Citation : 2015 Latest Caselaw 6052 Del
Judgement Date : 18 August, 2015
$~43
* IN THE HIGH COURT OF DELHI AT NEW DELHI
% Judgment delivered on: 18.08.2015
+ WP(C) No. 3966/2015 & CM 7080/2015
SOCIETY FOR INNOVATIVE EDUCATION AND DEVELOPMENT
.... Petitioner
versus
UNION OF INDIA & ORS. ..... Respondents
Advocates who appeared in this case:
For the Petitioner : Mr S.K. Rout with Mr Vinay Kumar
For the Respondent DDA : Mr Pawan Mathur with Mr Hmanshu Gupta
For the Respondent L&B/LAC : Mr Siddharth Panda
CORAM:-
HON'BLE MR JUSTICE BADAR DURREZ AHMED
HON'BLE MR JUSTICE SANJEEV SACHDEVA
JUDGMENT
BADAR DURREZ AHMED, J (ORAL)
1. The counter affidavit of respondent nos. 1 & 2 handed over by Mr
Panda is taken on record. The learned counsel for the petitioner does not
wish to file any rejoinder affidavit as all the necessary averments are
contained in the writ petition.
2. The petitioner seeks the benefit of Section 24(2) of the Right to
Fair Compensation and Transparency in Land Acquisition, Rehabilitation
and Resettlement Act, 2013 (hereinafter referred to as 'the 2013 Act')
which came into effect on 01.01.2014. A declaration is sought to the
effect that the acquisition proceeding initiated under the Land Acquisition
Act, 1894 (hereinafter referred to as 'the 1894 Act') in respect of which
Award No.14/1987-88 dated 26.05.1987 was made, inter alia, in respect
of the petitioner's land comprised in Khasra Nos.991 (4-16), 992 (4-16),
993 (3-00), 985/2 min (1-00) and 1034/2/1 (2-3) measuring 15 bighas 15
biswas in all in village Satbari, New Delhi, shall be deemed to have
lapsed.
3. The stand of the respondents is that physical possession of the said
land was taken on 14.07.1987. This is disputed by the petitioner, who
claims to be in actual physical possession of the subject land.
4. In so far as the question of compensation is concerned, the same
has not been paid to the petitioner but, according to the respondents, the
same has been deposited in the treasury. Therefore, they seek to invoke
the second Proviso to Section 24(2) of the 2013 Act, which was
introduced by virtue of the Right to Fair Compensation and Transparency
in Land Acquisition, Rehabilitation and Resettlement (Amendment)
Ordinance, 2015 (hereinafter referred to as "the said Ordinance").
5. So far as the applicability of the second Proviso to Section 24(2) of
the 2013 Act is concerned, the same cannot be relied upon by the
respondents inasmuch as the Ordinance of 2014 has been held to be
prospective in nature and does not take away vested rights. This has so
been held by the Supreme Court in recent decision in M/s Radiance
Fincap (P) Ltd. & Ors. v. Union of India & Ors. decided on 12.01.2015
in Civil Appeal No. 4283/2011 wherein the Supreme Court held as
under:-
"The right conferred to the land holders/owners of the acquired land under Section 24(2) of the Act is the statutory right and, therefore, the said right cannot be taken away by an Ordinance by inserting proviso to the abovesaid sub-section without giving retrospective effect to the same."
6. The same has been reinforced by the Supreme Court in Karnail
Kaur & Ors. v. State of Punjab & Ors. Civil Appeal No. 7424/2013
decided on 22.01.2015.
7. From the above decisions, it is evident that the said Ordinance of
2014 is prospective in nature and the rights created in favour of the
petitioners as on 01.01.2014 by virtue of the 2013 Act are undisturbed by
the second Proviso to Section 24(2) of the 2013 Act, which has been
introduced by the said Ordinance. The same would apply in respect of
the said Ordinance of 2015.
8. Without going into the controversy with regard to the physical
possession, this much is clear that the Award was made more than five
years prior to the commencement of the 2013 Act and the compensation
has also not been paid to the petitioner, but has only been deposited in the
treasury, which does not amount to payment of compensation as
interpreted by the Supreme Court in Pune Municipal Corporation and
Anr v. Harakchand Misirimal Solanki and Ors: (2014) 3 SCC 183.
9. All the necessary ingredients for the application of Section 24(2) of
the 2013 Act as interpreted by the Supreme Court and this Court in the
following cases stand satisfied:-
(1) Union of India and Ors v. Shiv Raj and Ors: (2014) 6 SCC 564;
(2) Sree Balaji Nagar Residential Association v. State of Tamil Nadu and Ors: Civil Appeal No. 8700/2013 decided on 10.09.2014;
(3) Surender Singh v. Union of India & Others: WP(C) 2294/2014 decided on 12.09.2014 by this Court; and
(4) Girish Chhabra v. Lt. Governor of Delhi and Ors:
WP(C) 2759/2014 decided on 12.09.2014 by this Court.
10. As a result, the petitioner is entitled to a declaration that the said
acquisition proceedings initiated under the 1894 Act in respect of the
subject land are deemed to have lapsed. It is so declared.
11. The writ petition is allowed to the aforesaid extent. There shall be
no order as to costs.
BADAR DURREZ AHMED, J
SANJEEV SACHDEVA, J AUGUST 18,2015 kb
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!