Friday, 01, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Pankaj Goel vs State ( Through Cbi)
2024 Latest Caselaw 3176 Del

Citation : 2024 Latest Caselaw 3176 Del
Judgement Date : 15 April, 2024

Delhi High Court

Pankaj Goel vs State ( Through Cbi) on 15 April, 2024

Author: Sudhir Kumar Jain

Bench: Sudhir Kumar Jain

                          $~

                          *      IN THE HIGH COURT OF DELHI AT NEW DELHI

                          %                              Reserved on: January 04, 2024
                                                         Decided on: April 15, 2024

                          +      CRL.A. 1202/2015

                                 PANKAJ GOEL                                ..... Appellant
                                                   Through:     Mr. D. S. Kohli, Mr. Yash
                                                                Kadyan, Mr. Himanshu
                                                                Dahiya, Mr. Mannat Kohli,
                                                                Advocates.
                                                   V

                                 STATE (THROUGH CBI)                        ..... Respondent
                                                   Through:     Mr.      Yudhvir     Singh
                                                                Chauhan, APP for State with
                                                                SI Naresh Kumar, P.S. Anti-
                                                                Corruption Branch.

                                 CORAM
                                 HON'BLE DR. JUSTICE SUDHIR KUMAR JAIN

                                 JUDGMENT

1. The present criminal appeal is filed under section 374 of the Code

of Criminal Procedure, 1973 (hereinafter referred to as "the Code")

to set aside the judgement dated 29.10.2015 (hereinafter referred to

as "the impugned judgment") and order on sentence dated

02.11.2015 (hereinafter referred to as "the impugned sentence

order") passed by the court of Ms. Poonam Chaudhry, Special Judge

Signing Date:16.04.2024 CRL.A.1202/2015 Page 1

- 07, (PC Act Cases of ACB), GNCTD Central District, Tis Hazari

Court, Delhi (hereinafter referred to as "the trial court") bearing

CC no. 04/2012 titled as State V Pankaj Goel and another arising

out of FIR bearing no 0023/2004 registered under sections

467/468/471/420 read with section 120 B IPC along with sections

13(1)(d) and 13(2) of the Prevention of Corruption act, 1988

(hereinafter referred to as "PC Act") at P.S. Anti-Corruption Branch,

Delhi.

2.The brief facts of the case are that M/s Aruna Builders and

Suppliers, Shakti Nagar, Delhi was awarded four work orders bearing

no 254, 255, 256 and 257 dated 07.08.1998 amounting to Rs.6.8 lacs

pertaining to improvement of roads in the area of Jahangir Puri. The

fresh bitumen as per terms and conditions of the work orders was to

be procured by the contractor from any of the Government Oil

Companies which are M/s IOCL, BP and HP for execution of the

work orders and receipt issued by the government Oil Company was

to be deposited with MCD, Delhi and no receipt of any other dealer

was allowed to be submitted. Pankaj Goel (hereinafter referred to as

"the appellant") was serving as a Junior Engineer and C.B. Singh,

Signing Date:16.04.2024 CRL.A.1202/2015 Page 2

the co-convict was serving as an Executive Engineer in Division No.

XVI, Civil Lines Zone, Municipal Corporation of Delhi (MCD) on or

before 07.08.1998 and they entered into a criminal conspiracy with

M/s Aruna Builders & Suppliers, 26/87, Shakti Nagar, Delhi through

its proprietor/contractor Arun Kumar Bansal (who was stated to be

died during the investigation) along with Naresh Gupta, Assistant

Engineer/co-accused (who also died in 2006 during the investigation)

to defraud MCD with aim to pass bills and release payment to the

contractor resulting in a pecuniary gain of Rs. 6.8 lacs through the

use of forged invoices. Arun Kumar Bansal in furtherance of

conspiracy used substandard/unauthorised bitumen in execution of

work orders and submitted bills amounting to Rs.6.8 lacs along with

forged vouchers/invoices regarding the purchase of bitumen from

M/s Indian Oil Corporation Ltd. and said bills were cleared by the

engineers of Division No. XVI MCD by abusing their official

position as public servant thereby causing pecuniary benefit to M/s

Aruna Builders and Suppliers.

2.1 Rajinder Singh Manku (PW16) in May, 2004 was posted as

Inspector in ACB, GNCT Delhi and received source information to

Signing Date:16.04.2024 CRL.A.1202/2015 Page 3

said effect. ACP Rajinder Singh Manku verified veracity of

information and thereafter prepared a detailed report and submitted to

Senior Officer regarding commission of offences under section 120B

IPC read with section 420/468/471/467 IPC and section 13(2) read

with section 13(l)(d) of PC Act. ACP Rajinder Singh Manku with the

approval of Senior Officers prepared a rukka dated 25.05.2004

(Ex.PW16/A) and accordingly FIR bearing no 23/2004 (Ex. PW1/A)

was got registered and investigation was assigned to PW20 Inspector

S.S. Sandhu posted in Anti-Corruption Branch.

2.2 PW20 S.S. Sandhu during investigation received files (Ex.

PW3/A to Ex. PW3/H from PW3 Pushkar Raj, Head Clerk, MCD

which were seized vide seizure memo Ex.PW3/J. PW20 S.S. Sandhu

sent a letter Ex.PWI5/B to the General Manager (Sales), IOCL,

Mathura and received reply Ex. PW15/A from the Chief Engineer,

Chief Refinery Coordinator wherein it was mentioned that in the year

1998 there was no customer in their record by the name of M/s Aruna

Builders and Suppliers and invoices prepared by IOCL were

computer generated but the invoices submitted by the M/s Aruna

Builders and Suppliers were manually prepared. PW20 S.S. Sandhu

Signing Date:16.04.2024 CRL.A.1202/2015 Page 4

also sent one letter to Executive Engineer, Division no. XVI, MCD to

provide measure books/registers bearing no 1766 Ex. PW13/A and

1769 Ex. PW13/B relating to work orders no. 254 to 257 and work

order no. 186 and 535 and received measurement books Ex. PW13/A

(as exhibited in another case) and Ex. PW13/B (as exhibited during

trial arising out of FIR no 24/04) vide letter Ex. PW17/A from PW17

Ashok Drabu, Executive Engineer.PW20 S.S. Sandhu interrogated

the appellant co-convict C.B. Singh and co-accused Naresh. PW19

Inspector K.L. Meena was entrusted with further investigation on

22.11.04 and interrogated co-accused Naresh Gupta and the

appellant. PW19 Inspector K.L. Meena called Head Clerk K.P. Singh

and PW4 Khazan Singh, UDC of Account Section during

investigation who informed that tender files and account files of the

work orders Ex. PW3/A to Ex. PW3/H bear the signatures of the

appellant, co-accused Naresh Gupta (since deceased), co-convict

C.B. Singh and Arun Kumar Bansal (since deceased). The further

investigation was transferred to PW21 Inspector Santosh Kumar on

13.12.2005.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 5

2.3 PW21 Inspector Santosh Kumar during investigation he arrested

co-accused Arun Kumar Bansal (since deceased) vide arrest memo

EX.PW6/A. PW21 Inspector Santosh Kumar took the specimen

signatures of the contractor, the appellant and co-convict C.B. Singh

Ex.PW8/Al to A10 and PW8/B1 to B11 respectively on 12.03.2009

and specimen signatures of the co-accused (since deceased)

PWIO/AI to A10 on 09.03.2009 and sent specimen signatures and

questioned documents to FSL through PW7 HC Dasan and obtained

FSL report Ex.PW21/A. PW21 Santosh Kumar obtained sanctions

Ex. PW14/A and Ex. PW13/A for prosecution against the appellant

and co-convict C.B.Singh respectively. PW21 Santosh Kumar also

obtained bio data Ex. PW2/A and Ex. PW2/B and posting orders of

the appellant and co-convict C.B. Singh. PW21 Inspector Santosh

Kumar also arrested the appellant and co-convict C.B. Singh vide

arrest memos and personal search memos Ex. PW5/A to Ex. PW5/D.

PW21 Inspector Santosh Kumar also sent a letter Ex. PW21/B to

Superintendent Engineer, MCD regarding the procedure for

procurement bulk bitumen from Indian Oil Corporation for

construction work and received reply Ex. PW17/B from concerned

Signing Date:16.04.2024 CRL.A.1202/2015 Page 6

official. The charge sheet after completion of investigation was filed

against the appellant and co-convict C.B Singh for offences

punishable under sections 120B/420/467/468/471 IPC read with

sections 13(1)(d)/13(2) of the PC Act.

2.4 The court of Sh. Rakesh Siddhartha, Special Judge: (PC ACT) -

6, Delhi vide order dated 08.04.2011 framed charges for the offences

punishable under sections 120B/420/467/468/471 IPC read with

sections 13(1)(d) and 13(2) of the PC Act against the appellant and

the co-convict C.B. Singh to which they pleaded not guilty and

claimed trial. The prosecution in support of its case examined 21

witnesses.

2.5 The appellant and co-convict C. B. Singh were examined under

section 313 of the Code wherein he denied incriminating evidence

and pleaded false implication and innocence. The appellant stated

that a junior engineer is not involved in process of award of work

orders. The investigation was not fair and proceedings were

manipulated. The sanction Ex. 13/A was not given by a competent

person. The co-convict stated that he was not involved in the process.

It was responsibility of the contractor regarding genuineness of the

Signing Date:16.04.2024 CRL.A.1202/2015 Page 7

documents. The investigation was not fair and proceedings were

manipulated. The documents submitted by the contractor were to be

examined by the account department. The appellant and co-convict

C.B. Singh preferred to lead defence evidence and examined three

witnesses.

2.6 The appellant and co-convict CB Singh were convicted for the

offences punishable under sections 120B IPC, sections 13(1)(d) and

13(2) of the PC Act read with section 120B IPC and under section

420 IPC read with section 120B IPC vide impugned judgment dated

29.10.2015.

2.6.1 The appellant along with co-convict C.B. Singh vide impugned

order on sentence dated 02.11.2015 were sentenced to undergo

rigorous imprisonment for 02 years each with fine of Rs. 5,000/- each

for the offence punishable under section 120B IPC and in default of

the payment of fine to further undergo simple imprisonment for three

months. The appellant and co-convict were also sentenced to undergo

rigorous imprisonment for 02 years each with fine of Rs. 10,000/-

and in default to further undergo simple imprisonment for three

months for the offence punishable under section 420 IPC read with

Signing Date:16.04.2024 CRL.A.1202/2015 Page 8

section 120B IPC. The appellant and co-convict were also sentenced

to undergo rigorous imprisonment for 02 years each with fine of Rs.

5,000/- each and in default to further undergo simple imprisonment

for three months for the offence punishable under sections 13(1)(d)

and 13(2) of the PC Act read with section 120B IPC. All the

sentences were ordered to be run concurrently. The benefit under

section 428 of the Code was extended to the appellant and co-convict

CB Singh. The appellant has paid the fine.

3. The appellant being aggrieved filed the present appeal to challenge

the impugned judgment dated 29.10.2015 and impugned order on

sentence dated 02.11.2015 primarily on the grounds that the

impugned judgment is against the law and contrary to the facts and

circumstances. The trial court has not considered the inherent

inconsistencies and contradictions in the prosecution case and the

evidence and benefit of doubt ought to have been extended to the

appellant. The appellant was not under obligation to insist for invoice

from the contractor as an evidence of procurement of bitumen from

authorized source or to verify genuineness of invoice. There is no

evidence to draw an inference regarding the appellant arrived at any

Signing Date:16.04.2024 CRL.A.1202/2015 Page 9

agreement to do any legal act through illegal means. The prosecution

has failed to prove that the appellant had any knowledge about the

invoices being fabricated document and as such the appellant could

not have been convicted for having committed offences of

conspiracy, cheating or misconduct. The trial court has erred in

concluding that MCD has suffered any wrongful loss in relation to

the work orders subject matter of present case as MCD never

received any complaint regarding quality of work and too much

weight was given to the invoice and payments were released against

the actual work executed at site. The responsibility as per work order

of procuring bitumen from authorized source was on the contractor

only and the appellant being a Junior Engineer had no role in

procurement of bitumen. The appellant was one of the supervisory

officer to ensure execution of the work in consonance with the

quality stipulated under the work order. The trial court has committed

grave illegality in rejecting testimony of the defence witnesses. The

trial court has wrongly relied upon sections 91 and 92 of the Indian

Evidence Act to brush aside Ex. DW 6/DA. The trial court has

ignored serious infirmities in the investigation which cumulatively hit

Signing Date:16.04.2024 CRL.A.1202/2015 Page 10

at the root of the case of the prosecution. The trial court has wrongly

invoked section 106 of the Indian Evidence Act to shift the burden of

proof upon the appellant. The impugned judgment suffered from

various legal defects. The appellant also raised various other grounds

to challenge impugned judgment and impugned order on sentence.It

was prayed that the impugned judgment and order on sentence be set

aside.

4. The perusal of impugned judgment reflect that the trial court

considered argument advanced on behalf of the appellant that the

present case was registered on the basis of a source information as

deposed by PW16 but the source of the said information was not

disclosed. The prosecution neither examined informer as a witness

nor inquiry report stated to be conducted by PW16 was placed on

record. It was also argued that PW16 submitted detailed report to

seniors and a criminal case was got registered with the approval of

senior officers but the approval of senior officers was not placed on

record. It was also argued on behalf of the prosecution that PW16

conducted secret enquiry before registration of FIR and PW16 after

being satisfied that the appellant and other accused were guilty of

Signing Date:16.04.2024 CRL.A.1202/2015 Page 11

serious misdemeanour registered against them. The trial court opined

and held that non-disclosure of source of secret information was not

fatal to the case of prosecution as prosecution is not bound to disclose

the source of its information and purpose of secret enquiry was to

find out whether criminal proceedings can be resorted to save honest

public servants from vexatious prosecution.

4.1 The counsel for the appellant argued that registration of case

without conducting preliminary enquiry was fatal for the prosecution.

The perusal of rukka Ex. PW16/A reflected that no effort was made

by PW16 to conduct enquiry before registration but rukka

Ex.PW16/A was drawn by PW16 pursuant to the receipt of the secret

information on 25.05.2004 and within 5 minutes thereof FIR bearing

no 23/2004 Ex. PW1/A was registered.

4.2 The impugned judgment reflects that PW16 Inspector Rajinder

Singh Manku in May, 2004 received source information that M/s

Aruna Builders and Suppliers, Shakti Nagar, Delhi was awarded four

work orders bearing numbers 254, 255, 256 and 257 dated

07.08.1998 amounting to Rs.6.8 lacs pertaining to improvement of

roads in the area of Jahangir Puri and as per terms and conditions of

Signing Date:16.04.2024 CRL.A.1202/2015 Page 12

the work orders fresh bitumen was to be procured by the contractor

from any of the Government Oil Companies for execution of the

work orders. The engineers of Division No XVI MCD, Delhi while

executing work entered into a criminal conspiracy with accused Arun

Kumar Bansal with the intention to cheat MCD and in furtherance of

said conspiracy accused Arun Kumar Bansal used

substandard/unauthorised Bitumen. Subsequently bills amounting to

Rs.6.8 lacs along with forged vouchers/invoices submitted by the

contractors regarding the purchase of bitumen from M/s Indian Oil

Corporation Ltd. were cleared by the engineers of Division No. XVI

MCD including the appellant by abusing their official position as

public servant thereby caused pecuniary benefit to M/s Aruna

Builders and Suppliers. PW16 after verification of veracity of

information submitted a detailed report to his Senior Officer and with

approval of senior officer present case was registered. It is

established that PW16 conducted preliminary secret enquiry before

registration of case and if said preliminary enquiry report is not

placed on record, it is not fatal to case of the prosecution. The trial

court was justified in holding that that non-disclosure of source of

Signing Date:16.04.2024 CRL.A.1202/2015 Page 13

secret information was not fatal to the case of prosecution as

prosecution is not bound to disclose the source of its information.

5. The trial court also considered argument advanced on behalf of the

appellant and co-convict C.B. Singh that there was nothing on record

to show that substandard quality of bitumen was used by the accused

Arun Kumar Bansal, proprietor of M/s Aruna Builders and Suppliers

in execution of work orders in question except from bald allegations

in FIR. PW20, the first Investigating Officer in cross examination

deposed that he had not received any complaint in respect of the

work carried out with regard to work orders in question and further

deposed that he had not visited the sites nor collected the samples

from the site and as such samples could not be sent to the laboratory.

It was further argued that DW5 also deposed that the material used

for road works in question was in conformity with the technical

specifications and proved the lab test reports of the work orders as

Ex. DW5/A to DW5/P. The trial court noted that DW5 in cross

examination deposed that the reports were notprepared in his

presence and accordingly opined that authenticity of the reports Ex.

DW5/A to Ex. DW5/P was not proved did not find much substance

Signing Date:16.04.2024 CRL.A.1202/2015 Page 14

in the said argument as the work orders stipulated that original receipt

of bitumen procured from an authorized government refinery was to

be submitted to MCD which was not done.

5.1 The counsel for the appellant argued that it was obligation of the

contractor to furnish original invoice for proving fresh receipt of

bitumen and referred stipulation 6 and 7 of work orders Ex. PW3/A,

3/C, 3/E & 3/G to establish that it was obligation of the contractor

and no corresponding responsibility was assigned to the junior

engineer to ascertain the genuineness of the documents furnished by

the contractor. The appellant being a junior engineer was responsible

for adhering to the quantitative and qualitative work executed at site

and the prosecution has not pointed out any deficiency in respect of

the measurements of the work actually executed at site and relied

upon the lab test reports independently carried out by the independent

laboratory set up by the MCD to prevent any defiance from the

specifications in the work actually executed at site.

5.2 There is factual force in argument advanced by the counsel for

the appellant that it was obligation of the contractor to furnish

invoices regarding purchase of bitumen from government agency and

Signing Date:16.04.2024 CRL.A.1202/2015 Page 15

there is nothing on record to establish that the appellant being a

junior engineer was under such obligation for producing original

invoices regarding procurement of bitumen from government agency.

It is also established on record as deposed by DW5 that material used

for road work in question was in conformity with the technical

specifications and proved the lab test reports of the work orders as

Ex. DW5/A to DW5/P. The trial court was not justified in rejecting

lab test reports Ex. DW5/A to Ex. DW5/P merely on ground that

these reports were not prepared in presence of DW5.

6. The trial court in impugned judgment considered argument that Sh.

Sant Lal, the Chief Engineer, MCD had sent a written statement with

a circular Ex. PW20/DA to the investigating officer PW20 in

pursuance of a notice for joining investigation wherein stated that the

work orders were executed as per the terms and conditions stated

therein. PW18 also stated that no complaint was received with

respect to the quality and quantity of the work orders. The

investigating officer PW19 also deposed that he had not verified from

MCD regarding the deficiency in execution of work orders. PW19

also did not conduct investigation as to the source from where

Signing Date:16.04.2024 CRL.A.1202/2015 Page 16

bitumen was purchased. The first investigating officer PW16 also

stated that no complaint was received regarding the quality and

quantity of the four work orders and also deposed that he did not

make enquiry regarding the process of sale supply of bitumen from

IOCL. Accordingly the prosecution has failed to prove deficiency in

the work orders or that bitumen was not purchased from an

authorized government oil company. It was further argued that

invoice was of no significance as DW6 Shri K.S. Sandhu, retired

Director, MCD deposed that invoice was a document submitted by

the contractor as proof of his claim as regards the quality and

quantity of material and the claim ofthe contractor was not binding

on the department. DW6 also deposed that for release of payment, the

account division had to verify the entries in MB/register and

laboratory test reports. DW6 further deposed that CPWD manual Ex.

DW6/A applicable to MCD provides that the role of engineers was

only inspection of work at site, recording entries in MB/register and

there was no mechanism available to engineers to verify the invoices

submitted by the contractor and the contractor was responsible for the

correctness of the documents submitted by him. The trial court noted

Signing Date:16.04.2024 CRL.A.1202/2015 Page 17

that DW6 in cross examination stated that in case a complaint was

received regarding submission of fake invoices by contractor then it

could be sent to the police. It was also argued that the investigating

officer neither seized any document nor inspected site. However the

trial court did not agree with these arguments by observing that

PW16 received source information in 2004 whereas the work of

repair under the work orders in question were carried out in 1998 and

during this period roads in question might have repaired more than

once and with regard to non seizure of documents during enquiry, the

trial court observed that it was not incumbent upon investigating

officer to do so as it was not an investigation but only a preliminary

inquiry. The trial court under given facts and circumstances of case

has rightly observed in this regard.

7. It was also argued on behalf of the appellant and co-convict C. B.

Singh before the trial court that the prosecution has failed to prove

that the invoices were forged. The invoices were to be submitted by

the contractor and it was not the duty of the appellants and co-convict

C.B. Singh being engineers to verify the invoices. The contractor was

responsible for the genuineness and correctness of the documents.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 18

The investigating officer PW20 was confronted with Ex.PW20/DA

which was statement/report of Chief Engineer, MCD, addressed to

PW20 wherein it was stated that the responsibilities of the engineers

of MCD was restricted to the execution of work and not to ascertain

the correctness and genuineness of the documents furnished by the

contractors. It was also argued that the circular Mark PW12/B of

MCD also provided that the contractor was solely responsible for the

correctness and genuineness of the invoices and documents submitted

by him. DW1 also deposed that it was the duty of contractor to

purchase bitumen and furnish invoice and the engineers get work

executed as per the contract. DW2 K.P. Singh, Superintendent

Engineer also deposed that it was the contractor who was responsible

for the correctness of documents submitted by him and the accounts

department had to scrutinize the documents.

7.1 It was argued on behalf of the prosecution that DW2 on being

questioned with regard to Mark C to C of circular Mark 12B admitted

that as per the said circular the contractor had to attest the documents

to be submitted in the presence of the Engineer in charge or

divisional accountant and Ex.PW20/DA was dated 06.07.04 and

Signing Date:16.04.2024 CRL.A.1202/2015 Page 19

circular Mark 12B was dated 24.05.01 whereas the work orders were

dated 07.08.98 and as such Ex. PW20/DA and Mark 12/B had no

relevance to the agreements/contracts work orders as they could not

be retrospective in operation. DWl in cross examination deposed that

Executive Engineer can return the bills in case of any discrepancy in

the bills.

7.2 The trial court observed that the engineers have also to verify the

genuineness of the bills. The trial court also noted that the original

work orders were primary evidence of documents and oral evidence

could not be led to contradict its terms and referred sections 61 and

62 of the Indian Evidence Act, 1872. The trial court also referred

section 91 and 92 of the Indian Evidence Act to dispel contention of

the defence counsel with regard to Ex. PW20/DA and Mark 12/B.

The trial court also observed that fresh bitumen was to be purchased

by the contractor as per the terms and conditions of the work orders

and original receipt of purchase of same was to be submitted to

MCD. The trial court ultimately held that it was incumbent on the

accused including the appellant to comply with the terms of the work

orders and documents Ex. PW20/DA and Mark 12/B relied upon by

Signing Date:16.04.2024 CRL.A.1202/2015 Page 20

accused including the work orders of no significance in view of the

express terms of the work orders and agreements.

7.3 The counsel for the appellant argued that the appellant that being

a junior engineer has to supervise execution of work at site and was

not under obligation to ascertain the veracity of the invoices

furnished by the contractor and his actual job was to record the

activities of execution in the measurement book and furnish the

details regarding the actual execution of work at site. It was further

argued that this prevailing practice was codified by the department in

terms of the circular dated 24.05.2001 EX-PW20/A. The counsel for

the appellant relied on testimonies of DW2 K.P. Singh and DW6 K.S.

Sandhu. It was further argued that verification of genuineness of the

invoice was the sole responsibility of the contractor and the engineers

were not under obligation to verify the same.

7.4 It is correct that it was duty of the contractor as per terms and

conditions of work orders to procure bitumen from the government

agency and thereafter to submit original invoices. The contractor has

to submit the bills and was responsible for genuineness of the

documents which are required to be verified by the account

Signing Date:16.04.2024 CRL.A.1202/2015 Page 21

department. The engineers including the appellant were required to

verify the bills as per terms and conditions of work orders but it does

not mean the engineers including the appellant were responsible to

ensure that the bitumen was actually purchased by the contractor i.e.

Aruna Contractor and Suppliers. The document Ex. PW20/DA

although issued subsequent to work orders should not be over looked

by the trial court which cast duty on contractor regarding genuineness

of the bills/invoices. The document Ex.PW20/DA was prepared by

MCD itself.

8. The defence counsel before trial court argued that the invoices

were genuine. The Public Prosecutor argued that the accused C.B.

Singh EE (co-covict), Pankaj Goel JE (the appellant) and Naresh

Gupta (AE, since deceased) in furtherance of conspiracy with Arun

Kumar Bansal, contractor (since deceased) to cheat MCD passed the

bills on forged invoices and released payments to Arun Kumar

Bansal thereby causing pecuniary gain to the contractor to the tune of

Rs.6.8 lacs and the appellant and co-convict C.B. Singh by abusing

their position as public servants dishonestly and fraudulently cheated

MCD by permitting withdrawal of payment for the bills on forged

Signing Date:16.04.2024 CRL.A.1202/2015 Page 22

invoices. It was also argued that it was for the prosecution to prove

affirmatively that accused by corrupt or illegal means and by abusing

their position obtained pecuniary advantage for themselves or any

other person. It was for the prosecution to show that accused with

oblique motive departed from the terms of the work orders and knew

that the contractor had not purchased fresh bitumen from authorized

government Oil Company. The defence counsel relied on Major

S.K. Kale V State of Maharashtra, 1977 SCC Crl356.

8.1 The trial court observed that to establish the offence of

conspiracy, the prosecution relied on the testimony of PW16

Inspector Rajinder Singh Manku who deposed that he had received

source information to the effect that M/s Aruna Builders and

Suppliers, Shakti Nagar, Delhi had been awarded 4 (four) work

orders bearing no. 254, 255, 256 and 257 dated 7.8.98 Ex. PW3/A to

Ex. PW3/H pertaining to improvement of road in the area of Jahangir

Puri amounting to Rs.6.8 lacs by the Engineering Division of MCD,

Delhi. PW16 further deposed that as per the terms and conditions of

the work orders, fresh bitumen had to be purchased by the contractor

from any government refinery and the original receipt of the same

Signing Date:16.04.2024 CRL.A.1202/2015 Page 23

was to be submitted to the MCD. PW16 further deposed that the

Engineers of Division no. XIV, MCD while executing the work

orders entered into a criminal conspiracy with the contractor Arun

Kumar Bansal, proprietor of M/s Aruna Builders & Suppliers to cheat

MCD by using sub-standard/unauthorized bitumen. PW16 further

deposed that in furtherance of the said conspiracy, the contractor

Arun Kumar Bansal used sub-standard unauthorized bitumen and

submitted bills amounting to Rs.6.8 lacs pertaining to four work

orders along with forged invoices vouchers relating to purchase of

bitumen from Indian Oil Corporation which were cleared by

Engineer of Division No XVI by abusing their official position as

public servants and thereby causing pecuniary benefit to M/s Aruna

Builders and Suppliers and loss to MCD.

8.2 The trial court also considered arguments advanced on behalf the

prosecution that the first investigating officer PW20 deposed that

during investigation he had sent a letter Ex. PW15/B to the General

Manager, Sales of IOCL, Mathura Refinery to verify and report

regarding the cash memos and gate passes produced by contractor

Arun Kumar Bansal regarding sale and dispatch of bitumen and to

Signing Date:16.04.2024 CRL.A.1202/2015 Page 24

confirm whether the bills/cash memos and gate passes were genuine

or otherwise. PW20 received reply Ex.PW15/A stating that on

verification of record pertaining to the relevant period, it was found

that there was no customer by the name of M/s Aruna Builders &

Suppliers in their customer master record. IOCL also intimated that

during the relevant period the challans were computer generated and

at no point of time manual challans were issued to parties regarding

the supply of bitumen from their terminal. The defence counsel on

other hand argued that the testimony of PW20 could not be relied

upon as he did not join any official from Bitumen Section of IOCL,

Mathura in the investigation and also did not seize record of Bitumen

Section of IOCL, Mathura. The trial court also relied on sections 101

and 106 of the Indian Evidence Act.

8.3 The trial court observed that it was for the accused including the

appellant to explain that manually prepared invoices placed on record

were of the IOCL but the accused including the appellant did not

prove their defence by preponderance of probability and as such

adverse inference has to be drawn against them to effect that the

invoices were not of IOCL Mathura, Refinery. The accused including

Signing Date:16.04.2024 CRL.A.1202/2015 Page 25

the appellant were required to explain unusual practice of issuing

manual invoices by IOCL, Mathura, Refinery. No explanation was

given by the accused including the appellant regarding the

circumstances in which manual invoices were issued by IOCL,

Mathura which pointed towards the complicity of accused including

the appellant in the conspiracy to manipulate invoices and cause

wrongful loss to MCD and section 106 of the Indian Evidence Act is

applicable to the facts of the case and raises a strong presumption that

accused including the appellant were conspirators in the offences of

cheating MCD by abusing their official position. The trial court also

observed that the accused including the appellant in statements under

section 313 of the Code stated that original receipt of purchase of

bitumen from an authorized government oil company was to be

submitted by the contractor/proprietor of M/s. Aruna Builders &

Suppliers to MCD as per the terms and conditions of the work orders

and denied that the invoices submitted by the contractor were forged.

Accordingly the accused including the appellant had to prove their

defence that the invoices were genuine by preponderance of

probability.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 26

8.4 The counsel for the appellant argued that there was no evidence

to establish conspiracy and trial court has committed grave illegality

holding the appellant guilty of conspiracy while observing existence

of conspiracy amongst the appellant and other accused for cheating

MCD and thereby the appellant in capacity of a public servant having

committed misconduct punishable under section 13 (2) read with

13(1) (d) of the PC Act. The prosecution cannot be absolved of the

responsibility of bringing sufficient circumstances pointing towards

existence of an agreement amongst the conspirators to do an 'illegal

act' or 'a legal act through illegal means'. The counsel for the

appellant placed reliance on Central Bureau of Investigation,

Hyderabad V K. Narayana Rao, (2012) 9SCC 512; P.K.

Narayanan V State of Kerala, (1995)1SCC 142; Sherimon V State

of Kerala, AIR 2012 SC 493; State of Kerala V P. Sugathan &

another, (2000)8SCC 203; SardarSardul Singh Caveeshar V State

of Maharashtra, MANU/SC/0063/1963.

8.4.1 The counsel for the appellant further argued that the trial court

has erred in taking aid of section 106 of the Indian Evidence Act to

shift the burden of proof upon the appellant. The procurement of the

Signing Date:16.04.2024 CRL.A.1202/2015 Page 27

Bitumen and furnishing of invoice from authorized refinery as a

token of purchase of fresh Bitumenwas sole obligation of the

contractor and the JE had no role to play in it and as such invocation

of section 106 of Indian Evidence Act to shift the burden of proof

merely on the premise that the appellant during statement under

Section 313 of the Code has denied that invoice was forged but,

failed to offer any explanation regarding the circumstances in which

the manual invoice was prepared by IOCL.

8.4.2 The counsel for the appellant argued that entire case of the

prosecution is resting on communication dated 24.06.2004 Ex.

PW15/A in response to communication dated 16.06.2004 Ex.

PW15/B and assumption that the invoice furnished by the contractor

was a fabricated document but the appellant was not having any

knowledge regarding fabrication of the documents. It was further

argued that there was no evidence to establish cheating or misconduct

of the public servant. It was also argued that there is no evidence in

respect of fraudulent and/or dishonest act attributable to the appellant

leading to inducement. The prosecution has failed to bring any

circumstance or any direct evidence pointing towards an overt act

Signing Date:16.04.2024 CRL.A.1202/2015 Page 28

committed by the appellant which was either dishonest or fraudulent

and has led to inducing the employer for fetching wrongful loss or

offering wrongful gain to the contractor. The work at site was

completed and except for the complaint which culminated into the

FIR, there was no complaint with respect to quality of work and/or

quantity of work actually executed at site. The bills as per the

procedure before release of payment to the contractor were placed

before the account clerk who scrutinizes before recommending bills

for realization. PW4 Khajan Singh scrutinized the bill of the

contractor and he did not find any irregularity or deficiency and

recommended for passing of the bill by the accountant PW18 R.K.

Bahal. The Additional Public Prosecutor defended the impugned

judgment during arguments.

9. Section 120A of IPC defines "criminal conspiracy"

which reads as under:

120A. Definition of criminal conspiracy.--When two or more persons agree to do, or cause to be done,--

(1) an illegal act, or (2) an act which is not illegal by illegal means, such an agreement is designated a criminal conspiracy:

Provided that no agreement except an agreement to commit an offence shall amount to a criminal conspiracy unless

Signing Date:16.04.2024 CRL.A.1202/2015 Page 29

some act besides the agreement is done by one or more parties to such agreement in pursuance thereof.

Explanation. It is immaterial whether the illegal act is the ultimate object of such agreement, or is merely incidental to that object.

Section 120 B provides punishment for criminal conspiracy which

reads as under:-

120B. Punishment of criminal conspiracy.--(1) Whoever is a party to a criminal conspiracy to commit an offence punishable with death, imprisonment for life or rigorous imprisonment for a term of two years or upwards, shall, where no express provision is made in this Code for the punishment of such a conspiracy, be punished in the same manner as if he had abetted (2) Whoever is a party to a criminal conspiracy other than a criminal conspiracy to commit an offence punishable as aforesaid shall be punished with imprisonment of either description for a term not exceeding six months, or with fine or with both.

9.1 The Supreme Court in State through Superintendent of Police

V Nalini & others, (1999) 5 SCC 253 discussed and summarized

ingredients to constitute a criminal conspiracy which are as follows:

i) Conspiracy is when two or more persons agree to do or cause to be done an illegal act or legal act by illegal means.

ii) The offence of criminal conspiracy is an exception to the general law, where intent alone does not constitute crime. It is the intention to commit a crime and join hands with persons having the same intention

iii) Conspiracy is hatched in private or in secrecy. It is rarely possible to establish a conspiracy by direct evidence.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 30

Usually, the existence of the conspiracy and its objects have to be inferred from the circumstances and the conduct of the accused.

iv) Where in pursuance of the agreement, the conspirators commit offenses individually or adopt illegal means to do a legal act that has a nexus to the object of the conspiracy, all of them will be liable for such offenses even if some of them have not actively participated in the commission of those offenses.

The Supreme Court in Yakub Abdul Razak Memon V State of

Maharashtra, (2013) 13 SCC 1 followed these principles and

reiterated that to establish conspiracy it is necessary to establish an

agreement between the parties and the offence of criminal conspiracy

is of joint responsibility, all conspirators are liable for the acts of each

of the crimes which have been committed as a result of the

conspiracy. The Supreme Court again in Sanjeev V State of Kerala,

Criminal Appeal No 1134 of 2011 decided on 09 th November, 2023

and Pavana Dibbur V The Directorate of Enforcement, Criminal

Appeal No 2779 of 2023 decided on 29.11.2023 again referred these

principles.

10. It is reflecting that M/s Aruna Builders and Suppliers, Shakti

Nagar, Delhi was awarded four work orders bearing no 254, 255, 256

and 257 dated 07.08.1998 Ex. PW3/A to Ex. PW3/H amounting to

Signing Date:16.04.2024 CRL.A.1202/2015 Page 31

Rs.6.8 lacs and as per terms and conditions of the work orders fresh

bitumen was to be procured by the contractor i.e. M/s Aruna Builders

and Suppliers from M/s IOCL, BP and HP which are Government Oil

Companies and the receipt only issued by the Government Oil

Company was to be deposited with MCD, Delhi. The appellant was a

Junior Engineer and co-convict C.B. Singh was Executive Engineer

in Division No XVI, Civil Lines Zone, MCD. PW16 Inspector

Rajinder Singh Manku in May, 2004 received source information that

the appellant and co-convict C. B. Singh entered into a criminal

conspiracy with M/s Aruna Builders & Suppliers through its

proprietor/contractor Arun Kumar Bansal along with co-accused

Naresh Gupta, Assistant Engineer to defraud MCD by passing bills

on forged invoice and thereafter to release payment to the contractor

resulting in a pecuniary gain of Rs. 6.8 lacs to the contractor. Arun

Kumar Bansal allegedly used substandard/unauthorised bitumen in

execution of work orders and submitted bills amounting to Rs.6.8

lacs along with forged vouchers/invoices regarding the purchase of

bitumen from M/s Indian Oil Corporation Ltd. The engineers of

Division No XVI MCD including the appellant cleared said bills.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 32

Inspector Rajinder Singh Manku after verification and with approval

of senior officer prepared a rukka dated 25.05.2004 Ex.PW16/A and

accordingly FIR bearing no 23/2004 Ex. PW1/A was got registered.

The Chief Engineer, Chief Refinery Coordinator vide reply Ex.

PW15/A intimated that there was no customer in their record by the

name of M/s Aruna Builders and Suppliers in the year 1998 and

IOCL prepared computer generated invoices. PW20 S.S. Sandhu also

collected measure books/registers bearing no 1766 Ex. PW13/A and

1769 Ex. PW13/B relating to work orders no. 254 to 257.PW19

Inspector K.L. Meena who was entrusted with further investigation

was informed by the account officials/officers that tender files and

account files of the work orders Ex. PW3/A to Ex. PW3/H bear the

signatures of the appellant, co-accused Naresh Gupta (since

deceased), co-convict C.B. Singh and Arun Kumar Bansal (since

deceased.

11. The trial court to establish conspiracy against the appellant and

other accused in impugned judgment relied on the testimony of

PW16 Inspector Rajinder Singh Manku who received source

information that the appellant and other accused including contractor

Signing Date:16.04.2024 CRL.A.1202/2015 Page 33

M/s Aruna Builders and Suppliers entered into criminal conspiracy to

cause wrongful gain to the tune of Rs. 6.8 lacs to the contractor who

did not procure bitumen from any government refinery in execution

of work orders bearing no. 254, 255, 256 and 257 dated 7.8.98 Ex.

PW3/A to Ex. PW3/H and used sub-standard/unauthorized bitumen.

The contractor Arun Kumar Bansal submitted bills along with forged

invoices vouchers relating to purchase of bitumen from Indian Oil

Corporation amounting to Rs.6.8 lacs which were cleared by

Engineer of Division No XVI including the appellant by abusing

their official position as public servants and caused pecuniary benefit

to M/s. Aruna Builders and Suppliers and loss to MCD. The reply

Ex.PW15/A reflected that there was no customer by the name of M/s

Aruna Builders & Suppliers in the customer master record of IOCL

and challans were happened to be computer generated. The trial court

also relied on sections 101 and 106 of the Indian Evidence Act by

observing that the accused including the appellant could not explain

about manually prepared invoices which were placed on record and

led the trial court to draw adverse inference against the appellant and

other accused and to presume complicity of accused including the

Signing Date:16.04.2024 CRL.A.1202/2015 Page 34

appellant in the conspiracy to manipulate invoices and cause

wrongful loss to MCD. The trial court also referred statement of the

appellant under section 313 of the Code wherein the appellant denied

that the invoices submitted by the contractor were forged. The trial

also held that the accused including the appellant had to prove their

defence that the invoices were genuine by preponderance of

probability as per section 106 of the Indian Evidence Act. It has come

on record that the contractor i.e. Arun Kumar Bansal was responsible

to procure bitumen from government refinery in terms of work orders

Ex. PW3/A to Ex. PW3/H and was also responsible to submit

original invoices for payment of bills. The appellant being junior

engineer was not responsible for submission of original invoices

which was to be done by the contractor Arun Kumar Bansal as

proprietor of M/s Aruna Builders and Suppliers. The source

information received by the PW16 regarding alleged conspiracy

between the accused including the appellant is not sufficient to

presume existence of conspiracy between the accused including the

appellant. The trial court was not justified in applying section 106 of

the Indian Evidence Act once on basis of reply Ex. PW15/A wherein

Signing Date:16.04.2024 CRL.A.1202/2015 Page 35

it was stated that IOCL issued computer generated challan and it was

for the prosecution that manual invoices/challans allegedly issued by

IOCL were forged and fabricated and the accused including the

appellant were not obliged to prove genuineness of invoices/challans

submitted by the contractor on preponderance of probabilities with

application of section 106 of the Indian Evidence Act. The evidence

against the appellant is that he signed invoices and other documents

as verification, which were submitted by the contractor for payment,

which is not sufficient to establish misuse of public authority by the

appellant. There is no sufficient and convincing evidence that the

appellant entered into a conspiracy with other accused to cause

wrongful gain to the contractor amounting to Rs. 6.8 lacs as public

servant.

11.1 The appellant should not be convicted for offence under section

420 IPC and was not justified in holding the appellant guilty of

cheating in pursuance of the conspiracy by getting bills passed on

false invoices with the dishonest intention to cheat MCD and release

of payment to the contractor/accused.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 36

11.2 There is force in arguments advanced by the counsel for the

appellant that there was no evidence to establish conspiracy and trial

court has committed grave illegality holding the appellant guilty of

conspiracy and the trial court has erred in taking aid of section 106 of

the Indian Evidence Act to shift the burden of proof upon the

appellant.

12. The trial court in impugned judgment after considering and

analysing evidence led by the prosecution rightly observed that the

court does not sit in appeal over the sanction order and in believing

testimonies of PW13 and PW14 who deposed that sanction was

granted after application of mind. The trial court also observed that

protection under section 197 of the Code is available to a public

servant only when the alleged act alone by a public servant is

reasonably connected with the discharge of his official duty and

sanction is not necessary when the offence complained of has nothing

to do with the discharge of his public duty. The trial court rightly

observed that regarding charges of conspiracy and cheating, no

sanction was required for prosecution of the accused including the

appellant.

Signing Date:16.04.2024 CRL.A.1202/2015 Page 37

13. The trial court with regard to the offences under sections 467/468

IPC and 471 IPC observed that the burden of proving that invoices

were forged by accused including the appellant was not discharged

by prosecution. The trial court held that the prosecution has failed to

prove affirmatively that the accused including the appellant had

forged the invoices.

14. The trial court observed that to establish the offence under

Section 13(l)(d) of the PC Act, the prosecution had to establish that

the accused including the appellant being public servants abused their

position to obtain for themselves or any other person any valuable

thing or pecuniary advantage. The trial court considered argument

advanced on behalf of the accused including the appellant that

prosecution has failed to prove that they had abused their official

position to obtain for themselves or for any other person pecuniary

advantage or any valuable thing. It was evident that contractor had

submitted the invoices of bitumen to MCD and the duty of engineers

was only to verify the work at site and the engineers did not have any

role in the verification of bills. PW4 and PW9 had deposed that they

had verified the invoices with the entries in the MB/register. The

Signing Date:16.04.2024 CRL.A.1202/2015 Page 38

prosecution has failed to prove dishonest intention or mens rea on

part of accused including the appellant to cheat MCD in conspiracy

with contractor by cogent evidence. The trial court held that mens rea

is not an essential ingredient to constitute an offence U/S 13 (l)(d) of

the PC Act after relying on Runu Ghosh & Others V CBI, Crl. A.

482/2002, 509/2002 and 536/2002 decided by this Court on

21.12.2011. The trial court while holding the appellant guilty for

offence under section 13 (1) (d) read with section 13 (2) of PC Act

accepted argument advanced on behalf of the prosecution that a

report was already received from IOCL, Mathura Refinery that there

was no customer by the name of M/s Aruna Builders and Suppliers in

their customer record and PW15 had deposed that manual invoice

were never issued by IOCL, Mathura Refinery; the accused including

the appellant abused their official position to obtain pecuniary benefit

for contractor without public interest and the accused including the

appellant in conspiracy with the contractor to cause wrongful loss to

MCD and wrongful gain to the contractor passed the bills on forged

invoices while they were expected to act in public interest and fairly.

The trial court ultimately held that there is sufficient evidence

Signing Date:16.04.2024 CRL.A.1202/2015 Page 39

adduced by the prosecution to bring home the charge for the offence

punishable under section 13(l)(d) read with section 13(2) of the PC

Act read with section 120B IPC.

14.1 It has been established on record that the contractor as per terms

and conditions of work orders was responsible for procuring bitumen

from authorised government agency which is IOCL in present case

and the appellant being junior engineer was not responsible for

procurement of bitumen. The contractor also submitted

invoices/challans to account department of MCD for encashment of

bills. The prosecution could not prove existence of conspiracy

between the accused including the appellant. The incriminating

evidence against the appellant is that he along with other engineers

verified invoices along with bills which is not sufficient to hold the

appellant guilty for offence under section 13 (1) (d) read with section

13(2) of PC Act.

15. The trial court was not justified in holding guilty for offences

punishable under section 120B IPC, 420 IPC read with section 120B

IPC and under section 13(l)(d) punishable under section 13(2) PC

Act read with section 120 IPC. The impugned judgment and

Signing Date:16.04.2024 CRL.A.1202/2015 Page 40

impugned order on sentence cannot sustain in law and accordingly

set aside. The appeal is allowed and the appellant is accordingly

acquitted. However, nothing in this judgment be taken as opinion on

merit pertaining to co-convict C. B. Singh. The fine, if any, deposited

by the appellant is liable to be refunded.

16. The present appeal along with pending applications, if any, stands

disposed of.

DR. SUDHIR KUMAR JAIN (JUDGE) APRIL 15, 2024 N/ABK/HVK

Signing Date:16.04.2024 CRL.A.1202/2015 Page 41

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter