Citation : 2013 Latest Caselaw 5621 Del
Judgement Date : 5 December, 2013
*IN THE HIGH COURT OF DELHI AT NEW DELHI
% Date of decision:5th December, 2013
+ RFA 54/2004
TEEN MURTI CONSTRUCTION (P) LTD. ..... Appellant
Through: Dr. Sarbjit Sharma & Ms. Arpita
Bhalla, Advs.
Versus
M/S NIRMAL TEXTILES (P) LTD. ..... Respondent
Through: Mr. S.S. Saluja, Adv.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
RAJIV SAHAI ENDLAW, J
1. The appeal impugns the judgment and decree dated 26.08.2003 of the
Court of Additional District Judge (ADJ), Delhi in Suit No.530/2002 filed
by the appellant / plaintiff and in counterclaim (which appears not to have
been numbered) filed by the respondent / defendant and whereby, while the
suit of the appellant / plaintiff was dismissed, the counterclaim of the
respondent / defendant for recovery of Rs.5,96,840/- with interest was
decreed against the appellant / plaintiff.
2. Notice of the appeal was issued and subject to deposit of decretal
amount in this Court, execution was stayed. A sum of Rs.7,25,160/- is
reported to have been deposited by the appellant / plaintiff in response
thereto. The appeal was on 18.08.2004 admitted for hearing and the amount
so deposited by the appellant / plaintiff permitted to be withdrawn by the
respondent / defendant subject to furnishing security. The amount so
deposited is reported to have been released to the respondent / defendant
against security bond and by restraining the respondent / defendant from
selling, alienating or parting with possession of the property mentioned
therein. The appeal was on 30.01.2013 dismissed in default of appearance
of the parties and the security bond furnished by the respondent / defendant
was discharged. However, on application of the appellant / plaintiff, the
appeal was vide order dated 15.07.2013 restored to its original position
along with the security bond. The counsels for the parties have been heard.
Though the appeal was accompanied with an application for remand of the
case to the Trial Court and another application for production of additional
documents but the counsel for the appellant / plaintiff while addressing
arguments did not refer to the said applications, inspite of it being so pointed
out by the counsel for the respondent / defendant. Accordingly, while
reserving the judgment, it was noted in the order that the said applications
are deemed to be not pressed.
3. The appellant / plaintiff instituted the suit from which this appeal
arises, for recovery of Rs.11,87,000/- with interest from the respondent /
defendant, pleading:
(i) that the appellant / plaintiff is engaged in the business of
construction:
(ii) that the respondent / defendant had in the year 1999 approached
the appellant / plaintiff for construction of their building at
Sector-14, Gurgaon;
(iii) that after settling the terms and conditions, the appellant /
plaintiff started the work of construction of the factory building
i.e. Rolex and Nirmal and in the course of construction raised
running bills which were duly paid by the respondent /
defendant; and,
(iv) that the appellant / plaintiff submitted the 8th running bill in the
sum of Rs.11,87,118/- as per the work done upto 31.03.2000
and though the respondent / defendant assured and promised
payment thereof but did not pay, also inspite of legal notice.
4. The respondent / defendant filed a written statement-cum-
counterclaim pleading:
(A) that the plaint was vague, no details of measurement of
construction work with its costs or of the earlier seven running
bills had been furnished; though the respondent / defendant had
filed an application under Order VII Rule 14 of the CPC but in
compliance therewith also all the documents were not sent and
the alleged five running bills and the statement of account were
missing;
(B) that the appellant / plaintiff amended the rate of construction to
Rs.235/- per sq.ft. vide letter dated 16.04.1999 and final bill
dated 18.03.2000 for Rs.25,98,160/- in respect of total area of
construction of 11056 sq. ft. was submitted by the appellant /
plaintiff;
(C) that the respondent / defendant had paid a sum of
Rs.30,00,000/- on account from 20.04.1999 till 29.01.2000 to
the appellant / plaintiff and the appellant / plaintiff had thus
been over paid and the respondent / defendant was entitled to
recover back Rs.4,01,840/- from the appellant / plaintiff;
(D) denying that any running bills were submitted by the appellant /
plaintiff or that the bill of Rs.11,87,118/- was submitted and
denying that any such amount was due from the respondent /
defendant to the appellant / plaintiff; and,
(E) besides the counterclaim of the principal amount claimed to be
due of Rs.4,01,840/-, interest thereon at 18% was also claimed
and thus a counterclaim for Rs.5,96,840/- made.
5. The appellant / plaintiff filed replication to the written statement-cum-
counterclaim pleading:
(I) that the letter dated 18.03.2000 was given in good faith to the
respondent / defendant for the purpose of closing his books of
accounts; otherwise also the said letter had no relevancy since
the letter dated 16.04.1999 makes a mention that all the terms
of the offer dated 11.04.1999 remained unchanged;
(II) that work over a covered area of 14,181.14 sq.ft. had been
carried out;
(III) that the respondent / defendant had paid a total sum of
Rs.47,43,300/- against cheques as on 03.03.2000 and the
statement of accounts furnished by the respondent / defendant
pertained only to Nirmal and not to Rolex which project also
was undertaken by the appellant / plaintiff;
(IV) the respondent / defendant had paid an amount of
Rs.30,00,000/- as on 31.01.2000 towards Nirmal and an amount
of Rs.17,61,300/- as on 31.01.2000 towards Rolex; and,
(V) that the appellant / plaintiff from the first running bill had been
making a mention of Nirmal and Rolex in its running bills; that
after receipt of the payments, amount of Rs.20,48,577/- was due
towards Rolex and a further sum of Rs.45,08,542/- towards
Nirmal i.e. total amounting to Rs.65,57,119/- out of which the
respondent / defendant had paid an amount of Rs.49,50,000/-
by means of cheques and a sum of Rs.4,20,000/- in cash leaving
behind a balance of Rs.11,87,119/- to be paid to the appellant /
plaintiff.
6. The respondent / defendant filed a replication to the written statement
to the counterclaim:
(a) denying that the letter dated 18.03.2000 was given by the
appellant / plaintiff for the purpose of closing the books of
accounts;
(b) that the work done by the appellant / plaintiff regarding chhajja,
mumty and water tank was completely unsatisfactory and sub-
standard and had to be re-build;
(c) that the water tank was leaking and the appellant / plaintiff
neglected and failed to make the water tank workable;
(d) water proofing was also done by the respondent / defendant at
its own costs; and,
(e) denying that Rs.45,08,542/- was due to the appellant / plaintiff
from the respondent / defendant.
7. On the aforesaid pleadings of the parties, the following issues were
framed in the suit on 02.04.2003:
"1. Whether the suit has been signed, verified and instituted by a duly authorized person? OPP
2. Whether there is no cause of action in favour of the plaintiff as alleged in the written statement? OPD
3. Whether the plaintiff is entitled to suit amount?
4. Whether the plaintiff is entitled to interest, if so at what rate and for what period?
5. Whether the defendant is entitled to the counter-
claim as well as interest on the amount of counter- claim if so, at what rate and for what period? OPD
6. Relief.
8. The appellant / plaintiff examined its Director Mr. Ashok Aggarwal in
support of its case and the respondent / defendant examined its General
Manager and Power of Attorney holder and two other witnesses in support
of its defence / counterclaim.
9. The learned ADJ, in the impugned judgment and decree, has found /
observed / held:-
(i) that the suit had been filed and plaint signed and verified by the
duly authorized person on behalf of the appellant / plaintiff;
(ii) that the appellant / plaintiff had not placed on record the
agreement / contract entered into between the parties to prove
who were the parties to agreement and what were the terms and
conditions agreed between the parties:
(iii) that the onus was on the appellant / plaintiff;
(iv) that the Director of the appellant / plaintiff in cross-examination
had admitted that M/s Nirmal Textiles (P) Ltd. i.e. the
respondent / defendant and M/s Rolex Hosiery Pvt. Ltd. were
private and independent companies and had issued separate
TDS certificates in favour of the appellant / plaintiff;
(v) that the said to companies were separate and distinct legal
entities;
(vi) that M/s Rolex Hosiery Pvt. Ltd. was not a party to the suit;
(vii) that the appellant /plaintiff had raised the running bills
Ex.PW1/2 to Ex.PW1/9 in the joint names of the respondent /
defendant and M/s Rolex Hosiery Pvt. Ltd.;
(viii) that the statement of accounts proved by the appellant / plaintiff
was of joint account maintained by the appellant / plaintiff in
the name of the respondent / defendant and M/s Rolex Hosiery
Pvt. Ltd.;
(ix) there was nothing to show that the respondent / defendant had
entered into the agreement for and on behalf of Rolex Hosiery
Pvt. Ltd. for construction of their factory known as Rolex;
(x) that the appellant / plaintiff had withheld the agreement /
contract which was the best piece of evidence and an adverse
inference had to be drawn against the appellant / plaintiff;
(xi) that had the contract been proved, it would have been proved
that the respondent / defendant had entered into the agreement
with the appellant / plaintiff for its building known as Nirmal
only and not for construction of the building known as Rolex
for and on behalf of M/s Rolex Hosiery Pvt. Ltd.;
(xii) it could not be said that the respondent / defendant owed any
liability to the appellant / plaintiff for the dues if any
outstanding from M/s Rolex Hosiery Pvt. Ltd.;
(xiii) that though the statement of account proved by the appellant /
plaintiff being not primary evidence was not to be looked into
but was in the joint name of respondent / defendant and M/s
Rolex Hosiery Pvt. Ltd. and did not show that which particular
payment was made by the respondent / defendant and which
particular payment was made by M/s Rolex Hosiery Pvt. Ltd.; it
also did not spell out that the entire payment of Rs.47,43,300/-
was by the respondent / defendant;
(xiv) on the contrary, the respondent / defendant had duly proved its
statement of account as well as original books of accounts and
no cross examination with respect thereto was done by the
appellant / plaintiff; the same have thus to be admitted;
(xv) that as per the said statement of account of the respondent /
defendant, the respondent / defendant had made a total payment
of Rs.30,00,000/- to the appellant / plaintiff from 01.04.1999 to
31.03.2000;
(xvi) the very fact that the appellant / plaintiff had itself filed the
TDS certificates issued in favour of the appellant / plaintiff by
M/s Rolex Hosiery Pvt. Ltd. showed a total payment of
Rs.17,61,300/- by the said M/s Rolex Hosiery Pvt. Ltd. to the
appellant / plaintiff;
(xvii) the same also showed that the respondent / defendant was not
making and was not required to make payment on behalf of M/s
Rolex Hosiery Pvt. Ltd.;
(xviii) that the respondent / defendant had denied that any running
bills were being raised and it was its case that ad-hoc payments
were being made from time to time;
(xix) the appellant / plaintiff had failed to prove that eight running
bills were delivered to the respondent / defendant;
(xx) had the appellant / plaintiff been raising running bills on the
respondent / defendants, the payments by the respondent /
defendant to the appellant / plaintiff would have been of the
exact amounts of the said bills but it was not so and which
falsified the claim of the appellant / plaintiff of raising running
bills on the respondent / defendant;
(xxi) that the Director of the appellant / plaintiff had admitted having
submitted a final bill in the sum of Rs.25,98,160/- to the
respondent / defendant;
(xxii) that the appellant / plaintiff had failed to prove having done
work for the respondent / defendant for any more amount;
(xxiii) that the appellant / plaintiff had also failed to prove that the said
final bill for Rs.25,98,160/- was only for the purpose of closing
the accounts;
(xxiv) that the final bill on the face of it, was not subject to any
running bill;
(xxv) accordingly, Issues No.2&3 were decided against the appellant /
plaintiff and in favour of the respondent / defendant; and,
(xxvi) since as per the document of the appellant / plaintiff itself, the
appellant / plaintiff had done work for the value of
Rs.25,98,160/- for the respondent / defendant as against the
payment admittedly received of Rs.30,00,000/- vide letter dated
11.04.1999, the appellant /plaintiff was liable to refund the
excess payment received of Rs.4,01,840/- with interest.
10. The appellant / plaintiff, in the memorandum of appeal, has inter alia
stated:
(I) that the appellant / plaintiff in April, 1999, after settling terms,
commenced the work at the construction site of the respondent /
defendant;
(II) after few days, the Director of the respondent / defendant again
approached the appellant / plaintiff and requested it to take over
the completion and finishing of the existing structure of the
factory premises owned by the sister concern of the respondent
/ defendant viz. M/s Rolex situated on the adjacent plot,
construction site of the respondent / defendant; accordingly, on
24.04.1999, the appellant / plaintiff started work of the said
sister concern of the respondent / defendant also on the same
rates as being charged to the respondent / defendant;
(III) that the Director of the appellant /plaintiff had handed over
copy of the aforesaid letter dated 11.04.1999 to his Advocate so
that the same could be placed on record but the said lawyer of
the appellant / plaintiff appeared to have been won over by the
respondent / defendant and did not place the said letter on
record;
(IV) even at the time of cross-examination of the Director of the
appellant / plaintiff, his advocate satisfied him by saying that he
would place the same on record at the time of final arguments;
(V) that the said letter dated 11.04.1999 would show that the parties
had agreed to a figure of Rs.285/- per sq. ft. as the rate of
construction;
(VI) that from time to time the appellant / plaintiff issued eight
running bills to the respondent / defendant and separate bills to
its sister concern but maintained a consolidated memorandum
of payment because the payment of the appellant / plaintiff was
sometimes from the accounts of respondent / defendant and
sometime from the account of its sister concern M/s Rolex;
(VII) that the details of the various running bills are given in the
memorandum of appeal;
(VIII) that the Director of the respondent / defendant had on
18.03.2000 approached the Director of the appellant / plaintiff
for issuance of a back dated quotation along with a final bill for
its tax purpose at the rate of construction of Rs.235/- per sq. ft.
and since the respondent / defendant was a potential customer,
the appellant / plaintiff agreed to oblige;
(IX) however, the said quotation letter dated 16.04.1999 referred to
the earlier offer letter dated 11.04.1999;
(X) that similarly the final bill dated 18.03.2000 was issued in good
faith for the convenience of the respondent / defendant; and,
(XI) that the respondent / defendant however committed breach of
trust and misused the back dated quotation letter dated
16.04.1999 and bill dated 18.03.2000.
11. Though the counsel for the appellant / plaintiff, as aforesaid, has not
pressed the applications filed along with the appeal for remand of the case
and for filing documents but a perusal thereof shows that the appellant /
plaintiff therein also is wanting to place on record the letter dated
11.04.1999 and an opportunity to lead additional evidence with respect
thereto.
12. The counsel for the appellant / plaintiff besides drawing attention to
the pleadings, evidence and the judgment has also informed that the
appellant / plaintiff had after the impugned judgment lodged a complaint
with the Bar Council of Delhi against the Advocate engaged by it in the suit.
However, on enquiry as to the fate of the said complaint, the counsel fairly
admits that the appellant / plaintiff has not followed up the same. The
counsel for the appellant / plaintiff has further contended that the bone of
contention between the parties is whether the appellant / plaintiff after
having quoted the rate of construction of Rs.285/- per sq.ft. in its quotation
dated 11.04.1999 could have after five days, in the quotation dated
16.04.1999, reduced the same to Rs.235/- per sq. ft., when the work of
construction had not even commence till then. He has further argued that no
such plea was taken by the respondent / defendant in the reply to the legal
notice preceding the suit. He has yet further contended that the lawyer
engaged by the appellant / plaintiff before the Trial Court is to be blamed.
13. The counsel for the respondent / defendant per contra has merely
supported the impugned judgment.
14. As would be obvious from the aforesaid, the case set up in the
memorandum of appeal is entirely different from the case set up in the suit,
without even filing any application for amendment. Needless to state that
the new case so set up in the memorandum of appeal, which though is
cogent and plausible, cannot be looked at.
15. I have yet further enquired from the counsel for the appellant /
plaintiff as to what could be the purpose or even taxation purpose for which
the respondent / defendant may have required a back dated quotation, as the
quotation dated 16.04.1999 is stated to be or a final bill and both of which
according to the appellant / plaintiff now, did not reflect the true contractual
position agreed between the parties. I have further enquired as to what could
be the reason for the appellant / plaintiff to so oblige the respondent /
defendant. It is not the case of the appellant / plaintiff that the Directors /
officers of the appellant / plaintiff had prior or friendly relationship with the
Directors / officers of the respondent / defendant. It belies logic as to why
such documents, which did not represent the true contract between the
parties, were prepared and as to why the appellant / plaintiff obliged the
respondent / defendant especially when no reason even of the need of the
respondent / defendant therefor is forthcoming.
16. No answer is still forthcoming from the appellant / plaintiff.
17. Once the appellant / plaintiff in the appeal has sought to justify its
claim on facts different from those set up in the suit and has abandoned the
case set up in the suit, there is no need for this Court to discuss in detail the
evidence in the suit. Suffice it is to state that I have perused the evidence
recorded and find the learned ADJ to have, on a correct appreciation of the
same, rightly held that the appellant / plaintiff had failed to prove its case
and the respondent / defendant had proved its counterclaim.
18. Once the appellant / plaintiff fails in its suit claim, no error can be
found in the judgment decreeing the counterclaim of the respondent /
defendant.
19. Resultantly, the appeal is dismissed. However, since the possibility of
the appellant / plaintiff having suffered at the hands of its Advocate cannot
be ruled out, though the appellant / plaintiff is itself to be blamed equally for
having, inspite of the written statement the counterclaim of the respondent /
defendant having not corrected position in the replication and or in the
written statement to the counterclaim, I refrain from imposing any costs.
20. The security bond furnished by the respondent / defendant for
restitution of the monies which it was permitted to withdraw, is discharged.
Decree sheet be prepared.
RAJIV SAHAI ENDLAW, J
DECEMBER 05, 2013 'gsr'..
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!