Friday, 24, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Hydro-Electric Power ... vs M/S Ali Mohammed Baba & Sons
2013 Latest Caselaw 547 Del

Citation : 2013 Latest Caselaw 547 Del
Judgement Date : 5 February, 2013

Delhi High Court
National Hydro-Electric Power ... vs M/S Ali Mohammed Baba & Sons on 5 February, 2013
Author: Indermeet Kaur
25
*     IN THE HIGH COURT OF DELHI AT NEW DELHI

%                                Date of Judgment:05.02.2013

+     FAO(OS) 78/2013

NATIONAL HYDRO-ELECTRIC POWER
CORPORATION LTD                              ..... Appellant
                 Through  Mr. Kailash Vasdev, Sr. Adv.
                          with    Mr.    Ajit      Pudussery,
                          Ms.Joanne Pudussery, Mr. Dinesh
                          Khurana and Mr. Shreejiges
                          Singhvi, Advs.
                 versus

M/S ALI MOHAMMED BABA & SONS                           ..... Respondents
                 Through  Nemo.

CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MS. JUSTICE INDERMEET KAUR


INDERMEET KAUR, J.

CM No. 2120/2013 (Exemption)

1 Exemption allowed, subject to all just exceptions.

CM No.2122/2013 (delay of 13 days in refiling the appeal)

2 In view of the averments contained in the instant application,

delay of 13 days in refiling the appeal is condoned.

 3     Application stands disposed of.


FAO (OS) No. 78/2013 & CM No.2121/2013 (for stay)

4     The respondent had entered into a contract with the appellant in

terms of a letter of Award dated 13.07.1989 whereby the respondent had

agreed to supply materials for commissioning of a 33 KV transmission

line for the URI hydro-electric project located at Baramullah District of

Jammu and Kashmir. The entire work was to be completed within a

period of nine months i.e. by 12.04.1990. The case of the appellant was

that the respondent did not adhere to the time schedule. The supply part

of the contract was not completed within the stipulated period and the

respondent even failed to complete the construction part within time.

The contract was ultimately abandoned. Disputes arose between the

parties which were referred to a sole Arbitrator who was the Chief

Engineer, In-Charge of the appellant's project. The Award was

pronounced on 30.04.2003. The appellant not satisfied with the Award

filed objections under Sections 30 & 33 of the Arbitration Act, 1940

(hereinafter referred to as the said 'Act') which were disposed of vide

the impugned order dated 11.09.2012.

5 Learned counsel for the appellant has confined his arguments on

two points. His first submission is that vide letter dated 17.01.1992, the

respondent had himself abandoned the contract and once it was clear

that the contractor had abandoned the work, the appellant was justified

in retaining 10% of each bill; even otherwise the letter dated 17.01.1992

was written by the contractor much after the time when the contract was

to be completed and the contractor had highlighted the problem relating

to non-availability of site only at that time which was disputed by the

appellant; not taking away the fact that this letter dated 17.01.1992 was

written much after the stipulated date of completion of the contract and

there was no justification for the contractor in not completing his part of

the contract.

6 This argument had been raised before the learned Single Judge

and it had been answered while dealing with claim No. 2. The Single

Judge had noted that in respect of claim No. 2 elaborate reasons had

been given by the Arbitrator and after considering the material brought

on record had given a definite finding as regards the failure on the part

of the appellant to make available the site to the contractor as to where

the line was to be laid; it also did not create a conducive atmosphere for

the work. This was after consideration of the evidence including the

testimony of the witnesses. Learned Single Judge had noted that the

view taken by the Arbitrator being a plausible one; he being an expert in

the field and being aware of the ground realities; the Award on this

count did not suffer from any illegality. The Single Judge refused to

interfere with this finding which finding stands endorsed by this Court.

7 The second submission of the learned counsel for the appellant is

bordered on reference to Clauses No. 39.1 to 39.3 of the contract which

read as under:-

"29.Clauses 391.1 to 39.3 of the contract read as under:

39.1 All costs, claims, damages or expenses which the Corporation may have paid for which under the contract the Contractor is liable, may be deducted by the Corporation from Performance Guarantee or from any moneys due or may be recovered from the Contractor.

39.2 Any sum of money due and payable to the Contractor (including Performance Guarantee returnable to him) under this contract may be appropriated by the Corporation and set off against any claim of the Corporation out of or under any contract made by the Contractor with the Corporation.

39.3 It is an agreed terms of the contract that the sum of money so withheld or retained under this clause by the Corporation shall be kept, withheld or retained as

such by the Corporation till the claims arising out of in the same contract are either mutually settled or determined by the Arbitrator, and the Contractor shall have no claim for interest or damage whatsoever on this account or any other ground in respect of any sum of money withheld or retained under this clause and duly notified a such to the Contactor."

8 Submission being that there was an express prohibition on the

payment of interest.

9 Learned Single Judge had rightly noted that only when the

appellant retains the money payable under the performance bank

guarantee; the contractor shall have no claim for interest; the prohibition

of payment of interest would not apply to any legitimate claim made by

the contractor for a wrongful withholding of the moneys payable to him

and once it is held that some money was due to the contractor which was

not legitimately paid to him then obviously the prohibition against

payment of interest would be inapplicable. It was rightly noted that there

was no absolute prohibition on the payment of interest if the claim set

up by the contractor was a legitimate claim. Compound interest has been

disallowed by the Single Judge and to that extent the Award stood

modified directing that the interest would be payable only on the

principal sum.

10 On neither count does the order of the learned Single Judge brook

any interference. The appeal is without any merit. Appeal as also the

stay application stands dismissed.

INDERMEET KAUR, J.

FEBRUARY 05, 2013                    SANJAY KISHAN KAUL, J.
A





 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter