Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Page No.# 1/4 vs The Union Of India And 2 Ors
2025 Latest Caselaw 7889 Gua

Citation : 2025 Latest Caselaw 7889 Gua
Judgement Date : 17 October, 2025

Gauhati High Court

Page No.# 1/4 vs The Union Of India And 2 Ors on 17 October, 2025

Author: Devashis Baruah
Bench: Devashis Baruah
                                                                    Page No.# 1/4

GAHC010065262018




                                                              2025:GAU-AS:13969

                        THE GAUHATI HIGH COURT
  (HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)

                            Case No. : WP(C)/2123/2018

         MRT SIGNALS LTD.
         2, RAJA WOODMUNT STREET, 3RD FLOOR, KOLKATA, WEST BENGAL



         VERSUS

         THE UNION OF INDIA AND 2 ORS.
         REP. BY THE COMM. AND SECY. TO THE GOVT. OF INDIA, MINISTRY OF
         RAILWAY, NEW DELHI

         2:N. F. RAILWAYS

          REP. BY THE GENERAL MANAGER
          HAVING HIS OFFICE SITUATED AT MALIGAON
          GUWAHATI.

         3:THE DY. CHIEF SIGNAL AND TELECOM ENGINEER/CONSTRUCTION

          AGARTALA AT MALIGAON
          GUWAHATI



                                  BEFORE
               HON'BLE MR. JUSTICE DEVASHIS BARUAH


     Advocates for the petitioner(s)    :Mr. A Goyal


     Advocates for the respondent(s) : Mr. B Sarma

Standing Counsel, Page No.# 2/4

NF Railways

Date of hearing & judgment :17.10.2025

JUDGMENT & ORDER(ORAL)

Heard Mr. A Goyal, the learned counsel appearing on behalf of the petitioner. Mr. B Sarma, the learned Standing Counsel, NF Railways appears on behalf of all the respondents.

2. The present writ petition has been filed by the petitioner being aggrieved by the actions on the part of the respondent authorities in reducing the amount to which the petitioner is entitled to for the contract which the petitioner had completed with due satisfaction of the respondent authorities.

3. It is the specific case of the petitioner that as per the contract agreement, the petitioner had to "Design, Manufacture, Supply of Solid State (Electronic) Interlocking System, which included 530 numbers of Function/Bit and the price for each individual Bit was fixed at Rs.51,950/- and, therefore, the total price on account of supply of 530 numbers of Function/Bit was fixed at Rs.2,75,33,652/-.

4. It is the further case of the petitioner that the Contract Agreement which was entered into by and between the petitioner and the respondent No.3, the work had to be completed within 120 days from date of issuance of the letter of Page No.# 3/4

acceptance and the value of the contract was fixed at Rs.6,16,37,725.34/-. During execution of the project, it was found that as per the design approved by the Office of the respondent No.3, there was an excess of 195 Function/Bit Hardware System cater for Function/Bit of about 195 in numbers would be required to complete the entire project as assessed by the respondent No.3/the Site Engineer and accordingly the petitioner supplied the additional Hardware System required to cater the additional functions of the Bit. In that view of the matter, a Subsidiary Agreement was executed by the parties on 08.07.2016 and in view of the Subsidiary Agreement, the original contract price which was fixed at Rs.6,16,37,725.34/- was increased to Rs.8,40,05,226/-. The petitioner received an amount of Rs.7,68,94,000/- and a balance amount of Rs.71,00,000/- was pending.

5. It is the grievance of the petitioner that the respondent authorities, more particularly, the respondent No.3 had finalised the dues of the petitioner at Rs.7,64,52,665/- ex-parte and the petitioner was asked also to sign another document accepting the ex-parte decision, which the petitioner refused and approached this Court.

6. This Court duly takes note of that as per the terms and conditions entered into by and between the petitioner and the respondents, there is an arbitration agreement in Clause 34 of the terms and conditions of the contract, which refers to Clause 63, 64.1 to 64.7 of the General Conditions of the Contract of the NF Railway 1998 Edition, subject to any correction made prior to the opening of the tender. Therefore, it is seen that the dispute in question is arbitrable in Page No.# 4/4

nature.

7. This Court had heard the learned counsels appearing on behalf of both the parties and as it is the specific submission made by the learned counsel appearing on behalf of the petitioner that the said decision was taken ex-parte without making the petitioner aware. It is the opinion of this Court that the petitioner should be given an opportunity to submit a representation before the respondent authorities, more particularly the respondent No.3, agitating the grievance, insofar as, the alleged ex-parte, reconciliation of the accounts.

8. Mr. A. Goyal, the learned counsel appearing on behalf of the petitioner submits that the same would be done within a period of 15 days from today.

9. Considering the above, this Court directs the respondent Nos. 2 and 3 to decide on the representation, if so submitted by the petitioner within 24.11.2025, within a period of 60(sixty) days from the date of submission of the representation. It is the further opinion of this Court that if the petitioner is aggrieved by the outcome of the decision in the representation, the petitioner can take resort to Clause 34 of the Terms and Conditions of the Agreement.

10. The writ petition, accordingly, stands disposed of.

JUDGE

Comparing Assistant

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter