Citation : 2012 Latest Caselaw 2044 Del
Judgement Date : 26 March, 2012
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ W.P.(C) 12201/2009 & C.M.No.12423/2009(stay)
Date of Decision: 26th March, 2012.
IN THE MATTER OF:
NORTH DELHI POWER LTD ..... Petitioner
Through: Mr. K. Datta, Adv. for Mr.Manish
Srivastava, Adv.
versus
INDIAN HYDRAULIC INDUSTRIES (P) LTD AND ANR ..... Respondents
Through: Mr. P.K. Malik, Adv. for R-1.
Mr. S.C. Gupta, Adv. for R-2.
CORAM:
HON'BLE MS. JUSTICE HIMA KOHLI
HIMA KOHLI, J (Oral)
1. The petitioner/NDPL is aggrieved by the order dated 31.08.2009
passed by the Consumer Grievance Redressal Forum (CGRF) for NDPL
on a complaint filed by the respondent No.1/Consumer for refund of
the excess amount stated to have been recovered from it by the
predecessor-in-interest of the petitioner on account of the delay in
reduction of load from LIP to SIP category.
2. By the impugned order dated 31.08.2009, two preliminary
objections raised by the petitioner as to the maintainability of the
complaint filed by respondent No.1, firstly that the matter was liable
to be referred to arbitration in accordance with the terms and
conditions of the agreement governing the parties and secondly, that
the complaint was barred by limitation, were turned down.
3. Briefly stated, the facts of the case are that on 15.02.1980
respondent No.1/Consumer had entered into an agreement with the
predecessor-in-interest of the petitioner, namely, Delhi Electricity
Supply Undertaking (DESU) for the supply of bulk energy. The said
agreement contained an arbitration clause. On 27.07.1992,
respondent No.1/Consumer had approached DESU for reduction of
load. Correspondence was exchanged between the respondent No.1/
Consumer and DESU from the year 1992 to 1999 for completion of the
commercial formalities for reduction of load. As per the respondent
No.1/Consumer, in the year 1999, it had completed all the requisite
commercial formalities and its load was reduced accordingly. It is the
case of respondent No.1 that thereafter, it exchanged voluminous
correspondence with the petitioner/NDPL till May, 2005 seeking refund
of the purported excess charges recovered from it by the predecessor-
in-interest of the petitioner.
4. The stand of the respondent No.1/Consumer is that vide letter
dated 21.07.2005, the petitioner had informed it that as per the
records, the load had not been converted from LIP to SIP due to non-
completion of some commercial formalities. Respondent No.1/
Consumer was, therefore, directed to contact the office of the
petitioner for resolving the said issue. Respondent No.1/Consumer
claims that meetings took place between its officers and the petitioner
and finally in the year 2008, it approached the Monopolies and
Restrictive Trace Practices (MRTP) Commission claiming a refund of
the excess amount of `23,90,162.51 with interest from the petitioner.
5. As per the records, the aforesaid complaint filed by respondent
No.1/Consumer before the MRTP Commission was disposed of vide
order dated 02.09.2008 observing inter alia that there was an
Authority appointed under the Electricity Act, 2003 to deal with such
matters. As a result, the respondent No.1/Consumer was granted
liberty to approach the said Authority. Thereafter, respondent No.1/
Consumer filed a complaint case before the Consumer Grievance
Redressal Forum (CGRF) praying inter alia for refund of the excess
amount of `23,90,162.51 with interest @ 18% payable from December,
1997 and a further amount of `70,821/- with interest @18% payable
from September, 1996 and a sum of `10,00,000/- as compensation.
6. Upon notice being issued to the petitioner/NDPL in the aforesaid
complaint case, preliminary objections were raised by the
petitioner/NDPL as regards the maintainability of the said petition.
One of the objections raised was that the dispute related to the year
1993 and, therefore, the case was hopelessly barred by limitation.
7. The preliminary objections raised by the petitioner/NDPL were
considered and overruled by the CGRF in the impugned order dated
31.08.2009. Aggrieved by the aforesaid order, the petitioner/NDPL
has approached this Court in this petition.
8. Counsel for the petitioner/NDPL submits that the impugned order
is erroneous and liable to be set aside for the reasons that the CGRF
failed to appreciate the fact that the limitation for taking any action
against the petitioner for refund of the alleged excess amount paid by
respondent No.1/Consumer had expired in the year 1995 itself for the
reason that the limitation prescribed for taking such an action for
recovery of money is three years and the cause of action in the
present case had accrued in favour of respondent No.1/Consumer in
the year 1992-93. He further urged that reliance placed by respondent
No.1/Consumer on the letter dated 21.07.2005 issued by the
petitioner to it to come for a meeting for settlement of the grievance,
cannot be treated as an acknowledgement of dues within the meaning
of the Limitation Act and in any case, the said letter only referred to
the non-completion of some commercial formalities on the part of
respondent No.1/Consumer for converting the connection from LIP to
SIP. Further, it is submitted that it is not the case of respondent
No.1/Consumer that the conversion of the load had taken place in the
year 2005 rather, it is the stand of respondent No.1 in its complaint
that the petitioner had converted the load from LIP to SIP in the year
1999.
9. This court has heard the counsels for the parties and perused the
impugned order. The facts of the case as narrated above are
undisputed and, therefore, need not detain the Court. The only issue
that has been argued on behalf of the petitioner is that while
dismissing the objections raised by the petitioner/NDPL with regard to
limitation, no reasons whatsoever have been assigned for the same by
the CGRF.
10. A perusal of the impugned order reveals that after taking note of
the stand of both the sides as also the decisions relied upon by the
counsels for the parties, the CGRF had observed that prima facie the
case indicated that the request for reduction of load had been initially
made by the complainant in July, 1992 and the tariff had been
changed from LIP to SIP in the month of March, 1999. It was further
observed that the complainant (respondent No.1 herein) had sought
relief to the extent of `80 lacs approximately in the case.
Immediately thereafter, comes the operative para of the impugned
order wherein the CGRF has overruled the preliminary objections
raised by the petitioner/NDPL with regard to the arbitration clause
governing the parties and the limitation aspect and then proceeded to
adjourn the case for hearing arguments on merits.
11. There is no discussion, much less any reasoning reflected in the
impugned order for arriving at the aforesaid conclusion. The stand
taken by the petitioner/NDPL that the complaint filed by respondent
No.1/Consumer was barred by limitation as the cause of action had
arisen in the year 1993 whereas, it had not filed any claim before any
judicial forum till as late as the year 2008 when it approached the
MRTP Commission for the first time, is borne out from the records and
the same has not even been disputed by the respondent
No.1/Consumer.
12. The submission of the counsel for respondent No.1/Consumer
that the letter dated 21.07.2005 issued by the petitioner/NDPL gives a
fresh cause of action to the respondent No.1/Consumer is untenable
for the reason that a perusal of the aforesaid letter reveals that the
petitioner had only replied to the request made by the respondent
No.1 for refund of the security and the purported excess charges
deposited by it, in the light of the completion of the commercial
formalities and it was not as if the petitioner/NDPL had acknowledged
that any outstanding dues were to be refunded by it to the respondent
No.1/Consumer.
13. It is also relevant to note that the cause of action for filing a
claim of recovery against the petitioner/NDPL had accrued in favour of
respondent No.1/Consumer way back in the year 1993. Even if, the
period of three years is reckoned from the year 1999, i.e., the year
when the connection was apparently converted from LIP to SIP, it
would have taken the respondent No.1/Consumer upto the year 2002
and not beyond that. Respondent No.1, however, approached the
MRTP Commission after a period of six years therefrom, i.e., in the
year 2008 and it approached the CGRF after a period of seven years
therefrom, i.e., in the year 2009. While the complaint of the
respondent No.1/Consumer filed before the MRTP Commission was
rejected with liberty granted to it to approach the appropriate forum
under the Electricity Act, it is a matter of record that respondent No.1
approached the CGRF only in the year 2009, after about six months
after the order of the MRTP Commission was passed. Even in the
complaint filed before the CGRF, respondent No.1 had again claimed
that the period of limitation stood extended in its favour by predicating
its case on the letter dated 21.07.2005 addressed by the petitioner to
it.
14. The fact remains that for the purpose of calculating limitation,
only the complaint filed by the respondent No.1/Consumer is required
to be examined and a perusal of the application filed by it before the
CGRF reveals that the respondent No.1 had itself acknowledged in
paras 27 and 30 thereof that the petitioner/NDPL had converted the
connection from LIP to SIP in March, 1999 and it had installed a new
meter on the basis of completion of commercial formalities, that had
taken place long ago. In such circumstances, the complaint of
respondent No.1/Consumer was not maintainable before the CGRF, the
same being hopelessly barred by limitation.
15. At this stage, counsel for respondent No.1/Consumer states that
if the petitioner/NDPL had a grievance against the order of the CGRF,
it was for it to have approached the Ombudsman by preferring an
appeal instead of filing the present petition. The aforesaid submission
is, however, devoid of merits for the reason that sub-section 6 of
Section 42 of the Electricity Act, 2003 prescribes that a consumer, who
is aggrieved by non-redressal of grievance before the CGRF can
approach the Ombudsman in appeal but the said provision does not
give any such option to the Discom like the petitioner herein. In such
circumstances, reliance placed by learned counsel for respondent
No.1/Consumer on the Delhi Electricity Regulatory Commission
(Guidelines for establishment of Forum for Redressal of Grievances of
the Consumers and Ombudsman) Regulations, 2003 cannot be of any
assistance as the Regulations have been framed under the Act. In any
case, even Regulation 19, referred to by the counsel for the
respondent No.1/Consumer, does not empower the Ombudsman to
entertain an appeal filed by a Discom as the said forum is empowered
to receive representations only from the complainants aggrieved by an
order of the Forum.
16. In view of the aforesaid facts and circumstances, the present
petition succeeds and the same is allowed. The impugned order dated
31.08.2009 passed by the CGRF is quashed and set aside and it is held
that the complaint filed by the respondent No.1/Consumer is
hopelessly barred by limitation and, therefore, rejected.
17. Parties are left to bear their own costs.
(HIMA KOHLI) Judge MARCH 26, 2012 'anb'/sk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!