Citation : 2009 Latest Caselaw 2298 Del
Judgement Date : 28 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ LPA No. 182 OF 2009 & CM Nos.5894/2009 &
5897/2009
BASANT BAGDE ..... Appellant
Through: Dr.A.M. Singhvi, Sr. Advocate with
Mr. Amit Anand Tiwari, Mr. Vivek Singh and
Mr. Amit Bhandari, Advocates.
versus
M/S HINDUSTAN PREFAB LTD. ..... Respondent
Through: Mr. Manoj Sharma, Advocate.
CORAM:
HON'BLE THE CHIEF JUSTICE
HON'BLE MR. JUSTICE NEERAJ KISHAN KAUL
ORDER
% 28.05.2009
1. The present appeal arises out of the order of the learned single
Judge dated 19th March, 2009. Briefly, stated the facts of the case
are; the respondent No.1 issued notice on 20th March, 2008 inviting
sealed tenders for construction of houses with infrastructure in
Raipur city. Under clause 5 of the Special Conditions of Contract,
the tenderer was required to quote rates on percentage basis
below/at par/above the SOR of 1999. On 1st April, 2008, the
competent authority amended the SOR of 1999 and increased the
rate of item No.8 of Chapter 4 (steel) from Rs.24 per kg. to Rs.50 per
kg. As per the appellant( the original petitioner in the writ petition),
the tender document stated that the bid was to be made on
percentage basis of SOR of 1999 and its amendments are applicable
for such tenders and, therefore, once an amendment of a scheduled
item is made ipso facto same would apply to the tender in question.
2. On 3rd April, 2008 the petitioner submitted its tender on
percentage rate basis of SOR of 1999 after taking into account the
amended rates. The respondent No.1 entered into an agreement with
the appellant at Delhi awarding 5 packages to the appellant.
Pursuant to the award of the said contract the appellant commenced
work. The appellant submitted its running account bill for the work
executed on 18th September, 2008 to respondent no.1. In the said
bill the appellant while calculating the rate of steel took into account
the rate of steel as amended on 1st April, 2008 by the competent
authority. The respondent No.1 vide its letter dated 18th September,
2008 refused to calculate the bill on the basis of the revised rates of
steel on the ground that though the Engineer-in-Chief, Public Works
Department, Chhattisgarh has left the decision to respondent no.1
HPL with respect to implementation of the said revised rates, the
same had not been done by HPL till date. Accordingly, as per the
petitioner, it was left with no alternative but to file the writ petition
out of which the present appeal arises.
3. By our order dated 21st May, 2009, State of Chattisgarh was
impleaded as respondent. Notice was issued and served on the State
of Chattisgarh. However, no one appeared on behalf of the State of
Chattisgarh today.
4. The learned single Judge dismissed the writ petition of the
appellant on the ground of alternative remedy as also on the ground
that this High Court have no territorial jurisdiction. The learned
single Judge while dismissing the writ petition imposed a cost of Rs.
50,000/- on the appellant.
5. The senior counsel for the appellant has drawn our attention to
letter dated 1st April, 2008 (page 38 of the paper book) issued by the
Public Works Department, Raipur whereby the rates were increased
from Rs.24/- to Rs.50/- per kg. The learned senior counsel then
drew our attention to letter dated 2nd September, 2008 written by
respondent No.1 to the Public Works Department, Chattisgarh,
Raipur whereby respondent No.1 sought directions as to whether rate
should be fixed at Rs.50/- per kg. according to the amendment order
or at Rs.24/- per kg. The learned senior counsel also relied on the
letter dated 10th September, 2008 (page 64 of the paper book)
wherein the Public Works Department, Chattisgarh, Raipur
categorically stated that the rate had been increased from Rs.24/- to
Rs. 50/- per kg. and directed respondent No.1 to take a decision at
its level in respect of bills as per the contract. Our attention was also
drawn to letter dated 18th September, 2008 (page 44 of the paper
book) written by respondent No.1 wherein the respondent No.1 had
stated that the Public Works Department, Chattisgarh, Raipur had
directed that the appropriate decision be taken by respondent No.1.
However, no decision had been taken by respondent No.1 on the said
issue.
6. In view of the categorical stand of the respondent no.1 that
they had been directed by the Public Works Department, Chattisgarh
to take a decision in the matter, we fail to understand as to why the
said decision has not yet been taken by them. We, accordingly,
deem it fit to direct respondent No.1 to take a decision in the said
matter within a period of two weeks. We may also add here that we
are unable to agree with the view of the learned single Judge that this
Court does not have any territorial jurisdiction to entertain the
matter. It is pertinent to mention that the entire tender process took
place in Delhi, the work order was issued from Delhi, all securities
and EMDs were deposited at Delhi by the appellant, agreement was
entered between the parties at Delhi and bills were made from Delhi.
As per clause 5 of the agreement, dispute between the parties was
subject to jurisdiction of the Delhi courts. Thus, clearly part of the
cause of action had arisen in Delhi and this High Court does have the
territorial jurisdiction to entertain the writ petition. We also do not
agree with the finding of the learned single Judge that being a
contractual matter the appellant could not invoke the writ
jurisdiction. It is well settled that even in contractual matters if the
action of the State and its instrumentalities is arbitrary,
unreasonable and illegal, the Court can exercise its extraordinary
jurisdiction under Article 226 of the Constitution of India. In A.B.
International Ltd. Vs. Export Credit Guarantee Corpn. Of India
Ltd.,(2004) 3 SCC 553 the Supreme Court observed that the
question whether a writ petition under Article 226 of the Constitution
of India is maintainable to enforce a contractual obligation of the
State or its instrumentality, by an aggrieved party is no more res
integra and is settled by a large number of judicial pronouncements
of the Supreme Court. On a given set of facts if 'the State' acts in an
arbitrary manner even in a matter of contract, an aggrieved party can
approach the court by way of writ under Article 226 of the
Constitution and the court depending on facts of the said case is
empowered to grant the relief. In the present case there has been an
amendment to the rates on the basis of which the appellant has
raised its demand. No decision has been taken on the bills raised by
the appellant as per the revised rates. This indecision and inaction
clearly is unacceptable and unreasonable. We have, accordingly,
directed respondent No.1 which had floated the tender enquiry on
behalf of the State of Chattisgarh to take a decision within a period of
two weeks. It will be open to the appellant to take appropriate
remedies in accordance with law in case it is aggrieved by the
decision of the respondent no.1. With these observations, the
present appeal as also the writ petition stand disposed of as nothing
further survives in the same.
7. We also deem it fit and proper, in the light of our above
discussion, to waive the costs imposed on the appellant by the
learned single Judge. It is ordered accordingly.
CHIEF JUSTICE
NEERAJ KISHAN KAUL, J.
MAY 28, 2009 RS
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!