Citation : 2026 Latest Caselaw 1468 Chatt
Judgement Date : 9 April, 2026
Digitally signed
YOGESH by YOGESH
TIWARI
TIWARI Date: 2026.04.15
10:18:14 +0530
1
2026:CGHC:16503
NAFR
HIGH COURT OF CHHATTISGARH AT BILASPUR
WPC No. 1428 of 2020
Vakeel Ahmad S/o Shri Hatim Kahn, Aged About 57 Years R/o House
No. 90, Gaji Nagar, Birgaon, Raipur Chhattisgarh
... Petitioner
versus
1 - Union of Bharat Through Its Secretary Ministry of Road, Transport
And Highway, New Delhi
2 - National Highway Authority of India Through Project Director And
Project Implementation Unit 51/96, Behind B T I College, Shankar
Nagar, Raipur Chhattisgarh
3 - Regional Officer National Highway Authority of India, Anupam Nagar
Raipur Chhattisgarh
4 - The Land Acquisition Officer Cum Sub Divisional Officer (Revenue)
Raipur Chhattisgarh
... Respondents
(Cause-title taken from Case Information System) For Petitioner : Mr. Shivam Mishra, Advocate on behalf of Mr. Kishan Lal Sahu, Advocate For Respondents No.2 & 3 : Mr. B. Gopa Kumar, Advocate For State/Respondent No.4 : Mr. Siddharth Sharma, Panel Lawyer
Hon'ble Shri Amitendra Kishore Prasad, Judge Order on Board 09.04.2026
1. By filing the present petition, the petitioner calls in question the
inaction and arbitrary conduct of the respondent authorities in
failing to deposit the compensation awarded under the
supplementary award dated 11.04.2018, despite acquisition of the
petitioner's land for the widening of National Highway No. 30/200
Raipur-Bilaspur Project, thereby depriving the petitioner of the
justly entitled compensation for the loss of property. The petitioner
has prayed for following relief(s) :-
"10.1 To call the entire records of the case for kind perusal of the this Hon'ble Court in respect of the petitioner.
10.2 To issue an appropriate writ of Mandamus or direction to the respondent authority to pay compensation in the respect of the property affected in the proceeding of land acquisition and property been demolished by the respondents with interest rate of 18%.
10.3 To direct the respondent No. 1 to 3 to deposit compensation according to the supplymentory award dated 11.04.2018 before the competent authority.
10.4 Any other relief deemed fit in the facts and circumstance of the case may also granted."
2. Learned counsel for the petitioner submits that the respondents
acquired the petitioner's land under the provisions of the National
Highway Act, 1956 (for short, 'Act of 1956'), through a land
acquisition proceeding initiated in the year 2012 for the purpose of
widening National Highway No. 30/200. At the time of acquisition,
the petitioner had constructed and was running a shop on the said
land. Despite repeated claims and complaints made before the
competent authorities, the petitioner has not been compensated
for the loss of property, including the superstructure constructed
on the land. It is submitted that the petitioner, along with other
affected persons from village Sankra Saddu, approached the
competent authority seeking redressal of the loss suffered due to
the acquisition. The competent authority, respondent No. 4,
directed the Executive Engineer of the Rural Engineering Service
to evaluate the petitioner's loss. Pursuant to this direction, a
report evaluating the property loss was submitted, which
culminated in the issuance of a supplementary award dated
11.04.2018 granting the petitioner due compensation for the loss
of property.
3. Learned counsel further submits that despite the issuance of the
supplementary award, respondents No. 1 to 3 have failed to
deposit the awarded amount with the competent authority. Even
after the petitioner sent a reminder dated 28.09.2018 to
respondent No. 3, there has been no action taken by the
respondents to release the due compensation. The inaction and
omission on the part of the respondents have caused continued
harassment and undue hardship to the petitioner. It is submitted
that the failure of the respondents to pay the compensation
amounts to a violation of the petitioner's constitutional right to
property, recognized under the law, and constitutes arbitrary and
unlawful behavior. The respondents, by taking possession of the
land and allowing the destruction of the petitioner's property
without releasing the due compensation, have acted in a manner
that is both oppressive and legally impermissible.
4. In view of the foregoing, learned counsel for the petitioner submits
that the inaction of the respondents is bad in law and liable to be
corrected by this Court. It is, therefore, prayed that the
respondents be directed to pay the due compensation to the
petitioner within a stipulated period and take all necessary steps
to ensure compliance with the supplementary award dated
11.04.2018.
5. Learned counsel for respondents No. 2 and 3 vehemently
opposes the submissions made by learned counsel for the
petitioner and submits that the present petition is misconceived,
legally untenable, and not maintainable. At the outset, it is
submitted that every adverse contention raised in the petition, in
so far as it relates to the answering respondents, is denied unless
specifically admitted. The respondents reserve the right to file
additional or supplementary replies, if necessary, in the interest of
justice. It is submitted that the petitioner's claim primarily
challenges the so-called supplementary award dated 11.04.2018
in respect of land acquired for the widening of National Highway
No.30/200. The respondents submit that the supplementary
award was passed without following the statutory procedure
prescribed under the Act of 1956, and without providing the
respondents an opportunity to be heard. There is no provision
under the Act of 1956 that empowers the competent authority to
issue a supplementary award once the original award, passed in
2012, had become final and executed.
6. Learned counsel submits that the original award of 2012 had
already included compensation for the loss of property and
infrastructure on the acquired land. The compensation was
deposited in accordance with the provisions of the Act of 1956,
and the respondents have consistently complied with all legal
obligations in this regard. Any attempt to pass a supplementary
award after a lapse of six years, without verifying the correctness
of the original award, is contrary to law and amounts to an
unauthorized exercise of powers by the competent authority. It is
further submitted that under Section 3G(5) of the Act of 1956, if
any grievance arises regarding the payment or determination of
the compensation amount, the aggrieved party is required to
approach the arbitrator appointed under the Act of 1956. The
petitioner has not availed of this statutory remedy and has
approached this Court directly, which is not permissible under the
law. The statutory procedure is exclusive, and no alternate mode
of litigation is permissible in this regard. It is also submitted that
the concept of a supplementary award is a misnomer and is not
recognized under the Act of 1956. Once the original award was
passed in 2012, the Land Acquisition Officer became functus
officio and had no jurisdiction to modify or rewrite the award
except for correcting clerical or arithmetic errors. The
supplementary award, therefore, is ultra vires and legally void.
The respondents had duly filed an application under Section
3G(5) before the Divisional Commissioner, Raipur, acting as the
notified arbitrator, challenging the supplementary award and
seeking its invalidation.
7. Lastly, learned counsel for respondents No. 2 and 3 submits that
the petition filed by the petitioner is legally untenable and liable to
be dismissed. The respondents have acted strictly in accordance
with the provisions of the Act of 1956, and there is no occasion for
interference by this Court. The petitioner has an efficacious
statutory remedy under the Act of 1956, which has not been
availed, and therefore, the present petition is liable to be rejected.
8. Learned counsel for the State/respondent No. 4 submits that the
present petition is not maintainable as the land of the petitioner
was acquired for the widening and upgradation of National
Highway No. 30/200 Raipur-Bilaspur Project under the provisions
of the Act of 1956. The original award in Land Acquisition Case
No. 15(2)/A-82 Year 2010-11 was passed on 28.05.2012 by the
Land Acquisition Officer-Cum-Sub Divisional Officer, Raipur, after
due process. It is submitted that complaints regarding
determination of compensation for assets on the acquired land
were considered, and a supplementary award dated 11.04.2018
was passed after technical evaluation by the Executive Engineer,
Rural Engineering Services, Raipur, and examination of the
Tahsildar's enquiry report. The respondents No. 2 & 3/NHAI have
not disbursed the amount pending adjudication of their application
under Section 3G(5) of the Act of 1956 before the Divisional
Commissioner, Raipur, who is the notified arbitrator. As such, the
petition filed by the petitioner against the State/respondent No. 4
is not tenable.
9. I have heard the learned counsel for the parties at length and
have carefully perused the pleadings, documents, and other
material available on record.
10. In order to appreciate the issue on hand it would be apposite to
first extract the provisions of Section 3-G(5) and 3-G(6) of the
National Highways Act and Section 34 of the Arbitration and
Conciliation Act.
"Section 3-G(5) If the amount determined by the competent authority under sub-section (1) or sub-section (2) is not acceptable to either of the parties, the amount shall, on an application by either of the parties, be determined by the arbitrator to be appointed by the Central Government. Section 3-G(6) Subject to the provisions of this Act, the provisions of the Arbitration and Conciliation Act, 1996 (26 of 1996) shall apply to every arbitration under this Act.
Section 34 of the Arbitration and Conciliation Act. Application for setting aside arbitral award.-(1) Recourse to a Court against an
arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-
section (3).
(2) An arbitral award may be set aside by the Court only if-
(a) the party making the application 1 [establishes on the basis of the record of the arbitral tribunal that)-
(i) a party was under some incapacity, or
(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication. thereon, under the law for the time being in force; or
(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
(iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:
Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or
(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
(b) the Court finds that-
(1) the subject matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or
(ii) the arbitral award is in conflict with the public policy of India
[Explanation 1. For the avoidance of any doubt, it is clarified that an award is in conflict with the public policy of India, only if-
(i) the making of the award was induced or affected by fraud or corruption or was in violation of section 75 or section 81: or
(ii) it is in contravention with the fundamental policy of Indian law; or
(iii) it is in conflict with the most basic notions of morality or Justice.
Explanation 2.-For the avoidance of doubt, the test as to whether there is a contravention with the fundamental policy of Indian law shall not entail a review on the merits of the dispute.
[(2A) An arbitral award arising out of arbitrations other than international commercial
arbitrations, may also be set aside by the Court, if the Court finds that the award is vitiated by patent illegality appearing on the face of the award: Provided that an award shall not be set aside merely on the ground of an erroneous application of the law or by reappreciation of evidence.)
(3) An application for setting aside may not be made after three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal:
Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter.
(4) On receipt of an application under sub-
section (1), the Court may, where it is appropriate and it is so requested by a party, adjourn the proceedings for a period of time determined by it in order to give the arbitral tribunal an opportunity to resume the arbitral proceedings or to take such other action as in the opinion of arbitral tribunal will eliminate the grounds for setting aside the arbitral award.
((5) An application under this section shall be filed by a party only alter issuing a prior notice
to the other party and such application shall be accompanied by an affidavit by the applicant endorsing compliance with the said requirement.
(6) An application under this section shall be disposed of expeditiously, and in any event, within a period of one year from the date on which the notice referred to in sub-section (5) is served upon the other party.)"
11. A reading of Section 3-G(6) of the Highways Act clearly provides
that, in respect of every arbitration under the Highways Act, the
provisions of the Arbitration Act would apply. The language of
Section 3G is unambiguous. Therefore, it is clear that against the
award passed under Section 3-G(5) it is only an application under
Section 34 of the Arbitration and Conciliation Act to set aside the
same can be filed.
12. The provisions of Section 3-G(5) of the Highways Act vis-a-vis
Section 11 of the Arbitration and Conciliation Act was called into
question in a judgment of the Hon'ble Supreme Court reported in
National Highways Authority of India v Sayedabad Tea
Company Limited, (2020) 15 SCC 161 . The question that arose
for consideration was whether the application under Section 11 of
the Arbitration and Conciliation Act 1996 was maintainable in view
of Section 3-G(5) of the National Highways Act which provides for
appointment of an Arbitral Tribunal. In the said case, the land
owner being dissatisfied with the award of compensation
determined by the competent authority under Section 3-G(1) of
the Highways Act had filed an application for appointment of an
Arbitrator in terms of Section 3-G(5) of the Highways Act to the
Central Government. Since there was no response from the
Central Government, the applicant had filed an application under
Section 11(6) of the Arbitration and Conciliation Act. Thereafter, an
Arbitrator was appointed. The High Court had observed that since
the Central Government had refused to comply with the request of
the applicant, their right to appoint an Arbitrator stood forfeited. A
review application was thereafter filed bringing to the notice of the
Court that as per the Highways Act the procedure for appointment
of an Arbitrator exclusively vested with the Central Government
under Section 3-G(5) of the Highways Act and that the application
under Section 11(6) of the Arbitration and Conciliation Act is not
maintainable. However, the review application was dismissed.
Thus aggrieved the National Highways Authorities had moved the
Hon'ble Supreme Court. The Hon'ble Supreme Court relying upon
the earlier judgments of the Hon'ble Supreme Court reported in
National Highways & Infrastructure Development Corpn. Ltd.
v. Prakash Chand Pradhan, (2020) 15 SCC 533 had observed
as follows:-
"18. After analysing the scheme, it can be assumed that the legislature intended the 1956 Act to act as a complete code in itself for the purpose of acquisition until culmination including disbursement and for settlement of
disputes and this conclusion is further strengthened in view of Section 3-J of the Act which eliminates the application of the Land Acquisition Act, 1894, to an acquisition under the 1956 Act.
19. It is settled principles of law that when the special law sets out a self-contained code, the application of general law would impliedly be excluded. In the instant case, the scheme of the 1956 Act being a special law enacted for the purpose and for appointment of an arbitrator by the Central Government under Section 3-G(5) of the 1956 Act and sub-section (6) of Section 3-G itself clarifies that subject to the provisions of the 1956 Act, the provisions of the 1996 Act shall apply to every arbitration obviously to the extent where the 1956 Act is silent, the arbitrator may take recourse in adjudicating the dispute invoking the provisions of the 1996 Act for the limited purpose. But so far as the appointment of an arbitrator is concerned. the power being exclusively vested with the Central Government as envisaged under sub-section (5) of Section 3-G of the 1956 Act. Section 11 of the 1996 Act has no application."
13. In another judgment of the Hon'ble Supreme Court reported in
National Highways Authority of India v. Sheetal Jaidev Vade,
(2022) 16 SCC 391, the Hon'ble Supreme Court was considering
a issue as to whether the High Court exercising power under
Article 226 of the Constitution of India was competent to execute
an award passed by the Arbitrator. The learned Judges had held
as follows in paragraph nos. 11 and 12:-
'11. Therefore, once the original writ petitioner was having an efficacious, alternative remedy to execute the award passed by the learned Arbitral Tribunal/Court, by initiating an appropriate execution proceeding before the competent executing court, the High Court ought to have relegated the original writ petitioners to avail the said remedy instead of entertaining the writ petition under Article 226 of the Constitution of India which was filed to execute the award passed by the Arbitral Tribunal/Court. If the High Courts convert itself to the executing court and entertain the writ petitions under Article 226 of the Constitution of India to execute the award passed by the Arbitral Tribunal/Court, the High Courts would be flooded with the writ petitions to execute awards passed by the learned arbitrator/Arbitral Tribunal/Arbitral Court.
12. We disapprove the entertaining of such writ petitions under Article 226 of the Constitution of India to execute the award passed by the learned Arbitral Tribunal/Court, without relegating the judgment creditor in whose favour the award is passed to file an execution proceeding before the competent executing Court."
14. A Division Bench of the Hon'ble Karnataka High in the case
reported in National Highways Authority of India v. P.V.
George, 2024 SCC OnLine Ker 4236, was also dealing with the
maintainability of a Writ Petition challenging the decision of the
Arbitrator (The issue of limitation was also an issue before the
Division Bench). With reference to the limitation, the Bench had
observed that the limitation would not apply in arbitration under
the National Highways Act and with reference to the
maintainability of the Writ Petition they had held that the remedy is
to challenge the decision by invoking the provisions of Section 34
of the Arbitration and Conciliation Act.
15. The Hon'ble Bombay High Court in the judgment reported in
Omanand Industries v. Secretary to the Government of India,
2023 SCC OnLine Bom 784, was considering a batch of Writ
Petitions challenging the award passed by the Arbitrator under
Section 3G5 of the National Highways Act (as in the instant case).
The learned Judge after referring to the various judgments and
after briefly touching upon the scheme of the National Highways
Act relevant to the determination of the compensation, observed
as follows:-
"The mode of conducting the proceedings before the Arbitrator, in case the claimant is not satisfied with the award passed by the Competent Authority, is also governed by the provisions of Section 3 -G (6) of the N.H. Act, which applies the provisions of the A & C Act, to proceedings before the Arbitrator. It is, thus, apparent that a remedy of approaching the
'Court', as defined in Section 2(1)(e) of the A & C Act, has been provided to the claimant, against the award as may be passed by the Arbitrator under Section 3-G-(5) of the N.H. Act, which is a special Statute, governing the acquisition of lands for the National Highways."
16. Reverting to the facts of the case at hand in the light of the above-
stated judgments, it is quite vivid that the controversy raised by
the petitioner revolves around the entitlement to, and enforcement
of, compensation allegedly determined by way of a supplementary
award dated 11.04.2018. The core grievance of the petitioner is
the non-deposit and non-disbursement of the said amount by the
respondent authorities. However, it is equally evident from the
record that the very validity, legality, and enforceability of the said
supplementary award is under challenge at the instance of the
respondents before the statutory Arbitrator appointed under
Section 3-G(5) of the National Highways Act, 1956. Thus, the
dispute between the parties is not merely administrative inaction
simpliciter, but a substantive dispute touching upon the
correctness and sustainability of the determination of
compensation itself.
17. In such a situation, once the statute provides a complete and
efficacious mechanism for adjudication of disputes relating to
compensation including determination by the competent authority,
adjudication by the Arbitrator under Section 3-G(5), and thereafter
a challenge under Section 34 of the Arbitration and Conciliation
Act, the parties are bound to adhere to the said statutory
framework. The National Highways Act, being a special
enactment, constitutes a self-contained code governing
acquisition, determination of compensation, and resolution of
disputes arising therefrom. Therefore, any grievance with respect
to the quantum or validity of compensation cannot be permitted to
be agitated dehors the mechanism expressly provided under the
statute.
18. It is also of considerable significance that the proceedings before
the Arbitrator are already stated to be pending at the instance of
respondents No. 2 and 3, wherein the supplementary award itself
is under challenge. In such circumstances, any direction by this
Court for deposit or disbursement of compensation, as prayed for
by the petitioner, would necessarily amount to pre-empting the
outcome of the arbitral proceedings and would render the
statutory remedy illusory. The writ jurisdiction under Article 226 of
the Constitution of India cannot be invoked in a manner that
defeats or bypasses the statutory adjudicatory process,
particularly when disputed questions relating to entitlement and
validity of the award are yet to be conclusively determined.
19. Furthermore, the law is well settled that where an efficacious
alternative remedy is available, especially one which is not only
adequate but also specifically designed by the legislature for
redressal of such grievances, the High Court ought to exercise
restraint in entertaining a writ petition. The present case does not
fall within any of the recognized exceptions warranting
interference under Article 226, such as violation of principles of
natural justice, lack of jurisdiction, or patent illegality apparent on
the face of the record. On the contrary, the issues raised herein
are intrinsically linked with factual adjudication and statutory
interpretation, which are best left to be examined by the
competent forum under the Act of 1956.
20. In view of the aforesaid analysis, this Court is of the considered
opinion that the present writ petition, seeking enforcement of the
supplementary award and consequential directions, is not
maintainable in law at this stage. The petitioner, if aggrieved by
any determination or outcome arising from the arbitral
proceedings, is at liberty to avail the remedy available under
Section 34 of the Arbitration and Conciliation Act, in accordance
with law.
21. Accordingly, the writ petition stands dismissed as not
maintainable. However, it is made clear that the petitioner shall be
at liberty to pursue appropriate remedies as available under the
statutory framework governing the field.
22. There shall be no order as to costs.
Sd/-
(Amitendra Kishore Prasad) Judge Yogesh
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!