Citation : 2012 Latest Caselaw 5068 Del
Judgement Date : 28 August, 2012
13.
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 28.08.2012
% FAO (OS) No.413 /2012
DAVENDER KUMAR SHARMA ..... Appellant
Through: Mr. H.C. Mittal, Advocate.
versus
MOHINDER SINGH & ORS. ..... Respondents
Through:
CORAM:
HON'BLE MR. JUSTICE SANJAY KISHAN KAUL
HON'BLE MR. JUSTICE VIPIN SANGHI
VIPIN SANGHI, J. (Oral)
C.M. No. 14864/2012 (for exemption)
Exemption allowed, subject to all just exceptions.
FAO (OS) No.413/2012
1. The appellant assails the order dated 16.07.2012 passed by
the learned Single Judge in I.A. No.404/2012 (under Order 39 Rule 1
and 2 CPC) preferred by the plaintiff, and I.A. No.8907/2012 (under
Order 39 Rule 3 and 4 CPC) preferred by defendant nos.1 to 10. The
learned Single Judge has dismissed the plaintiffs/appellants
application to seek interim injunction under Order 39 Rule 1 and 2
CPC by the impugned order and, consequently, the other interim
application stands allowed.
2. The appellant has filed the aforesaid suit to seek specific
performance of the agreement to sell executed between the parties.
The case of the appellant is that vide agreement to sell dated
14.03.2011, and memorandum of understanding (MOU) of the same
date, defendant nos.1 to 10, who are jointly the owners of property
No.MPL No.WZ-14-C, built on Ahata No.40 admeasuring 200 sq. yds.
out of khasra nos.217, 218, 219 and 220, Manohar Park, Delhi had
agreed to sell to the plaintiff rights in the said immovable property
for a total consideration of Rs.95 lacs.
3. The appellant states that the said respondents had agreed to
sell the ground floor of the property. It was further agreed that on
receiving possession of the ground floor of the property, the
appellant would demolish the same and construct a four storey
building on it. The ground and third floor of the building to be so
constructed, were to come to the share of the appellant, whereas
the first and second floors were to go to the share of respondent
nos.1 and 2. Respondent nos.3 to 10 were to get the amount of
Rs.95 lacs in lieu of their share in the property and, under the MOU,
it was provided that respondent nos.3 to 10 shall relinquish their
share and interest in the property in favour of respondent nos.1 and
2. The appellant admittedly paid an amount of Rs.66,16,666/- to
defendant nos.1 to 10.
4. The appellant preferred the aforesaid suit complaining of non
compliance of the said agreement and the MOU by the respondents.
It was alleged that the respondent nos.3 to 10 had not surrendered
their share in the property in favour of respondent nos.1 and 2, nor
the possession of the property had been delivered to the appellant.
5. The appellant preferred the aforesaid application under Order
39 Rule 1 and 2 CPC alongwith the suit to seek interim injunction
against the respondents to restrain them from dealing with the suit
property. The respondents also moved an application for vacation
of the ad-interim injunction, being I.A. No.8907/2012. Both these
applications were disposed of by the impugned order.
6. The learned Single Judge has dismissed the appellants
application for injunction pending the disposal of the suit by
accepting the respondents submission that the agreement to sell
and the MOU were incapable of being specifically enforced under
Section 14(1)(b) and (d) of the Specific Relief Act (the Act). The
learned Single Judge has drawn strength from the decision of the
Supreme Court in Vinod Seth v. Devinder Bajaj & Anr., (2010) 8
SCC 1. The learned Single Judge has held that since the
agreement/MOU could not be specifically enforced, no injunction
could be granted to prevent its breach in terms of Section 41(c) of
the Act.
7. The learned Single Judge examined the present case on the
parameters and considerations laid down by the Supreme Court in
the aforesaid case. It was observed that there was no agreement
between the parties as regards the specifications of the proposed
construction on the suit property; the agreement does not say as to
what would happen if the plan for construction of floors, agreed
between the parties, is not sanctioned by the MCD/DDA; the
agreement is silent as to what would happen if the parties do not
agree on the specifications of the proposed construction; the
agreement does not provide for any mechanism to carry out joint
supervision and quality control during construction; the agreement
does not say that the specifications of materials for construction
would be unilaterally decided by the appellant and/or the quality of
the construction will not be disputed by the respondents; there is no
provision in the agreement for the respondent to supervise the
construction; the agreement does not provide for the eventuality,
where the construction raised by the appellant is not found
acceptable by the respondents; the agreement does not prescribe
any time within which the proposed construction would be
completed; it does not provide as to what would happen if the
appellant does not complete the construction or does not even
commence it at all, after taking possession from the respondents.
8. In this background, the Court concluded that it is not possible
for the Court, or even the Court Commissioner, to supervise the
construction. Consequently, the learned Single Judge has concluded
that the agreement cannot be specifically enforced by virtue of
Section 14(1)(b) and (d) of the Act.
9. We find ourselves in agreement with the aforesaid reasoning
adopted by the learned Single Judge. We may also note that the
MOU is not an agreement which is enforceable, but only an
agreement to agree, whereunder respondent nos.3 to 10 had
agreed to, in future, agree to transfer their share in the property in
favour of respondent nos.1 and 2. An agreement to enter into an
agreement in future, cannot be enforced, much less specifically
enforced.
10. Learned counsel for the appellant argues that the
specifications could be as prescribed by the CPWD. That is not the
issue in hand. This submission itself demonstrates that the parties
had not agreed between themselves in respect of a very material
and pertinent aspect. In any event, it is not possible for the Court to
supervise, on a continuous basis, the construction on the property in
question, particularly when the specifications have not been clearly
set out. The Court cannot compel the respondent nos.3 to 10 to
transfer their share in the property in favour of respondent nos.1
and 2.
11. The next submission of learned counsel for the appellant is
that, atleast, the agreement in respect of the ground floor can be
enforced, and the respondents can be directed to transfer the
ground floor of the property to the appellant for a consideration of
Rs.95 lacs.
12. In our view, there is no merit in this submission either. The
agreement is not only in respect of the ground floor, but also in
respect of the other floors. Whereas the appellant was to get the
ground and third floor, respondent nos.1 and 2 were to get the first
and second floor, when constructed. The agreement and the MOU
form part of the same transaction. They cannot be bifurcated. It
cannot be stated that the third floor, which constitutes nearly half of
the property agreed to be acquired by the appellant, constitutes a
small fraction of the property. It cannot also be said that the
amount of Rs.95 lacs forms the only consideration for transfer of the
ground floor premises. The appellant also had the obligation to
construct the upper floors so that they would become available to
the respondents.
13. Consequently, the decision in Gurdial Kaur (D) by LRs v.
Piara Singh (D) by Lrs, AIR 2008 SC 2019 as relied upon by the
appellant, would have no application. Moreover, under the
transaction, the rights of the respondents inter se were also
required to be settled. The appellant cannot contend that only its
rights should be partially settled leaving the respondents,
particularly respondent nos.1 and 2 in the lurch.
14. For all the aforesaid reasons, we find no infirmity in the
impugned order and dismiss the present appeal.
15. We, however, make it clear that the observations made by us
shall not come in the way of the appellant/plaintiff in prosecuting
the suit, as the observations have been made only for the purpose
of dealing with the present appeal arising out of the impugned
order.
C.M. No. 14863/2012
In view of the aforesaid, no directions are called for in this
application. The same is accordingly disposed of.
VIPIN SANGHI, J
SANJAY KISHAN KAUL, J
AUGUST 28, 2012 sr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!