Citation : 2022 Latest Caselaw 4138 Gua
Judgement Date : 27 October, 2022
Page No.# 1/20
GAHC010179982020
THE GAUHATI HIGH COURT
(HIGH COURT OF ASSAM, NAGALAND, MIZORAM AND ARUNACHAL PRADESH)
Case No. : WP(C)/5308/2020
MAKSUD AHMED MAZUMDER
S/O LATE MOHIBUR RAHMAN MAZUMDER
RESIDENT OF BERENGA PART II
PO BERENGA PART II, PS SILCHAR, DIST CACHAR, ASSAM 788005
VERSUS
FOOD CORPORATION OF INDIA AND 7 ORS.
HAVING ITS HEADOFFICE AT 16-20, BARAKHAMBA LANE, NEW DELHI
110001, INDIA AND REGIONAL OFFICE AT PALTAN BAZAR, GUWAHATI
KAMRUP M ASSAM 781008
2:EXECUTIVE DIRECTOR
FOOD CORPORATION OF INDIA
(HEADQUARTER) 16-20
BARAKHAMBA LANE
NEW DELHI 110001. INDIA
3:THE GENERAL MANAGER
ENGINEERING
FOOD CORPORATION OF INDIA
(HEADQUARTER) 16-20
BARAKHAMBA LANE
NEW DELHI 110001. INDIA
4:THE DEPUTY GENERAL MANAGER
(CE)
FCI ZONE OFFICE (NORTH EAST) GUWAHATI 7
KAMRUP M ASSAM
Page No.# 2/20
5:THE ASSISTANT GENERAL MANAGER (CE)
FCI. REGIONAL OFFICE
PALTAN BAZAR
GUWAHATI KAMRUP M ASSAM 781008
6:THE AREA MANAGER
FCI
DO SILCHAR
CACHAR
7:THE MANAGER (DEPOT)
FCI
FSD
RAMNAGAR
SILCHAR
DIST CACHAR
ASSAM
8:THE JUNIOR ENGINEER (CE)
FCI
DO SILCHAR
CACHAR
ASSA
Advocate for the Petitioner : MR. K N CHOUDHURY
Advocate for the Respondent : SC, F C I
BEFORE THE HON'BLE MR JUSTICE ARUN DEV CHOUDHURY
For the petitioner :Mr. KN Chowdhury, Sr. Advocate Mr. BJ Ghosh, Advocate
For the Respondents : Mr. BK Singh, SC, FCI
Date of Hearing : 09.06.2022
Date of Judgment & Order : 27.10.2022 Page No.# 3/20
JUDGEMENT & ORDER (CAV)
Heard Mr. KN Choudhury, learned Senior counsel assisted by Mr. BJ Ghosh, learned
counsel for the petitioner. Also heard Mr. BK Singh, learned standing counsel for the FCI.
2. The brief fact of the case:
The respondent FCI invited e-tender on 01.11.2017 for the construction of
Cement Concrete Road proposed to be around 4 numbers of existing Food Storage
Godowns at FSD, Ramnagar, Silchar, Cachar with an estimated cost of Rs.
2,26,10,750/-, which is to be completed within a period of 90 days. The petitioner, a
Class-1 contractor participated in the NIT. The petitioner submitted his quoted bid
value of Rs. 2,38,12,642/-, which was accepted by the respondent FCI through their
letter dated 27.02.2018. Thereafter, the respondent FCI requested the petitioner to
arrange for Design Mix M-30 from any renowned Government Engineering College and
the same was done by the petitioner. Thereafter, NIT, Silchar evaluated the M-30
design mix and submitted the report to FCI on 27.04.2018 but no approval was given
to the petitioner and asked the petitioner for fresh M-30 Design mix from NIT Silchar
and accordingly the petitioner submitted the sample material for evaluation to NIT
Silchar. Again, the respondent FCI vide letter dated 14.12.2018 asked the petitioner for
fresh evaluation of the M-30 Design Mix from NIT Silchar in presence of Junior
Engineer. The respondent FCI again vide letter dated 28.01.2019 asked for a fresh
evaluation report of the M-30 Design Mix from IIT, Guwahati which was received on
20.03.2020. According to the the petitioner, he had made several communications with
FCI for delay in starting of the remaining work due to the non approval of the M-30 Page No.# 4/20
Design Mix, but the respondent FCI vide letter dated 04.03.2020 issued show cause
notice on the petitioner which was replied by the petitioner through his letter dated
13.05.2020, denying the allegations made in the show cause notice and the petitioner
expressed his desire to complete the work in the event the respondent FCI agrees to
enhance 30 % from the quoted rate to restart the remaining works due to the increase
of price of materials in last 24 months, which is beyond the date of completion.
Thereafter, the petitioner filed WP(C) 3907/2020, however, such writ petition was
withdrawn by the petitioner with a liberty to file a fresh petition in order to assail the
termination order dated 08.06.2020 and the petitioner filed fresh writ petition being
WP(C)4856/2020 challenging the impugned final notice dated 08.06.2020, which was
also withdrawn as the respondent FCI issued impugned tender notice dated
20.11.2020 with a liberty to file fresh petition challenging the final notice dated
08.06.2020.Accordingly, the petitioner filed this writ petition.
3. The facts pleaded by the petitioner:
I. On 01.11.2017, Executive Director on behalf of Food Corporation
of India invited e-tender for construction of Cement Concrete Road
proposed to be executed around 4 numbers of existing Food Storage
Godowns at FSD, Ramnagar. Respondent authority accepted the offer of
the petitioner vide letter dated 23.02.2018.
II. On 14.03.2018, the petitioner was requested to execute formal
agreement and take possession of the work site and to start the work
and also asked to arrange for Design Mix M-30 from any renowned
Government Engineering College and on 19.03.2018, a contract Page No.# 5/20
agreement was executed between the petitioner and the respondent
authority.
III. Thereafter, the petitioner submitted petition on 28.04.2018
informing the authority that work site clearly not handed over and it has
affected the WBM and concrete work held up for quite long time and the
work was delayed.
IV. On 18.05.2018, the petitioner again informed the respondent
authority that the work could not be proceeded further due to heavy rain
and vehicle are running in the construction area.
V. Thereafter, the respondent authority received the report of Mix
Design M-30 from NIT Silchar but could not be finalized. And thereafter,
on 22.06.2018, the petitioner requested the respondent authority to
hand over the site for PCC work by making vehicle free zone as WBM
work completed because only scope of work only is PCC work since the
M-30 design is not finalized.
VI. The petitioner was directed to send requisite materials for fresh
evaluation of design mix from NIT Silchar on 25.07.2018. and samples
were sent on 27.07.2018.XIV. A letter was submitted on 30.08.2018
before the respondent FCI for approval of Design Mix M-30 otherwise
work will not progress.
VII. On 08.10.2018, he Asst. General Manager, CE directed the
petitioner to complete the drains and culverts till finalization of Design
Mix M-30.
Page No.# 6/20
VIII. On 06.11.2018, Assistant General Manager, CE extended the
time for completion of work up to 31.12.2018 without informing the
petitioner.
IX. On 14.12.2018, the Assistant General Manager, CE again issued
another letter directing the petitioner to arrange Design Mix M-30. And
thereafter, on 24.12.2018, the without any information to the petitioner
extended the time up to 30.01.2019.
X. On 28.01.2018, the Assistant General Manager, CE requested the
petitioner to supply samples of the materials to be sent to IIT Guwahati
for testing of Design Mix M-30.
XI. Thereafter, the Assistant General Manager, CE without any
information to the petitioner extended the time up to 28.02.2019 on
28.01.2019 and further went on extending the validity period of the
agreement till 30.03.2019 without any consent from the petitioner.
XII. On 09.05.2019, the petitioner submitted letter to disassociate
himself from the agreement as the authority was not approving the
design of M-30 grade mix concrete and also requested to allow him to lift
his T&P machines etc. from the site.
XIII. However, on 23.05.2019, the respondent Assistant General
Manager, CE issues a show cause to which, the petitioner submitted a
reply on 29.05.2019 denying each and every allegation made and
requested for return of PG with interest at prevailing rate.
XIV. The petitioner submitted final bills on 04.07.2019 and requested Page No.# 7/20
for payment. And on 10.08.2019 The petitioner submitted notice under
Clause 25 of the agreement for settlement of disputes along with list of
claims.
XV. On 25.09.2019, the Assistant General Manager, CE refuted the
claims of 30% enhancement of quoted price as requested by the
petitioner on untenable and whimsical grounds and also discarded the
claims made under Clause-25.
XVI. Thereafter, on 04.03.2020, show cause notice was issued to
the petitioner and on 13.05.2020, the petitioner replied to the show
cause notice denying each and every allegation. A final notice was
issued on 08.06.2020 to which, the petitioner replied on 13.06.2020,
interalia taking a stand that the contract agreement has already expired
long before and does not exist anymore as of now.
4. Learned Senior counsel Mr. K N Choudhury appearing for the
petitioner submits as follows:
I. From the facts and record available there is no dispute on the fact that
the execution of the project has been delayed for non-approval of the Design
mix at the end of the respondent employer and not for any fault on the part of
the petitioner inasmuch as in view of such fault on the respondent employer, the
petitioner is entitled for escalation in prices as price of materials has already
increased. Further, delay is also admittedly attributable for non-handing over of
the site. Therefore, the authority could not have issued the fresh tender and it
ought to have allowed the petitioner to complete the work by allowing price Page No.# 8/20
escalation.
II. The termination itself is having no meaning inasmuch as prior to such
termination not only the contract period was over but also the petitioner had
withdrawn from the contract itself and took recourse to the provision of Clause
25 of the contract itself for redressal of the dispute. However same has also
been rejected by a cryptic order. Therefore, the employer is not competent
under the terms of the contract to issue the impugned order and advertisement
and the petitioner is entitled to complete the work with escalated price.
III. The impugned order of debarring the petitioner in participating in
future tender process relating to the work contract is without any reason. The
action of the State and its instrumentality must be supported by a reason and
when such order is not supported by any reason, the action hits at the root of
Article 14 of the Constitution of India and therefore, the impugned order is
liable to be set aside and quashed.
IV. When an instrumentality of the State is a party to a contract, it has an
obligation to act fairly, justly and reasonably which is requirement of Article 14
of the Constitution of India. In the present case, the basic prayer is for quashing
the order whereby, the petitioner is barred from participation in future tender
process relating to the work in question inasmuch as the petitioner had himself
withdrawn from the contract for the reason of delay caused in executing the
contract for the fault of the employer and denial of escalation in price.
V. The action of the respondents in the face of it is arbitrary and
unreasonable resulting in violation of the petitioner's right under Article 14 of Page No.# 9/20
the Constitution of India. In support of such contention Mr. Choudhury relies on
a judgment of the Hon'ble Apex Court in A.B.L International Limited -Vs-
Export Credit Guarantee Corporation of India Limited reported in 2004
3 SCC 553 and the judgment of the Hon'ble Apex Court in Kumari Shrilekha
Vidyarthi, -Vs- State of UP reported in 1991 1 SCC 212.
5. The pleaded case of the respondent FCI can be summarized
as follows:
I. Petitioner's tender was accepted by the FCI at the estimated cost of Rs.
2,26,10,750/-. And On 14.03.2018, the petitioner was asked to take possession
of site and start work.
II. The petitioner submitted report on 27.04.2018 of Mix Design (M30)
wherein Cement consumption per cubic meter was 450 kg.
III. As the first report of design mix M-30 was not in conformity with the
specifications laid down in the contract, therefore, the petitioner on 25.07.2018
was asked to arrange fresh design mix M-30 from any renowned Government
Engineering College.
IV. As the design Mix of M-30, which was carried from NIT Silchar two
times but still the cement consumption was on a higher side as compared with
DSR 2016 items, as such FCI requested the petitioner to provide samples to the
FCI, RO so that FCI can submit to IIT, Guwahati for testing of M-30 design mix.
V. On 23.02.2019, FCI, Silchar requested petitioner again to arrange M-30
design mix from IIT-Guwahati along with detail properties of all constituent Page No.# 10/20
materials. However, the petitioner on 09.05.2019 proclaimed disassociated from
the said agreement and claimed for damages and losses.
VI. The FCI claims that contract is still alive and requested the petitioner to
collect samples for RMC plant for M-30 test. Since the petitioner was not taking
out any effort to arrange design Mix from IIT, Guwahati, the FCI vide its letter
dated 01.07.2019 requested IIT, Guwahati to arrange the Mix design.
VII. In the meantime, on 19.08.2019, the petitioner invoked Clause 25 and
filed list of claims including damages. Thereafter, on 25.09.2019, FCI asked the
petitioner to pursue the IIT-Guwahati to get M-30 design.
VIII. After getting the report from IIT, on 27.01.2020, FCI sent M-30
design to the petitioner and asked to restart work. Again on 06.02.2020, FCI
requested the petitioner to restart the work. On 04.03.2020, FCI issued show
cause notice because of delay and suspension of work by the petitioner. And in
the meantime, on 20.03.2020, FCI submitted full-fledged report of M-30 issued
by IIT, Guwahati.
IX. The petitioner replied to the show cause and agreed to work at
enhanced rate by 30%. As the 30% enhancement is against the provision of
agreement and therefore, action as per agreement was necessary to be taken
against the petitioner.And accordingly issued order impugned in the present writ
petition.
6. The learned counsel for the respondent FCI submits as
follows:
Page No.# 11/20
Mr. BK Singh, learned standing counsel for the respondent FCI submits the
following:
I. Clause 10(A) of the tender agreement says that it is the sole
responsibility of the petitioner to supply the materials for testing at his
own cost.
II. Clause 5 of the tender agreement says about the time and
extension for delay. The respondent FCI refutes that the time of
completion of work was extended solely because of negligence on the
part of the respondent in taking the decision to approve Mix Design M-
30.
III. The present is a contractual dispute and therefore, the writ
Court may not like to interfere with such contractual decision.
IV. The deficiency in performance of the contract as well as
abandoning the contract site and the legality of the reasons thereof
cannot be a subject matter of a writ petition inasmuch as for such
determination evidences are required. Due to inability of the petitioner to
perform the contract, the FCI was compelled to terminate the contract by
the impugned order and had decided not to allow such a contractor to
participate in the tender.
V. It is well settled that dispute relating to the contract cannot be
agitated under Article 226 of the Constitution of India. Mr. Singh, learned
counsel relies on paragraph 6 of a judgment of the Hon'ble Apex Court in
National Highway Authority of India. -Vs- Ganga Enterprises Page No.# 12/20
reported in AIR 2003 SC 3823.
7. Reason and determination:
This Court has given anxious consideration to the submissions made by the learned
counsel for the parties, gone through the materials available on record. The basic
issue for determination is whether this Court should entertain the present writ
petition interfering with the order of termination of the contract and also the
consequential orders and the same are discussed in the following manner.
A. The termination of the contract:
I. The Hon'ble Apex Court while dealing with a difference between statutory
contracts and private contract between private individual and instrumentally of
the State, held in Pimpry Chinwad Municipal Corporation Vs. Gayatri
Construction Company reported in (2008) 8 SCC 172 that if a term of
contract is violated, ordinary remedy is not the writ petition under Article 226 of
the Constitution of India. It was also held that a contract would not become
statutory simply because it is for construction of a public utility and it has been
awarded by a statutory body. It was further held that the dispute relating to
interpretation of the term and conditions of such contract cannot be agitated in a
petition under Article 226 of the Constitution of India, rather it is a matter for
adjudication by a Civil Court or in arbitration, if provided for in the contract. It
was also held that a contract between the parties is a contract in the realm of
private Law.
II. The Hon'ble Apex Court also in catena of decision considered the scope
of exercise of power by High Court under Article 226 of the Constitution of India Page No.# 13/20
in relation to contractual obligation of the State or its instrumentalities with the
citizens in the backdrop of violation of right of citizens under Article 14 of the
Constitution of India. The Hon'ble Apex Court in the case of Ramana Dayaram
Shetty -VS- the International Airport Authority of India reported in AIR
1979 SC 1628 held that modern welfare state which is committed to egalitarian
values and dedicated to the rule of law has to act while awarding contract, under
the Constitutional mandate of Article 14 of the Constitution of India and the
Government cannot act arbitrarily in its sweet will like private individual and the
action of the State must be in conformity with standard or norm which is not
arbitrary, irrational and irrelevant. The Hon'ble Apex Court in the case of Kasturi
Lal Lakshmi Reddy -VS- State of Jammu and Kashmir reported in AIR
1980 SC 1992 held that whatever the activity, a Government is still a
Government and is subject to restrain inherent in its position in a democratic
society and the power of Government cannot be exercised arbitrarily or in an
unprincipled manner. In the case of A.B.L International Limited -Vs- Export
Credit Guarantee Corporation of India Limited reported in (2004) 3 SCC
553, the hon'ble Apex Court held that a writ petition involving serious disputed
question of fact which requires consideration of evidence will not normally be
entertained by a court in exercise of its writ jurisdiction, but there is no absolute
rule that in all cases involving disputed question of fact the parties should be
relegated to a civil suit. It was further held that on a given set of facts if the
State acts in an arbitrary manner even in a matter of contract an aggrieved party
can approach the court by way of writ petition and the writ court, depending on Page No.# 14/20
facts of the said case is empowered to grant relief.
III. Thus law is by now well settled that High Court has a discretion to
entertain or not entertain a writ petition involving contractual disputes, wherein
state or its instrumentality is a party and such discretionary power shall not be
exercised in exclusion of alternative remedies until and unless the action of the
State is arbitrary, unreasonable resulting in violation of the right of a citizen
under Article 14 of the Constitution of India.
IV. It is also a settled proposition of law that in a case of dispute arising out
of a statutory contract, a judicial review under Article 226 of the Constitution of
India is permissible. When an instrumentality of the State acts contrary to public
good and public interest, unfairly, unjustly and unreasonably in its contractual,
constitutional or statutory obligation it really acts contrary to the Constitutional
guarantee under Article 14 of the Constitution.
V. Thus when the dispute arises out of performance or non performance of
contractual liabilities as per the term of the contract and if the allegation and
counter allegations are made regarding violation of terms of the contract, a writ
Court generally shall not enter into the arena of such dispute and rather the
parties should be relegated to the remedy of a civil Court or to any other remedy
that the parties has agreed between them for determination of such disputes,
including arbitration. It is also well settled that when the action challenged
involves exercise of administrative power/executive power, arising out of a
contract, a judicial review under Article 226 of the Constitution of India shall be
permissible inasmuch as exercise of such administrative power/executive power Page No.# 15/20
is not controlled by the term of the contract.
VI. From catena of decision, it can safely be concluded that a writ Court
should not exercise its extra ordinary power in the case of pure contractual
matters/disputes and it can exercise its power when the petitioner can satisfy
the writ court that the remedy is not a private law remedy but a public law
remedy.
VII. Since, the present contract in question is a contract between the
respondent FCI and the petitioner for execution of a work contract and governed
by the terms of the contractual obligations, the considered opinion of this Court
is that such contractual obligation is a matter of private law remedy. The
correctness of satisfaction of the respondent FCI cannot be tested by this court
in exercise of its power of judicial review inasmuch as the reason for such
termination is stated to be violation of the terms of the contract. Therefore, this
Court is not inclined to interfere with the impugned decisions to terminate the
contract.
B. The Advertisement:
I. From different pronouncements of Hon'ble Apex Court ( Tata
Cellular Vs Union of India-1994 6 SCC 651 , Afcons Infrastructure
Ltd. Vs Nagpur Metro Rail Corpn. Ltd. - (2016) 16 SCC 818 , Silppi
Constructions Contractors vs. Union of India and Another - (2020)
16 SCC 489) this court can take judicial notice that there has been a rise in
scrutiny of tender in writ proceedings under Article 226 of the Constitution of
India and almost all tenders are sought to be challenged by way of the writ Page No.# 16/20
petition in a matter of routine. In the aforesaid backdrop, Hon'ble Apex court
has repeatedly held that in certain aspects relating to tender judicial review is
equivalent to judicial restraint. The Hon'ble Apex court has viewed that such
review should relate not to the decision itself but to the decision making
process. It is well settled that the writ court does not have the expertise to
correct such a decision by substituting its own decision for the decision of the
authority.
II. From the aforesaid pronouncements of the Hon'ble Apex court, it
can safely be concluded that the Apex Court has consistently viewed that
judicial review of a decision of public authorities, so far it relates to the award
of the contract, should be limited. It is equally well settled that as the process
of tender involves public authorities, the court does have the authority to
intervene in terms of how a decision, action or process was arrived at.
Therefore, to intervene in such a situation, while making a judicial review of
the action, the court must satisfy that the action of the authority is arbitrary,
irrational, malifide, whimsical or contrary to law, done to favour someone,
done with an ulterior motive, misuses its power or such action has adversely
affected public interest. The court can also intervene, if it is shown that a
condition which is essential is not complied with or which is not essential is
being insisted upon and applying such method contract work is allotted to
some favoured party.
III. From the discussions made herein above the following proposition
of the Law can be summarized:
Page No.# 17/20
a. When a State or its instrumentalities enters into any contract
its conduct should be fair and reasonable and cannot be arbitrary and
unreasonable.
b. When any State action is violative of Article 14, including in
realm of contract, a writ petition shall be maintainable.
c. In case of pure contractual matters such as interpretation and
implementation of a clause in contract cannot be a subject matter of a
writ petition inasmuch as such dispute shall fall within the realm of a
private Law remedy.
d. In case of contract between the State and person aggrieved is
non statutory and purely contractual the rights are governed only by
terms of the contract.
e. When the action impugned is issued in exercise of executive /
administrative power and beyond the scope of the contract, writ court
can exercise its jurisdiction when found to be arbitrary, irrational and
illegal.
IV. Now coming to the challenge to the advertisement, this court is of
the considered opinion that after withdrawal of the petitioner from the
contract and rejection of his claim under clause 25 of the agreement at the
hands of the respondent FCI, the petitioner shall not have any right to
obstruct the respondent FCI proceeding with the tender process. Of course,
the petitioner shall have a right to challenge the decision of the authority
declining the claim of the petitioner under clause 25 of the contract before Page No.# 18/20
the appropriate forum including forum agreed to by the parties under the
contract, which is not a writ court in view of the reasons and settled
proposition of law as discussed hereinabove and being a pure contractual
dispute. As discussed hereinabove, such issuance of tender cannot be open
to judicial scrutiny as invitation of tender is in the realm of contract inasmuch
as the petitioner wants to stall the tender process for the reason of alleged
breach of contract by the respondent FCI. The petitioner in the considered
opinion of this court is left with the option either to take recourse to the
Specific Relief Act and / or Specific Performance of the Contract or is at
liberty to sue for damages. Accordingly, this court is not inclined to interfere
with the tender process already initiated.
C. The decision to debar the petitioner to participate in the tender process:
I. The learned counsel for the FCI has not been able to show any
terms in the contract, which empowers the respondent FCI to debar the
contractor from participating in the future tender process for the same
work, as a penal action, in a situation when the contract in question is
terminated for the alleged fault/ non-performance of the contractor.
Therefore, the action of the authorities in debarring the petitioner from
participating in the future tender process relating to the same work is not
under any term of the contract rather it's an executive/ administrative
decision. And therefore, such action is having public law character. In the
case in hand, as no power is discernable under the contract to debar the
petitioner from the future tender process, passing of the said order Page No.# 19/20
without giving any opportunity of hearing to the petitioner hits at the very
root of Article 14 of the Constitution of India inasmuch as in the given
facts such action is arbitrary and illegal. The same also violates the
petitioner's right under Article 19 (1)(G) of the Constitution of India.
Therefore, this Court is of the unhesitant view that the action of debarring
the petitioner from participating in the future tender process is not
supported by the terms of the contracts and same amounts to denial of
equal protection of law and in violation of principle of natural justice.
Therefore, in the considered opinion of this Court such decision can be
judicially reviewed in exercise of power of this Court under Article 226 of
the Constitution of India and same is liable to be interfered with for being
violative of right of the petitioner under Articles 14 and 19(1)(G) of the
Constitution of India.
II. The decision of the FCI to debar the present petitioners from
participating in the future tender process arising out of the same work,
after termination of the contract cannot be said to be an action in exercise
of any power under the terms of the contract in view of the settled
proposition of law as discussed hereinabove.
8. The directions:
For the reasons discussed hereinabove and the determination made, this writ
petition is disposed of with the following directions:
I. The Prayer for setting aside and quashing the
termination of contract is rejected. The final termination notice Page No.# 20/20
is upheld. The employer, FCI shall be at liberty to continue with
the impugned tender processor it can initiate fresh tender for
the execution of the work in question.
II. The decision to not to allow the petitioner to
participate in future tender process relating to work contract in
question is interfered with and the petitioner shall be permitted
to participate in the tender process, if the petitioner so desires
III. The petitioner shall be at liberty to proceed against
the FCI regarding the termination of the Contract and his claim
of damages and compassion as per the terms of the Contract.
The FCI shall also be at liberty of proceed against the
petitioner, in the similar nature and as per terms of the
contract.
JUDGE
Comparing Assistant
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!