Citation : 2012 Latest Caselaw 3651 Del
Judgement Date : 31 May, 2012
IN THE HIGH COURT OF DELHI AT NEW DELHI
O.M.P. 480 of 2006
Reserved on : May 2, 2012
Decided on: May 31, 2012
INDIAN RAILWAY CONSTRUCTION
CO. (IRCON) ..... Petitioner
Through Mr. Chandan Kumar, Advocate.
Versus
ROYAL FORGINGS PVT. LTD. & ANR ..... Respondents
Through Ms. Anjani Aiyagari, Advocate.
CORAM: JUSTICE S. MURALIDHAR
JUDGMENT
31.05.2012
1. The challenge by the Petitioner Indian Railway Construction Company
('IRCON') in this petition under Section 34 of the Arbitration and
Conciliation Act, 1996 ('Act') is to an Award dated 30th June 2006 passed by
the learned sole Arbitrator in the dispute between IRCON and the
Respondent No.1 Royal Forgings Private Limited ('RFPL') arising out of the
contract for supply of Double Shank Elastic Spikes ('DSES') which a
fastener used for holding the railway track to wooden sleepers.
2. It is stated that in terms of Clause 15 of the Special Conditions of Contract
('SCC'), time was the essence of the contract. In Clause B 6.3.8, Technical
Specifications ('TS') as set out in Annexure-III of Purchase Order ('PO')
dated 24th July 2001, it was provided that the finished product should have
specific marking. It was provided that each component of the fastener shall
"in addition to manufacturer's name, also carry the initials 'BR' and the last
two digits of the year of manufacture. The delivery was to be made by the
Respondent No.1 herein at Ishurdi, Bangladesh by meeting the entire cost of
transportation, insurance and tax liabilities except custom duty. Clause 12 of
SCC made it clear that the supply of material and its delivery at Ishurdi,
Bangladesh was to be the supplier's responsibility and that IRCON would not
be able to extend any help except for the payment of custom duty in
Bangladesh. Clause 25.1 specified that the supplier was to communicate the
relevant dispatch particulars immediately after the despatch to the consignee.
Documents which were required to be sent as per the PO are as under:
"i. Commercial invoice ii. Packing list iii. Transport consignment note iv. Certificate of origin v. Full transit insurance cover vi. Test certificates."
3. Initially the PO dated 24th July 2001 was placed for supply of one lakh
pieces. After the successful completion of that supply, an additional order for
one lakh pieces was placed on 25th February 2003 which was also completed.
By its letter dated 6th May 2003 the Petitioner placed on the Respondent No.1
a further order for supply of 50,000 pieces of DSES which was to be made by
31st May 2003.
4. The case of IRCON is that despite agreeing to the above schedule,
Respondent No.1 did not supply the stipulated extra quantity within time.
The extension of time was granted up to 20th June 2003 and thereafter up to
5th July 2003. According to IRCON, due to non-supply of the additional
quantity it was constrained to procure and use concrete sleepers and incurred
an additional expenditure of Rs. 6,65,600 for completing the project.
5. The dispute that arose between the parties due to non-supply of 50,000
pieces was referred to the learned sole Arbitrator. There were 10 claims
raised by the Respondent No.1 towards various heads of which learned
Arbitrator rejected Claim No. 2 relating to reimbursement of excise duty,
Claim No. 5 in relation to loss of profit, Claim No. 7 towards loss of business
opportunity, Claim No. 9 as well as Claim No. 10 concerning the interest on
Claims 1 to 8. As regards Claim No. 6 it was agreed between the parties that
the second deposit and earnest money would be released to the Respondent
No.1. Against Claim No. 1 for undelivered consignment, the learned
Arbitrator awarded an amount of Rs. 33,58,361. Against Claim No. 3 which
was for reimbursement of cost of storage and transport, the learned Arbitrator
awarded an amount of Rs. 19,000. Against Claim No. 4 for loss of export
benefit, a sum of Rs. 3,39,590 was allowed and against Claim No. 8 towards
cost of litigation, an amount of Rs. 25,000 was awarded.
6. The counter claim of IRCON for a sum of Rs. 6,65,600 towards loss
incurred by it as a result of procuring the concrete sleepers instead of
wooden sleepers due to non-supply of 50,000 pieces of DSES by the
Respondent No.1 was rejected.
7. This Court has heard the submissions of Mr. Chandan Kumar, learned
counsel for IRCON and Ms. Anjani Aiyagari, learned counsel for the
Respondent No.1.
8. It is submitted that time was the essence of the contract and delivery of
50,000 pieces of DSES having not been made within the time, Respondent
No.1 was not entitled to any compensation. Further, Respondent No.1 had
not proved that 50,000 pieces had been manufactured by it. More importantly
it was not shown that pieces of DSES were manufactured after 6th May 2003.
It was also not shown that 50,000 pieces had marking of 'BR' as well as the
year of manufacture in two digits. It is submitted that the inspection
undertaken during the pendency of the arbitral proceedings showed that
pieces did not have marking 'BR'. This was erroneously rejected on the
reasoning that it was a minor lapse. On the other hand it is contended by the
Petitioner that the pieces found in the store of Respondent No.1 without the
initials 'BR' meant that they were not attributable to the contract or
manufactured for it.
9. It is stated by learned counsel for the Petitioner that in respect of 25,000
pieces alleged to have been dispatched on 23rd June 2006, no transporter's
consignment note, transit cover insurance, test certificates were provided.
Consequently, the manufacture date and date of despatch were not genuine.
No certificate of insurance of the said quantity had been proved. No test
report was sent in relation to the despatch of the goods on 23rd June 2003.
Consequently, there was no compliance of the requirement of Clause 17 of
the SCC.
10. The learned Arbitrator in the impugned Award noted in paras 6.4.1 and
6.4.4 as under:
"6.4.1 ...... I agree with the Respondent that it is not complete waiver of inspection, but makes the Claimants responsible for testing the samples as per schedule in order to ensure that the
material conforms to the specifications."
6.4.4 ..... I have already agreed with the Respondents that Claimants failed in not sending Test Certificates, Insurance Certificate, Transporter's consignment note and timely intimation regarding dispatch of 25000 nos. of DSES"
11. On the other hand it is pointed out by learned counsel for the Respondent
No.1 that the Petitioner had never insisted the Respondent No.1 to send the
test certificate and there has been complete waiver of the requirement of test
as the Petitioner declined to depute Engineer for the same and instead
directed the Respondent No.1 to dispatch the same. Respondent No.1 was not
under any obligation to forward the test certificate to the Petitioner when the
Petitioner had not even asked for the same or mentioned the same in any of
its communications.
12. Accordingly it is submitted that the finding of the learned Arbitration is
that there was not even a whisper from the Petitioner regarding lack of
documents for import permit or any failure of Respondent No.1 was correct.
In fact the Petitioner had requested Respondent No.1 by its letter dated 1st
August 2003 to hold the consignment as it was facing problem regarding
import permit. It was further submitted that none of the specific grounds set
out in Section 34 (2) (a) (i) to (v) or Section 34 (2) (b) (i) & (ii) were
attracted to the present case.
13. It must be noticed that since doubts were being raised regarding the
manufacture and existence of 50,000 pieces of DSES, the learned Arbitrator
directed the Petitioner to depute a representative to visit the workshop of
Respondent No.1 at Raipur to physically check the stock jointly and submit
the report. The report submitted by the Petitioner's representative was to the
following effect:
"(i) The quantity of 50,575 was found as against 50,200 shown in stock register.
(ii) Test inspection reports of raw material production tests or sample tests were not available.
(iii) The DSES did not bear marking of BR (B' desk Rly) as required under the P.O. Technical Specification."
14. The learned Arbitrator noted the acceptance by the Respondent No.1 that
DSES were not marked 'BR'. This was however sought to be explained by
pointing out that even earlier, two lakhs numbers of DSES supplied were also
not marked 'BR'. In the circumstances, the learned Arbitrator treated this as
'a minor lapse' for which a token penalty of a maximum 1% could be
imposed.
15. This Court is unable to appreciate the above finding of the learned
Arbitrator which appears to be in the teeth of the facts brought on record and
accepted by the Respondent No.1 itself. Once it was clear that date-wise
manufacture of 50,000 pieces of DSES had not been furnished, and the
marking of BR had not been done and further that Respondent No.1 did not
sign the full documents required for the export formalities including
inspection/test certificates/insurance certificate and transporter's consignment
note, there was no question of awarding any compensation under Claim No.
1. Merely because in the letter dated 1st August 2003 the Petitioner did not
mention about the lack of documents in obtaining import permit and it was
silent up to 20th February 2004 could not lead to an inference that the
Petitioner was perhaps feeling guilty in not taking or pursuing the supply
from the Respondent No.1.
16. This Court, therefore, concludes that the Award in respect of Claim No. 1
is without any evidence and contrary to the express terms of the contract and
also the joint inspection report. The Award in respect of Claim No. 1 for
undelivered consignment cannot be sustained in law and is hereby set aside.
17. As regards Claim No. 3 for reimbursement of cost of storage and
transport, again no document was furnished to the Petitioner about
transportation and warehousing charges. The learned Arbitrator appears to
have merely gone by surmises and conjectures in awarding Rs. 19,000 for
cost of transportation of 25,000 pieces from Kolkata to Raipur. The Award
in respect of Claim No. 3 is therefore, set aside.
18. Claim No. 4 was for US $ 14500 for loss of export benefit to the extent of
20% of cost of supply order. This again was linked with Claim No. 1 which
was for cost of the undelivered consignment, the award in respect of which
has been set aside by this Court. The Award of Rs. 25,000 towards cost of
litigation is also not justified.
19. For all the aforementioned reasons the impugned Award cannot be
sustained in law and is hereby set aside. Accordingly, the petition is allowed
with no order as to costs.
S. MURALIDHAR, J.
MAY 31, 2012 rk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!