Citation : 2014 Latest Caselaw 6476 Del
Judgement Date : 4 December, 2014
$~42
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ CONT.CAS(C) 970/2013
Decided on : 4TH December, 2014
VLS FINANCE LTD ..... Petitioner
Through: Mr. Jayant K. Mehta, Ms. Madhavi Khare &
Mr. Ashok K. Sharma, Advocates.
versus
SOUTHEND INFRASTRUCTURE PVT LTD THR ITS
DIRECTOR, MR DINESH KUMAR GUPTA, @ D K GUPTA
& ANR ..... Respondents
Through: Mr. Kapil Arora & Ms. Sanghitra Sawant,
Advocates for R-1.
Mr. Dushyant Dave & Mr. Chetan Sharma,
Senior Advocates with Mr. Vijay K. Sondhi,
Mr. Venancio D'Costa, Mr. Ashish Kr.
Singh & Mr. Azeem Samuel, Advs. for R-2.
CORAM:
HON'BLE MR. JUSTICE V.K. SHALI
V.K. SHALI, J. (ORAL)
1. By virtue of the present order CM No.4181/2014 filed by respondent
No.2 is being decided. The question which has arisen for
consideration in this application is as to whether the contempt court,
which has passed the order dated 09.01.2014 in CM No.20181 of
2013, to the R-2/Wonder Space Properties Pvt. Ltd in whose favour
rights have been created by respondent No.1 as described in conveyance deed dated 01.06.2013 in respect of property No.B-319,
Okhla Industrial Area, Phase I, New Delhi can be continued or not.
2. It may be pertinent here to mention that by the aforesaid order dated
29.01.2014, the respondent No.2 was directed to maintain status quo
while as the present application has prayed for vacation of that order.
3. Before dealing with the contentions of the learned senior counsel
appearing for respondent No.2/applicant, it will be pertinent to give a
brief background of the case.
4. The petitioner had entered into some property transaction for the
development of a plot of land measuring 34,275 square meters
bearing No.C-20, 1A/10, Block C, Sector 62, NOIDA. The aforesaid
plot was to be developed for IT and IT enabled services. The
petitioner had entered into this agreement with M/s BMS IT Institute
Private Limited. There were some disputes between these two
contracting parties which led to filing of a petition under Section 9 of
the Arbitration and Conciliation Act, 1996 by the present
petitioner/VLS Finance Limited against BMS IT Institute and eleven
other parties. The respondent Nos.2 to 10 were individuals and a
private company while respondent Nos.11 & 12 were two other companies. The allegations made respondent Nos.2 to 9 were the
individuals/contractors of respondent No.1/company. It was further
alleged that apart from these individual respondents, who were the
contractors/office bearers of respondent No.1/company, were also
having the controlling effect in respect of other three companies who
were impleaded as respondent Nos.10 to 12. These companies
included respondent No.1 herein/Southend Infrastructure Pvt. Ltd.
having its office at B-319, which is the property in question in respect
of which restraint order has been issued on 09.01.2014. The court
passed an order on 27.04.2012 in OMP NO.383/2012 restraining the
respondent Nos.2 to 12 from alienating, selling, transferring,
mortgaging, encumbering, disposing of or in any manner dealing with
their immovable property. On 04.09.2012, the learned single Judge
which was dealing with OMP No.383/2012 was informed that the
affected parties have approached for arbitration of their disputes and
consequently there was no need to continue with the OMP and it can
be treated as disposed of. The learned single Judge after hearing the
learned counsel for the parties made the order dated 27.04.2012
absolute during the pendency of arbitration proceedings with the direction that the said order shall continue to be in operation till the
time the same is varied or modified by the learned arbitrator on an
application being filed by any of the parties.
5. The present petitioner/VLS Finance Limited filed subsequent thereto
CCP No.970/2013 alleging that the aforesaid restraint order has been
wilfully and deliberately violated by R-1 herein i.e.Southend
Infrastructure Pvt.Ltd. by executing a conveyance deed in favour of
the R-2/Wonder Space Properties Pvt. Ltd on 10.06.2013 in respect of
property bearing No.B-319, Okhla Industrial Area Phase I, New Delhi
and thus they are both guilty of having wilfully disobeyed the orders
of the court and deserve to be proceeded against under the Contempt
of Courts Act, 1971. Notices were issued to both the parties on
09.01.2014 and while doing so, the learned Judge issued a fresh ad
interim order directing that the respondents shall maintain status quo
as of that date in respect of property bearing No.B-319, Okhla
Industrial Area, Phase I, New Delhi.
6. The respondent No.2 filed its reply and contested the claim.
Similarly, the respondent No.1 filed its reply and contested the claim.
Now CM No.4181/2014 has been filed by the respondent No.2 seeking modification/variation of the ad interim order passed by the
court on 09.01.2014.
9. I have heard Mr. Dave, the learned senior counsel for the
applicant/respondent No.2 on the application as well as Mr.Jayant
K.Mehta, the learned counsel for the petitioner/non applicant and
have also gone through the record.
10.The learned senior counsel for respondent No.2 has contended that the
ad interim order dated 09.01.2014 deserves to be vacated on account
of the fact that the respondent No.2 was neither a party to the OMP
proceedings nor is a party before the learned arbitrator as there is no
privity of contract between the petitioner and the respondent No.2. It
has been contended that even the proceedings which have been
initiated before the arbitrator by way of statement of claim by the
present petitioner, does not include the respondent No.1/ Southend
Infrastructure Pvt.Ltd as a party and, therefore, the ad interim order
which was passed by the court on 27.04.2012 and confirmed on
04.09.2012 ceases to have any validity qua respondent No.1 so far as
property bearing No. B-319, Okhla Industrial Area, Phase I, New
Delhi is concerned.
11. It has next been contended by the learned senior counsel that
moreover the property in question in respect of which order of status
quo has been passed was not at all involved in the agreement between
the petitioner and the BMS IT Institute Private Limited for the
purpose of development of IT and IT-enabled services. The property
which was to be developed was in Sector 62, NOIDA and not the
property bearing No.B-319, Okhla Industrial Area, Phase I, New
Delhi and, therefore, the aforesaid restraint order could not have been
passed.
12. Thirdly, it has been contended by the learned senior counsel for
respondent No.2 that assuming though not admitting that such an
order could have been passed, the said order does not affect the right
of the respondent No.2/Wonder Space Properties Pvt. Ltd which is a
company registered under the Companies Act, 1956 and is a bona fide
purchaser of the land in question vide conveyance deed dated
10.06.2013. In the reply, it has been contended by him that the
respondent No.2 has acted with due diligence. It had inserted
advertisements inviting objections from the parties having any right,
title or interest in the property in question and pursuant thereto objections were received from three different parties and dealt with by
the respondent No.2, but no objections whatsoever were either
received from the side of the petitioner and, therefore, it could not be
contended that respondent No.2 was not a bona fide purchaser.
Moreover, it was stated that the respondent No.2 had also conducted
an inspection in the office of the Sub Registrar and a certificate of
search showing that the property was free from encumbrances was
also obtained from a counsel pursuant to which they went ahead for
the purpose of transacting that property. Therefore, it was contended
that the rights of the respondent No.2 in respect of the property in
question could not be estopped, acquired or impaired by the ad
interim order issued by this court on 09.01.2014. The learned senior
counsel has also placed reliance on the judgments of the apex court in
Parents Association of Students v. M.A.Khan and Anrs. (2009) 2 SCC
641 to contend that the contempt court was not the court which could
enlarge the scope of the original order by passing an ad interim order.
13. The learned counsel for the petitioner has very vehemently contested
the submissions made by the learned senior counsel for R-2. He has
contended that the restraint order which was passed by the court on 27.04.2012 and confirmed on 04.09.2012 in OMP No.383/2012 was
not only against respondent Nos.2 to 9, who were the Directors of the
respondent No.1/BMS IT Institute Private Ltd. in respect of which a
contract had been entered into, but also in effect with respect to the
property owned by three other companies including the respondent
No.1 herein also. This was so because these respondents had a
controlling interest in the three companies which were made parties in
the OMP which included respondent No.1/Southend Infrastructure
Pvt.Ltd also. It has been contended by the learned counsel that in a
matter of this nature, the court is required to lift the veil and see as to
who have the controlling interest and whether by the act and omission
of the respondents, the orders of the court are being flouted or not.
14. It has also been contended by the learned counsel for the petitioner
that the apex court has also ruled in a number of cases that where a
contempt is committed by a party, the party who is guilty of contempt
prima facie must restore status quo ante and it cannot be permitted to
enjoy fruits of its illegal acts of having committed the contempt. The
reliance in this regard is being placed on i) Mohammad Idris and Anr.
Rustam Jehandir Babuji and Ors; (1984) 4 SCC 216 and ii) DDA v. Skipper Construction Company Private Ltd and Anr; AIR 1996 SC
2005.
15. I have carefully considered the submissions made by the learned
counsel for the parties. There is no dispute about the fact that the
restraint order which was issued on 27.04.2012 in the OMP
No.383/2012 was against respondent Nos.2 to 12 where respondent
No.1 herein was a party as respondent No.12. It is also not in dispute
that the respondent No.1 was the only party which was a signatory to
the agreement between the petitioner and the respondent No.1 through
its director for the purpose of development of a plot of land situated in
NOIDA and so far as the plot No. B-319, Okhla Industrial Area,
Phase I, New Delhi is concerned, that was not all in issue either in the
OMP or in the statement of claim filed before the learned arbitrator.
16. Therefore, even if it is assumed that an order of restraint was issued
directing the respondent Nos.2 to 12 to maintain the status quo with
regard to the properties in question, that order was subject to
modification/variation by the arbitrator on an application under
Section 17 of the Arbitration and Conciliation Act, 1996. Admittedly
no application has been moved by any of the parties before the learned arbitrator and certainly not filed by the respondent No.1. But
at the same time, the fact remains that the respondent No.1 is not a
party before the arbitrator and rightly so because it was not signatory
to the arbitration agreement with the petitioner. Therefore, even if
there was an interim order passed by the arbitrator, the very fact that it
was not made as a party before the arbitrator, the stay order passed on
27.04.2012 and confirmed on 04.09.2012 ceases to exist qua
respondent No.1.
17. I do not agree with the contention of the learned counsel for the
petitioner that while considering the contempt committed by a person
which would include the juristic or a natural person, the court will be
called upon to lift the corporate veil and see as to whether the
directors of a company 'X' has a controlling interest in another
company 'Y' and then by a process of deduction and presumption
hold the company 'Y' guilty of contempt. This cannot be permitted to
be done as the law of contempt carries punitive sanction and like other
criminal law, which has to be construed strictly, the contempt law has
also to be construed strictly as it entails incarceration and imposition
of fine by way of punishment. Therefore, in my considered opinion, this submission of the learned counsel for the petitioner does not have
any merit.
18. So far as passing of an interim order by the contempt court is
concerned on 09.01.2014, in this regard also I feel such an order
ought not to have been passed. The reason for this is that the job of a
contempt court is to see as to whether the order/direction/judgment
which has been passed by a court has been disobeyed by a party or not
and if disobeyed whether this disobedience is wilful and deliberate. If
both these conditions are satisfied, the contempt court undoubtedly
has the power to visit such a person with a sanction and the person
who has got the benefit, must necessarily cause reparation of the
benefit which he has taken. But it is not a case of reparation. The
question is the contempt court cannot in my view enlarge the scope of
an original order and then pass fresh ad interim order on account of
the alleged wilful breach, which may give rise to a fresh cause of
action to the petitioner to obtain such appropriate relief which it may
want against the third party. In other words, the contempt court,
could not have passed an ad interim order directing a party/respondent
No.2 who was not a party to the arbitration proceedings to maintain status quo with regard to the property which was not all at all in issue
in contract itself between the petitioner and that too between a third
party and not the party which owned the property.
19. The learned counsel for the petitioner has referred to aforementioned
two judgments of the apex court where the Supreme Court has
observed that a party cannot be permitted to retain the benefits of the
contempt and has been made to repay or purge the same.
20. I have gone through both these judgments but the facts are totally
distinguishable from the facts of the present case. Therefore, those
authorities do not help the petitioner in any manner. Moreover, I am
fully satisfied that the respondent No.2 could not have been directed
to maintain status quo with regard to property No.B-319, Okhla
Industrial Area, Phase I, New Delhi and in any case the respondent
No.2 is a bona fide purchaser who has taken all steps which are
expected of a normal person to be taken by taking due diligence
before a property is transacted.
21. There is absolutely no defence in this regard to be put up by the
petitioner and therefore I feel that the evidence which has been
brought on record by the respondent No.2 shows by preponderance of probability that it is a bona fide purchaser.
22. Another argument of the learned counsel for the petitioner is that in
case the court does not intend to continue the ad interim order dated
09.01.2013 against the respondent No.2, it is liable to pay some
money to the respondent No.1 and, therefore, it should be directed to
pay the said money either to the petitioner or alternatively it be
ordered to deposit in this court.
23. I do not agree with the contention of the learned counsel that such an
order can be passed by the court in a contempt petition. Assuming
that such an order can be passed, it is liable to be unsustainable in
which the present order is being vacated. Therefore, this prayer of the
petitioner is disallowed.
24. For the reasons mentioned above, I feel that the application of the
respondent No.2 deserves to be allowed and the ad interim order dated
09.01.2014 deserves to be recalled/vacated.
25. Ordered accordingly.
26. The parties are left to bear their own costs.
V.K. SHALI, J DECEMBER 04, 2014/dm
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!