Citation : 2014 Latest Caselaw 1296 Del
Judgement Date : 11 March, 2014
7
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ FAO 43/2013 and CM No. 1616/2013 (Stay)
% 11th March, 2014
INDIA TOURISM DEVELOPMENT CORPORATION LTD......Appellant
Through: Mr. Karunesh Tandon, Advocate
VERSUS
INTEGRATED DIGITAL SOLUTION (P) LTD. ...... Respondent
Through: Mr. Atul Tandon, Mr. Amit Tewari, Advocates
CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA
To be referred to the Reporter or not?
VALMIKI J. MEHTA, J (ORAL)
1. This first appeal is filed under Section 37 of the Arbitration and
Conciliation Act, 1996 (the Act) impugning the judgment of the court below
dated 16.10.2012 by which the objections filed by the appellant/objector
(respondent in the arbitration proceedings) under Section 34 of the Act have
been dismissed. Impugned Award dated 27.1.2009 awards an amount of
Rs.16,41,054/- alongwith interest against the appellant.
2. The facts of the case are that respondent herein accepted a tender with
respect to a sound and light show at Chittorgarh, Rajasthan in the year 2003.
As per the contract the respondent was to supply the material required for
execution of the sound and light show. Originally the proposal was a
comprehensive one for the supply of mannequins and other material for a
sum of Rs. 1,60,40,240/-, but subsequently the quantity was reduced,
including the quantity of the mannequins, and therefore, the second proposal
was made by the respondent for a sum of Rs. 1,43,64,530/-. In this second
proposal there was no motorized mannequins included, and therefore, seven
motorized mannequins were included in a final contract with the total
amount of contract agreed at Rs. 1,49,00,000/-. For this purpose a letter of
intent dated 12.6.2003 was issued by the appellant in favour of the
respondent and subsequently a formal agreement was executed on 20.6.2003
between the parties. After entering into of the contract six additional
mannequins were ordered by the appellant making the mannequins to a total
number of 13. This order was placed upon the respondent by the appellant
by its letter dated 23.3.2005 and which reads as under:
"AC/SEL/CHITTOR/03 23.3.05
M/s. Integrated Digital Solutions Pvt. Ltd.
B-21/3, Okhla Industrial Area-Phase-2 New Delhi-110020.
Dear Sirs,
Sub: Motorized Mannequins for Day Show, Chitorgarh Fort.
This is with reference to the motorized mannequins for the Day Show at Chittorgarh Fort. We hereby confirm the number of mannequins has been increased from seven(7) to thirteen (13). As discussed and explained in the meeting with Sr. Vice President, ITDC recently, the amount payable for thirtee mannequins reached at site will be Rs. 9,95,429/- only @ Rs. 76,571.43.
Thanking you,
Yours faithfully For India Tourism Development Corpn. Ltd.,
Sd/-
(R. Sridharan) Sr. Manager (Culture)"
3. The respondent initially objected to the price as stated in the aforesaid
letter dated 23.3.2005, by its reply-letter dated 24.3.2005 which reads as
under :
"Our reference : IDS/SEL-CG/2103-01
March 24, 2005
Deputy General Manager-Ashok Creatives India Tourism Development Corporation Limited Scope Complex - Core 8 Lodi Road New Delhi 110 003.
Kind attention : Ms. Madhu Dubey
Dear Madam
Re: Chittorgarh Mannequins
Kindly recall our discussions of the last week where we expressed our displeasure in the delays on part of ITDC on the matter related with the issue of amendment for the additional mannequins, release of related with-held payments and the decision on the locations where these mannequins are required to be mounted.
During this meeting, we were assured that all the matter will be resolved within a week.
On the contrary, we are shocked to receive a letter from your office, bearing # AC/SEL/CHITTOR/03 dated 23 rd instant, which has no bearing either with previous discussions or with the provisions of the contract agreement and has no rationale too, as it suggests that we supply the additional 6 mannequins at a meager total amount of Rs. 45 thousand approximately.
As per the contract agreement:
- the entire project is on a fixed upper-limit value (Rs.
149.00 lacs), except for the mannequins.
- unit rate of the mannequins has been fixed (Rs.
1,35,700.00)
- tentative requirement of the mannequins (seven nos.) included in the originally agreed upper-limit value of the contract and
- where, for any additional requirement (six now) of the mannequins, an enhancement in the upper-limit value (by Rs. 8,14,200.00 now) was warranted, irrespective of whether the upper-limit of the agreed contract amount is crossed or not.
Therefore, in view of the above, we wish to clarify that your letter, referred above, is not acceptable to us, as we find it arbitrary and not conforming to the true spirit of the contract agreement.
You are kindly aware that the mannequins are already at site since long and it is relevant to take decision, in terms of the contract agreement, without any further delay.
Kind regards
Sincerely yours, For integrated Digital Solutions Private Limited
Mukesh Bhargava Director"
4. The respondent however in spite of objections to the price as stated in
its letter dated 23.3.2005 without further ado as to the price stated in the
appellant's letter dated 23.3.2005 supplied the six additional mannequins.
After completion of the contract respondent sought the price of the
mannequins at around Rs. 1,35,700/- per mannequin instead of Rs.76,571.43
as stated in the order-letter dated 23.3.2005. There were also two other
disputes between the parties pertaining to the cost incurred by the respondent
towards security inasmuch as the appellant took charge of the project with
delay and also the claim of interest on the amount which was due and
payable on the respondent, but not paid. Matters were hence referred to
arbitration.
5. The arbitrator allowed all the three claims of the respondent by
rejecting the defence of the appellant that the price of additional mannequins
should not be Rs. 1,35,700/- per mannequin but only Rs. 76,571.43 as stated
in the letter dated 23.3.2005. The arbitrator further held that since the
appellant was guilty of delay the respondent would have incurred cost
towards security, and therefore, cost of security and related expenses were
awarded in favour of the respondent. Interest was also allowed on the
awarded amount by the arbitrator.
6. The court below has dismissed the objections by refusing to accept
that only Rs. 76,571.43 per mannequin was payable as per the stand of the
appellant vide its letter dated 23.3.2005. Other objections to the awarded
claims have also been rejected on account of the fact that once there is delay,
the respondent would have incurred cost on security and that the interest was
liable to be paid as per Section 31(7)(a) of the Act.
7. Before me, learned counsel for the appellant has very vehemently
argued that once the appellant specified a specific price for the additional
mannequins at Rs. 76,571.43 per mannequin as per its letter dated 23.3.2005,
it was perfectly open to the respondent not to supply the mannequins
because there was no compulsion upon the respondent to enter into a fresh
contract for supply of additional mannequins @ Rs. 76,571.43 per
mannequin. Learned counsel for the appellant argues that the objection
raised by the respondent in terms of letter dated 24.3.2005 is of no effect
because one of the ways in which contract is accepted is by giving
performance of the offer as contained in the letter of the appellant dated
23.3.2005 and the respondent very much performed the contract by
supplying additional mannequins. Reliance is also placed on behalf of
appellant upon Sections 7 and 8 of the Indian Contract Act, 1872 to argue
that contract is implied when performance takes place of an offer or
obligation/promise under a contract. Counsel for the appellant has also
argued that the respondent ought not to have been allowed costs towards
security expenses and interest as has been awarded by the arbitrator.
8. Learned counsel for the respondent has very vehemently disputed the
arguments urged on behalf of the appellant. So far as the first issue of the
cost of the mannequins is concerned it is argued that in hindsight it is
convenient for the appellant to claim the cost of mannequins only to Rs.
76,571.43 per mannequin in terms of its letter dated 23.3.2005, however, the
same ignores the factual position that the respondent had to complete the
contract. It is also argued that the case of the appellant that no costs were
incurred towards security is not correct because bills have been filed
showing incurring of expenditure and that evidence has been considered by
the arbitrator and consequently re-appreciation of the evidence cannot be
done under Section 34 of the Act. It is also argued that the court below has
rightly relied upon Section 31(7)(a) of the Act to confirm the Award of the
arbitrator awarding interest to the respondent.
9(i) In my opinion, the appeal is liable to be accepted so far as the
first issue which is urged being the cost of the mannequins is concerned and
is liable to be rejected so far as the two other claims which have been
awarded by the arbitrator.
(ii) In my opinion, appellant is justified in relying upon Sections 7
& 8 of the Indian Contract Act, 1872 because one of the ways in which a
contract is entered into is by giving performance under the offer. The
specific and categorical offer of the appellant was of supplying of
mannequins at Rs. 76,571.43 per mannequin in terms of letter dated
23.3.2005 and there was never any compulsion to the respondent to supply
additional mannequins if according to the respondent the price stated in the
letter dated 23.3.2005 was inadequate. The letter of the respondent dated
24.3.2005 amounted to a counter-offer qua the price but there is no
confirmation/acceptance to the same by the appellant. Thus when the supply
of additional mannequins was made by the respondent it can only be taken
as supply in terms of the appellant's letter dated 23.3.2005. I cannot agree
with the argument urged on behalf of the respondent that in hindsight
appellant is now failing to appreciate conditions inasmuch as the respondent
was under no contractual obligation to supply six additional mannequins,
and therefore, contract would always have been completed and performed
without any breach by the respondent which was entered into for the supply
of original seven mannequins and the respondent was not in any manner
bound to supply the six additional mannequins if according to it the rate of
Rs. 76,571.43 was not adequate. In my opinion, once the respondent
supplied the additional mannequins, merely objecting to the rate after supply
was made is not enough to claim a higher price because if the respondent
was not agreeable to the rate as offered by the appellant it should have never
supplied the six additional mannequins and for which it was not legally
bound to do so. Therefore, in my opinion, the arbitrator has clearly
committed an illegality inasmuch as Section 28(3) of the Act clearly states
that the arbitral tribunal shall decide only in accordance with the terms of the
contract and the contract in my opinion is complete in terms of amount
stated in the letter of the appellant dated 23.3.2005 inasmuch as respondent
has acted upon this letter dated 23.3.2005 and the same consequently
resulted in a binding contract as per the provisions of the Indian Contract
Act, 1872 including Sections 7 and 8 related to implied contract and contract
by performance. I therefore accept the appeal and the objections to the
extent that the cost of six additional mannequins will only be at Rs.
76,571.43 per mannequin and not at the amount of about Rs. 1,35,700/- per
additional mannequin as awarded by the arbitrator.
10. So far as the case for security charges are concerned, I am unable to
accede to the argument urged on behalf of the appellant because respondent
no doubt would have incurred charges on account of delay of appellant in
taking over the project inasmuch as a valuable project after completion of
the same with its expensive equipment could not have been left without any
security. Once there was security, and bills were filed by the respondent to
show incurring of charges then at best in my opinion two views will be
possible and the arbitrator was hence entitled to take one of the two views to
hold that the respondent had incurred charges towards security for awarding
the claim in this regard. Taking of one possible view is not a perversity
which can be interfered with under Section 34. This contention on behalf of
the appellant is accordingly rejected.
11. So far as the third aspect of claim of interest is concerned, the court
below has rightly relied upon the provision of Section 31(7)(a) which allows
the arbitrator to award interest for the period prior to the arbitration
proceedings. Once interest is not paid for a sufficiently long period, in my
opinion, the same itself becomes a principal amount and there is nothing
grossly illegal if on the said amount which was due on the date of the
commencement of the arbitration proceedings, further interest is awarded.
The appellant cannot take benefit of its own wrong in failing to pay the
amount due and yet claim that in spite of passing of a long period of time
interest should not become part of the principal. Even nationalized banks
when they lend money charge interest at quarterly rates i.e after every three
months interest becomes part of the principal. I thus do not find any
illegality or perversity in the Award in granting interest because at best two
views are possible and arbitrator is entitled to take one possible and
plausible view.
12. In view of the above discussion, the appeal is partly allowed so far as
the cost of six additional mannequins whose price is held to be @ Rs.
76,571.43 per mannequin are concerned and the appeal is dismissed so far as
the other objections are concerned. Parties are left to bear their own costs.
MARCH 11, 2014 VALMIKI J. MEHTA, J godara
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!