Citation : 2026 Latest Caselaw 1518 Chatt
Judgement Date : 10 April, 2026
1
2026:CGHC:16530-DB
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 1656 of 2026
Govind Agrawal S/o B.L.Agrawal, Aged About 58 Years R/o Azad
Chowk Shankar Ward Bhatapara, District Baloda Bazar-Bhatapara
493118 (C.G.)
... Petitioner(s)
versus
1. State of Chhattisgarh Through The Secretary, Public Works
Department, Mahanadi Bhawan, Mantralaya, New Raipur, District
Raipur (C.G.)
2. Engineer In Chief, Public Works Department, Nirman Bhawan,
Nawa Raipur Atal Nagar, District Raipur (C.G.)
3. Chief Engineer (E And M) Public Works Department, Raipur Zone,
Sirpur Bhawan, Raipur (C.G.)
4. Superintending Engineer (E And M) Raipur Circle, Sirpur Bhawan,
Raipur (C.G.)
5. Executive Engineer (E And M) Public Works Department, Division
Raipur, District Raipur (C.G.)
...Respondent(s)
Digitally signed by
MORLE BRIJMOHAN BRIJMOHAN MORLE Date:
2026.04.10 (Cause-title taken from Case Information System) 17:59:15 +0530
For Petitioner : Mr. Tushar Dhar Diwan, Advocate. For Respondent/State : Mr. Praveen Das, Additional Advocate General.
Hon'ble Shri Ramesh Sinha, Chief Justice Hon'ble Shri Ravindra Kumar Agrawal, Judge Order on Board Per Ramesh Sinha, Chief Justice 10.04.2026
1. Heard Mr. Tushar Dhar Diwan, learned counsel for the petitioner.
Also heard Mr. Praveen Das, learned Additional Advocate General,
appearing for the State.
2. The present petition has been filed by the petitioner under Article
226 of the Constitution of India, seeking following reliefs :-
"10.1 That, this Hon'ble Court may kindly be pleased
to call the entire records pertaining to case of
petitioner, from the respondents.
10.2 That, this Hon'ble Court may kindly be pleased to
issue writ of mandamus directing the respondent No.5
to release the amount of Rs. 4,82,158/- along with
interest from the date the bill became due, for
electrical work completed at a Government High
School in Baloda Bazar, Chhattisgarh completed on
16.03.2024.
10.3 To kindly grant any other relief which may be
deem fit in the given facts and circumstances of the
instant case.
10.4 Cost of the petition."
3. Learned counsel for the petitioner submits that the petitioner is a
small contractor engaged in execution of government works,
contributing towards effective utilization of public funds, timely
completion of projects, and ensuring that essential public infrastructure
reaches the intended beneficiaries. He further submitted that the
petitioner was awarded a contract vide work order dated 18.01.2024 for
electrification work in the Government High School Building at
Salihaghat, Block Bilaigarh, District Baloda Bazar-Bhatapara, for a total
contract value of Rs. 5.03 lakhs.
4. Learned counsel for the petitioner would submit that the petitioner
duly executed and completed the entire work within the stipulated
period on 16.03.2024 to the full satisfaction of the competent
authorities. As per the Measurement Book and Memorandum of
Payment, a sum of Rs. 4,82,158/- became due and payable to the
petitioner, which remains undisputed. He further contended that the
departmental authorities themselves have repeatedly acknowledged the
completion of work and recommended release of payment through
official communications dated 05.06.2024, 18.07.2024, 08.08.2024, and
26.12.2024. Even thereafter, a specific direction was issued on
07.05.2025 by the superior authority to ensure immediate payment of
the petitioner's dues. Despite such categorical recommendations and
directions, the respondents have failed to release the admitted amount
till date, without assigning any lawful justification.
5. It is further submitted by the learned counsel, appearing for the
petitioner that the inaction on the part of the respondents is not only
arbitrary but reflects gross administrative apathy. The excuse of
increase in tender cost or pendency of administrative approval is wholly
untenable in law and cannot be used as a ground to deny payment for
work already executed and accepted by the department. He also stated
that the petitioner had undertaken the work by arranging finances from
private sources, and due to prolonged non-payment, he is facing severe
financial distress, including mounting interest liabilities. The continued
withholding of legitimate dues is causing irreparable injury and mental
agony to the petitioner.
6. Learned counsel submits that the action of the respondents is
violative of Articles 14 and 21 of the Constitution of India, as it is
arbitrary, unreasonable, and deprives the petitioner of his rightful dues
without any authority of law. It is further submitted that the amount due
to the petitioner, being an admitted and crystallized liability, partakes the
character of property, and its withholding without lawful justification is
violative of Article 300-A of the Constitution of India.
7. Learned counsel for the petitioner places strong reliance upon the
judgment passed by the Division Bench of this Hon'ble Court in WA
No.123 of 2025, State of Chhattisgarh vs. Baba Vishwanath
Construction & Another, wherein it has been categorically held that
once the work awarded by the State is completed and there is no
dispute regarding quality or quantity, the State authorities cannot
withhold payment on the ground of internal or procedural irregularities.
The Hon'ble Court further held that such action is arbitrary and
impermissible, and the undisputed amount must be released
expeditiously.
8. It is submitted that the ratio laid down in the aforesaid judgment
squarely applies to the facts of the present case, as the respondents
have admitted completion of work and their liability to pay, yet are
illegally withholding the petitioner's dues.
9. Learned counsel contended that it is a settled principle of law that
the State cannot take advantage of its own administrative lapses to
deny legitimate dues of a contractor. Any internal irregularity or delay is
required to be dealt with departmentally and cannot prejudice the rights
of the petitioner.
10. In view of the above facts and settled legal position, the petitioner
is entitled for immediate release of the admitted amount of
Rs.4,82,158/- along with appropriate interest for the inordinate and
unjustified delay caused by the respondents.
11. On the other hand, learned State counsel opposes the
submissions made by the learned counsel for the petitioner and submits
that the writ petition as framed and filed are not maintainable as the
disputed question of facts cannot be adjudicated in writ petition under
Article 226 of the Constitution of India.
12. We have learned counsel for the parties, perused the impugned
order and other documents appended with writ petition.
13. It is settled law that the High Court should not exercise its
jurisdiction under Article 226 of the Constitution of India when it raises
disputed question of facts.
14. The Hon'ble Supreme Court in the case of Chairman, Grid
Corpornation of Orissa Ltd. (GRIDCO) & Others v. Sukamani Das
(Smt.) & Another, reported in (1999) 7 SCC 298 was dealing with the
question of whether the High Court had made an error in entertaining a
writ petition filed seeking compensation for the death of a person due to
electrocution, which had allegedly been caused due to the negligence of
the authorities. The Hon'ble Supreme Court in the said case observed
as under:
"6. In our opinion, the High Court committed an error in entertaining the writ petitions even though they were not fit cases for exercising power under Article 226 of the Constitution. The High Court went wrong in proceeding on the basis that as the deaths had taken place because of electrocution as a result of the deceased coming into contact with snapped live wires of the electric transmission lines of the appellants, that "admittedly/prima facie amounted to negligence on the part of the appellants". The High Court failed to appreciate that all these cases were actions in tort and negligence was required to be established firstly by the claimants. The mere fact that the wire of the electric transmission line belonging to Appellant 1 had snapped and the deceased had come in contact with it and had died was not by itself sufficient for awarding
compensation. It also required to be examined whether the wire had snapped as a result of any negligence of the appellants and under which circumstances the deceased had come in contact with the wire. In view of the specific defences raised by the appellants in each of these cases they deserved an opportunity to prove that proper care and precautions were taken in maintaining the transmission lines and yet the wires had snapped because of circumstances beyond their control or unauthorised intervention of third parties or that the deceased had not died in the manner stated by the petitioners. These questions could not have been decided properly on the basis of affidavits only. It is the settled legal position that where disputed questions of facts are involved a petition under Article 226 of the Constitution is not a proper remedy. The High Court has not and could not have held that the disputes in these cases were raised for the sake of raising them and that there was no substance therein. The High Court should have directed the writ petitioners to approach the civil court as it was done in OJC No. 5229 of 1995."
(emphasis supplied)
15. The aforesaid judgment has been relied/ reiterated by the Hon'ble
Supreme Court in S.P.S. Rathore v. State of Haryana & Others,
reported in (2005) 10 SCC 1 wherein it observed as follows:
"16. In Chairman, Grid Corpn. of Orissa Ltd. (Gridco) v. Sukamani Das [(1999) 7 SCC 298] the question which arose for consideration was, can the High Court under Article 226 of the Constitution award compensation for death caused due to electrocution on account of
negligence, when the liability was emphatically denied on the ground that the death had not occurred as a result of negligence, but because of an act of God or of acts of some other persons. The Court held that it is the settled legal position that where disputed questions of facts are involved, a petition under Article 226 of the Constitution is not a proper remedy. Therefore, questions as to whether death occurred due to negligence or due to act of God or of some third person could not be decided properly on the basis of affidavits only, but should be decided by the civil court after appreciating the evidence adduced by the parties. In T.N. Electricity Board v. Sumathi [(2000) 4 SCC 543] it was held that when a disputed question of fact arises and there is clear denial of any tortious liability, remedy under Article 226 of the Constitution may not be proper. The Court carved out exception to this general rule by observing that, it should not be understood that in every case of tortious liability, recourse must be had to a suit. When there is negligence on the face of it and infringement of Article 21 is there, it cannot be said that there will be any bar to proceed under Article 226 of the Constitution."
(emphasis supplied)
16. Similarly, the Hon'ble Supreme Court in Shubhas Jain v.
Rajeshwari Shivam, reported in 2021 SCC OnLine SC 562 has held
as under:
"26. It is well settled that the High Court exercising its extraordinary writ jurisdiction under Article 226 of the Constitution of India, does not adjudicate hotly disputed questions of facts. It is not for the High Court
to make a comparative assessment of conflicting technical reports and decide which one is acceptable."
17. Subsequently, in Union of India vs. Puna Hinda, reported in
(2021) 10 SCC 690, the Hon'ble Supreme Court has observed:
"24. Therefore, the dispute could not be raised by way of a writ petition on the disputed questions of fact. Though, the jurisdiction of the High Court is wide but in respect of pure contractual matters in the field of private law, having no statutory flavour, are better adjudicated upon by the forum agreed to by the parties. The dispute as to whether the amount is payable or not and/or how much amount is payable are disputed questions of facts. There is no admission on the part of the appellants to infer that the amount stands crystallised. Therefore, in the absence of any acceptance of joint survey report by the competent authority, no right would accrue to the writ petitioner only because measurements cannot be undertaken after passage of time. Maybe, the resurvey cannot take place but the measurement books of the work executed from time to time would form a reasonable basis for assessing the amount due and payable to the writ petitioner, but such process could be undertaken only by the agreed forum i.e. arbitration and not by the writ court as it does not have the expertise in respect of measurements or construction of roads."
18. Recently, the Hon'ble Supreme Court in the case of M.P. Power
Management Co. Ltd. v. Sky Power Southeast Solar India (P) Ltd.,
reported in (2023) 2 SCC 703, while dealing with the issue of exercise
of writ jurisdiction by a Court in matters arising out of a contract, has
stated:
"82.7. The existence of an alternate remedy, is,
undoubtedly, a matter to be borne in mind in declining
relief in a writ petition in a contractual matter. Again,
the question as to whether the writ petitioner must be
told off the gates, would depend upon the nature of the
claim and relief sought by the petitioner, the questions,
which would have to be decided, and, most
importantly, whether there are disputed questions of
fact, resolution of which is necessary, as an
indispensable prelude to the grant of the relief sought.
Undoubtedly, while there is no prohibition, in the writ
court even deciding disputed questions of fact,
particularly when the dispute surrounds demystifying of
documents only, the Court may relegate the party to
the remedy by way of a civil suit."
(emphasis supplied)
19. A reading of the aforesaid judgments makes it clear that it is well
settled proposition of law that when there are disputed question of facts
involved in a case, the High Court should not exercise its jurisdiction
under Article 226 of the Constitution of India. It has been held that the
remedy under Article 226 of the Constitution of India may not be proper.
20. In the present case, although the petitioner asserts that the
amount is admitted and payable, this Court finds that the claim arises
purely out of a contractual relationship. The determination of entitlement
to payment, including verification of measurements, sanction of amount,
and compliance with contractual conditions, requires detailed
examination of records and evidence, which cannot appropriately be
undertaken in proceedings under Article 226 of the Constitution of India.
21. The judgment relied upon by the learned counsel for the petitioner
in Baba Vishwanath Construction (supra) is distinguishable on facts
as well as on the nature of jurisdiction exercised. The said judgment
arose from an order passed by the learned Single Judge, which was
considered in writ appeal in the backdrop of clear and unequivocal
admission of liability, leaving no scope for factual adjudication. However,
in the present case, this Court is exercising jurisdiction under Article 226
of the Constitution of India in a writ petition, where such detailed factual
determination, including assessment of measurements, verification of
records, and compliance with contractual conditions, is required. In writ
proceedings, this Court does not undertake such adjudication of
disputed or unverified claims. Therefore, the ratio of the said judgment
cannot be applied to the facts of the present case.
22. Considering the submissions advanced by learned counsel for the
parties, the nature of the claim involved, and in view of the law laid
down by the Hon'ble Supreme Court in the above-stated judgments
(supra), we do not find any good ground to entertain this writ petition
under Article 226 of the Constitution of India.
23. Accordingly, the present writ petition, being not maintainable, is
liable to be and is hereby dismissed. However, liberty is reserved in
favour of the petitioner to take recourse to other alternate remedies
available to him under the law. No cost(s).
Sd/- Sd/-
(Ravindra Kumar Agrawal) (Ramesh Sinha)
Judge Chief Justice
Brijmohan
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!