Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Brij Lal & Sons vs Union Of India And Anr.
2014 Latest Caselaw 1992 Del

Citation : 2014 Latest Caselaw 1992 Del
Judgement Date : 22 April, 2014

Delhi High Court
M/S. Brij Lal & Sons vs Union Of India And Anr. on 22 April, 2014
Author: Valmiki J. Mehta
*              IN THE HIGH COURT OF DELHI AT NEW DELHI

+                           FAO No.435/2011

%                                                     22nd April, 2014

M/S. BRIJ LAL & SONS                                  ..... Appellant
                    Through:             None.

                            Versus

UNION OF INDIA AND ANR.                                    ..... Respondents
                  Through:               Ms. Aarti Sharma, Advocate.

CORAM:
HON'BLE MR. JUSTICE VALMIKI J.MEHTA

To be referred to the Reporter or not?


VALMIKI J. MEHTA, J (ORAL)

1.             This first appeal is filed under Section 37 of the Arbitration

& Conciliation Act, 1996 (hereinafter referred to as 'the Act')

impugning the judgment of the court below dated 21.5.2011 by which

the objections filed by the appellant under Section 34 of the Act against

the Award of the arbitrator dated 23.10.2006 were dismissed.             The

appellant/contractor was given the contract of repairing of approach road

around Fish Market Complex Phase-I in Trans-Yamuna Area in Delhi

and with respect to which disputes arose resulting in arbitration

proceedings.

FAO 435/2011                                                    Page 1 of 6
 2.            The arbitrator by the Award dated 23.10.2006 dismissed the

claim Nos.1,2 and partly allowed claim No.3. Appellant filed objections

against the rejection of the claim Nos.1, 2 and 3. These objections have

been dismissed by the court below by making the following relevant

observations:-

     "7.      The petitioner pleaded that while deciding the claim no.
     1, the respondent no.2 had not rightly interpreted the two
     statements furnished by the parties to ascertain the rate for the
     work. Perusal of the record reveals that while deciding the said
     claim, the respondent no. 2 duly considered the submissions and
     the documents including Ex.C-1, Ex.C-2 and Ex.C-3 furnished by
     both the parties in support of their case. The respondent no.2
     clearly held that one had to go by the record of pre measurement,
     since measurements were not feasible after pot holes had been
     filled up; it was for the petitioner to satisfy himself the all per-
     measurements of pot holes were recorded in MB before he filled
     them up; his statement in Ex.C-2 dated 17.07.1997 and Ex.C-3
     dated 24.07.1997 had been made after the work of filling pot
     holes was carried out. While deciding the said claim the arbitrator
     has also duly considered the letter dated 06.09.1997 Ex.C-8. It is
     also revealed that on 27.6.2006, the petitioner was asked to file
     additional proof, if any, in support of his claim, which he failed to
     furnish. In the present petition, the petitioner has not challenged
     any of the said findings given by the respondent no.2 for
     dismissal of the said claim. As such, the said findings have
     attained finality.
     8. Regarding the claim no.2, the petitioner pleaded that the
     respondent no.1 back dated the date of completion of the work
     and the respondent no.2 had not rightly considered his plea.
     Perusal of the award reveals that the arbitration recorded and
FAO 435/2011                                                    Page 2 of 6
    considered the submissions of the respective parties. The
   respondent no.2 also given the opportunity to the petitioner to
   produce any document to substantiate that he carried our
   additional work and the measurements were recorded to that
   effect. However, no such record was produced by him. The
   respondent no.2 also observed that if the petitioner had actually
   done so much additional work as claimed by him, it was not clear
   why he signed even under protest and then claimed the final bill.
   The petitioner has not challenged the findings of the respondent
   no.2 while dismissing his said claim and the same has attained
   finality.

   9. Regarding the claim np.3, the petitioner pleaded that the
   respondent failed to produce the receipt of bitumen or issue the
   bitumen in MAS account duly signed by the petitioner. Hence, his
   whole claim should have been allowed. To dispose of hte said
   claim, the respondent no. 2 placed reliance on Ex.C-8 and drawn
   an inference that the bitumen was supplied at least partly. The
   claimant has not pleaded that the reliance of the respondent no. 2
   on the said document and the inference drawn by him was not
   correct. As such, the same has attained finality.

   10.      In fact, the petitioner has completely filed to mention and
   explain under which provision of section 34 of the Act, his
   objection lie. The main grievance of the petitioner is that while
   passing the award, the respondent np.2 has not interpreted the
   documents and material available on record according to his
   version. Perusal of the arbitration record reveals that while
   deciding the claims filed by the petitioner the respondent no.2
   dealt with each and every plea raised by the petitioner in the
   present petition. While discussing the said pleas and the
   documents available on record, the respondent no. 2 passed a
   reasoned and speaking award. As discussed above, the petitioner
   has not challenged the findings of the respondent no.2 and the
   same have attained finality. In the present case, it can be said that
FAO 435/2011                                                  Page 3 of 6
      the grievance of the petitioner is that the respondent np.2 should
     have adopted the other interpretation of the documents than the
     interpretation which he adopted while passing the award. It is a
     settled law that while deciding the petition u/s 34 of the Act, the
     court should not sit as an appellate court and thereby its own
     interpretation to judge the sustainability of the award. In my view,
     merely because the another interpretation could be possible, is not
     a ground under section 34 of the Act to interfere and set aside the
     award." (underlining added)

3.            The court below has rightly considered the facts of the case

and scope of Section 34 of the Act and rightly held that arbitrator has

taken one possible view from the appreciation of evidence and it cannot

be interfered by a court hearing objections under Section 34 of the Act.

If the scope of hearing objections under Section 34 of the Act is limited,

then, surely scope of an appeal against an order dismissing objections

will have to be further limited.

4.            The Award of the arbitrator in this case shows that so far as

claim No.1 is concerned, it was a claim for the area filled up in pot holes

but the issue of measurement was raised after the pot holes were filled

up and therefore there was no evidence available after the pot holes were

filled up and more so when the appellant had accepted the first bill in

which the quantities filled up were stated and which were not disputed.



FAO 435/2011                                                   Page 4 of 6
 Claim No.1 was therefore rightly rejected and objections against which

were rightly dismissed by the court below.

5.          So far as the second claim with respect to additional work

done is concerned, the arbitrator notes that the claimant did not submit

any proof in support of the claim that he had executed work of 3335 sq

mtrs. The appellant/claimant was asked to produce documents regarding

order to carry out additional work and measurements recorded if any,

but the same was not produced. Appellant also had signed the bill

issued and in which there was no signature of signing under protest.

Accordingly, arbitrator dismissed the claim no.2 and which cannot

therefore be disputed within the scope of hearing objections under

Section 34 of the Act.

6.          So far as claim No.3 of claim of additional bitumen is

concerned, the arbitrator notes that records were lost and consequently

by the best assessment taken, part of the claim was allowed, and to

which neither the court hearing objections under Section 34 and nor this

Court could do any better.




FAO 435/2011                                                Page 5 of 6
 7.           In view of the above, there is no merit in the appeal, and the

same is therefore dismissed, leaving the parties to bear their own costs.




APRIL 22, 2014                                VALMIKI J. MEHTA, J.

Ne

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter