29.3.2000 to 28.11.2018 on net amount payable in column no.22. The Executing Court has further observed that the Executing Court cannot go beyond the decree. Thus, it has been observed that the claimants are entitled to get Rs.7/- per sq.mtr. for irrigated land and Rs.6/- per sq.mtr. for non- irrigated land, 30% solatium and 6% severance charges, 12% additional compensation and thereafter 9% interest and 15% interest as per the provisions of the Land Acquisition Act.

13. Thus, this Court is of the view that the Executing Court has not gone beyond the decree as contended by the learned advocate for the applicant. Further, the Executing Court has also not awarded interest on interest as contended by learned advocate for the applicant.

14. In view of the aforesaid facts and circumstances of the present case, this Court is of the view that no jurisdictional error is committed by the executing court while passing the impugned order dated 15.12.2018 in LAR Execution Petition Nos.142 of 2010 to 155 of 2010 and hence, no interference is required in these

C/SCA/13857/2019 ORDER DATED: 12/04/2022

Civil Revision Applications. Accordingly, all these Civil Revision Applications are dismissed."

2.10 Though the aforesaid Civil Revision Applications preferred by the respondents were dismissed, since the present set of petitions were preferred under Article 226 and 227 of the Constitution of India whereas those group of petitions were filed as Civil Revision Applications, all these mattes were not tagged and heard together and, therefore, though Civil Revision Applications preferred by the respondents were dismissed, the present group of petitions remained pending and are being heard today.

3. Heard learned advocate Mr.Sharvil Majmudar with learned advocate Mr.Kakadia for the petitioners, learned advocate Mr.Ankit Shah with learned advocate Mr.Brijesh Ramanuj for the respondents and learned Assistant Government Pleader Mr.Nikunj Kanara and learned Assistant Government Pleader Mr.Akash Chhaya for the respondent - State authorities.

4.1 Learned advocate Mr.Majmudar submitted that the present petitioners being lost their land pursuant to the land acquisition and in fact the award was passed only on 24.03.1988 whereas for the first time after award was passed amount was deposited in the registry in the year 2012 i.e. after 12 years of the order dated 24.03.2022 and, therefore, though Reference Court has taken care of directing respondents to make payment of interest from 28.03.2000 till 28.11.2018 for a period of 18 years and 08

C/SCA/13857/2019 ORDER DATED: 12/04/2022

months, the trial Court has lost sight of the fact that interest was not awarded and directed to be paid to the petitioners for a period from the date of award i.e. 24.03.1988 till 28.03.2000.

4.2 Learned advocate Mr.Majmudar further submitted that as the interest has not been paid in time, the petitioners have suffered lost on account of financial crunches and even today after the order dated 15.12.2018, after about more than three years also the amount has not been deposited by the respondents and the order of the Reference Court merely remained on paper and has not been executed and, therefore, he prayed for direction directing the respondents to make payment of the amount of interest from 24.03.1988 till 28.03.2000.

5.1 As against that, learned advocate Mr.Ankit Shah for the respondents vehemently opposed the petition and submitted that in fact the petitioners demand for interest from 24.03.1988 till 28.03.2000 has already been considered by the Reference Court. He submitted that in view of calculation-chart produced before the Reference Court, in column no.24, the aspect of interest for a period for which petitioner have claimed interest has been take care of and, therefore, there is no question of making payment of interest once again.

5.2 Mr.Shah further submitted that the very order,

C/SCA/13857/2019 ORDER DATED: 12/04/2022

which is under challenge by way of this group of petitions, has already been examined by the coordinate Bench of this Court and by dismissing petitions preferred by the Respondent No.2 - Defense Estate Officer, the Coordinate Bench of this Court has confirmed the award and pronounced that Reference Court has not committed any error. Mr.Shah submitted that aforesaid order passed by the coordinate Bench of this Court dated 30.11.2021 is binding on this Court as this Court cannot take different view as if the Court is sitting in appeal over the aforesaid order. Mr.Shah further submitted that the order dated 30.11.2021 is not challenged by the Respondent No.2 till date and, therefore, this Court may not take any other view but confirm the order dated 15.12.2018, which is the subject matter of challenge before this Court.

6. Learned Assistant Government Pleader Mr.Akash Chhaya for the respondent - State also opposed the petition by adopting the submissions made by learned advocate Mr.Ankit Shah for the private respondent and prayed for dismissal of the present petition.

7. At this stage, learned advocate Mr.Majmudar clarified that actual the trial Court i.e. Executing Court has committed error by mentioning column no.28 instead of column no.31 and actual grievance in respect of column no.31, which is not disputed by learned advocate Mr.Ankit Shah for the private respondent.

C/SCA/13857/2019 ORDER DATED: 12/04/2022

8.1 Considering the arguments advanced by learned advocates for the parties and after perusing the material available on record as well as the order dated 30.11.2021 passed in Civil Revision Application No.335 of 2021 and allied matters, which is not on record, but it has been provided by both the learned advocate Mr.Majmudar and learned advocate Mr.Ankit Shah appearing for respective parties, this Court is of the view that Reference Court has, in detailed, examined the grievance of the petitioners. In fact, the Reference Court directed both the parties to place on record the respective calculation by the parties. When the calculation submitted by the respondent No.2 - Defense Assistant Officer was disputed and the issue went upto this Court by way of Special Civil Application No.10650 of 2018 and allied matters, ultimately vide order dated 06.11.2018 the Coordinate Bench of this Court directed the Executing Court that the calculation that may be placed by the petitioner on record be decided by the Executing Court independently and ultimately calculation provided by the petitioner was believed except for the calculation no.31 ( as claimed by learned advocate Mr.Majmudar) which is the column whereby the petitioners have claimed for interest which is concurrent interest over interest and above statutory interest @ 15% for a period from 24.03.1988 till 28.03.2000. As such the petitioners are entitled to further interest @ 15% over the interest amount as mandatory as provided by the Act for a period from 24.03.1988 till

C/SCA/13857/2019 ORDER DATED: 12/04/2022

28.03.2000.

8.2 The aforesaid issue was examined by the trial Court and the trial Court has categorically observed in paras:20, 21 and 22 as under:-

"20. The applicant is as such entitled to unpaid amount as on 28.03.2000 as per column no.27 of the Calculation sheet produced at Mark- 455/1. The applicant thereafter at column no.28 claims 15% interest from 29.03.2000 to 28.11.2018 and at column no.30 shows total amount payable as on 28.11.2018 (column no.27 + column no.28 + column no.29 cost awarded by court). The applicant at column no.31 claims 15% interest per day on unpaid amount as on 28.03.2000 i.e. on column no.27.

However, so far as the calculation of applicant in Calculation sheet Mark - 455 / 1 at column no.28 is concerned the applicant is claiming 15% interest on column no.27 but this column no.27 is already including the amount of interest till 28.03.2000. As held in the judgment relied by opponent Prem Nath Kapur Versus National Fertilisers Ltd., 1995 (0) GLHEL - SC 21457 claimants are not entitled to deduct from the amount of compensation towards costs, interest additional amount under section - 23 (1A) within interest and then to claim total balance amount with further interest. Therefore the applicant cannot claim interest over interest amount i.e. 15% column no.27 but applicant is entitled to 15% interest on column no.22. As such the applicant is entitled to 15% interest from 29.03.2000 to 28.11.2018 on Net amount payable at column no.22 and accordingly 15% interest per day on Net amount payable at column no.22.

(21) It is profitable to note that as this court is executing court it is settled principle that

C/SCA/13857/2019 ORDER DATED: 12/04/2022

Executing Court cannot go beyond the decree. In this matter some facts are admitted that land was acquired, award was passed, award was challenged before Hon'ble High Court, thereafter till Supreme Court, Hon'ble High Court has only reduced by Rs.1 the rate fixed by Hon'ble District Court and has not disturbed any other benefits available to the applicants under other heads as awarded by District Court. So this court is of the opinion that the claimants are entitled to get Rs.7 for irrigated land and Rs.6 for non irrigated land and 30% solatium, 6% severance charges, 12% additional compensation and thereafter 9% interest and 15% interest as per the provisions of Land Acquisition Act.

(22) In view of the above discussion the Calculation sheet produced by the applicant at Mark-455/1 is partly considered and the amount remaining unpaid as on 28.03.2000 is as per column no.27. I also agree with the argument of Ld.Adv. For opponent that claimants cannot claim interest over interest and as such, the amount shown at column no.28 of this Calculation sheet is not correct and instead the applicant is entitled to 15% from 29.03.2000 to 28.11.2018 on Net amount payable shown at column no.22 and following order is passed in interest of justice."

8.3 The aforesaid order of the trial Court is confirmed by the Coordinate Bench of this Court vide order dated 30.09.2021. This Court is mindful of the fact that the order of the Coordinate Bench of this Court is passed in respect of the same order dated 15.12.2018 and considering the fact that entire issue revolves around issue agitated about wrong calculation and about entitlement of the petitioners on interest over interest and hence when the aforesaid order dated 15.12.2018 is confirmed by Coordinate Bench of this Court dated

C/SCA/13857/2019 ORDER DATED: 12/04/2022

30.09.2021, this Court cannot sit in appeal over the aforesaid order and, therefore, this Court is of the view that while passing the order dated 15.12.2018 the learned Principal Senior Civil Judge, Palanpur has not committed any error while deciding LAR Execution Petitions being Nos.60 of 2010 to 68 of 2010 and allied matters.

8.4 However, as far as grievance of the learned advocate Mr.Majmudar in respect of the fact that the respondents have not deposited the amount till 15.12.2018 is concerned, the respondents are directed to deposit the amount within a period of two months from today in view of the order which is under challenged by way of this petitions.

9. With the aforesaid observations and directions, present petitions deserve to be dismissed and they are dismissed accordingly. Notice is discharged, in each petition. No order as to costs.

9.1 Office of the Registry to tag the copy of the present order in each petition.

Direct service is permitted.

(NIRZAR S. DESAI,J) MISHRA AMIT V.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter