Citation : 2021 Latest Caselaw 12904 Guj
Judgement Date : 31 August, 2021
C/SCA/13249/2020 ORDER DATED: 31/08/2021
IN THE HIGH COURT OF GUJARAT AT AHMEDABAD
R/SPECIAL CIVIL APPLICATION NO. 13249 of 2020
With
CIVIL APPLICATION (FOR VACATING INTERIM RELIEF) NO. 1
of 2021
In R/SPECIAL CIVIL APPLICATION NO. 13249 of 2020
============================================
SHOBHNABA VIRAJI LALJI SODHA
Versus
DISTRICT COLLECTOR AND DISTRICT MAGISTRATE
============================================
Appearance:
DARSHAN M VARANDANI(7357) for the Petitioner(s) No. 1,2
MR ISHAN JOSHI AGP (1) for the Respondent(s) No. 1
MR GAURAV S MATHUR(5365) for the Respondent(s) No. 2
SINGHI & CO(2725) for the Respondent(s) No. 2
============================================
CORAM:HONOURABLE MR. JUSTICE NIKHIL S. KARIEL
Date : 31/08/2021
ORAL ORDER
1. Heard learned Advocate Shri Darshan M. Varandani for the petitioners, learned Advocate Shri Gaurav Mathur for the respondent No.2 and learned AGP Shri Ishan Joshi for the respondent No.1.
2. This petition has come up for hearing along with the Civil Application for vacating the interim relief. Having regard to the subject matter and dispute herein, this Court has deemed it expedient with the consent of the parties to take up main writ petition for hearing.
3. Learned Advocate Shri Darshan Varandani draws attention of this Court to the Rules being the Works of Licensees Rules, 2006, more particularly Sub-Rule 3(1)(a) thereof and submits that under the said Rules,
C/SCA/13249/2020 ORDER DATED: 31/08/2021
before laying down of an electric supply line or other works, prior consent of the owner and occupier of any building or land is required. Learned Advocate further draws the attention of this Court to an order passed by the Central Electricity Authority dated 27.01.2021 issuing authorization under Section 164 of the Electricity Act, 2003 for laying of electric line under the transmission scheme "Connectivity to M/s. Adani Green Energy Limited for its proposed 300 MW wind farms in Bhuj, Gujarat." and submits that such authorization has been granted subject to certain conditions and whereas learned Advocate relies upon condition (vi) of the said authorization which reads as under:
"the approval is subject to the compliance of the requirement of the provisions of the Electricity Act, 2003 and the Rules made thereunder by the applicant"
4. Learned Advocate Shri Varandani has sought to contend that the authorization under Section 164 required the respondent No.2 to follow the provisions and Rules made under the Electricity Act, 2003 and whereas since Rules referred to hereinabove framed under Clause E of Sub-section 2 of Section 176 read with Sub-Section 2 of Section 67 of the Electricity Act, 2003, therefore, it was incumbent upon the respondent inspite of having authorization under Section 164 of the Electricity Act to have taken prior consent of the land owners i.e. the present petitioner before entering into the land of the petitioner to construct tower for laying down electricity transmission lines. Learned Advocate further submits that this Court may confirm the interim relief till final disposal of the present petition.
5. As against the same, learned Advocate Shri Mathur for the respondent No.2 has drawn the attention of this Court to the judgment of the Division Bench of this Court dated 06.11.2020 in Letters Patent Appeal No.534 of 2020 in case of Gujarat State Energy Transmission Corporation
C/SCA/13249/2020 ORDER DATED: 31/08/2021
Ltd. Vs. Ratilal Maganji Brahmbhatt (Barot), more particularly, Clause 58.13, 58.14, 58.16 which reads as under:
"58.13 Having taken into consideration the relevant provisions of the Indian Telegraph Act, 1885 and Electricity Act, 2003 and analysis of Section 67 and section 164 of the Electricity Act, 2003, the legal position is that, whenever an order is passed by the appropriate Government, in exercise of powers under Section 164 of the Electricity Act, 2003, for placing of electric lines for the transmission of electricity, conferring upon any public officer, licensee or any other person engaged in the business of supplying electricity any of the powers which the telegraph authority possesses under the Indian Telegraph Act, 1885, with respect to the placing of telegraphic lines and posts for the purposes of a telegraph established by the Government, such public officer, licensee or any other person engaged in the business of supplying electricity, exercises all the powers, as that of the telegraph authority, under the Indian Telegraph act, 1885.
58.14 However, in the absence of such an order under Section 164 of the Electricity act, 2003, if a licensee i.e., a person who has been granted a licence to transmit electricity or to distribute electricity under the Act, proposes to place electric lines, electric plant or other works necessary for transmission or supply of electricity, Section 67 of the Electricity Act, 2003 comes into operation and consequently, prior consent of the concerned owner or occupier, may be required, under Section 12 (2) of the Indian Electricity Act, 1910.
58.16 Section 16 states that if there is any resistance or obstruction, the District Magistrate may in his discretion, order that the telegraph authority shall be permitted to exercise all the powers.
C/SCA/13249/2020 ORDER DATED: 31/08/2021
Further, after such an order, a person offering any further resistance is deemed to have committed offence under Section 188 of the Indian Penal Code. Once the technical feasibility of the project, has been approved by the appropriate Government, by issuing an order under Section 164 of the Electricity Act, 2003, no land owner or person interested can seek for shifting or re-aligning of the route, on the premise that the District Collector-cum-District Magistrate, has the powers to do so. The District Collector has no powers to alter any route or alignment, except to remove the difficulties faced by the licencee or the person authorised, pursuant to the orders issued under Section 164 of the Act."
6. Learned Advocate based upon the said conclusion has submitted that the Division Bench of this Court has clearly laid down that a licensee is required to follow the provisions of the Works of Licensees Rules, 2006 made under Section 67(2) of the Electricity Act, 2003 till such time the licensee is granted an authorization under Section 164 of the Electricity Act, 2003 and whereas once such an authorization is granted then no consent or prior permission of an owner or occupier of the land is required before entered into land for placing transmission line. Learned Advocate submits that the petition has been preferred at a stage when the respondent No.2 had been granted authorization under Section 164 of the Electricity Act and whereas the allegation at the relevant point of time was that though the respondent No.2 was exercising authority under the Works of Licensees Rules, 2006 yet as envisaged under the Rules, the respondent No.2 had not take prior permission of the petitioner before entering into the land of the present petitioner. It is further submitted in this regard that at the relevant point of time, the respondent No.2 had not entered into the land of the present petitioner and it is further submitted that in any case, now the respondent No.2 has been granted authorization by the Central Electricity Authority under Section 164 of the Electricity Act, 2003, therefore, there is
C/SCA/13249/2020 ORDER DATED: 31/08/2021
no question of seeking prior permission or giving notice to the owner or occupier of the land in question. It is therefore, submitted by learned Advocate Shri Mathur that present petition is now covered by the decision of the Division Bench and hence, nothing remains and therefore, present petition may be dismissed.
7. In rejoinder, learned Advocate Shri Varandani has submitted that since the authorization under Section 164 clearly requires that the condition shall be followed and one of the condition being to follow the provision of the Electricity Act and Rules made thereunder and since the Works of Licensees Rules, 2006, are framed under the Electricity Act, therefore, it was incumbent upon the respondent No.2 to have followed the said Rules and take prior permission from the land owner i.e. the present petitioner.
8. Having regard to the submission made by the learned Advocates for the parties, this Court is of the prima facie opinion that the issue involved in this petition is squarely covered by the decision of the Division Bench of this Court in the case of Ratilal (Supra) and whereas once authorization under Section 164 of the Electricity Act, 2003 is granted by the competent authority under the Electricity Act, 2003, there is no requirement upon the licensee to take prior permission or consent from the land owner or the occupier. Under such circumstances, the interim relief granted earlier cannot be continued any more, at the same time, in view of the specific submission made by learned Advocate Shri Varandani for the petitioner as regards condition (vi) in the authorization under Section 164 of the Electricity Act to the respondent No.2, this Court deems it appropriate to direct the present petitioner to join the Central Electricity Authority as respondent No.3 so that appropriate clarification can be obtained. The present petition is therefore now restricted to this limited aspect of having clarification from the Electricity Authority with regard to the condition (vi) of the Authorization dated 27.01.2021 under Section 164 of the Electricity Act in
C/SCA/13249/2020 ORDER DATED: 31/08/2021
favour of the respondent No.2.
9. In view of the above discussion hereinabove, interim relief granted by this Court vide order dated 27.10.2020 shall stands vacated forthwith.
Upon Central Electricity Authority being joined as party respondent No.3, issue Rule to the said Authority returnable on 05.10.2021.
(NIKHIL S. KARIEL,J) Y.N. VYAS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!