Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jitendra Bhandari (Died) Through ... vs State Of Chhattisgarh
2023 Latest Caselaw 300 Chatt

Citation : 2023 Latest Caselaw 300 Chatt
Judgement Date : 16 January, 2023

Chattisgarh High Court
Jitendra Bhandari (Died) Through ... vs State Of Chhattisgarh on 16 January, 2023
                                  1
                                                         FA No. 346 of 2016


                                                                    NAFR

      HIGH COURT OF CHHATTISGARH, BILASPUR

(Arising out of judgment and decree dated 13.7.2016 passed by the 5 th
     Additional District Judge, Raipur in Civil Suit No.3-B/2013)

                       FA No. 346 of 2016

   Jitendra Bhandari (Died) Through Lrs. As Per Hon'ble Court
    Order            Dated            14-07-2020.


   1.1 - (A). Anju Bhandari Wd/o Late Jitendra Bhandari Aged
    About 48 Years R/o House No. 569, Ward No. 35, Ramdev
    Mandir     Ward,   Durg,   District   Durg   Chhattisgarh.


   1.2 - (B). Jatin Bhandari S/o Late Jitendra Bhandari Aged
    About 12 Years Since Minor, Represented Through Legal
    Guardian (Mother) Anju Bhandari, Wd/o Late Jitendra
    Bhandari, Aged About 48 Years, R/o House No. 569, Ward
    No. 35, Ramdev Mandir Ward, Durg, District Durg
    Chhattisgarh.                              ---- Appellants

                              Versus

  1. State Of Chhattisgarh Through Collector, Raipur, District
     Raipur, Chhattisgarh ................Defendant No.1,

  2. Executive Engineer, Public Works Department, Government
     Of    Chhattisgarh,     Raipur,     Division     No.2,      Raipur,
     Chhattisgarh ................Defendant No.2

  3. Executive Engineer, Public Works Department, Government
     Of    Chhattisgarh,     Raipur,     Division     No.1,      Raipur,
     Chhattisgarh ................Defendant No.3

  4. Engineer-In-Chief Engineer, Public Works Department,
     Government Of Chhattisgarh, Sirpur Bhawan, Raipur,
     Chhattisgarh ................Defendant No.4

  5. Chief Engineer, Public Works Department, Government Of
                                    2
                                                        FA No. 346 of 2016


      Chhattisgarh,           Sirpur      Bhawan,               Raipur,
      Chhattisgarh ................Defendant No.5

   6. Superintendent     Engineer,     Public   Works    Department,
      Government Of Chhattisgarh, Raipur Circle No.1, Raipur,
      Chhattisgarh ................Defendant No.6

   7. Sub    Divisional Officer, Public Works Department,
      Government Of Chhattisgarh, Raipur, Sub-Division-4,
      Raipur, Chhattisgarh ........Defendant No.7 --- Respondents



For Appellants            :- Mr. Kshitij Sharma, Advocate &
                             Mr. Rahul Tamaskar, Advocate
For Respondent/State      :- Mr. D.C. Verma, GA.


             Hon'ble Shri Justice Goutam Bhaduri
            Hon'ble Shri Justice N.K. Chandravanshi
                     Judgment On Board

Per Goutam Bhaduri, J.

16.1.2023

1. Heard.

2. The appeal is against the judgment and decree dated

13.7.2016 passed by the Court of 5th Additional District

Judge, Raipur in Civil Suit No. 3-B of 2013 whereby the suit

filed by the appellant for recovery of ₹55,11,498/- with

interest was dismissed.

3. The plaintiff claims that the suit was filed on the basis of a

contract in-between the parties executed on 13.2.2002

(Exhibit P12) to lay down the bitumen over two parts of the

FA No. 346 of 2016

road that is Bangoli-Murra-Mohrenga of 7.4 Kms and further

to lay down bitumen over the road Kosrangi- Farhada-

Budgaon Koli of 11 Kms. The appellant being the lowest

tenderer, was given the work contract. According to the

appellant, the entrusted work was valued at ₹65.90 Lacs

with addition of 13.86% SOR, total amounting to ₹84.17

Lacs. According to the appellant/plaintiff, the said work was

carried out and the amount was also paid. Plaintiff /

appellant contended that apart from the work comprised in

the contract, he was made to carry out additional work and

he carried out the additional work as per the order issued. It

is stated that according to the prevailing rules, normally for

the additional work carried out apart from the contract are

evaluated and thereafter it is paid for which the respondent /

Executive Engineer and other persons in the site had

affirmed. Plaintiff stated that as per the measurement book

(Exhibit P22) which contains the signature of the Sub-

Engineer at the site, additional work of Rs. 34,57,653/- was

carried out which was revised to Rs. 32,42,058/- by

respondents and despite the different follow up it was not

paid. It is further stated that the Executive Engineer of the

concerned site by its letter dated 22.11.2006 (Exhibit P19)

and the Chief Engineer by letter dated 06.5.2010 (Exhibit

P20) made a correspondence for non payment of such work

carried out, but, the payment was eventually not made.

FA No. 346 of 2016

Therefore, after the service of legal notice, the suit was filed

for recovery.

4. In defense, it was stated that plaintiff/ appellant is not

entitled for any work carried out as no written

communication was ever made. Further ground was raised

that the suit is barred by limitation as for the work of year

2002, eventually the case was filed in the year 2011.

5. The learned Additional District Judge, Raipur on the basis of

the pleadings framed issues and came to a conclusion that

plaintiff has failed to prove that he was legally entitled to

receive the amount and eventually dismissed the suit.

Hence, this appeal.

6. Learned counsel for the appellant would submit that dispute

about execution of the contract of laying down the bitumen

over the two sites is not in dispute. He further submits that

the amount of the main contract was paid but the dispute is

about the non payment of additional work carried out. He

submits that the letter of the respondent would show that

they admitted the fact about carrying out the additional work

on the site which would entitle the appellant / plaintiff for a

claim. Referring to the clause 13 and 7.9 of the contract

(Exhibit P12) he would submit that addition and alterations

are permissible under the contract at the instance of the

FA No. 346 of 2016

Executive Engineer and undisputedly, in the case, the

additional job was carried out at the instructions of the

Executive Engineer. It is stated for such additional work

done would entitle the appellant/ plaintiff to claim for the

amount as execution of the work is proved by the

measurement book (Exhibit P22). He would submit that

despite the fact the learned trial Court held that the suit is

within limitation. The claim is denied only on the ground that

it has not been legally proved. He also refers to the

judgment of the Supreme Court in the matter of Venkatesh

Construction Company Vs. Karnataka Vidyuth Karkhane

Limited reported in [(2016) 4 SCC 119] to submit that in the

claim of like nature that when extra work is carried out apart

from the contract, it was consented by the parties, the

plaintiff/ appellant would be entitled to get it reimbursed.

Therefore, submits that the order of the learned Additional

District Judge, Raipur may be set-aside and a decree may

be passed.

7. Per contra, learned State counsel opposes the submission

made by learned counsel for the appellant and submits that

the order of the Court below is well merited which does not

call for any interference. He would further submit that suit

was apparently barred by the law of limitation and any claim

of the year 2002-06 filed in the year 2011 would be barred.

FA No. 346 of 2016

He would submit that though the cross objection has not

been preferred, the State is entitled to make such

submissions under Section 3 of the Limitation Act, 1963,

therefore, the appeal preferred by the appellant is liable to

be dismissed.

8. We have heard learned counsel for the parties at length and

perused the documents and evidence on record.

9. Since we are in hold of the appeal to decide both facts and

law, the primary question has been raised about the

limitation in view of the Section 3 of the Limitation Act, 1963.

We therefore would first examine as to whether the suit was

within limitation despite the fact that the cross objection has

not been preferred by the State. The learned trial Court in its

judgment had stated that revised estimate was sent by the

Executive Engineer on 22.11.2006 (Exhibit P19). Thereafter,

the notices served by the plaintiff in the years 2007, 2008,

2010 and 2011 and since the demand was not fulfilled, it

would save the limitation. The contract in this case is of the

year 2002 (Exhibit P12). According to the plaintiff he carried

out additional job as per the instructions of the respondent

for which correspondence were made to pass the estimate,

initially by letter dated 22.11.2006 Exhibit P19, followed by

another letter dated 06.5.2010 Exhibit P20. Perusal of both

the Exhibits P19 and P20, the language of it would show

FA No. 346 of 2016

that certain clarifications were sought for at the end of higher

State officials as to why certain payments were not made.

The letter Exhibit P21, internal correspondence addressed

by the Chief Executive dated 04.10.2010 specifies the

reference of work done which stood completed on

15.6.2004. The query though made as till date why the

payments were not made for work completed in the year

2004 shows that work assigned to appellant was completed

much prior in the year 2004.

10. Corresponding reading of Exhibits P19, P20 and P21 would

show that the work which was carried out by the appellant /

plaintiff was in the year 2004. These letters nowhere

acknowledge the fact of any outstanding dues of liability.

Irrespective of the merit as to whether demand was legal or

not, prima facie, by application of the Article 18 of the

Limitation Act, 1963 would show that for the price of work

done by the plaintiff/ appellant for the defendant at his

request, where no time has been fixed for payment, time

limit for claim would be three years from the date of work.

For ready reference the Article 18 of the Limitation Act, 1963

is reproduced here under:-

FA No. 346 of 2016

Article Description of suit Period of Time from which limitation period begins to run

18 For the price of work done Three years When the work is by the plaintiff for the done.

defendant at his request, where no time has been fixed for payment.

11. Exhibit P21 which has been relied on by the plaintiff would

show that the work definitely was completed on 15.6.2004

reckoning such period from 15.6.2004, the limitation would

be for three years. The finding of the learned trial Court

since the notices were served by the plaintiff / appellant

calling upon to release the payment would save the

limitation, in our opinion appears to be wrong and this Court

in exercise of power conferred by Section 3 of the Limitation

Act, 1963 can very well go into such fact of limitation. Prima

facie, it appears that the suit filed by the plaintiff / appellant

in the year 2011 was beyond period of limitation.

12. Now coming to the other aspect of the merit, we went

through the clause of the agreement/ contract, marked as

Exhibit P12. The clause 7.9 which was referred by the

appellant purports that right to increase and decrease the

work is within the domain of the Engineer-in-charge during

the currency of the contract and the contractor will be bound

FA No. 346 of 2016

to comply with the order. In the instant case, the additional

work of laying down the bitumen was carried out as WBM

road was already existing and the specification of the work

which is shown in the Schedule group D also fortified those

facts about laying down of the bitumen over the road.

13. Clause 13 of the contract speaks about addition and

alterations in specification and design. For ready reference

Clause 13 of the contract is reproduced here under:-

"Clause 13 - The Engineer-in-charge shall have power to make any alterations in, comissions from additions to, or substitutions for, the original specifications drawings, designs and instruction, that may appear to him to be necessary or advisable during the progress of the work, and the contractor shall be bound to carry out the work in accordance with any instruction which may be given to him in writing signed by the Engineer-in-charge and such alterations omissions additions or substitution shall not invalidate the contract and any altered, additional or substituted work which the contractor may be directed to do in the manner above specified as part of the work shall be carried out by the contractor on the same conditions in all respects on which he agreed to do the main work and at the same rates as are specified in the tender for the main work, provided the total value of such increased or altered or substituted work does not exceed 25% of the amount put to tender, inclusive of contractor's percentage. If such value exceeds 25% it shall be open to the contractor either to determine the contract or apply for extension."

FA No. 346 of 2016

14.Reading of above clause would show that the Engineer-in-

charge shall have power to make any alterations in,

commissions from additions to, or substitution for, the

original specifications drawings, designs and instructions,

that may appear to him to be necessary or advisable during

the progress of the work.

15.According to the plaintiff, the additional work of bitumen was

carried out which is evident from the measurement book

Exhibit P22. The clause 13 specifically says that direction

for addition and alterations are required to be in writing. It

was not a case of the appellant that apart from the laying

down the bitumen over road Bangoli-Murra-Mohrenga or

Kosrangi- Farhada-Budgaon Koli, additional bitumen on

some other roads was laid down.

16.The plaintiff asserted that the quantity of the bitumen and

other materials exceeded to carry out the work in those

roads, therefore, how it would be within the ambit of addition

or alteration coupled with the fact that even such addition

and alterations are accepted, the requirement in writing was

absent.

17.The reliance placed in the matter of Venkatesh

Construction Company (Supra) by learned counsel for the

appellant would show that it was in respect of the extra work

FA No. 346 of 2016

done for the reason of seepage of water from nearby river

while carrying out foundation to a certain depth. Therefore,

extra earthwork, embankment work, extra bed concrete work

and extra stone masonry work was carried out. The case in

hand is a different one and would not come to help the

appellant as the appellant while accepting the tender to lay

down the bitumen over certain parts of the roads was aware

of the existing reality and without any written

communication, if extra/ additional work by appellant is

carried out, at the instance of some officer, claim cannot be

passed on to the State as it would be an apparent flagrant

breach of the conditions of terms of contract.

18.In view of such discussions, we are of the view that the

judgment and decree passed by the Court below, do not call

for any interference by this Court. Accordingly, the appeal

stands dismissed.

19.Decree be drawn accordingly. No order as to cost.

               SD/-                                        SD/-
         (Goutam Bhaduri)                        (N.K. Chandravanshi)
              Judge                                    Judge




Ayushi
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter