Citation : 2009 Latest Caselaw 2066 Del
Judgement Date : 15 May, 2009
* IN THE HIGH COURT OF DELHI AT NEW DELHI
+ Date of Decision: 15.05.2009
% CS(OS) 1220A/2005 & I.A. No.9532/2005
AMAR NATH MEHRA & CO. ..... Plaintiff
Through: Mr. B.K. Dewan and Mr. Bhavesh
Kumar Sharma, Advocate
versus
UNION OF INDIA ..... Defendant
Through: Mr. R.C. Nangia, Advocate
CORAM:
HON'BLE MR. JUSTICE VIPIN SANGHI
1. Whether the Reporters of local papers may No
be allowed to see the judgment?
2. To be referred to Reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
VIPIN SANGHI, J. (Oral)
1. These are objections to the award made by the learned sole
arbitrator Mr. S.C. Jain dated 16.08.2005, preferred by the respondent,
Union of India, under Sections 30 & 33 of the Arbitration Act, 1940.
The petitioner had entered into an agreement with the respondent to
provide portage service to the respondent. Disputes arose out of the
said contract, which were referred to arbitration of Mr. S.C. Jain by
order dated 02.09.2004 passed in CS(OS) 1378A/1984. The learned
arbitrator has made an award in the sum of Rs.1,57,010/- in favour of
the petitioner/claimant, which is now under challenge. The
proceedings and the award are governed by the Arbitration Act, 1940.
2. The respondent/ objector has raised general grounds of
challenge to the award which need no mention. Specific challenge has
been raised in respect of claim Nos.1, 5, 8 to 11, 13, 16 & 17.
3. So far as the claim No.1 is concerned, the same had been
made for refund of Rs.88,803.71, which was stated to have been
wrongfully and unjustifiably recovered from the dues of the claim. The
respondent, Union of India, had sought to justify the deduction on
account of employment of departmental labour and bazaar labour to
the tune of Rs.83,599.09 due to the failure of the petitioner/claimant to
provide enough labour to do the work. Ex.1-G has been referred to by
the arbitrator in his award and, therefore, can be looked into by the
Court. Ex.1-G is a communication dated 12.11.1974 sent by the
Divisional Superintendent, New Delhi to the AAO (TA) Northern
Railway, Jalandhar City, which encloses a statement showing
particulars of engineering departmental as well as bazaar labour
utilized on behalf of the petitioner during their entire contact period.
Along with the said communication the tabulation showing the
engagement of bazaar labour as well as engineering departmental
labour has been enclosed. The learned arbitrator also takes note of
Ex.1-N dated 03.12.1974, which is a communication sent by the
Divisional Superintendent, New Delhi to the petitioner claimant. This
communication gives details of the bazaar labour and departmental
engaged on behalf of the petitioner during the period May, 1974 to 15th
August, 1974. The credit given to the petitioner, as per Ex.1-N, works
out to Rs.15,944.16. On the basis of these two documents, learned
arbitrator has concluded that the respondent has not been able to
justify the recovery of any amount beyond Rs.15,944.16. The
arbitrator has found that the actually deducted amount was
Rs.89,836.30. He has, therefore, awarded refund of amount of
Rs.73,892/- in favour of the petitioner/claimant. Learned counsel for
the objector, Mr. R.C. Nangia, has sought to read and rely upon
Annexures R-3 to R-7 filed along with the objection petition to say that
the claimant/petitioner was repeatedly put to notice about short supply
of labour. Firstly, it is not open to the Court to look into documents not
referred to in the award. Secondly, these documents, in any event, do
not throw light on the quantum of labour engaged by the respondent
on the petitioner's account. In my view, no error can be found in the
award of claim No.1. The objection is, therefore, rejected.
4. The next objection has been raised in respect of award on
claim No.5. This claim had been made of Rs.13,227.90 on the ground
that the same had been wrongfully and unjustifiably withheld as
demurrage charges. Mr. Nangia, counsel for the respondent/objector
has again sought to rely on various documents to show that the
petitioner/ claimant had been put to notice regarding supply of short
labour i.e. Annexures R-3 to R-7. He also relies on clause No.10 of the
contract which permits the levy of demurrage on the contractor on
account of his failure to provide sufficient labour, which causes delay in
the process of loading and unloading of the wagons.
5. I find no merit in the objection raised by the respondent. A
perusal of the reply given in response to claim No.5 before the
arbitrator shows that the reply is totally vague and devoid of any
particulars. Learned arbitrator has found that the respondent has not
shown any calculation to arrive at the amount deducted towards
demurrage. Even if the respondent was entitled to claim demurrage
for the alleged short supply of labour by the petitioner/claimant, it was
for the respondent to justify the computation of the amount of
demurrage levied upon the petitioner, which had not been done. No
error can be found in the award made on claim No.5. The objection is
rejected.
6. So far as the award on claim No.8 is concerned, it had been
made for Rs.18,000/- for payment of less rates for loose goods at the
rate of Rs.21/- per wagon as against the petitioner's claim of Rs.80/-
per wagon. Claim No.9d had been made for Rs.9,000/- for labour
employed in transshipment of meter gauge wagon to box wagon. The
award is not reasoned and it is not permissible for the Court to go
behind the award. Moreover, in response to the reliance placed on
Note 12 to the agreement which relates to rates for "special goods", by
learned counsel for the respondent/objector, the petitioner has placed
reliance upon Appendix A Entry 2(i) of the contract, which contains the
rates applicable to "loose goods". Award on claim No.8 shows that it
pertains to "loose goods" and therefore, there is no merit in the
submission of the respondent. The objection to award on claim No.8 is
rejected. Similarly, the award on claim No.9 cannot be questioned as
the respondent has not established that the work of transshipment
from meter gauge wagon to box wagon was covered within the scope
of the petitioner's contractual obligation. It is not for the Court to
interpret the agreement. As aforesaid, the award is unreasoned and
the Court cannot examine the basis on which the award has been
made in these circumstances. The objections are rejected.
7. The objection to the award on claim No.10, which were made
for supply of labour for loading coal sweeping in wagons, for supply of
coal to Loco Shed and also for carrying by head load for feeding the
crane for over 800 yds., is without any reason and it is not open to the
Court to go into the mind of the arbitrator and examine the basis on
which the award has been made. Similarly, the objection to the award
on claim no.11 for payment of goods dumped on the ground and
loaded after 24 hours (mid night) is claimed as a fresh operation under
Clause 4 (iii) of the agreement, is also unreasoned and the same does
not disclose any error on the fact of it. I may also note that in
response to claim Nos.10 & 11, in the reply before the arbitrator, the
only response of the respondent was that payment had been made in
accordance with the contract.
8. The position with regard to the award on claim No.13 is also
the same. The award is unreasoned. The said claim had been made
for Rs.8,000/- on account of wagon being declared damaged by TXR for
load adjustment after loading as it required further labour. Since no
reasons have been given, it is not possible for the Court to go behind
the award. The objection to claim No.13 is, therefore, rejected.
9. The award on claim No.16 was made on account of failure of
the respondent to make payment of the claimant's bills. The learned
arbitrator has awarded an amount of Rs.6,000/-, as opposed to the
claim of Rs.25,000/- made by the claimant/petitioner. The arbitrator
has recorded that he has gone into the record. He has, in fact, granted
a reduced amount by taking note of the usual delays involved in
making payment by the Railways, which is a government department.
I see no reason to interfere with the award made on claim No.16.
10. Under claim No.17 the learned arbitrator has awarded interest
@ 12% per annum from 21.11.1981 i.e. the date of invocation of
arbitration till payment. Considering the fact that the award pertains
to the period 1973-74, as also the fact that the arbitration had been
invoked in the year 1981 when the rates of inflation/interest were
considerably high, I find no justification to interfere with the award of
the arbitrator on the aspect of the interest. Accordingly, the award is
made `Rule' of the Court. The petitioner shall also be entitled to
further interest @ 9% per annum from the date hereof on the principal
amount of Rs.1,51,010/- till payment. The petitioner shall also be
entitled to costs quantified at Rs.10,000/-.
VIPIN SANGHI, J.
MAY 15, 2009 rsk
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!