Citation : 2025 Latest Caselaw 1675 Gua
Judgement Date : 1 August, 2025
Page No.# 1/5
GAHC010106222019
2025:GAU-AS:10007
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/3316/2019
ARUP GOGOI
SON OF LATE TARA NATH GOGOI, RESIDENT OF HOUSE NO.-23, BYE
LANE-1, AJANTA PATH, SURVEY, BELTOLA, P.S.- HATIGAON, GUWAHATI-
781028, DISTRICT- KAMRUP(M), ASSAM.
VERSUS
THE STATE OF ASSAM AND 2 ORS.
REPRESENTED BY THE SECRETARY TO THE GOVERNMENT OF ASSAM,
URBAN DEVELOPMENT DEPARTMENT, DISPUR, GUWAHATI- 781006,
KAMRUP(M), ASSAM.
2:ASSAM URBAN WATER SUPPLY AND SEWERAGE BOARD
( AN ASSAM GOVERNMENT UNDERTAKING)
REPRESENTED BY THE MANAGING DIRECTOR
AMRITPUR PATH
GANESHGURI
GUWAHATI- 781006
KAMRUP(M)
ASSAM.
3:EXECUTIVE ENGINEER
DIBRUGARH DIVISION
ASSAM URBAN WATER SUPPLY AND SEWERAGE BOARD (AN ASSAM
GOVERNMENT UNDERTAKING)
DIBRUGARH
ASSAM
Page No.# 2/5
BEFORE
HON'BLE MR. JUSTICE DEVASHIS BARUAH
Advocate for the petitioner(s): Ms. C M Deka
Advocate for the respondent(s): Mr. R Talukdar for respondent Nos.1 and 2
Date of hearing & judgment : 01.08.2025
JUDGMENT & ORDER(ORAL)
Heard Ms. M Deka, the learned counsel appearing on behalf of the petitioner. Mr. R Talukdar, the learned counsel, who represents the respondent Nos.1 and
2. None appears on behalf of the respondent No.3.
2. The petitioner herein has approached this Court being aggrieved on account of non-payment of an amount of Rs.12,37,524/- which the petitioner claims to be entitled to having completed the work in question. The materials on record show that the preliminary work order was bearing No.UWS(T)- 1237/2005/Pt-1/63/261 dated 29.08.2012 was issued to the petitioner for construction of water retaining structure (Balance part of 550cm capacity Elevated Service Reservoir) for Makum Town Water Supply Scheme was allotted to the petitioner for an amount of Rs.58,50,924/- thereupon, the agreement was entered into by and between the petitioner and the respondent authorities and pursuant thereto a final work order was issued on 16.10.2012.
Page No.# 3/5
3. It is the case of the petitioner that the petitioner had already received an amount of Rs.54 lakhs, out of the total contractual amount of Rs.58,50,924/- and there was a balance of Rs.4,50,924/-, which the petitioner was entitled to. In addition to that, the petitioner was also entitled to the security deposit of Rs.3,00,600/- and Rs.4,86,000/- which was deducted @9% as Performance Security. In total, the petitioner was entitled to Rs.12,37,524/-. But the petitioner on various occasions requested the respondent authorities to make payment of the said amount. However, as no payment was made, the petitioner approached this Court by filing the present writ petition.
4. It is seen that this Court issued notice on 24.05.2019. Thereupon, the respondent No.3 had filed an affidavit-in-opposition wherein it has been categorically mentioned that the petitioner did not complete the work in the entirety. The stand of the respondent No.3 can be seen from paragraph 6 of the said affidavit-in-opposition which is reproduced hereinunder:
"6. That with regards to the paragraph 5 of the writ petition, the deponent begs to state that the work was allotted to the petitioner for execution, testing and commissioning of the work in all respect and to be completed within 8(Eight)
months failing which penalty may be imposed as per clause 2 of the agreement which was signed between the petitioner and the respondent Board, represented by Respondent No.2. The petitioner was required to do the testing of the Elevated Service Reservoir which is required to comply of from the date of commissioning and handing over the works to the then Respondent No.3, the defect liability period of the contract remains for 12(Twelve) months. Any defects occurred in between that period will have to be rectified by the contractor at his own cost and risk. During testing of the said Elevated Service Reservoir (ESR), by the respondent Board several leakages occurred in Elevated Service Reservoir(ESR) and the respondent Board requested the petitioner to Page No.# 4/5
rectify the said leakages. The then Respondent No.3 also requested the petitioner to remove the scaffolding
used for the Elevated Service Reservoir (ESR) to clear the site, which the petitioner did not abide by. Since the petitioner did not repair the leakages after several requests by the respondent Board, the officials of the respondent Board had to take initiative of its own for repairing the said leakages for the sake of the project. The petitioner did not complete the work as per tender agreement."
5. From the above quoted paragraph, it would be seen that the respondent authorities categorical stand is that the petitioner is not entitled to any further amount on the ground that the petitioner had failed to complete the entire work as per the tender agreement. It is further pertinent to take note of that the said affidavit-in-opposition was filed on 30.08.2019 and there was no reply filed to the said averments made in the said affidavit-in-opposition, more particularly, paragraph 6 as quoted hereinabove. From the above, therefore, it appears that there are disputed questions of fact as to whether the petitioner is entitled to the amount so claimed in the instant writ petition or not. This disputed question of fact cannot be adjudicated in exercise of the jurisdiction under Article 226 of the Constitution.
6. Accordingly, this Court dismisses the instant writ petition on the ground of non-entertainability.
Page No.# 5/5
7. Before parting with the records, this Court, however, observes that the period during which the instant writ petition has been pending i.e. from 14.05.2019 till date be excluded while computing the period of limitation, if the petitioner prefers any suit before the competent Court of Jurisdiction.
JUDGE
Comparing Assistant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!