Citation : 2017 Latest Caselaw 977 Del
Judgement Date : 20 February, 2017
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment Reserved on: 20.01.2017
Judgment delivered on: 20.02.2017
+ FAO(OS) 21/2017
NATIONAL HIGHWAYS AUTHORITY OF INDIA ..... Appellant
versus
GAMMON ATLANTA (JV) ..... Respondent
Advocates who appeared in this case:
For the Appellant : Mr Ramesh Kumar.
For the Respondent : Mr Sumit Goel with Mr Akash Jindal &
Ms Raveena Rai.
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE ASHUTOSH KUMAR
JUDGMENT
ASHUTOSH KUMAR, J
CM 2336/2017 (Exemption) Allowed, subject to all just exceptions.
FAO(OS) 21/2017
1. The appellant, NHAI, has challenged the judgment of the learned
single Judge dated 15.11.2016 whereby the two OMPs, one filed by the
appellant (OMP No.107/2008) and the other by the respondent (OMP
No.99/2008) was disposed of by a common judgment.
2. The appellant had put up a challenge to the award with respect to
the claim Nos.1.1, 1.4, 1.5, 1.9, 2.1 and 2.2, all of which have been
upheld by the learned single Judge
3. The appellant, in October, 2000 had invited bids on International
Competitive bidding basis for a contract package OR-1 for widening of
4/6 lanes and strengthening of existing 2 lane carriageway of NH-5 in the
State of Orissa from 387.700 Kms to 414.00 kms (Khurda-Bhubneshwar).
4. The respondent namely Gammon Atlanta JV was held to be
successful in its bid and the contract of agreement between the appellant
and respondent was signed on 20.12.2000.
5. The contract contained "Conditions for Particular Application
(hereinafter called as COPA) and Technical Specifications (TS)"
whereunder some general conditions of the contract were amended. The
term of the contract was for 36 months beginning from 15.01.2001 to
14.01.2004. The total contract price was Rs.118,90,10,112/-.
6. Because of certain disputes having arisen between the parties, the
arbitration clause was invoked by the respondent; whereupon the disputes
were referred to a three member Arbitration Tribunal (AT).
7. We are concerned, in the present appeal, with the award given on
claims No.1.1, 1.4, 1.5, 1.9, 2.1 and 2.2.
8. Claim No.1.1 pertained to payments which were made by the
respondent as hiring charges for site office for the engineer which,
according to the appellant was not reimbursable. The claim of the
respondent was based on the fact that Bill of Quantities (BoQ) item
Nos.8.15 and 8.16 required the respondent to provide for site office for
engineer including furnishing the office as per drawing and technical
specifications. Because the land was not made available for such
construction, an alternative arrangement was made by the respondent by
hiring a building and which arrangement was accepted by the appellant.
The respondent, therefore, sought payment for the aforesaid work with
price adjustment as also the interest for delayed period for Rs.7,92,670/-
by way of declaratory award. Maintenance charges were also claimed for
subsequent period till completion of work.
9. The aforesaid claim was contested by the appellant on the ground
that such claim was not covered under BoQ items Nos.8.15 and 8.16 and
construction and maintenance of field lab at PIU by the respondent was
only incidental to the work and therefore, no separate payment was
admissible as per general TS and supplementary TS (Clause 121.1).
10. The Arbitral Tribunal directed for filing of a copy of the lease
agreement dated 14.02.2001 of the office building which disclosed that a
monthly rental of Rs.18,000/- was paid by the respondent along with an
interest free deposit of Rs.54,000/-. The lease was renewable on mutually
agreed terms. The rent was paid for more than four years. The respondent
(claimant) did not place any other document regarding enhancement of
the rent. The Arbitral Tribunal accepted and allowed the claim of the
respondent with respect to the rent paid for the site office as well as
towards maintenance. The learned single Judge did not find any
perversity in the decision arrived at by the Arbitral Tribunal. We do not
find any fault with the assessment of the learned single Judge.
11. Claim No.1.9 of the respondent related to payment of cost for
reinforcement in crash barrier and friction slab. BoQ item No.8.29
required construction of RCC crash barrier monolithic with friction slab
M-30 as per approved drawing and technical specification and included
the cost of necessary material, framework and reinforcement. The unit for
payment was linear metre. However, the relevant drawing tendered at the
time of the pre-bid meeting did not show any reinforcement in the crash
barrier but only friction slab was shown without reinforcement. The
respondent (claimant) contended that reinforcement in the concrete crash
barrier and friction slabs were provided on the instructions of the
engineer. Since at the time of tendering, no reinforcement was shown in
the relevant drawing for the crash barrier, the same was not included in
the quoted rate and it was only imperative for the appellant to have paid
for the same. The appellant, had countered before the Arbitral Tribunal
that since the wordings of BoQ item No.8.29 and the drawings provided
to the respondent did not include any reinforcement or friction slab,
therefore, the same was not payable separately. It was also canvassed that
technical specifications in clause 809.6 stipulated for minimum
reinforcement conforming to IRC-21.
12. The AT directed the parties to furnish rate analysis of BoQ No.8.29
at the time of tendering as also at the time of detailed project report stage.
The AT found that sub clause 5.2.2 of COPA, the terms of the bid,
appendix to the bid and addenda had a preference over technical
specifications, drawings and the priced BoQ. IRC 21 (Clause 305.19) laid
down minimum reinforcement to be provided. The AT therefore, was of
the view that even though the drawing at the time of tendering did not
show any reinforcement in the crash barrier, the claimant was duty bound
to include at least minimum reinforcement in the crash barrier and was
justified in quoting the rate for the same accordingly. Even with respect
to payment, the AT devised a formula of making payments separately in
addition to the payment released under BoQ item No.8.29 towards
reinforcement used in the crash barrier in excess of 0.8% of all the weight
of concrete in crash barrier.
13. The learned single Judge rejected the argument of the appellant that
the respondent was wrongly compensated and at best over compensated
and upheld the award of the AT. We do not feel inclined to disturb the
findings of either the Arbitral Tribunal or the learned single Judge for the
reasoning accorded appears to be just and in tune with the requirements
of tendered document.
14. The appellant had challenged the award with respect to claim
No.1.4 which related to payment of additional cost of GSB (Granular Sub
Base) and WMM (Wet Mix Macadam) in Profile Corrective Course. The
relevant BoQ item No.4.04 reads as follows:-
"Providing and laying profile corrective course with dense bituminous macadam complete as per drawing and technical specification Clauses 501 & 507."
The appellant had directed the respondent to lay down profile
corrective course using GSB and WMM in certain stretches. However,
the payments were only made in terms of rates mentioned in BoQ item
Nos.3.01 and 3.02. It was argued by the respondent that the rates for
profile corrective work in GSB/WMM could not be the same as the rates
in BoQ item Nos.3.01 and 3.02 which was for the work done in normal
course. Profile correction required different rates of GSB and WMM. On
the contrary the appellant insisted upon the same being covered under
BoQ item Nos.3.01 and 3.02. The Arbitral Tribunal rejected the
contention of the appellant and held that the work of GSB/WMM in
profile correction are not covered under BoQ item Nos.3.01 and 3.02 and
required to be paid separately. Considering the nature of work of profile
correction in GSB and WMM layers, the Arbitral Tribunal awarded 10%
extra over the rates of item Nos.3.01 and 3.02. The learned single Judge
rightly rejected the contention of the appellant and upheld the award with
respect to the aforesaid claim.
15. The challenge to the award with respect to claim No.1.5 (payment
at revised rates for the construction of additional flyover No.5 at Jaydev
Vihar at Km 418) could also not succeed before the learned single Judge.
The engineer had recommended for revised rates with detailed rate
analysis. The Appellate Tribunal, on going through the contract clause 52
regarding valuation of variations was of the view that it was Engineer's
prerogative to fix the rates after consultation with the employer and the
contractor. The engineer had actually fixed the rates which was accepted
by the appellant. The Arbitral Tribunal found that since the engineer's
rate analysis was a detailed one and was not faulty, the same ought to be
relied upon.
16. The learned single Judge rightly affirmed the award and we do not
wish to interfere on that count as well.
17. Claim Nos.2.1 and 2.2 dealt with compensation for losses incurred
on account of overheads and expected profits for reduced productivity of
machinery and equipment deployed. The tendered rates included
provision for overheads and profits at 27.28% of the tendered cost. It also
included a provision for 14.28% towards overheads. The claim of the
respondent was not challenged seriously and, therefore, the Arbitral
Tribunal, as held by the learned single Judge, rightly accepted the
overheads at 14.28%. Thus on the count of overhead, Rs.37 crores was
awarded and for delay in handing over the site, Rs.5.28 crores was
awarded.
18. With respect to claim for loss of profit, the Arbitral Tribunal
rightly observed that even though the details regarding deployment of
machinery and equipment showed that machinery and equipment were
deployed as per approved programme but the respondents also were
responsible, in some measure for under utilization of machinery which
was occasioned because of various factors namely repairs, non
availability of complementary units, inadequate supply of basic materials
etc. In the opinion of the Arbitral Tribunal, work to the extent of Rs.37
crores was not completed due to default of the appellant in handing over
the site but the respondent could not be compensated on this account to
the extent of 10% as machinery component. The AT, therefore, awarded
5% as machinery component. The aforementioned award has not been
found to be perverse or contrary to record by the learned single Judge.
We also do not find any anomaly in the reasonings given by the Arbitral
Tribunal and the assessment by the learned single Judge.
19. The argument of the learned counsel for the appellant that the
learned single Judge completely overlooked the errors committed by
Arbitral Tribunal has only been noted to be rejected. The paramaters for
interfering with an award of the AT is ingrained in Sections 5 and 34 of
the Arbitration and Conciliation Act, 1996. Section 34 clearly stipulates
that an arbitral award could be set aside under certain conditions
enumerated in the section and no other; those conditions being primarily
with respect to process through which the award is delivered and not
actually on the merits of the award. As stated earlier Section 5 of the Act
which deals with the extent of judicial intervention clearly mandates that
no judicial authority shall intervene except where so provided in the Act.
The aforesaid provisions of the Act are aimed at ensuring that the AT
operates within its jurisdictional limits and provides reasons for the
arbitral award. This, in turn, would pave way for minimum judicial
intervention. The only area where the merits of an arbitral award could be
gone into is Section 2(b)(ii) of Section 34 of the Arbitration and
Conciliation Act, 1996 which contemplates assessment of an award for
being rescinded if the award is in conflict with the public policy of India.
The concept of "Public Policy" includes fundamental policy of Indian
Law, interests of India, Justice or morality and the legality of the award.
If an award is contrary to the fundamental policy of Indian law or against
the interests of India or against morality or if it is patently illegal, it could
be challenged under Section 13(5) and Section 16(6) of the Act.
20. A Court of law does not sit in appeal over an award of the Arbitral
Tribunal by reassessing or reappraising the evidence. The learned single
Judge has gone in detail and has examined each and every claim under
challenge and has found the assessment of the Arbitral Tribunal to be fair
and just.
21. We have also given our anxious consideration over the issues and
did not find any anomaly with either the award or the judgment of the
learned single Judge.
22. Thus, finding no merit in the appeal, we dismiss the same.
CM 2337/2017
1. In view of the appeal having been dismissed, the application has
become infructuous.
2. The application is disposed of accordingly.
ASHUTOSH KUMAR, J
BADAR DURREZ AHMED, J FEBRUARY 20, 2017 k
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!