Citation : 2011 Latest Caselaw 5099 Del
Judgement Date : 17 October, 2011
* THE HIGH COURT OF DELHI AT NEW DELHI
Judgment reserved on: 23.09.2011
% Judgment delivered on: 17.10.2011
+ WP(C) 534/2011
RDS PROJECTS LTD. ...... PETITIONER
Vs
RATANGIRI GAS AND POWER PVT. LTD. & ORS. ..... RESPONDENTS
Advocates who appeared in this case:
For the Petitioner: Mr Jagdeep Dhankar, Sr. Advocate with Ms Asha Jain Madan & Mr
Mukesh Jain, Advocates.
For the Respondents: Mr A.S. Chandhiok, ASG with Mr S.K. Taneja, Sr. Advocate with Mr
Puneet Taneja & Mr Anant Kumar Sinha, Advocates for Respondent No.
1/RGPPL.
Mr Gourab Banerji, ASG with Mr Ajit Pudussery and Mr Dinesh
Khurana, Advocates for Respondent No. 2/GAIL.
Ms Indira Jai Singh, ASG with Mr Ashok Mathur & Ms Sonam Anand,
Advocates for Respondent No. 3/EIL.
Mr Neeraj Chaudhari, CGSC with Mr Mohit Auluck and Mr Khalid
Arshad, Advocates for Respondent No. 4/UOI.
CORAM :-
HON'BLE MR JUSTICE SANJAY KISHAN KAUL
HON'BLE MR JUSTICE RAJIV SHAKDHER
1. Whether the Reporters of local papers may
be allowed to see the judgment ? Yes
2. To be referred to Reporters or not ? Yes
3. Whether the judgment should be reported Yes
in the Digest ?
RAJIV SHAKDHER, J
1. This writ petition would bear testimony to the adage that truth is a
conundrum wrapped in mystery surrounded by a multitude of lies. The petitioner
is in court, the second time round, much harried and exasperated. In the first
round the petitioner, i.e., RDS Projects Ltd. (hereinafter referred to as „RDS‟) by
WP(C) 534-2011 Page 1 of 50
way of a writ petition bearing no. 8252/2010, sought to challenge the decision of
respondent no. 1, i.e., Ratnagiri Gas & Power Pvt. Ltd. (hereinafter referred to as
„RGPPL‟) dated 04.10.2010, conveyed to it on 06.10.2010, seeking to scrap/
cancel the tender bearing no. 6724/T-138/08-09/SPL/24 (hereinafter referred to as
the "1st Tender") after it had been declared the lowest tenderer, i.e., L-1. RDS
withdrew the said writ petition alongwith an application for grant of interim relief
in view of the stand of RGPPL that it had exercised its rights as an owner under
Article 28.1 of the 1st tender. Since the petitioner apprehended his exclusion by
the respondents in the subsequent round, it sought leave and liberty of this court to
take recourse to a legal remedy in accordance with the law. A Division Bench of
this court of which one of us (i.e., Sanjay Kishan Kaul, J) was a party, granted
such liberty to the petitioner vide order dated 14.12.2010.
2. True to form, RGPPL through aegis of Respondent No. 2, i.e., Gas
Authority of India Ltd. (hereinafter referred to as „GAIL‟), and respondent no. 3,
i.e., Engineering India Ltd. (hereinafter referred to as „EIL‟), floated a fresh tender
bearing no. 6724/T-183/10-11/SKG/28 (hereinafter referred to as the „2nd
Tender‟); albeit with a change/amendment. The change/amendment with which
the petitioner is aggrieved pertains to clause 8.1.1.1. It is pertinent to mention here
that clause 8.1.1.1 deals with past experience of the bidder in executing a similar
work. We would be referring to the requisites set out in clause 8.1.1.1 with
respect to qualifying work, and as one goes along, the change in specifications
brought about by amendment made in clause 8.1.1.1 in the 2nd tender. We would
WP(C) 534-2011 Page 2 of 50
come back to the amendment in the said clause made in the 2nd tender, but before
that, why the change has taken place is pertinent, as the petitioner has pleaded
malice, apart from the usual grounds of arbitrariness and unreasonableness and the
lack of fairness on the part of the respondents in bringing about the said change.
We may note at the outset that the change is brought about in clause 8.1.1.1, which
found a mention in the 1st tender as compared to those which have been
incorporated in the very same clause, in the 2nd tender; even though subtle, are
significant from the point of view of the petitioner. Therefore, the reason for
narrating the background in which the respondents issued the 2nd tender.
BACKGROUND
3. The Maharashtra State Government, it appears, wanted to resuscitate the
Dabhol Power Project (in short „DPP‟) which had run into troubled waters; a story
which has been widely recorded. The job of resuscitation was entrusted to
National Thermal Power Corporation (in short „NTPC‟) and GAIL. The DPP,
inter alia, included a gas based component, that is, a cycle power project alongwith
an integrated LNG terminal with associated infrastructure facilities; situate in the
district of Ratnagiri, in the State of Maharashtra. Thus, insofar as DPP was
concerned, both components required revival. The first one being a power block
and the second being, the LNG block. In order to execute the task entrusted to
NTPC and GAIL, a joint venture company was incorporated which, resulted in the
birth of RGPPL. The co-owners of RGPPL were appointed as the owners‟
engineers to revive the power block as well as the LNG block. The LNG terminal
required protection and hence, what in technical terms is referred to as
„breakwater‟ had to be constructed in the sea on shores of which, evidently, the
LNG terminal block was situated. Since the job entailed specialized technical and
engineering experience, knowledge and skill accompanied with marine facilities as
its core competence, GAIL in turn engaged the services of EIL. The EIL was thus
appointed as the primary project management consultant. The EIL in turn sought
and obtained approval of GAIL to involve one U.K. based entity, namely, Scott
Wilson as their back-up consultant for marine works. RGPPL thus had the luxury
of having at its disposal not one, not two, but three experts.
4. The extent of the role played by the experts is demonstrable from the
averments made by RGPPL in its pleadings before us wherein it is averred and
therefore candidly admitted, that the board of directors in their deliberations held
on 04.10.2010 had come to a conclusion that in respect of aspects pertaining to:
revival/completion of the power blocks as well as LNG block which would pertain
to strategies for "packaging", "tendering mode", and "award recommendations"
including "price negotiations" wherever required; it would have to rely on the
owners engineers, i.e., NTPC and GAIL. Thus, RGPPL‟s formalization of award
of various contracts, including the contract in issue, was to be based on the
recommendation of the owner‟s engineers.
5. GAIL, in turn, in its pleadings before us, has taken the stand that as per the
arrangement arrived at between the parties, (which inter alia includes RGPPL),
EIL was to prepare the tender, float tender enquiries, evaluate offers received and
finally recommend the award of contract to GAIL in respect of LNG terminal
project. GAIL was thus required to examine and approve the recommendations of
the various stages of the tendering process which included approving the tender,
bidders evaluation criteria, approving price bids, and finally giving its
recommendation for award of the contract. GAIL thus, in the pleadings, has taken
the stand that in the exercise undertaken by it, of examination and evaluation of
bids till the stage of forwarding the award recommendation to RGPPL - it
followed its own contract in procurement procedures. It is in this background that
it became relevant for us to refer from hereon the events which led the EIL to float
the 1st tender; the queries raised by RGPPL; the reiteration of EIL of its
evaluation, the consequent declaration of the petitioner as L-1, and finally the
curious turn-around of EIL and GAIL (though sub-silentio) in declaring that the
petitioner had been wrongly declared as L-1; a recommendation dated 01.09.2010
which apparently formed the basis of RGPPL decision of 04.10.2010 to cancel the
1st tender.
6. The 1st tender was floated by EIL on 26.06.2009. Against the said tender,
bids were received from five (5) bidders, i.e., the petitioner before us i.e. RDS,
M/s ESSAR Construction Ltd., M/s Afcons Infrastructure Ltd., Joint Venture of
M/s Hojgaard Punj Lloyd Ltd. and lastly the Joint Venture of M/s Hung-Hua &
Ranjit Buildcon Ltd. The bids of the aforesaid five (5) bidders were evaluated by
EIL alongwith their back-up consultant, Scott Wilson, U.K. Upon evaluation, it
was found that Hung-Hua & Ranjit Buildcon Ltd. were not technically qualified,
resultantly, the said bidder was disqualified. This resulted in four (4) bidders
being left in the field. Consequently, EIL recommended to GAIL that the price
bids of the said four bidders be opened. It would be pertinent to note at this stage
that under the terms of the 1st tender, which are no different, we are told in the 2nd
tender, the price bids could only be opened qua bids which were found to have
qualified in the techno-commercial round, i.e., their bids were found technically
and commercially suitable. (See clauses 24 and 25 of the instructions to bids).
7. It is in this background that EIL on 24.12.2009 recommended the name of
the remaining four (4) bidders for appropriate approval of GAIL in respect of their
price bids. It appears that GAIL, while evaluating EIL‟s recommendation
observed that the foreign consultant, i.e., Scott Wilson, U.K., had not accepted the
adoption of "sling" methodology used by RDS for transporting, loading and
placement of rock armour for construction of breakwater, in the contract evidently
earlier executed by RDS. Therefore, by a communication dated 30.12.2009, GAIL
sought reconfirmation from EIL, whether it ought to accept the sling methodology
adopted by RDS. EIL by a return letter 31.12.2009, confirmed that RDS would
not use the sling methodology while loading out and placing rock armour and that
instead, it would use what is known as "hydraulic grab" technology. GAIL,
however, by a communication dated 25.01.2010 called upon EIL to seek the
opinion of Scott Wilson, U.K. in that regard. EIL evidently discussed the matter
with Scott Wilson, U.K, and thereupon, vide letter dated 01.02.2010 forwarded the
Scott Wilson, the U.K. addendum to their earlier technical evaluation report dated
29.01.2010. By virtue of this addendum, Scott Wilson, U.K. evidently confirmed
the inclusion of RDS in the list of those bidders whose price bids had been
recommended for being opened for appropriate evaluation. GAIL, thereupon
reviewed EIL‟s price bid opening recommendation, and after appropriate review
conveyed its approval for price bid opening of the very same bidders, who EIL
had recommended in the letter dated 24.12.2009. Once again RDS was included
in the list of recommended bidders.
8. Consequently, on 11.02.2010 in the presence of the said recommended
bidders, the price bids were opened. It was found that RDS, i.e., the petitioner,
was the lowest bidder at (approximately) Rs 390 crores, while the next lower
bidder was Afcons Infrastructure Ltd., whose price was higher by about Rs 160
crores in comparison to RDS, (having bid at Rs 550 crores). On 26.2.2010, EIL
forwarded their recommendation to GAIL. It is pertinent to note that the
justification cost (i.e., the estimated cost of the project) at the lower end of the
spectrum, was nearly Rs 662 crores (approximately).
9. On receipt of requisite recommendation and the back-up material, GAIL
upon appropriate examination and approval of the competent authority forwarded
its recommendation to RGPPL vide communication dated 08.03.2010. In this
communication, GAIL advised that while, executing the contract, RDS should
ensure that: it would inter alia provide suitably experienced staff with sufficient
equipment to ensure quality and adherence to time schedule; demonstrate and
implement appropriate planning and co-ordination of resources, undertake design
technical reviews to international standards; and lastly, provide site supervision
staff experienced in breakwater construction; once again, to ensure quality of
construction and compliance with specifications. To be noted, the communication
ended by explicitly stating therein that the recommendation had the approval of
competent authority, and is generally in line with GAIL‟s procedure and system.
10. From the point of view of the RDS, one would have imagined that the
execution of the formal contract hereon would be a given. This was, however, not
so as RGPPL by a letter dated 26.03.2010 sought various clarifications including
in respect of aspects mentioned in GAIL‟s letter dated 08.03.2010 issued to RDS,
to which we have made a reference hereinabove. The interesting part is that in
respect of query no. 5 raised in the aforementioned letter, RGPPL brought to
attention of GAIL that the estimated cost of the project was Rs 662.80 crores plus
minus 25%, whereas bid of RDS, which was declared as L-1, was lower than the
estimated cost by approximately 41.17%. RGPPL went on to state that if the bid,
is abnormally low, then it ought to give the owner sufficient cause to reject the bid
unless after due scrutiny and analysis of the rates, it is convinced about the
reasonableness of the bid. RGPPL thus sought GAIL‟s response to this query
amongst others. It would not be out of place to mention that RGPPL also raised a
doubt about RDS‟s ability to complete the breakwater project at hand in the given
time frame of thirty three (33) months when, on its own showing, it had taken
three (3) years for it to complete a breakwater project at Mus Car Nicobar, of 500
m; which incidently was shown as its qualifying work in the bid documents. In
this background, since the bid was valid till 30.04.2010, a request was made by
RGPPL to seek the extension of validity of the bid till 15.05.2010. RGPPL also
sought a copy of the recommendation of Scott Wilson, U.K. on the aspect of the
confirmation received from RDS that it would use hydraulic garb technology as
against the sling method for load out and placing of rock armour. GAIL, by its
letter dated 07.04.2010 gave a detailed point wise response to all eight queries, to
which we have made a mention hereinabove, including queries raised pertaining to
the difference between estimated cost and the bid price of RDS, and the capability
of RDS to execute the project within the stipulated thirty three (33) months, given
its experience in executing such like projects. The relevant part of the response on
this aspect reads as follows:
"......A.5 Accuracy of Cost Estimate:
The price quote of L1 bidder is reasonable as compared to lower bound cost estimate. The reasons for the same are as per Annexure
-1 attached with the letter.
A.6 Project Execution time and Bidders Capability: Based on the critical review of M/s RDS Projects offer, their replies to various technical queries and detailed presentation on execution/ construction methodology for the tendered work indicates that M/s RDS Projects is capable of executing the subject tender works in the stipulated time schedule.
Further, project execution time for any breakwater project is dependent on resources mobilization, availability of query at nearby location and marine environmental conditions at site etc. and
therefore project completion time periods may differ even though project physical parameters (size and shape) may be comparable...."
10.1 The communication ended with the GAIL appending the addendum to its
technical recommendation dated 29.01.2010, pertaining to the issue of the
technology which, RDS proposed to use for execution of the work at hand. It is
pertinent to note at this stage that both the recommendation of GAIL dated
08.03.2010 whereby, RDS was recommended for award of the work and, the
response dated 07.04.2010 pursuant to the first stage of queries raised by RGPPL,
vide its letter dated 22.03.2010 were sent under the hand of the same officer, i.e.,
Mr M.B. Gohil, General Manager (Project), GAIL.
10.2 Interestingly, in the interregnum as if by co-incidence, a writ petition was
filed in this court by Ranjit Buildcon Ltd., that is, the unsuccessful bidder, inter
alia, seeking a direction that RDS be declared as being „technically non-qualified‟
for undertaking the DPP and appropriate direction to quash any letter/LOI issued
by RGPPL in favour of RDS in respect of the said project. The affidavit appended
to the said writ petition is dated 22.03.2010. This writ petition, which was
numbered as WPC(C) No. 2142/2010 bears the date 23.03.2010. As indicated
above, the first set of queries of RGPPL to GAIL, is also a communication, dated
22.03.2010.
11. It appears that by a letter dated 25.03.2010, RGPPL formally informed
GAIL as regards institution of the writ petition by Ranjit Buildcon Ltd. This
communication was based evidently on a notice dated 23.01.2010 received from
the solicitors of Ranjit Buildcon Ltd. A copy of the writ petition was enclosed to
the said communication of RGPPL. A detailed reply was sought by RGPPL for its
purposes. GAIL in turn forwarded a copy of the writ petition to EIL vide its
communication dated 29.03.2010, while recording therein that discussions with
regard to the institution of the writ petition had been held in the office of
Managing Director of RGPPL on 26.03.2010. This letter was also issued under
the hand of M.B. Gohil. On 09.04.2010, EIL dispatched a point wise reply in
respect of the averments and allegations made in the writ petition filed by Ranjit
Buildcon Ltd. Apparently in respect of the qualification of RDS, the response
prepared by EIL was as follows:
"RDS Not Qualified (Reply to point nos. 25, 26, 28, 29, 30, 31, 32, 33 & 34) Requirement of Bidder‟s Qualification Criteria (in case of single bidder) as set out in the IFB are as follows:
The bidder shall have experience of having successfully completed, as a single bidder, or as a leader of a consortium/ joint venture, at least one project of a breakwater in an offshore location (offshore location is defined as the area submerged in the ocean sea) of minimum length of 400m during the last 20 (twenty) years to be reckoned from the last date of submission of bids. Documentary evidence submitted along with the bid offer conclusively established that:
Breakwater at MUS in Car Nicobar Island is located at an offshore location
(Refer Annexure - 1: Completion certificate issued by Ministry of Shipping, Road Transport and Highways - Department of Shipping, Little Andaman which mentions that "The entire work has been executed in sea (beyond low water line) by M/s RDS Projects Ltd., and they have successfully completed during June 2003".
M/s RDS has completed the entire works pertaining to breakwater at MUS in Car Nicobar island as a single entity on behalf of M/s Ellen Hinengo Ltd. (Refer Annexure -1: Completion certificate issued by Ministry of Shipping, Road Transport and Highways - Department of Shipping, Little Andaman). Hence, meeting the BQC requirement of qualifying project."
12. GAIL by a letter of even date, i.e., 09.04.2010, forwarded the same to
RGPPL. RGPPL wasted no time in responding to GAIL‟s communication and
thus, by a return communication of even date, i.e., 09.04.2010, sought the
following from GAIL:
(a) The letter of award containing detailed scope of work, contract value, payment
terms, completion schedule and other contractual stipulations, and
(b) the veracity of the completion certification submitted by RDS projects ltd.,
duly verified by GAIL/EIL.
12.1 These documents were sought ostensibly in order to enable RGPPL to
prepare its reply in response to the writ petition of Ranjit Buildcon Ltd. GAIL by
a return communication dated 12.04.2010, informed RGPPL that a work order for
the qualifying project (work) had already been submitted by RDS, though detailed
work order was not available with the bid documents filed by RDS. In so far as
the completion certificate is concerned, GAIL stated that RDS had furnished a
completion certificate issued by the Ministry of Shipping, Road Transport and
Highways Department of Shipping, Government of India and, therefore, they had
no reason to doubt the veracity of the document.
12.2 RGPPL reiterated its request for work order vide letter dated 28.04.2010.
EIL, on its part sent an email dated 24.05.2010 and 30.04.2010 seeking a copy of
the work order of its qualifying work. GAIL, by a letter dated 21.05.2010
informed RGPPL that though they had not received the work order from EIL, they
had been following up the issue.
12.3 Interestingly, RGPPL, it appeared, was looking for information which
perhaps, it already had in its possession by virtue of the Comptroller and Auditor
General (in short „CAG‟) report number 2/2002 which seemed to suggest that the
qualifying work, i.e., the breakwater constructed at Mus Car Nicobar Island in the
Andaman Nikobar Island had been constructed in "phases". Therefore, while the
website of Andaman Lakshdeep Harbour Works observed that there was only one
breakwater at Mus Car Nicobar Island with a length of 490 m, it desperately
wanted the work order to establish the fact that RDS had executed the qualifying
work/project not at one go but in different phases by virtue of the separate
contracts. Therefore, by a letter dated 26.05.2010, RGPPL once again sought the
copy of the work order. It is in this letter that RGPPL for the first time, revealed
the information that it had in its possession by virtue of what was available on the
website of Andaman Lakshdeep Harbor Works, and that which it found contained
in the CAG‟s report. It may be noted that GAIL evidently referred to contents of
this letter to EIL vide email dated 27.05.2010. RGPPL, on the other hand, raised
pointed queries for the first time with respect to qualification criteria provided in
clause 8.1.1.1. In the context of the qualification criteria provided therein, it
sought to know from GAIL that the GAIL had declared RDS as qualified based on
a certificate dated 05.04.2008 issued by the Dy. Chief Engineer, Andaman
Harbour Works. It was put to GAIL that since the certificate referred to a tender
of 26.05.1999, the certificate did not state the scope of the qualifying work
involved construction of a breakwater of 500 m length. It went on to say that
viewed in the background of the CAG‟s report (which is a report of 2002), the
scope of the tender was limited to 290 metre, therefore, it questioned the
conclusion arrived at by GAIL that RDS had the requisite experience of
constructing 500 metre breakwater. The communication ended with RGPPL
invoking clause 9 of the instruction for bidder (in short „IFB‟) which empowered it
to seek further documents from the bidder. Based on this clause, RGPPL asserted
its rights to receive a copy of the work order. It appears that GAIL sent a
communication dated 09.06.2010 on the aspects on which queries had been raised
by RGPPL. RGPPL on its part seems to have sought and obtained clarifications
from the Dy. Chief Engineer-IV, Andaman Harbour Works. The said Dy. Chief
Engineer-IV vide its letter dated 05.06.2010 issued its clarification which were
forwarded for consideration of GAIL and EIL. The said communication being
crucial for the purposes of adjudication of matter in issue, for the sake of
convenience, the relevant portion is extracted hereinbelow:
"With reference to the above, it is to inform that the work in question, "Construction of Breakwater and Wharf at Mus in Car Nicobar Island" was executed under Deputy Chief Engineer-IV circle. Most of the office records which were maintained in Little Andaman & Car Nicobar Island were washed away during Tsunami waves on 26th December 2004. The following details were furnished based on the available information.
It is reiterated that the subject breakwater was completed in June 03 and has witnessed Tsunami in the Dec 04 wherein entire establishment at Nicobar was washed away thus no records are available due to old case and havoc created by Tsunami. Thus clarification as asked for cannot be given as per format attached. However, it will be my endeavour to give details at my best. Briefly it is submitted that this only offshore breakwater of 22-490 mtr. Length (Constructed length of 500 mtr.) at Mus Car Nicobar was constructed in two phases/ contracts both of which were awarded to M/s EHL a tribal society of Car Nicobar Island in continuation i.e., before the first work completed the second was awarded.
First contract bearing no. EEM/LA/DB/A-10/95-96 dated 5.6.1995 valuing 14.10 crores, was awarded to M/s EHL with all items of work connected with construction of breakwater i.e., mining and supply of boulders of various sizes, Tetrapod casting and placing mining/ crushing aggregates etc. Subsequently to augment further progress, another agency M/s Reacon International was introduced
against work order valuing 6.28 crores against supply of boulders only. EOT granted to M/s EHL as delay not attribute table to them. Therefore, finally the balance work including left over items of 1st contract was put to tender and awarded to M/s EHL vide DCE/LA/DB/T-2/99-2000 Vol. IV 3318 dated 3rd Nov. 2000 valuing 30.01 crores for final completion of the structure. No EOT involved. It is hereby certified that M/s RDS Project Ltd. was the sole construction agency for and on behalf of M/s EHL, for undertaking all activities under these contracts to which their performance had been exemplary." (emphasis is ours)
13. EIL on its part, examined the certificate dated 05.04.2010 issued by the
Deputy Chief Engineer-IV, Andaman Harbour Works, in the light of the queries
raised by RGPPL and the clarification issued on 05.06.2010 by the said Deputy
Chief Engineer. In this regard, the CAG report number 2/2002 was also noticed
wherein it had been stated that the work had been completed in "phases". After
reviewing the material placed before it, EIL vide its communication dated
10.06.2010 concluded that even though the qualifying work at Mus Car Nicobar
Island had been completed in two phases, its recommendation did not "necessitate
any revision in the award recommendation". It is pertinent to note that the said
communication of 10.06.2010, which reviewed the material placed before it by
RGPPL, inter alia, the CAG report and the clarification dated 05.06.2010 issued
by the Deputy Chief Engineer -IV, Andaman Harbour Works indicating that the
qualifying project at Mus Car Nicobar Island, had been executed by RDS in two
phases and by virtue of two separate contracts, was signed off under the hand and
signatures of Sh. R.K. Bhandari, General Manager (Projects), EIL. The reason
why we have referred to the signatories would become clear as we progress further
with our narrative.
14. The communication dated 10.06.2010 was not, it appears, to the liking of
RGPPL. Consequently, RGPPL vide another communication dated 15.06.2010,
returned GAIL‟s recommendation of 08.03.2010 on the ground that documentary
evidence substantiating that the RDS met the Bidder Qualification Criteria (in
short „BQC‟), had not been furnished. In this communication, RGPPL went on to
say that the GAIL‟s recommendation was conditional (these so called conditions
have already been referred by us hereinabove in the earlier part of our judgment).
It directed RGPPL to withdraw these conditions appended to their
recommendation. It also went on to note that the clarification issued by the
Deputy Chief Engineer - IV, Andaman Harbour Works vide letter dated
05.06.2010 was not backed by any institutional data. In the context of all this, it
sought documentary evidence to establish "beyond doubt" (i) whether the RDS
was a single bidder for the qualifying (work) project; (ii) whether the RDS had
successfully completed one project of breakwater of minimum length of 400
meter; and (iii) whether the qualifying project breakwater was in an offshore
location as per BQC.
15. The letter dated 15.06.2010 was followed by RGPPL‟s letter dated
22.06.2010. It now sought clarification regarding non-submission of audited
financial statements by RGPPL for the immediately preceding financial year, i.e.,
2008-09. The purpose being: evidently to analyze the financial credentials of
RDS. GAIL, as in the past, by a communication dated 23.06.2010 written under
the hand of Mr M.B. Gohil, General Manager (PD-GP), forwarded the same to
EIL. This time the communication was addressed to one Shri Ravi Saxena, Dy.
General Manager (Project). Earlier, communications were addressed to
Mr.R.K.Bhandari, General Manager (Projects). As is evident, RGPPL had again
changed the goal post as it now sought to inquire as to whether the net worth of
RDS was positive during the financial year 2008-09. EIL vide letter dated
1.07.2010 once again sent a comprehensive reply to the RGPPL‟s letter dated
26.06.2010. EIL confirmed that the RDS met the financial criteria, as stipulated in
the tender. As regards non-availability of the balance sheet for the financial year
2008-09 was concerned, EIL informed that since the unpriced bid was opened on
16.09.2010, the tenderers, whose financial year closed thereafter, were at liberty to
submit the audited financial statements of those three (3) years which preceded the
said date. Nevertheless, audited financial statements of RDS of 2008-09 were also
obtained and furnished to GAIL for onward transmission to RGPPL. In order to
put the matter "beyond doubt", GAIL on its part, sought in the interregnum, the
opinion of the Attorney General of India on 28.06.2010. Suffice it to say, that the
Attorney General vide his opinion dated 30.06.2010, opined that RDS qualified
the single bidder qualification criteria provided in the 1st tender. It is pertinent to
note at this stage that even though the documents pertaining to the execution of the
qualifying work at Mus Car Nicobar Island had been obtained including the report
of the CAG and the clarificatory letter dated 05.06.2010 of the Dy. Chief
Engineer-IV, Andaman Harbour Works - the query on which the opinion of the
learned Attorney General was sought by GAIL, was in the light of the fact that the
qualifying work having been awarded to Ellon Hinengo Ltd. (in short „EHL‟),
whether RDS could be considered as the person who had executed the contract. In
other words, in the context of the fact that the work had been awarded to EHL,
whether RDS would stand in the position of a sub-contractor.
16. Given the response of EIL and the opinion of Attorney General received by
GAIL, GAIL by a communication dated 10.07.2010 forwarded the synopsized
response of EIL that; (i) the entire work of construction of breakwater at Mus in
Car Nicobar Island was executed by RDS on behalf of EHL; (ii) the contracted
length of the breakwater was 500 meters; (iii) the entire work was executed in
sea (beyond low water line) by RDS; (iv) the work was successfully completed in
June, 2003; (v) the qualifying work was executed by RDS as a single bidder
which met the BQC stipulated under the first tender; (vi) Even though the CAG
report no. 2/2002 and the clarificatory letter of the Deputy Chief Engineer - IV,
Andaman Harbour Works dated 05.06.2010 suggested that the work had been
completed in two phases/ contracts both of which were awarded to EHL; the
additional information did not necessitate any revision in the recommendation
for award of work to RDS; (viii) the completion certificate dated 05.04.2008 is
considered as adequate evidence of the qualifying work having been executed;
(vii) Learned Attorney General had opined that RDS having done the entire
work, was qualified under the expression „single bidder‟ in relation to the 500
meter breakwater project by RDS in Mus Car Nicobar Island; (ix) the conditions
thus far referred to in GAIL‟s letter dated 08.03.2010, were advisory in nature,
as indicated in GAIL‟s letter dated 09.04.2010; therefore, GAIL‟s
recommendation could not be construed as a conditional recommendation; (x)
RDS met the financial criteria, as was indicated in EIL‟s letter dated
01.07.2010; (xi) it specifically referred to item no. 6.2.3 in the agenda of the 6th
board of directors meeting of the RGPPL, wherein it had been in particular
observed that RGPPL would have to rely, inter alia, on the recommendations of
NTPC and GAIL qua the LNG block; and (xii) finally, after recording the
aforesaid, GAIL once again reiterated its recommendation of 08.03.2010 and
called upon RGPPL to re-consider the award of the said work to RDS.
16.1 The communication ended by noting that without the breakwater, capacity
utilization of LNG terminal would be limited to the extent of 20% and that
consequently the daily loss because of the failure to utilize the terminal to its full
capacity was working out to Rs 1.50 crores. The communication, however, ended
by putting the onus back on RGPPL by indicating therein that since RGPPL was
the owner, it would have a final view in the matter. This communication was once
again issued under the hand of Mr M.B. Gohil of GAIL. The letter contained
enclosures such as GAIL‟s recommendation dated 08.03.2010 (in original), copies
of EIL‟s letters dated 10.06.2010 & 01.07.2010 alongwith annexures and opinion
of Attorney General of India dated 30.06.2010.
17. It appears that in the meanwhile, RGPPL had preferred an application under
the Right to Information Act, 2005 (in short „RTI‟) with the Andaman Harbour
Works. Seeking information and documents vis-à-vis the qualifying work; this
included the work order dated 27.04.1995 awarded to EHL and the scope of work
of the qualifying tender. The documents obtained were forwarded to GAIL by
RGPPL vide its letter dated 26.07.2010. It would be important to note that a
perusal of the record submitted by RGPPL would show that just prior to issuance
of the letter dated 26.07.2010, its Board of Directors had convened a meeting on
20.07.2010. A perusal of the minutes would show that one of the Directors had
raised an objection as to why the Managing Director had initiated the agenda on
the LNG terminal while in respect of other LNG terminals meetings had been
initiated at the behest of the Dy. M.D. The Managing Director of RGPPL seems
to have suggested that the Board note had been prepared with the knowledge of
the Dy. M.D. and all versions of the draft notes had been shared with him. The
Dy. M.D., however, took the stand that since the Board note contravened the
opinion of the „GAIL Directors‟, he would not be amenable to appending his
signatures on the Board note. As a matter of fact, two Directors took the position
that since the owners‟ Engineers had opined that RDS fulfilled the BQC
requirements, the contract ought to be awarded to RDS. The Managing Director
took a contrary position. The events which followed hereafter would show that
this dissent for some curious reasons disappeared, even though there was no
material change in circumstances. Importantly, there is no reference to these
minutes in the affidavit filed by RGPPL. GAIL, on its part furnished, by a letter
of even date i.e., 26.07.2010, the said information to Mr R.K. Bhandari, General
Manager (Projects) of EIL. By this letter, GAIL called upon EIL to review its
recommendation based on the documents received through the RTI route,
particularly, in the context of its earlier evaluation of RDS as conforming to the
BQC under the 1st tender. This letter was sent under the hand of Mr M.B. Gohil,
General Manager, GAIL, and as indicated above, addressed to Mr R.K. Bhandari,
General Manager (Projects) in EIL. Since in the meanwhile, as noticed above,
Ravi Saxena had been given the task of evaluation on behalf of EIL, he did the
needful and communicated his assessment vide email dated 11.08.2010. After
"critically" reviewing the material at hand, which RGPPL had obtained through
the RTI route, EIL opined as follows:
"1. During the evaluation stage, M/s RDS offer was evaluated based on the documents furnished in their offer which include completion certificate no. DCE/LA/GI-20/928 dated 5.4.2008 issued by Dy. Chief Engineer - IV Andaman harbor Works Little Andaman. As the said completion certificate contained all the requisite information as per bid stipulations, M/s RDS was considered as qualified bidder.
2. Information which has now been made available to us additionally has been critically reviewed and it is found that contents of documents are not inconsistent with each other and therefore, we may not take cognizance of the said documents.
Moreover, though the work of breakwater at MUS has been carried out in two phases under two separate work orders, it may be considered as single project as Completion Certificate (No.
DCE/LA/GI-20/928 dated 5.4.2008) issued to M/s RDS is for the entire breakwater length. This fact is further corroborated by the letter No. DCE-IV/LA/ALHW/CAMP:PBF-35/764 dated 05/06/2010 issued by the office of Deputy Chief Engineer-IV which enumerates that M/s RDS was the sole construction agency for & on behalf of M/s EHL for undertaking all activities under these contracts to which their performance had been exemplary and also by the extract of CAG Report No. 2 of 2002 (Civil)." (emphasis is ours)
17.1 The communication included the opinion that no revision in the award
recommendation was necessitated at this stage.
18. Curiously, despite this emphatic stand, EIL took a complete u-turn on
01.09.2010 in response to GAIL‟s letter dated 26.07.2010 which had already been
replied by EIL vide its e-mail dated 11.08.2010. Based on the same material,
which as per the e-mail of 11.08.2010 had been critically reviewed, it came to an
entirely different conclusion and the person who came to this conclusion was the
very same gentleman, i.e., Ravi Saxena, who had issued the earlier
communication, i.e., e-mail dated 11.08.2010. In his communication of
01.09.2010 the officer opined as follows:
"Considering the facts as brought out from above mentioned documents, it is evident that Ministry has awarded project for construction of breakwater from chainage 22 to 200 meters and
project for construction of breakwater for chainage 200 to 330 meters subsequently extended to 490 meters as separate projects. In view of the documents made available and having perused all the documents in concurrence with each other, it emerges that since both the phases have been considered as separate projects by the Ministry, M/s RDS can not club the experience of having executed two separate projects to qualify the BQF which requires that the bidder should have experience of at least one project of a breakwater in an offshore location of minimum 400 m.
In light of above, it is concluded that experience submitted by M/s RDS can not be taken as execution in „single project‟ and therefore, M/s RDS does not meet the BQC requirement."
19. This aspect of the matter troubled us immensely. Therefore, in the hearing
held before us, we had put to the learned counsel for EIL, Mr Ashok Mathur as to
how on the very same material, the same person i.e., Ravi Saxena, Deputy General
Manager (Projects), EIL could have come to a diametrically converse conclusion.
Mr Mathur had no answers, till he was guided by an officer of EIL by drawing his
attention to a legal opinion on record of one Ms Smita Sehgal dated 26.08.2010.
We had put to Mr Mathur during the course of hearing, as to whether this aspect
had been disclosed in the counter affidavit filed by EIL in court. Mr Ashok
Mathur quite fairly conceded that this aspect had not been referred to in the
counter affidavit filed by EIL. In these circumstances we had put to Mr Mathur
whether at this point in time, when respondent no. 3/EIL had already concluded its
submissions in reply, would it be fair to refer to those documents or allow the said
legal opinion to be placed on record in the midst of the hearing when the petitioner
had no opportunity to deal with it in the rejoinder placed on record. EIL having
been caught on the wrong foot, however, persisted in its efforts. Consequently,
towards this end, an application was filed and moved before us on 12.09.2011
when, after recording our observations that there ought not to have been any need
to file the said additional affidavit (which was sought to be done by way of an
application) as EIL was aware of the case set up by the petitioner, and therefore,
our queries, could not have come as a surprise - the application was allowed and
EIL was permitted to place the documents filed on record even at that fag end of
the hearing, only to enable EIL to have its complete say; though the analysis of the
effect of the document was made subject to the final outcome of the case. The
application was allowed with cost of Rs 50,000/-. Liberty was granted to the
petitioner to meet this new development by way of an oral rejoinder at the hearing
to follow.
20. It would be, therefore, important to deal with this aspect of the matter
which evidently brought about change of heart and mind in the EIL‟s officer led
by Ravi Saxena. The affidavit accompanying the appeal adverts to the fact that
pursuant to email dated 11.08.2010 issued by Ravi Saxena of EIL, the then Dy.
General Manager (Projects) an internal meeting was held to ascertain the view,
(we assume of the legal department), in the light of additional material made
available to EIL. A decision was taken at this meeting evidently to refer the
matter to the legal department for their opinion. To be noted, the date of this
internal meeting is not adverted to in the additional affidavit dated 06.09.2011
filed by Ms Smita Sehgal. The affiant, however, adverts to an inter-office
memorandum dated 20.08.2010, whereby the material was forwarded to the legal
department seeking its opinion. It is in that background that legal department on
26.08.2010 opined that RDS did not meet the BQC requirement of the 1st tender.
We may only notice that the opinion concludes by stating that since the Ministry
had awarded the project for construction of breakwater (qualifying project) from
chainage 22 to 200 meters, and the project for construction of breakwater from
chainage 200 to 300 meters (subsequently extended 490 meters), RDS had
experienced not of a "single project" but of "two projects", and hence did not
qualify the BQC requirement of the 1st tender which required the bidder to have
experience of at least one project of a breakwater in an offshore location of
minimum length of 400 meters. The author of the opinion is also the affiant to the
additional affidavit. Ms Sehgal pivots this view on the strict construction of the
language of the document in issue and goes on to say that however "harsh"
"absurd" or even contrary to common perception the conclusion may be, that is
the only conclusion she could draw on the construction of the document. What is
even more interesting is that this very legal opinion bears the endorsement dated
27.08.2010 of Mr.Grover Director (Projects) - calling upon Mr R.K. Bhandari,
General Manager (Projects) to follow the opinion of the legal department. It is
important to remind ourselves at this juncture that till 10.06.2010, it was the same
R.K. Bhandari, who opined based on the very same additional information, (which
formed the edifice of Ms Smita Sehgal‟s opinion) that material forwarded did not
necessitate revision in award recommendation. There is no averment in the
affidavit as to whether Mr.Grover called a meeting of Mr.R.K.Bhandari and
Mr.Ravi Saxena to discuss the opinion of the legal department. Mr Grover‟s
endorsement suggests quite clearly that he left no scope for debate or discussion.
21. On receipt of EIL‟s revised recommendation of 01.09.2010, GAIL vide
communication dated 18.09.2010 simply forwarded the opinion of EIL to RGPPL.
In its communication, GAIL made it clear that since RGPPL was the owner under
the contract, it should take appropriate action at their end. The RGPPL was, at
this stage, not happy with the communiqué of GAIL whereby, the onus for the
final decision was put on it, therefore by a letter dated 20.09.2010 it called upon
GAIL to forward its recommendation based on the communication of EIL dated
01.09.2010. This letter of RGPPL dated 20.09.2010 is not on our record, though it
finds mention in paragraph 37 of the affidavit filed by Mr.M.B. Gohil. GAIL,
however, did not oblige as is evident from its letter dated 22.09.2010. GAIL after
giving reference to its earlier recommendation dated 08.03.2010, and also letters
dated 09.04.2010, 21.04.2010, 09.06.2010 and 10.07.2010, put the onus back on
RGPPL to take a decision in the matter being the owner of the project as it had in
its wisdom, all the relevant information, on the subject, available with it. The
author of letters dated 18.09.2010 and 22.09.2010 is one Sh. S.C. Khetan, Dy.
General Manager (PD), in GAIL, who appears to have taken over from M.G.
Gohil. It appears that given the stance of GAIL, RGPPL proceeded to take a
stance in the matter. Consequently, by email dated 07.10.2010, RGPPL informed
GAIL that they had taken a decision at their Board of Directors meeting held on
04.10.2010 to annul the 1st tender. It also indicated in the said communication
that by a letter dated 06.10.2010, this decision had also been conveyed to RDS.
Since RDS had been disqualified, their EMD was also sought to be returned.
GAIL, by this very communication had been asked to re-float a fresh tender. The
email of 07.10.2010 was followed by a letter dated 13.10.2010 of RGPPL to GAIL
broadly conveying the same information. Consequent thereto, GAIL informed
EIL vide letter dated 19.10.2010 to initiate a fresh tender process for construction
of breakwater works at the LNG terminal. On 31.12.2010, EIL forwarded the NIT
alongwith international competitive bidding (in short „ICB‟) and the BQC for
fresh tender (i.e., the 2nd tender) to GAIL for approval. The tender committee,
comprising of the executive director, approved the issuance of the said documents
with the amended clause 8.1.1.1. This document was further approved by the
competent authority, i.e, the Director (Marketing). The approval was obtained on
06.01.2011. Based on the above, EIL floated the 2nd tender inquiry on an ICB
basis on 12.01.2011. It is this 2nd tender which contains the amended clause
8.1.1.1 which is the cause of grievance in the present writ petition.
SUBMISSION OF COUNSELS
22. In the background of the aforesaid facts and circumstances, submissions
were made by counsels for parties. The arguments have been addressed before us
on behalf of petitioner/RDS by Mr Jagdeep Dhankar, senior advocate; on behalf of
RGPPL by Mr A.S. Chandhiok, Addl. Solicitor General (ASG); on behalf of
GAIL by Mr Gourab Banerji, ASG; and on behalf of EIL by Mr Ashok Mathur,
Advocate. Ms Indira Jai Singh, learned ASG made submissions on behalf of EIL
in support of the application filed, to bring on record the legal opinion, which has
been referred to above by us. Mr Neeraj Choudhari, CGSC made submissions on
behalf of UOI.
23. Mr Dhankar in his submissions has taken us minutely through those very
documents which we have referred hereinabove to show how the owners
engineers, GAIL as well as EIL till 11.08.2010 consistently adhered to the stand
that their recommendation to award the contract to RDS did not require any
revision. He submitted that the change which was brought about on 01.09.2010
was made with a malafide intention only to oust the petitioner. The decision in
respect of the said change was recommended by Ravi Saxena on behalf of the EIL,
who was also the author of the earlier communication dated 11.08.2010, wherein
he had conveyed to GAIL and through GAIL to RGPPL that notwithstanding the
qualifying work having been executed by the petitioner in "two phases" under two
contracts, the petitioner was eligible and its recommendations for award of
contract to RDS did not require a revision. Mr Dhankar submitted that the action
of the respondent was fraught with malice, arbitrariness and lacked complete
fairness, in as much as, the only intent of RGPPL was somehow to get the EIL and
GAIL to change their opinion so that RDS was ousted from the work in issue.
Having achieved in its design, RGPPL presented this court with fate accompli
when the petitioner/RDS filed a writ petition bearing no. 8252/2010 to challenge
RGPPL‟s decision of 04.10.2010 by cancelling the 1st tender altogether. The
petitioner/RDS was thus left with no option but to withdraw the petition and take
its chance in a fresh round if and when the work were to be awarded. The RDS‟s
apprehension, which is recorded in the court‟s order dated 14.12.2010, came true,
when in the fresh (2nd) tender floated by the respondents, the eligibility criteria
contained in clause 8.1.1.1. in the 1st tender, was significantly changed to ensure
its complete exclusion from the race, so to speak. Given the facts and
circumstances of the case in this matter, the court could come to no other
conclusion but that the respondents‟ action were malicious, unfair and contrary to
justice and equity. We may only note here that at the request of Mr Dhankar, Mr
Chandhiok, learned ASG had accorded an opportunity to the petitioner to inspect
briefly, RGPPL‟s record in court; based on which Mr Dhankar brought to our
notice, a significant fact, which is that on 17.09.2010, RGPPL had received a copy
of the completion report dated 09.08.2005 from the concerned authorities i.e.,
Deputy Chief Engineer-IV, which clearly indicated that the breakwater work (i.e.,
the qualifying work) at Mus Car Nicobar Island had been constructed and
completed. Mr Dhankar submitted that RGPPL, while issuing its communication
on 20.09.2010 to GAIL, called upon it to submit its recommendation (and not
simply forward that which EIL had given vide its communication dated
01.09.2010) - which ordinarily would have meant that it wanted its independent
input on the issue at hand; and therefore, in order to ascertain its view, it ought to
give every material it had at hand, including the completion report dated
17.09.2010, if its action were not motivated. Mr Dhankar submitted that otherwise,
all this while, RGPPL had been furnishing documents to GAIL to opine on the
matter, however, this crucial document had been withheld by RGPPL because by
this time, it had already received an opinion which it was so desperately seeking,
which was the ouster of RDS.
24. On behalf of GAIL, Mr Gaurab Banerji took us through a series of
documents and correspondence which had been exchanged amongst the parties on
the aspect pertaining to the qualifying work and its impact on the eligibility of
RDS. Mr Banerji laid special emphasis on the fact that the RDS had made a
misrepresentation, in as much as, in its bid document filed in respect of the 1st
tender against query no. 6, it had stated that it had executed a breakwater of total
length of 500 metres at Mus Car Nicobar Island; the milestone dates being:- date
of award - November, 2000; commencement of work - November, 2000; the
scheduled date of completion - June, 2003; and lastly, the actual date of
completion - June, 2003. According to the learned ASG, the said information
given in the aforementioned document by RDS had been confirmed against query
no.10 raised in the very same document. Mr Banerji submitted that by way of
evidence, the only proof that RDS provided to establish the veracity of the said
information concerning qualifying work, was the certificate of the Government of
India, Ministry of Shipping, Roadways and Highways dated 05.04.2008. Since the
material collected by RGPPL demonstrated that the qualifying work had in fact
commenced in 1995, and that it got concluded in 2003, demonstrated that RDS
had misrepresented facts which led both GAIL and EIL into believing that the
RDS was eligible. Mr Banerji laid stress on the fact that the contract in issue, i.e,
the 2nd tender envisaged execution of the work in three (3) years. He submitted
that if petitioner had taken eight (8) years to complete a breakwater of 500 metre
length then both the experts, i.e., GAIL and EIL including the owner had the right
to review their decision and cancel the contract as under the 2nd tender, a
successful bidder would be required to construct a breakwater of 1800 m length in
thirty three (33) months. Mr Banerji submitted that, the given the facts and
circumstances of the case and the documents on record, it could not be said that
respondents have taken a decision with the malicious intent or, that it was unfair
and arbitrary.
25. Mr Mathur, in his brief submissions, dittoed the arguments of Mr Banerji.
As indicated above, Mr Mathur had very little to say on the change of opinion of
EIL between 11.08.2010 and 01.09.2010. The reason for the opinion; which is
also noticed by us above, was the opinion obtained from the legal department of
EIL.
26. Mr Chandhiok, learned ASG appearing for the RGPPL argued that under
clause 28.1 of the IFB read with clause 19, RGPPL as the owner was entitled to
cancel the 1st tender. Mr Chandhiok submitted that under clause 9 of the ITB the
owner was entitled to seek additional information from the bidders. It was his
case that this information was sought from time to time from RDS through the
aegis of owners‟ engineers, who in turn prevailed upon EIL to seek this
information. Despite, several communications beginning from March, 2010, the
said information was not made available by RDS. RGPPL had to obtain the
information from various sources, including the RTI route. It was the information
which RGPPL had gathered, i.e., the CAG Report, and the information available
on the website of Andaman Harbour Works, which gave a clue to the fact that
RDS had neither constructed entire 500 metres of the qualifying work, purportedly
executed at Mus Car Nicobar Island, nor had it been executed under one single
contract in a single phase, as was the requirement of clause 8.1.1.1 of the 1st
tender. It was Mr Chandhiok‟s submission that, given this misrepresentation,
RGPPL as the owner, in public interest, was entitled to cancel the 1st tender. Mr
Chandhiok raised certain issues on the "maintainability" of the reliefs sought in
the writ petition. In this regard, Mr Chandhiok drew our attention to the reliefs
claimed by RDS whereby it sought a direction from this court to quash the
decision taken by RGPPL‟s board of directors on 04.10.2010, cancelling the 1st
tender. Learned ASG submitted that this relief could not be sought by RDS, in
the present writ petition, in view of the fact that RDS had withdrawn its earlier
writ petition, i.e., WP(C) No. 8252/2010 without seeking liberty to file a fresh writ
petition to challenge the very same decision. In order to buttress this submission,
Mr Chandhiok submitted that, at best, RDS could seek to challenge the 2nd tender
by way of the present writ petition, wherein allegation made is that the petitioner
was wrongfully excluded. It was the ASG‟s submission that liberty sought and
granted by this court by its order dated 14.12.2010 was of a limited nature. In
order to buttress his submission, learned ASG referred to an application bearing
no. 13791/2010 dated 07.10.2010, filed by RGPPL, in the writ petition filed by
Ranjit Buildcon Ltd. [WP(C) No. 2142/2010]. Learned ASG referred to
paragraphs 3, 5, 6, 7 & 10 of the said application. Based on the assertion made
therein, wherein broadly, it has been stated that RDS had been declared ineligible
for failure to meet the qualifying criteria - Mr Chandhiok submitted that a
Division Bench (which included one of us i.e., Sanjay Kishan Kaul, J) of this
Court had by an order dated 30.11.2010 dismissed the writ petition as withdrawn.
Mr Chandhiok submitted that even though the application contained allegations
against RDS, (which was impleaded as respondent no. 2 in the said writ petition),
no caveats were entered by RDS when it came up for hearing. For all these
reasons, it was Mr Chandhiok‟s submission that RDS is neither entitled to assail
the decision of RGPPL dated 04.10.2010 nor could it seek a writ of mandamus
calling upon RGPPL to award the contract in its favour.
27. On behalf of UOI, Mr Neeraj Choudhary adverted to only the averments
made in the counter affidavit filed by the UOI.
REASONS
28. Having heard the learned counsel for the parties and facts noticed
hereinabove, it is quite clear that after RDS was declared as L-1, a concerted
attempt was made to oust the RDS. Under the terms of the 1st tender, the job of
evaluating the eligibility of the bidders was that of EIL. EIL made its
recommendations, as regards techno-commercial qualification of RDS and that of
three (3) other bidders, as far back as, 24.12.2009. GAIL, after evaluating EIL‟s
recommendation sought its opinion on the technology that RDS would use for
loading out and placement of rock armour. GAIL insisted, that EIL should get the
back-up consultant, i.e., Scott Wilson, U.K to opine on the matter. EIL did the
needful and forwarded an addendum in that regard generated by Scott Wilson,
U.K. to its report on 29.01.2010. This cleared the way for opening the price bid.
It is not disputed, as it cannot be, that the price bid under the tender conditions
(i.e., the 1st tender) could only been opened in respect of those bidders who were
considered to be techno-commercially qualified. On 10.02.2010, GAIL gave its
approval to EIL to open the price bid of the four (4) bidders who had qualified the
techno-commercial round. Ranjit Buildcon Ltd., which had been disqualified in
the techno commercial round, stood aggrieved in the meanwhile. On 11.02.2010,
when price bids were opened, it was undisputedly found that RDS was the lowest
bidder at Rs 390 crores (approximately). It is also not in dispute that the
difference between the next lowest bidder, which was Afcons Infrastructure, is a
sum of Rs 160 crores (approximately). The EIL conveyed its award
recommendation to GAIL vide its letter dated 26.02.2010. GAIL in turn
forwarded its award recommendation, (after due examination of the award
recommendation of EIL) on 08.03.2010. Mr M.B. Gohil, on behalf of GAIL
communicated that recommendation. RGPPL, it appears was not happy with this
state of affairs. RGPPL raised various queries by its letter dated 22.03.2010; to
which we have already made a reference. This was followed by a series of letter
dated 09.04.2010, 26.05.2010 and 26.07.2010. In between, RGPPL had obtained a
CAG report no. 2/2002. A perusal of RGPPL‟s record would show that on
14.05.2010 it had written to CAG that it had downloaded its audit report no.2/2002
with respect to construction of breakwater at Mus Car Nicobar Island and that it be
given a certified copy of the same alongwith any additional record with regard to
the same. The CAG obliged evidently vide its letter dated 17.05.2010 by
forwarding a copy of its report no.2/2002. What is not known is when did RGPPL
for the first time download a copy of the report from the website despite the fact
that the matter had been hanging fire since 08.03.2010. More pertinently, these
letters are not referred to in the affidavit filed by RGPPL. It evidently, also
became wise to the information available on the website of the Andaman Harbour
Works, which indicated that the qualifying work at Mus Car Nicobar Island, which
the RDS claimed as its experience in executing the instant work, was only of a
length ad-measuring 490 metres. GAIL, at the insistence of RGPPL, conveyed
this information to EIL. It is pertinent to note that, keeping in mind the
information that RGPPL had, it called upon GAIL to obtain the work order issued
in respect of breakwater evidently constructed by RDS at Mus Car Nicobar Island.
Other queries were also raised (to which we have made a reference above) by
RGPPL, in its letter dated 08.06.2010. In the interregnum, RGPPL had also
received a letter from the Deputy Chief Engineer - IV, Andaman Harbour Works
dated 05.06.2010. This letter of Deputy Chief Engineer - IV Andaman Harbour
Works was also forwarded for consideration of the EIL. Sh.R.K.Bhandari, on
behalf of EIL, in his letter dated 10.06.2010 remained firm on his stand that the
material placed before him, which included CAG‟s report number 2/2002 as also
the letter of the Deputy Chief Engineer -IV, Andaman Harbour Works dated
05.06.2010, did not require a revision in EIL‟s award recommendation qua RDS.
Not being satisfied, RGPPL by a letter dated 15.06.2010 issued a missive to
GAIL, in which it inter alia observed therein for the first time [after nearly three
(3) months] that its initial recommendation of 08.03.2010 was conditional. GAIL,
in the meanwhile, also sought the opinion of the Attorney General on the issue
raised by RGPPL that since work at Mus Nicobar had been awarded to EHL could
it be said that RDS had executed the work as, it was only a sub-contractor, and
therefore did it come within the ambit of the expression "single bidder". The
Attorney General, however, to the misfortune of RGPPL as it would appear,
clearly opined that RDS was eligible and fell within the meaning of the expression
„single bidder‟. The rationale broadly given was that even though qualifying work
had been awarded to EHL, it did not have the necessary wherewithal, the work
having been executed by RDS, it could not be said that it was sub-contractor. It
may, however, be pertinent to emphasis the fact that the query put to the learned
Attorney General was restricted to whether RDS could be considered a sub-
contractor in view of the fact that the works had been awarded by the Government
of India to EHL.
28.1 The point to be taken note of is, that even though opinion of the learned
Attorney General was sought on 08.06.2010 when the CAG report of 2002/or at
least letter dated 05.06.2010 issued Deputy Chief Engineer-IV, Andaman Harbour
Works was available, no query was raised about the eligibility of RDS in the
context of the fact that the qualifying work had been executed at Mus Car Nicobar
Island in two (2) phases under two (2) contracts. The query to the learned AG was
confined to whether RDS fit the bill of a „single bidder‟.
29. RGPPL even at this stage did not let the matter lie. It evidently collected
material through the RTI route by making an application in that regard with the
Andaman Harbour Works. The information obtained was transmitted to GAIL,
under the cover of its letter dated 26.06.2010. EIL once again was called upon to
give its recommendation. EIL, by an email dated 11.08.2010, after a critical
review, came to the conclusion that, the mere fact that the qualifying work at Mus
Car Nicobar Island had been carried out in two (2) phases, it could not be said that
RDS was not a single bidder. EIL stuck to its decision that no revision in the
award recommendation was necessitated at this stage. Then of course, came the
internal meeting of EIL - as to when it was held is not disclosed in the additional
affidavit filed. The affidavit does not advert to the fact as to who all participated
in this internal meeting. At the internal meeting, the matter was evidently referred
to the legal department of EIL. The legal department gave an opinion on
26.08.2010, stating therein that principle of strict construction had to be applied to
the contract documents, and on application of the said principle it had to be
concluded that RDS had not fulfilled the BQC requirement stipulated in the
tender, (i.e. the 1st tender), however, "harsh" or "absurd" such conclusion may be.
It was submitted before us that this opinion became the edifice for the change of
view that the EIL took on 01.9.2010. We may note at the outset that the opinion is
completely converse to the stand taken by the EIL up to 11.08.2010. It is pertinent
to note (a fact we were told in the hearing) that the said legal opinion bears the
endorsement of Mr.Grover, Director (Projects) calling upon Mr.R.K.Bhandari,
General Manager (Project), EIL to simply comply with the view taken by the legal
department. As noticed here in above by us, Mr.R.K.Bhandari was the same
gentleman, who on 10.06.2010 had opined that no revision in the award
recommendation in favour of RDS was called for. The crucial question which
arises, is that, was Mr.R.K.Bhandari given a chance to express his view on the
opinion rendered by the legal department. This is a pertinent aspect of matter to
our minds since Mr.R.K.Bhandari, followed by Mr. Ravi Saxena, in EIL and,
Mr.M.B.Gohil in GAIL, were people who would have dealt with such like contract
on a number of occasions. Being experts in their respective fields, they would
know what was intended when terms like "single project" and "single bidder"
were put in Clause 8.1.1.1. Therefore, for the legal department of EIL to take a
contrary, though "absurd" and "harsh" view, required at least a modicum of
response from the expert, which was none other than Mr.R.K.Bhandari dealing
with the issue till 10.06.2010. Mr.Grover Director (Projects) did not deem it fit to
even ask for his comments. Therefore, the integrity of entire process is suspect to
say the least. In any event, in our view, the opinion is completely contrary to the
plain language of clause 8.1.1.1. At this juncture we may note the relevant
provisions of clause 8.1.1.1 as they obtained in the 1st tender:
"8.1.1.1 The bidder shall have experience of having successfully completed, as a single bidder or as a leader of a Consortium/Joint Venture, at least one project of a breakwater in an offshore location (as defined at clause No. 8.1.2.5 below) of minimum length of 400 m during the last 20 (twenty) years to be reckoned from the last date of submission of bids. The scope of work of the proposed qualifying project work should comprise of the design, engineering, project management and construction of the breakwater."
30. A perusal of the clause would show that a bidder, would have to have
experience of having successfully completed as a single bidder or as a leader of a
consortium at least one project of breakwater of a minimum length of 400 metre
located in an off shore location, during the last twenty (20) years to be reckoned
from the last date of submission of bids. Plain language of the said clause would
show that a project could be executed in different phases. The ordinary meaning
of the word „project‟ would be "planned undertaking or scheme" (See The
Conscise Oxford Dictionary Ninth Edition, 1995). Therefore, the fact that the
qualifying project at Mus Car Nicobar Island was executed by RDS in two (2)
phases could not have ousted it. In understanding the meaning of the words and
expression used in a contract, courts would ordinarily go by the meaning given to
the words by those who administer and operate the contract, unless that meaning is
completely at variance with the understanding of a common prudent person. Both
the experts, who dealt with the evaluation of the bids, i.e., GAIL and EIL, despite
receipt of material in the form of CAG report and the Deputy Chief Engineer-IV,
Andaman Harbour Works letter, which indicated that qualifying contract had been
executed in two (2) phases, came to the conclusion that RDS was eligible and,
therefore, the award recommendation did not require a review. We fail to
understand how the legal department could take a view, on this matter, contrary to
what the persons, who operate these contracts, understood the expression to mean.
In a construction of commercial contract (if one were to assume for a moment that
construction of contract was required to ascertain the intention of parties), the
accepted rule is that if semantic and syntactical construction is at variance with the
business common sense, then it must yield to business common sense. The
observations in Antaios Cia. Naviera S.A. v. Salen Rederierna A.B. (1985) A.C.
191 been apposite are extracted below:
"While deprecating the extension of the use of the expression „purposive construction‟ from the interpretation of statutes to the interpretation of private contracts, I agree with the passage I have cited from the arbitrators‟ award and I take this opportunity of restating that, if a detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business common sense, it must be made to yield to business common sense."
30.1 The purpose of construction has been described felicitously by Lloyd L.J.
in The Sounion (1987) 1 Lloyd‟s Re. 230 as follows: "Designed to separate the
purposive sheep from the literalist goats."
30.2 We may note at this stage that we had pointedly put to the ASG Ms.Indra
Jai Singh during the course of hearing, as to whether there was any doubt or
dispute that RDS had not executed the qualifying work at Mus Car Nicobar Island
equivalent to the contracted length of 500 metres. Ms.Indra Jai Singh, on
instructions, categorically informed us that this aspect of the matter was not in
issue. She, however, submitted that what was in issue, was the fact, that since it
had now emerged that RDS had completed the project in two (2) phases;
according to EIL, it was not eligible. With EIL having taken this stand, which was
not contradicted by GAIL at the hearing; it quite surprised us when, Mr.Chandhiok
appearing on behalf of RGPPL took the stand that RDS had not even constructed
the required minimum 400 metres length of the qualifying work. We may also
point out at this stage the stand of the UOI in its affidavit. UOI has categorically
supported its certificate dated 05.04.2008 and the clarification issued on
05.06.2010 by the Deputy Chief Engineer-IV, Andaman Harbour Works.
Therefore, this argument of RGPPL cannot be accepted.
31. The submission made on behalf of the respondents, in one form or the
other, that there had been a misrepresentation by RDS, in as much as, in the bid
document it had disclosed that the qualifying work had commenced in 2000 and
was completed in 2003, was put by us to Mr Dhankar. Mr Dhankar informed us
that the RDS somehow misconstrued the information sought in the bid document.
On being queried as to why RDS had withheld the work order, Mr Dhankar
submitted that since most of the records of the Andaman Harbour Works had got
swept in the tsunami of the December, 2004, it had become difficult to recoup the
work order. Mr Dhankar submitted that, nevertheless, the said information was
available with the respondents by July, 2010 and, therefore, they had every
opportunity to examine the effect of the same prior to issuance of recommendation
dated 11.08.2010.
32. Having examined the matter closely, we got a distinct impression that
RGPPL was somehow attempting to find a way around the recommendation
issued by GAIL and EIL. Even though the information given against the query no.
6 of the bid document filed by RDS was not completely accurate, it did appear to
us that RGPPL had with it the information that the qualifying work at Mus Car
Nicobar Island had commenced in 1995 and that it was awarded in two (2) phases,
under two (2) separate contracts. This distinct impression we get as the
information with regard to the fact that the qualifying work had been executed in
two (2) phases was available in the CAG report of 2/2002. Some part of the
information was also available on the website of the Andaman Harbour Works.
Therefore, whether the information given against query no. 6 in the tender
documents actually misled RGPPL is, in the facts and circumstances obtaining in
the case, difficult to believe. Notwithstanding this, the said information lost its
materiality in view of the fact that, the said information was sought to be used by
RGPPL only to say that RDS was not eligible as the qualifying work had been
executed in two (2) phases. The aspect pertaining to the time taken in the
execution of the qualifying the work; was a factor which did not even figure in the
mind of the Evaluator i.e., EIL on 01.09.2010; though Mr.Banerjee true to his craft
had attempted to make this an issue. The fact remains, that despite this
information being available, on review and examination at length, both GAIL and
EIL came to the conclusion that their initial recommendation of 08.03.2010 did
not require a revision. Therefore, for the EIL to have turned turtle, so to say, on
01.09.2010, based on a legal opinion generated by its legal department, belies
credibility to say the least. What is interesting, is that, even though GAIL, up to a
point took the stand that in respect of all recommendations qua award of contract
for DPP; RGPPL would have to rely upon on it - it collapsed under the weight of
RGPPL or perhaps threw up its hands in complete frustration, as it appears after
11.08.2010. This is evident from the fact that after the EIL‟s u-turn on
01.09.2010, GAIL refused to give its own view in the matter, which it was
required to do under the terms and conditions of the tender. RGPPL sought its
recommendation by its letter dated 20.09.2010, despite which, GAIL refused to do
so, as is evident from its return communication dated 22.09.2010, wherein it called
upon RGPPL to take the decision in its capacity as the owner in view of the fact
that the entire material was available with it. We have no doubt in our minds that
in this background, the decision taken at the Board of Directors‟ meeting of
RGPPL on 04.10.2010 was pregnant with malice, and that it had been taken for
considerations other than those which are in accord with good conscious, equity
and fairness. The new clause (which is the amended version of clause 8.1.1.1
obtaining in the 1st tender) was undoubtedly introduced in the fresh tender, (i.e.,
the 2nd tender), to completely oust RDS. For the sake of convenience the amended
clause is extracted hereinbelow:
"8.1.1.1 The bidder must have completed in a single contract, as a single bidder or as a leader of a consortium, at least one breakwater (using marine spread - refer Note 1) of minimum length of 400 m located in sea during the last 20 (twenty) years to be reckoned from the last date of submission of bids. The scope of work of the above referred qualifying job should comprise of design, engineering, construction and project management of the breakwater. Land connected breakwater having a minimum length of 400m located in sea is also acceptable provided construction has been carried out using marine spread as mentioned above."
33. A bare perusal would show that the respondents have called for bids only
for those bidders who have completed in a single contract as a single bidder or as a
leader of a consortium/ joint venture one project of a breakwater, located in sea, of
minimum length of 400 metre during the last twenty (20) years to be reckoned
from the last date of submission of bids. At the end of this amended clause, there
is also the insertion of the following provision "...Land connected breakwater
having a minimum length of 400 metre located in sea is also acceptable provided
construction has been carried out using marine spread...".
33.1 The respondents know-fully well that RDS can never apply or be found
eligible in respect of the 2nd tender as: the qualifying work which RDS had
executed, is a subject matter of two (2) contracts and not a single contract; and that
project was an offshore project as against one located in sea. The additional
provision of a land connected breakwater which was not an option available in the
1st tender is, according to RDS, deliberately inserted to accommodate bidders who
missed the bus, so to speak, in the first round. Since there is no material in respect
of the last part, we are not impressed by the same but it is definitely apparent to us
that the words „single contract‟ as also that the „qualifying work should be
located in sea‟, have been introduced in the facts and circumstances of the case to
exclude RDS. This is a clear case of malice in law which occurs when a person
or an entity commits a wrongful act intentionally without just cause or reason.
The following observations of Viscount Haldane in Shearer vs Shield (1914) AC
808 have been cited with approval in West Bengal State Electricity Board vs
Dilip Kumar Ray (2007) 14 SCC 568, para 19 at page 582:
"... „A person who inflicts an injury upon another person in contravention of the law is not allowed to say that he did so with an innocent mind; he is taken to know the law, and he must act within the law. He may, therefore, be guilty of malice in law, although, so far the state of his mind is concerned, he acts ignorantly, and in that sense innocently.‟"
33.2 It is quite apparent that RGPPL exercised its power solely with the object
of achieving a pre-meditated object to the detriment of the aggrieved party, i.e.,
the RDS. The action of RGPPL was thus geared to achieve an "authorized
purpose" which in our view could be construed as malice in law [see R.S. Garg vs
State of U.P & Ors. (2006) 6 SCC 430, para 25 at page 448]. That malice in law
is an incident or "dimension" of fair play in action; is now well established [see
Mahabir Auto Stores & Ors. vs Indian Oil Corporation & Ors. (1990) 3 SCC
752, para 13 at page 761 ].
34. Mr Chandhiok‟s submission that RDS could not lay a challenge to the
decision of the Board of Directors of RGPPL dated 04.10.2010 based on a fact that
RDS had withdrawn its writ petition [WP(C) 8252/2010] without liberty to file a
fresh writ petition is, according to us, completely misconceived and untenable.
The reason for that is simply the fact that the court did not adjudicate upon the
issues raised in the said writ petition. It would be important to note that prior to
the said writ petition being filed by RDS, one Ranjit Buildcon Ltd. had filed a
writ petition no. 2142/2010, in which, RGPPL had filed an application, wherein
broadly, it had been averred that the RDS had been declared ineligible in respect
of the 1st tender for its failure to meet the qualifying criteria. The said writ petition
of Ranjit Buildcon Ltd. was dismissed as withdrawn. RDS was impleaded as a
respondent in this writ petition.
34.1 RDS could have said very little in the matter, the petition being of Ranjit
Buildcon Ltd.. It is for this reason perhaps, that RDS instituted a separate and
independent writ petition being no. 8252/2010 seeking to challenge essentially the
decision of the board of directors of RGPPL dated 04.10.2010. When it was put
to the learned counsel for RDS that nothing would survive since the tender by
itself had been cancelled by RGPPL in exercise of its powers under Article 28.1 of
the said tender, it withdrew the writ petition with the caveat that if a fresh tender is
floated by RGPPL, it ought to have liberty to have recourse to an appropriate legal
remedy, in accordance with law, to challenge such a tender if it sought to exclude
the RDS. Said liberty was granted by the court in the order dated 14.12.2010.
34.2 In view of these factors it could hardly be contended by RGPPL that while
seeking to challenge the amended clause 8.1.1.1 (now inserted in the 2nd tender)
that RDS could not demonstrate that the decision arrived at by RGPPL‟s board of
directors on 04.10.2010 is fraught with malice in law and was otherwise contrary
to the principles of fairness, equity and good conscience. The submissions of Mr
Chandhiok on this count, in our view, are also without merit.
35. Given the aforesaid, in our view, we have no hesitation in moulding prayer
(A) in the writ petition and declaring that the amended clause 8.1.1.1 (inserted in
the 2nd tender) in the given facts and circumstances of this case is bad in law.
Similarly, for the reasons given above, we quash the decision taken by the RGPPL
in its board of directors‟ meeting held on 04.10.2010, whereby the bid of RDS in
the 1st tender was rejected and the bidding process in the 1st tender was annulled.
This would really mean that RGPPL would have to revisit the issue in the light of
observations made by us hereinabove. It would, while doing so, bear in mind the
fact that the GAIL has not given its opinion in the matter - which it is required to
render, given the fact that it is the owner‟s engineer.
36. This brings us to the last relief sought in the writ petition seeking a
direction against RGPPL to formalize award of contract in favour of RDS in
respect of DPP. We are afraid that we cannot grant this relief for the reason that
over the years the courts have demarcated certain boundaries for itself which
includes not issuing directions to the States and its instrumentalities to award
contracts in favour of one or the other party, however, aggrieved that party may
be. It appears to us this may at times seem frustrating to a litigant. At the end of
day the litigant wants, and rightly so, the fruits of litigation. It is no relief to the
petitioner to get, in a manner of speaking, a certificate from the court that the
actions of the respondents are illegal or invalid in law, but then being told that an
appropriate direction to do justice in the matter would flow finally from the
respondent state. It appears to us the reason and the rationale for this is that the
State and its instrumentalities at the end of the day, it is believed have the interest
of the republic in mind. It is believed that having erred, once the State would
correct its course. The State or its instrumentalities cannot but act in the interest
of the republic. Whether they do so or not is ordinarily left to those who govern
them. We say no more but leave it to the conscious of the superior officers and the
members of the Board of Directors‟ of the respondents, i.e., RGPPL, GAIL and
EIL to take a decision in accordance with fairness, equity and justice keeping the
interest of the State in mind. While taking the said decision, it would be wise to
revisit the entire issue including the fact that the RDS has offered a price which is
Rs 160 crores less than that of Afcons Infrastructure (i.e., L-2); and that despite
queries being raised that this was below the estimated cost of Rs 662 crores, both
experts in the field had granted its approval to the bid of RDS.
37. Before we part, we may also observe that we had directed both parties to
file their respective bill of cost. The bill of costs filed on behalf of the RDS
suggests that they have incurred on counsels‟ fee a sum of Rs.33,22,000/-. Since
RDS has succeeded to a large extent, we direct payment of 3/4th of the costs in its
favour. The three respondents, i.e., RGPPL, GAIL and EIL shall pay a sum of
Rs.24,91,500/- to RDS by way of cost in equal proportion. With the aforesaid
observations the petition is disposed of.
RAJIV SHAKDHER, J
SANJAY KISHAN KAUL,J OCTOBER 17, 2011 kk/yg
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!