Citation : 2017 Latest Caselaw 3218 Del
Judgement Date : 13 July, 2017
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO (OS)(COMM) 84/2017 and CM APPL. 14328/2017
Reserved on: 01.05.2017
Date of decision: 13.07.2017
IN THE MATTER OF:
M/S CWHEC-HCIL (JV) ..... Appellant
Through: Mr. Arvind Minocha and Mr. Mayank
Kshirsagar, Advocates
versus
M/S CHPRCL ..... Respondent
Through: Mr. Ramesh Kumar, Advocate
CORAM
HON'BLE MS.JUSTICE HIMA KOHLI
HON'BLE MS.JUSTICE SANGITA DHINGRA SEHGAL
HIMA KOHLI, J.
1. The present appeal under Section 37 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as „A&C Act‟) assails an
order dated 14.02.2017 passed by the learned Single Judge partly allowing
a petition under Section 34 of the A&C Act filed by the respondent, a joint
venture company, impugning an Arbitral Award dated 22.04.2009,
published by a three member Arbitral Tribunal.
2. A glance at the facts of case that are relevant for deciding the present
appeal are as follows:-
3. The respondent, Calcutta-Haldia Port Road Company Ltd. had
floated a tender for execution of the project i.e., "Four laning of Km 0/500
to Km 52/700 of Kolaghat-Haldia section of NH-41 in the State of West
Bengal -Package WB (Haldia)". The appellant, a joint venture formed
between two companies namely, M/s China National Water Resources &
Hydropower Engineering Company of P.R. China (subsequently named as
Syno Hydro Power Engineering Corporation) and M/s Harish Chandra
(India) Ltd., was a successful bidder in respect of the aforesaid work that
was awarded in its favour at a contract price of Rs.2,19,98,91,379/-. The
Agreement dated 24.07.2002 executed between the parties was an item rate
contract and had stipulated the date of commencement of the work as
10.09.2002. Under the said Agreement, the appellant had quoted rates
for different items, as was detailed in the Bill of Quantities (hereinafter
referred to as „BOQ‟). On disputes and differences arising between the
parties, the appellant invoked the arbitration clause and preferred seven
claims before the Arbitral Tribunal. The first four claims preferred by the
appellant were rejected by the Arbitral Tribunal. Against claim No.5
(raised towards additional payment on account of sand filling under Box
culverts in lieu of earth filling as per BOQ Item No. 5.42), a sum of
Rs.13,03,690/- was allowed as against a sum of Rs.13,03,694/- preferred by
the appellant. Against claim No.6, (raised towards extra payment for using
Grade-III filter media as directed, in place of Grade-I filter media) a sum of
Rs.13,00,495/- was allowed as against a sum of Rs.19,60,167/- preferred by
the appellant. Against claim No.7 (raised towards non-payment for
providing epoxy bonding layer) a sum of Rs.1,42,540/- was allowed as
against a claim of Rs.1,42,543.90 paise preferred by the appellant.
4. Aggrieved by the Arbitral Award, the respondent/company filed a
petition under Section 34 of the A&C Act, on which a limited notice in
respect of claims No.5 and 6 was issued by the learned Single Judge. Under
the impugned judgment, the objections raised by the respondent in respect
of claim No.5 awarded in favour of the appellant, were turned down and it
was held that there was no infirmity in the reasoning given by the Arbitral
Tribunal for granting additional payment to the appellant on account of
using sand instead of earthen material for filling under the box culverts etc.
Coming to the question as to whether the appellant would be entitled to any
additional amount on account of using material conforming to class-III
grading, the learned Single Judge has declined to interfere with the view
taken by the Arbitral Tribunal that the appellant ought to be compensated if
it had incurred any additional cost on that count, by observing that it was a
plausible view which did not deserve any interference. This left the
question as to whether there was any material placed before the Arbitral
Tribunal to ascertain as to whether the appellant had incurred additional
cost for entitlement to a sum of Rs.13,00,495/-.
5. On examining the findings of the Arbitral Tribunal on the third
aspect referred to above, the learned Single Judge concluded that the
Award was conspicuously silent as to the basis on which the rate of
Rs.345/- per cubic meter was worked out for arriving at a conclusion that
the appellant was entitled to any additional amount on the said basis.
Holding that the amount awarded in favour of the appellant under claim
No.6 was not based on any evidence and therefore could not be sustained,
that part of the Award was set aside. Aggrieved by the aforesaid findings,
the appellant has filed the present appeal.
6. Mr. Minocha, learned counsel for the appellant contended that the
scope of interference under Section 34 of the A&C Act is very limited and
while returning the findings in the impugned order, the learned Single
Judge has transgressed the said scope by going into findings of fact, which
is impermissible; that there was no dispute that the appellant had executed
the work, which was a variation and not included in the contract
specifications, for which it was entitled to receive additional payment and
that the respondent had never disputed that extra cost was being incurred
by the appellant in doing the extra work and that the analysis of extra cost
submitted by the appellant before the Arbitral Tribunal, was not questioned
by the respondent. He had also referred to the recommendations made by
the Dispute Review Board (DRB), that had recommended
that the Engineer should determine the rate payable to the appellant for the
filter media used by it as per the Grade-III specifications, in accordance
with the provisions of the contract by treating that the BOQ Item No.5.42
gave the rate for Grade-I filter media only and the difference of the two
rates ought to be paid by the respondent. To fortify his submission that
where the Arbitral Tribunal comprises of persons with technical
knowledge, who are well versed with the practice in their respective fields,
as in the present case, they were entitled to use their expertise to decide the
dispute, reliance was placed by learned counsel on the decision of the
Supreme Court in the case of P.R. Shah, Shares and Stock Broker (P) Ltd.
vs. B.H.H. Securities (P) Ltd. and Ors. reported as (2012) 1 SCC 594.
7. Per contra, Mr. Ramesh Kumar, learned counsel for the respondent
supported the impugned judgment and controverted the submission made
by the other side to the effect that the respondent had not disputed the extra
cost allegedly incurred by the appellant in executing the work under claim
No.6 or that it had never questioned the analysis of extra cost submitted by
the appellant before the Arbitral Tribunal. To counter the submission made
by the other side, he drew out attention to the submissions of the parties
recorded in the Arbitral Award in respect of claim No.6 and contended that
it was specifically recorded therein that as per the respondent, there was no
question of any extra payment being released in favour of the appellant,
over and above the rates quoted for BOQ Item No.5.03 and that the said
claim was inadmissible. Learned counsel canvassed that even if the
appellant had failed to produce any evidence to substantiate its claim for
extra payment under claim No.6 and the Arbitral Tribunal was of the view
that the claimant was entitled to extra payment, then nothing precluded the
Tribunal from calling for evidence from any third party or from the party to
the proceedings, as provided for under Section 25 and 27 of the A&C Act,
for arriving at a conclusion as to what was the amount, if any, that was
payable to the appellant towards the difference in the cost for executing of
the same work with material conforming to class-I Grade-A and class-III
Grade-A. But no such measures were taken by the Tribunal in the present
case. Reliance was placed on the decision of the Supreme Court in the case
of Delta Distilleries Limited vs. United Spirits Limited and Anr. reported as
(2014) 1 SCC 113, wherein it was held that if necessary documents are not
produced to justify a claim, then an adverse inference can be drawn by the
Arbitral Tribunal against the defaulting party and in circumstances where a
party fails to appear or produce documentary evidence, the Arbitral
Tribunal can still continue the proceedings and render an Award on the
evidence before it, which evidence can be sought from any third party or
from the party to the proceedings itself.
8. We had carefully considered the arguments advanced by learned
counsels for the parties at the stage of admission before reserving
judgment.
9. In the recent case of Associate Builders vs. DDA reported as (2015)
3 SCC 49, the Supreme Court has gone to great lengths to comprehensively
spell out the law on the aspect of the limitations that are placed on a court
that is hearing objections to an arbitral award under Section 34 of the A&C
Act, which prescribes the grounds on which such an award can be set aside.
It was observed that Section 34 read in conjunction with Section 5 (Extent
of judicial intervention) makes it clear that the arbitral award which is
governed by Part-I of the A&C Act can be set aside only on the grounds
mentioned in Section 34(2) and (3) and not otherwise. The Supreme Court
emphasized that none of the grounds available in Section 34(2)(a) deal with
the merits of the decision rendered by an arbitral award and it is only when
a grievance is raised that the award in conflict with the public policy of
India, can the merits of the said award be examined and that too, under
specified circumstances. The judgment has elaborated on the specific heads
of public policy in the above context. Under the sub-head of "the award
being contrary to the fundamental policy of the Indian law", have been
included the pre-condition of the award being compliant of the statutes and
judicial precedents, the need for a judicial approach, compliance with the
principles of natural justice and the Wednesbury principles of
reasonableness. The said judgment delineated the grounds on which an
award may be set aside as contrary to public policy, which include a
ground that the award is contrary to the interests of India, or is against
justice or morality or one that is patently illegal, i.e., induced or affected by
fraud or corruption.
10. While dealing with the first juristic principle discussed in the case of
Associate Builders (supra), namely, an award that is contrary to the
fundamental policy of Indian law, the Supreme Court has observed as
follows:-
"29. It is clear that the juristic principle of a "judicial approach" demands that a decision be fair, reasonable and objective. On the obverse side, anything arbitrary and whimsical would obviously not be a determination which would either be fair, reasonable or objective.
30. The audi alteram partem principle which undoubtedly is a fundamental juristic principle in Indian law is also contained in Sections 18 and 34 (2)(a)(iii) of the Arbitration and Conciliation Act. These Sections read as follows:
18. Equal treatment of parties - The parties shall be treated with equality and each party shall be given a full opportunity to present his case.
xxx xxx xxx
34. Application for setting aside arbitral award - (1)
xxx xxx xxx
(2) An arbitral award may be set aside by the Court only if-
(a) the party making the application furnishes proof that-
xxx xxx xxx
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case;
31. The third juristic principle is that a decision which is perverse or so irrational that no reasonable person would have arrived at the same is important and requires some degree of explanation. It is settled law that where-
(i) a finding is based on no evidence, or
(ii) an arbitral tribunal takes into account something irrelevant to the decision which it arrives at; or
(iii) ignores vital evidence in arriving at its decision,
Such decision would necessarily be perverse." (emphasis added)
11. Citing an earlier decision in the case of Kuldeep Singh vs.
Commissioner of Police reported as (1999) 2 SCC 10, where it was held
that a broad distinction has to be maintained between decisions which are
perverse and those which are not and if a decision is arrived at on no
evidence or such evidence which is thoroughly unreliable and no
reasonable person would act upon it, the said order would be perverse, the
Supreme Court has explained in para 33 as follows:-
"33. It must clearly be understood that when a court is applying the „public policy‟ test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. A possible view by the arbitrator on facts has necessarily to pass muster as the arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award. Thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. Once it is found that the arbitrators approach is not arbitrary or capricious, then he is the last word on facts. ......."
12. We now proceed to test the findings returned in the impugned order,
on the anvil of the guidelines laid down in the captioned decision. The
findings of the Arbitral Tribunal in respect of claim No.6 are as follows:-
"A T's Observations and findings We have gone through the pleadings of both the parties. We have also examined the documents filed by them and heard their respective arguments in the matter.
From the arguments and counter arguments being made by the parties, it is evident that the major area of disagreement is regarding sub-clause No.309.3.2 (B). The contractor is stating that sub-clause No.309.3.2(B) is applicable to the BOQ item No.5.03 against which the work of back filling with filter media behind structure has been done by them. On the contrary, the Respondent has taken a stand that the Cause No.309 of MORTH Specification is applicable to Surface and Sub-surface drains only and accordingly ,its sub-clause No.309.3.2(B) is not at all applicable for determination of the grading requirement of filter media behind Structures. The Respondent has further stated that in the absence of any specific provisions in the Contract regarding the grading of filter media behind the structures the Engineer would decide the same conforming to sound engineering practice. In view thereof, the stand of the Respondent is that decision taken by the Engineer shall be final and binding on the Contractor.
We have gone through Clause 305 of Technical specifications as well as Clause 309 in detail. We find that sub- clause No.305.4.4 of Tech. Specifications deals with the provision of filter media behind the structures wherein it is clearly provided that the material to be used for filter media shall conform to the requirement of filter medium spelt out in sub-clause No.309.3.2(B). We also find that as stated in sub- clause No.309.3.2(B), Table 300-3 governs the grading requirements of filter media.
In view of above clear provisions provided in the Technical Specifications, which is a part of the Contract, we do not find any merit in the contentions of the Respondent.
We are of the considered opinion that in view of the above said stipulations, the Contractor was entitled to use grade - I material for Filter Media against BOQ No.5.03 while the Engineer ordered to use grade - III material and that too with a different methodology of using two different types of Filter Media. Accordingly, the Contractor is entitled to payment as a variation item for the work so done.
We have analyzed the rate payable to the Contractor as extra expenditure incurred for using the Grade - III filter media in two columns of 300 mm thickness each, using different sizes of materials as per instructions/methodology approved by the Engineer. This analysis has been done, keeping in view the contract provisions.
We find that additional rate, over and above the rate quoted by the Contractor against BOQ item No.5.03, comes to Rs.345/- per CUM. So the Contractor is entitled to payment of 3769.55 cum x Rs.345/- = Rs.13,00,495.78 say Rs.13,00,495/-.
The Contractor is also entitled to price adjustment of the above said amount of Rs.13,00,495/-. For this purpose, the base index would be considered on the basis of the date on which the methodology was approved by the Engineer.
The Contractor is entitled to interest on the delayed payment. The rate of interest and period of interest would be governed by the provisions of sub-clause 43.1 and 43.2 of the Contract."
13. As noted above, though the Award records that the Tribunal has
analyzed the rates payable to the contractor as extra expenditure incurred
for using Grade-III filter media in two columns, there is no discussion with
respect to the material evidence that forms the basis of the said analysis.
Except for the appellant submitting before the Arbitral Tribunal, a
calculation sheet of the extra expenditure allegedly incurred by it for filter
media, admittedly, it did not lead any evidence to prove the said
computation. In such circumstances, we are of the opinion that the findings
returned by the learned Single Judge to the effect that the Award is
conspicuously silent as to the basis on which the rate of Rs.345/- per cubic
meter was worked out by the Arbitral Tribunal, cannot be faulted.
14. The next contention of the learned counsel for the appellant that the
calculation of extra expenditure submitted by the appellant before the
Arbitral Tribunal was not disputed by the respondent and therefore, there
was no requirement for the appellant to adduce evidence to prove the same,
is unacceptable in the light of the specific objection taken by the
respondent before the Arbitral Tribunal which has been so recorded in the
Award. In fact the stand of the respondent all along has been that the use of
class-III grade filter media was completely in consonance with the contract
specification and therefore, there was no question of making any extra
payment on the said head and the BOQ Item No.5.03 and the contract did
not make any mention about the grading of the material to be used in the
work. Having notice of a categorical objection taken by the respondent for
release of extra payment to the appellant, it was incumbent for the latter to
have produced material evidence to justify its claim of extra expenditure
for the work done beyond the BOQ items, which is completely absent in
the present case. Had the appellant produced some evidence, however
sketchy it may have been and the Arbitral Tribunal relying on that and
using its expertise in the field, had accepted the same and then proceeded to
recommend release of extra payment in its favour, then the decision in the
case of P.R. Shah, Share and Stock Brokers (P) Ltd. (supra) would have
had application to the said fact situation. However, in the absence of any
evidence produced by the appellant, neither the recommendations made by
the DRB, nor the Calculation Sheet submitted before the Arbitral Tribunal
would be of any value.
15. We may emphasize that the review that an Appellate Court
undertakes under Section 37 of the A&C Act, is not of the award published
by the Arbitral Tribunal but of the view taken by the learned Single Judge
in the impugned judgment. In other words, the scope of review available
under Section 34 of the A&C Act, is further constricted in appeal. Only if
the learned Single Judge has taken a view that is glaringly preposterous or
has overlooked a patent error, the same can be set right in appeal. But when
all the facts and the law on the aspects argued have been examined in the
impugned judgment and the decision taken is one which is found to be
plausible, even if it is not the only one that can be arrived at in law, the
Appellate Court would forbear from substituting the said view by its own
in appeal. In the present case, the learned Single Judge has reviewed the
Arbitral Award within the parameters of Section 34 of the A&C Act and
thereafter returned his findings. We are of the opinion that there is no
infirmity in the observation of the learned Single Judge that the findings
based on no material would fall foul of the public policy test laid down
under Section 34(2)(b)(ii) of the A&C Act and therefore they cannot be
sustained.
16. For the reasons stated above, we are inclined to concur with the view
taken in the impugned judgment in respect of the observations made with
respect to claim No.6. Accordingly, the present appeal is dismissed as
being devoid of merits, but with no orders as to costs.
(HIMA KOHLI) JUDGE
(SANGITA DHINGRA SEHGAL) JUDGE JULY 13, 2017 rkb/ap/mk/sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!