Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Cbate International vs Union Of India And Ors.
2014 Latest Caselaw 2502 Del

Citation : 2014 Latest Caselaw 2502 Del
Judgement Date : 16 May, 2014

Delhi High Court
M/S. Cbate International vs Union Of India And Ors. on 16 May, 2014
Author: Valmiki J. Mehta
*            IN THE HIGH COURT OF DELHI AT NEW DELHI

+                         FAO No.447/2011

%                                                           16th May, 2014

M/S. CBATE INTERNATIONAL                            ..... Appellant
                  Through:               Mr. K.B. Thakur, Advocate.


                          Versus

UNION OF INDIA AND ORS.                                     ..... Respondents

Through: Mr. Jagjit Singh, Advocate.

CORAM:

HON'BLE MR. JUSTICE VALMIKI J.MEHTA

To be referred to the Reporter or not?

VALMIKI J. MEHTA, J (ORAL)

1. This first appeal under Section 37 of the Arbitration &

Conciliation Act, 1996 (hereinafter referred to as 'the Act') is filed against

the impugned judgment of the court below dated 23.4.2011 which has

dismissed the objections filed by the appellant against the Award dated

9.10.2009.

2. Counsel for the appellant urges that Award which is passed

under the 1996 Act has to be a reasoned Award in view of Section 31(3) of

the 1996 Act. It is argued that the court below has wrongly ignored Section

31(3) in the facts of the present case inasmuch as the Award in question

dated 9.10.2009 is a non-speaking Award.

3. The disputes between the parties pertain to supply of stone

ballast by the appellant to the respondent under a contract and which contract

respondent terminated on account of breach by the appellant of failing to

supply the requisite quantity as also delay in supplying whatever quantity

was supplied.

4. The appellant had filed a claim petition before the arbitrator and

the respondent had filed a counter claim. The claim petition pertained to

release of payment as also various deposits which were made by the

appellant to the respondent and for recovery of deductions made by the

respondent from the payment made to the appellant. The counter claim

pertained to entitlement of the respondent to adjust all amounts claimed by

the appellant on account of risk purchase tender which was issued by the

respondent after terminating the contract on account of breaches by the

appellant.

5. The arbitration panel of three arbitrators have given the

following operative portion of the Award:-

"AFTER having heard and fully considered all arguments and evidence of the parties the said disputes and differences and having gone through the materials, papers and documents, and having considered all the matter submitted to us in connection with the aforesaid disputes and differences we do direct and award as follows:-

SN    Description   of Amount of claims Amount           of Reasons      of    amount
      claims           (Rs.)            award               awarded

1.    Extra payment 2,08,019.00             NIL              As per records available,
      for      material                                      Contractor had given his
      supplied       at                                      written consent to supply
      Tanda Yard                                             material in Tanda Yard
                                                             and also completion
                                                             period was extended
                                                             giving them opportunity
                                                             to complete the work.

2.    EMD Amount         50,000.00          NIL              This has been adjusted
                                                             against risk & cost dues
                                                             of Respondents as risk &
                                                             cost tender was done for
                                                             balance     work     and
                                                             completed successfully.

3.    Amount        of 2,50,000.00          NIL              This has been adjusted
      Fixed Deposits                                         against risk & cost dues
      as      Security                                       of Respondents as risk &
      Deposit                                                cost tender was done for
                                                             balance     work     and
                                                             completed successfully.

4.    Security Deposit 2,00,732.00          NIL              Security        Deposit
      deducted from                                          amounting Rs.2,27,957/-
      Running bill.                                          has been deducted from
                                                             running bills and has
                                                             been adjusted against
                                                             risk & cost dues of
                                                             Respondents.

5.    Amount      due 2,73,295.00           NIL              As per final bill prepared
      against supply                                         by the respondents the
      of material                                            cost of balance material
                                                             supplied by the claimant
                                                             is         Rs.2,73,295/-.
                                                             However the same has
                                                             been adjusted against
                                                             risk & cost dues of

                                                             Respondents as risk &
                                                            cost tender was done for
                                                            the balance work and
                                                            completed successfully.

      Total claim of 9,82,046.00          NIL
      contractor

Railway's Claims

SN    Description      of Amount of claims Amount        of Reasons     of    amount
      claims              (Rs.)            award            awarded

1.    Railway's Claim 17,76,783.74        17,44,232.74      As per details made
      on account of                                         available during hearing
      risk & cost                                           and details of counter
      tender                                                claims submitted by the
                                                            respondents total amount
                                                            to be recovered by
                                                            Respondents         from
                                                            Claimant due to Risk &
                                                            Cost tender comes as
                                                            Rs.25,45,484.74.
                                                            Respondents        already
                                                            have Rs.8,01,252.00 i.e.
                                                            [50,000 (Earnest money)
                                                            +      2,50,000     (Fixed
                                                            deposit     as    security
                                                            deposit) + 2,27,957/-
                                                            (security deducted from
                                                            bills) + 2,73,295/- (cost
                                                            of     balance   material
                                                            supplied by claimant)]
                                                            available against the
                                                            terminated contract of
                                                            claimant. Hence only
                                                            balance      amount,    of
                                                            Rs.17,44,232.74 are due
                                                            to the respondents.

      Total claim of      17,76,783.74    17,44,232.74


IN CONCLUSION M/S CBATE International shall pay to U.O.I. represented through Dy. Chief Engineer/Const/Jalandhar, Northern Railway (respondent) a sum of

Rs.17,44,232.74/- in full and final settlement of all claims/Counter Claims of both the parties arising out of the disputes and counter disputes as referred by the General Manager in his letter No.74-W/1/1/377/WA/JUC/ARB dated 21.04.08. THAT this amount as mentioned above should be paid to RESPONDENT within 45 days from the date of publication of the award failing which amount of award will carry simple interest of 10% thereafter i.e from the 46th day of publishing of this award till the date of payment."

6. Without question, the Award in this case is a non-speaking

Award because there is no discussion in the Award as to how the appellant is

held guilty of delay in performance of the contract and as to how respondent

is hence justified in issuing the risk purchase tender and thereafter adjusting

the amounts which were payable to the appellant. Of course, I am not saying

one way or the other on merits because either the case of the appellant can be

correct or the case of the respondent can be correct, however, reasons have

to be given under the 1996 Act and which are ex facie missing in the

impugned Award.

7. In view of the above, the appeal is allowed. Impugned

judgment as also the Award dated 9.10.2009 is set aside. In view of the

Division Bench judgment of this Court in the case of BSNL Vs. Canara

Bank & Anr. 169 (2010) DLT 253 (DB) the matter is remanded back for a

fresh decision by the arbitrators already appointed or if one or more of the

arbitrators are not available then, to any other arbitrator or arbitrators which

the respondent will appoint in accordance with law and the contract between

the parties. The arbitrators will take up the case from the stage of final

arguments and if the parties also want to lead any evidence, arbitrators will

allow the parties to lead additional evidence. The arbitrators will thereafter

decide the matter afresh in accordance with law without in any manner being

influenced by the fact that earlier an Award dated 9.10.2009 was passed.

Arbitration record be given back dasti to the counsel for the respondent who

undertakes to give the record to the requisite authority who keeps the

arbitration record or directly to the arbitrators themselves.

MAY 16, 2014                                          VALMIKI J. MEHTA, J.
Ne





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter