Citation : 2008 Latest Caselaw 1796 Del
Judgement Date : 3 October, 2008
*IN THE HIGH COURT OF DELHI AT NEW DELHI
+ OMP No. 367/2002
% Date of decision : 03.10.2008
UNION OF INDIA & ANR ....... Petitioners
Through: Mr. A.K. Bhardwaj with Ms Jagrati
Singh, Advocates
Versus
M/S SAMRAT PRESS ....... Respondent
Through: Mr Shiv Khorana, Advocate.
CORAM :-
HON'BLE MR. JUSTICE RAJIV SAHAI ENDLAW
1. Whether reporters of Local papers may
be allowed to see the judgment? No
2. To be referred to the reporter or not? No
3. Whether the judgment should be reported No
in the Digest?
RAJIV SAHAI ENDLAW, J.
1. Objections under Section 34 of the Arbitration and Conciliation
Act, 1996 have been preferred by the petitioner Union of India to the
award dated 27th June, 2002 as corrected on 10th October, 2002 of
Shri B.L. Nishad, Joint Secretary and Legal Advisor, Ministry of Law,
Justice and Company Affairs acting as the sole arbitrator.
2. The respondent was awarded the contract for one year from 9 th
May, 1993 for printing of Sainik Samachar Weekly Magazine. The
said contract was extended for one year on 23rd November, 1994 and
thereafter on 31st March, 1995 till 31st May, 1996. Disputes and
differences having arisen between the parties, the respondent
invoked the arbitration clause and Mr. B.L. Nishad aforesaid was
appointed as the sole arbitrator by the competent authority in the
Department of Legal Affairs vide order dated 21st September, 2001
and formal order for his appointment as sole arbitrator was issued by
the Secretary to the Government of India vide letter darted 3rd
October, 2001.
3. The respondent/claimant preferred claims under ten heads out
of which claim No.1 has been allowed, claim No.2 of interest has
been allowed at a rate lower than claimed by the respondent, claims
No.3 and 7 have been partly allowed. Claims No. 4 to 6 and 8 to 10
of the respondent were dismissed by the arbitrator. The respondent
has not preferred any objection against such dismissal and the
dismissal thereof has attained finality. The petitioner had also made
a counter claim for costs of proceedings which has also been
dismissed by the arbitrator and no objections have been preferred by
the petitioner with respect to the same and that has also attained
finality.
4. The petitioner has preferred objections against the claims
allowed and has also raised objections (i) that as per the agreement,
the arbitration was to be of the Director of Public Relations, Ministry
of Defence and the arbitration proceedings are thus vitiated; (ii) that
the award on the preliminary issues raised by the petitioner before
the arbitrator is without any reason whatsoever.
5. The objection that the arbitration proceedings are vitiated or
the award liable to be set aside for the reason of the arbitrator being
not as per the agreement between the parties is now no longer res
integra. The Division Bench of this Court in S.N. Malhotra & Sons
v Airport Authority of India (2008) IV AD (Delhi) 424 has held that
where the objection to the jurisdiction of the arbitrator as contained
in Section 16 is not raised before the arbitrator, a party is not
permitted to raise the same for the first time under Section 34. In
the present case no such objection was raised before the arbitrator
and it is now not permissible for the petitioner to raise the ground of
the arbitral tribunal being not in accordance with the agreement.
6. Even otherwise I find that the respondent applied to the
petitioner for the appointment of the arbitrator. It was open to the
petitioner to, at that time, appoint the Director, Public Relation as
the arbitrator. The petitioner did not do so and appointed its Joint
Secretary aforesaid as the arbitrator. The respondent made a claim
before the said arbitrator and the petitioner filed the reply and
participated in the arbitration proceedings without in any way
disputing the existence of the agreement for arbitration before that
forum. The respondent made the statement of claim before the
arbitrator and the petitioner by not controverting the jurisdiction of
arbitrator before whom claim was made, agreed to arbitration before
him, within the meaning of Section 7 of the Act. This objection of the
petitioner has no merit and is rejected.
7. The second objection is that the arbitrator did not record the
reasons for decision on the preliminary objections. A perusal of the
award shows that three preliminary objections were raised by the
petitioner before the arbitrator, i.e., of the claim being barred by
time; of the respondent being not registered under the partnership
Act and of the respondent having discussed and finalized its claims
in the meeting dated 6th November, 1997 and being not entitled to
make any other claim.
8. The arbitrator has, with respect to the preliminary objections
of limitation, held that the respondent/claimant demanded
arbitration on 21st February, 1997 and under Section 21 of the Act,
the arbitration commences on the date when the request as made by
the claimant is received by the respondent; that the petitioner herein
had released the security of the respondent only in May, 1998 and
thereafter the claim of the respondent having not been finalized the
claims are within limitation. Thus, it cannot be said that the
arbitrator has not given any reason for rejecting the preliminary
objection of the petitioner of limitation. It is significant that the
objection of the petitioner is not to the said reasoning being not in
accordance with law but only that no reason was given. The said
objection is not found to be correct. Even otherwise I have vis-à-vis
the claims of the respondent allowed by the arbitrator examined the
matter and do not find the reasoning given by the arbitrator on the
aspect of limitation to the contrary to law.
9. On the second preliminary objection of the petitioner of the
respondent being not entitled to the claim for the reason of being not
registered under the Partnership Act, the arbitrator has dismissed
the same holding that the respondent has produced the evidence by
filing the claims at serials No. 1 and 2 of its list of documents. Again,
the objection of the petitioner before this court of there being no
reasoning is found to be incorrect. The arbitral record was called for
before this court and I have perused the same and there is indeed on
record a list of documents having at serials No 1 and 2 thereof the
photocopies of the certificate of registration and of Form A under the
rules framed under the Partnership Act. Thus, the reasoning given
by the arbitrator for rejecting the second preliminary submission is
also not fallacious. The third preliminary objection of the petitioner
has also been dealt with by the arbitrator and dismissed with
reasoning. The arbitrator has found that the respondent in the
meeting held on 6th November, 1997 had not waived any of its
claims. The arbitrator has further reasoned that the respondent had
nowhere written down or recorded that besides the claims discussed
in the said meeting, it had no other claims. The arbitrator has
further reasoned that the respondent had in contemporaneous
correspondence, after the meeting dated 6th November, 1997,
requested for a decision on the balance pending issues also. Again
not only the third preliminary objection is disposed with reasons
which have not been challenged but the said reasons are plausible.
This court recently in Ircon International Limited
v Shri Krishna Trading Co. & Anr 2007(4) ARB LR 479 (Delhi) has
reviewed the legal position with respect to full and final settlement
and I do not find the award to be contrary thereto.
10. The next objection is to the claim No.1 of the respondent being
allowed by the arbitrator. The said claim was of Rs 8,01,299/- for
payment of the amounts illegally deducted by the petitioner from the
bills of the respondent. The same comprised of Rs 1,28,371/-
(wrongly recorded as 4,28,370/- in the award and subsequently
corrected as aforesaid) deducted during the year 1993-94 and the
sum of Rs 6,72,928/- deducted during the year 1995-96.
11. It was contended in the objection/petition that no such dispute
was referred to the arbitrator and subsequently that the said amount
having been deducted towards liquidated damages in terms of the
agreement between the parties, the award for the said amount is
contrary to the terms of the agreement. The objection of the
petitioner that no such dispute was referred to the arbitrator is not
correct. The arbitrator was appointed to adjudicate the claims and
counter claims. The respondent preferred a claim/petition before the
arbitrator, a perusal whereof shows the respondent to have in paras
4 to 7 thereof made the claim for refund of the amounts illegally and
unjustifiably deducted from the payments admittedly due from the
petitioner to the respondent.
12. The arbitrator allowed the said claim for the reasons, that the
contract between the parties required performance of reciprocal
obligation and the respondent could not perform its obligations
without the petitioner first performing its part of the agreement; that
there was sufficient evidence that it was the petitioner which had
delayed in performance of its part leading to the delay in the
respondent in performing its obligations; that the petitioner had
failed to prove any loss owing to the alleged delays; that the wording
of the agreement shows that the deductions made were not a
genuine pre-estimate mutually arrived at between the parties; that
the petitioner without proving any loss was not entitled to any
damages or liquidated damages; that liquidated damages of 50% was
in the nature of penalty. The arbitrator thus allowed the claim of
deductions made from the payments due for the years 1993-94 and
1995-96.
13. Objection is raised to the aforesaid findings of arbitrator
relying upon the Judgment of ONGC v SAW Pipes Ltd (2003) 5 SCC
705. I, however find that, that case turned on the peculiar language
of the agreement in question in that case. This court also has in
Indian Oil Corporation v M/s Lloyds Steel Industries Ltd
2008(1) R.A.J. 170 (Del) after noticing ONGC (supra) held that
without damage/loss being proved, liquidated damages could not be
allowed and no fault could be found with the arbitral award for the
said reason.
14. Merely because the agreement provides for liquidated
damages and the award does not allow liquidated damages for the
reason of the interpretation of law by the arbitrator would not make
the award contrary to the agreement so as to have the same set
aside. The arbitrator is entitled to adjudicate legality or
interpretation of a term of the agreement and not bound to follow
the same literally. If the arbitrator by examining the legal effect of
the agreement holds the same to be not entitling the petitioner to
liquidated damages without proving loss or damage, the same does
not call for interference with the arbitral award. The purpose of the
1996 Act was to reduce / limit the challenge to the arbitral awards.
Of course, the Apex Court in ONGC (supra) has interpreted the new
Act also to mean that the court is empowered to set aside the award
if not in accordance with law. In my view, an arbitral award would
be in accordance with law, if the correct law is applied, even though
a wrong view or interpretation of the same has been taken.
15. In the facts and circumstances of the present case, the
principle of law required application of facts and even if in such
application of facts the arbitrator reaches a conclusion different from
the one which the court may reach, the same still does not call for
setting aside of the award. Only if, irrespective of the factual
application, the conclusion reached by the arbitrator under no
circumstance can be reached under the law, is in my respectful view
a ground under Section 34 of the Act for setting aside of the award
made out. In this regard, I may notice that ONGC (supra) had struck
a different note than the then prevalent law. It had been held by a
Constitution Bench of the Apex Court in Fateh Chand v Balkishan
Das AIR 1963 SC 1405 that a provision in an agreement for
liquidated damages did not ipso facto call for such damages to be
awarded and to be entitled to damages, loss and damages had to be
proved. The Apex Court in ONGC (supra), relying upon the peculiar
language in the agreement of the parties having arrived at a genuine
pre-estimate of the loss which shall be suffered for the reason of the
delay and further agreeing that assessment of such loss was difficult,
had held the parties to be bound by the same and upheld the award
of liquidated damages. Notwithstanding the said judgment, as in
Indian Oil Corporation (supra), the courts have, depending upon
the facts of the case continued to follow the Constitution Bench
judgment unless finding the language to be as in ONGC case. The
arbitrator in the present case also has noticed that the agreement
did not provide of the liquidated damages being a genuine pre-
estimate and held the petitioner to be not entitled to the same. Thus,
it cannot be said that the award on the said claim is contrary to the
law prevailing or for that reason contrary to public policy. As long as
a correct law is applied even if a wrong view of the same is taken,
the arbitrator being a judge chosen by the parties themselves is
empowered by the parties to finally decide the matter not only of fact
but also of law and this court does not sit in appeal over the award.
See Tribal Co-operative Marketing Development Federation of
India Ltd v Auro Industries Limited and Anr. 98 (2002) DLT 654
and Flex Engineering Ltd v Antartica Construction Co. and Anr
2007 (2) ARB LR 387 (Delhi). The award cannot be set aside even if
the decision appears erroneous. Even under the 1940 Act where the
scope of interference with award was much more, the Apex Court in
Tarapore and Company v. Cochin Shipyard Ltd., Cochin and
Anr AIR 1984 SC 1072 and U.P. Hotels and Ors. v. U.P. State
Electricity Board AIR 1989 SC 268 held that arbitrator decision on
a question of law is also binding even if erroneous and in P. V.
Subba Naidu and Ors. v. Government of A.P. & Ors (1998) 9
SCC 407 the Apex Court further held that courts are not right in
examining and interpreting the contract to see whether the claim
was sustainable under the contract. I, therefore, do not find any
merit in this objection also of the petitioner.
16. The claim No.2 of the respondent was for award of interest on
the amounts subject matter of claim but @ 23% per annum under the
provisions of Small Scale and Ancillary Industrial Undertakings Act,
1993. The arbitrator has, however, allowed interest at 18% per
annum only and that too from 1st June, 1996 to September, 2001. The
arbitrator having found the monies of the respondent to have been
illegally withheld by the petitioner, was fully justified in awarding
interest and no fault can be found with the award under the said
head. The counsel for the respondent has before this court also
sought interest @ 23% per annum relying upon Assam Small Scale
Ind. Dev. Corp. Ltd. and Ors. v. J.D. Pharmaceuticals and Anr
AIR 2006 SC 131 and M/s Kanhai Engineering (Towers) Pvt Ltd v
M/s Telecommunications Consultants India Ltd 2007(3) R.A.J.
60 (Del) and argued that this court should modify the award to
award interest @ 23% per annum. However, the respondent having
not preferred any objection in this regard, I am not inclined to
enhance the rate of interest. Even otherwise, in my view, in the last
few years, except recently, the interest rates have been falling and
the award of interest at 18% per annum is in consonance with the
prevailing laws.
17. The arbitrator has allowed the claim of the respondent of Rs
5,37,856/- for payment of bills for unprinted issues. The arbitrator
has reasoned that the petitioner had in the meeting on 6th November,
1997 agreed that these bills for incomplete work will be processed
subsequently but had not processed the same. The arbitrator did not
find any merit in the objection of the petitioner in opposition to the
said claim. Thus, being factual dispute, and nothing having been
shown of the same being contrary to the agreement, no case for
interference under Section 34 of the Act is made out. The Apex
Court in Arosan Enterprises Ltd. v. Union of India AIR 1999 SC
3804 held findings of arbitrator purely based on appreciation of
material on record cannot be interfered with. The last claim of the
respondent which has been allowed by the arbitrator is of interest
for the delay in the refund of security deposit. The agreement
between the parties does not provide for anything required to be
done prior to the refund of the security deposit. The arbitrator has
on facts found that the security deposit ought to have been refunded
in January, 1996 and further found the petitioner to have failed to
refund the same without any reason, inspite of repeated reminders of
the respondent and thus awarded interest at 18% per annum from
July, 1996 till February, 1998 when the security deposit was
refunded. The same also being a factual matter and nothing having
been shown of the same being contrary to any part of the agreement,
no ground for interference with the said part of the award is also
made out.
18. The arbitrator has further awarded interest @ 18% per annum
on the awarded amounts from the date of award till actual
realization. Following Krishna Bhagya Jala Nigam Ltd.
v G. Harischandra Reddy and Anr AIR 2007 SC 817 and Flex
Engineering Ltd (supra) I however modify this part of the award.
The respondent shall be entitled to interest from date of award till
realization @ 9% per annum
19. Thus, the petitioner having failed to make out a case under
Section 34 of the Act, the petition is dismissed, save for the
modification of rate of post award interest.
RAJIV SAHAI ENDLAW (JUDGE) October 03, 2008 M
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!