Wednesday, 13, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Inderchand Patni vs Assistant Engineer And Others
2022 Latest Caselaw 817 Chatt

Citation : 2022 Latest Caselaw 817 Chatt
Judgement Date : 17 February, 2022

Chattisgarh High Court
Inderchand Patni vs Assistant Engineer And Others on 17 February, 2022
                                          1

                                                                                  NAFR

             HIGH COURT OF CHHATTISGARH, BILASPUR

                                 FA No. 189 of 2009

    Inderchand Patni S/o Shri Gulab Chand Patni, Rice And Dal Mill,
     Nayapara, Durg, Tahsil and District Durg(CG)

                                                                           ---- Appellant

                                      Versus

   1. Assistant Engineer, Chhattisgarh State Electricity Board, Durg, District
      Durg (CG)

   2. Superintending Engineer, Chhattisgarh State Electricity Board, Durg,
      District Durg (CG)

   3. Chhattisgarh State Electricity Board, Through Superintending Engineer,
      Chhattisgarh State Electricity Board, Durg, District Durg (CG)

                                                                     ---- Respondents

For Appellant : Shri P.R. Patankar, Advocate appears along with Shri Vaibhav Dhar Diwan, Advocate For Respondents : Shri B.P. Gupta, Advocate

Single Bench : Hon'ble Shri Justice Sanjay S. Agrawal

Order on Board

17.02.2022

1. This appeal has been preferred by the Plaintiff under Section 96 of the

Code of Civil Procedure, 1908 (hereinafter referred to as the 'CPC'),

questioning the legality and propriety of the judgment and decree dated

19.08.2009, passed by 8th Additional District Judge(FTC), Durg(CG) in Civil

Suit No.1-B/2005, whereby the Plaintiff's claim for recovery of

Rs.1,21,000/- has been dismissed. The parties to this appeal shall be

referred hereinafter as per their description before the Court below.

2. Briefly stated the facts of the case are that the Plaintiff instituted a suit

claiming recovery of Rs.1,21,000/- by submitting, inter alia, that on

07.03.2002, some of the employees of the Chhattisgarh State Electricity

Board, the Defendants herein, inspected the electric meter in his absence

and when he approached them, it was informed that the seal of the electric

meter was tampered and he was liable to pay Rs.65,058/-. It is pleaded

further that since the said amount of Rs.65,058/- has been recovered

illegally owing to the inspection of the meter installed by them in his

absence and as the same has been obtained by threatening that in case

the same is not paid, an FIR would be lodged against him, therefore, he is

entitled to get back the said amount of Rs.65,058/- along with its interest,

i.e. Rs.23,420/-. It is pleaded further that the Plaintiff was the owner of the

Mill situated at Nayapara, Durg and electricity supply for the same was

done through Electric Meter No.62-01-90-92-900949 of 40 HP installed by

the Defendants at the distance of 150 meters away from the Mill and being

consumer, the Plaintiff paid all the dues. It is pleaded further that in the

year 2000-01, the consumption of the electricity was reduced to a

considerable extent, as such, the Plaintiff moved an application on

10.04.2001 for reducing the load from 40 HP to 25 HP and as per the

rules, the same was to be acted upon within the period of 2 months,

however, the Defendants have failed to entertain the said application within

the prescribed period and instead, the same has been done after a delay

of 10 months, therefore, the Plaintiff is entitled to a sum of Rs.32,850/-

towards damages. The Plaintiff is, thus, entitled to recovery for a total sum

of Rs.1,21,000/- along with interest @ 1 % per month from the date of

institution of the suit till its realization.

3. Defendants have contested the aforesaid claim by submitting, inter alia,

that the electric meter installed at the premises was in the name of Gulab

Chand Patni and not in the name of Plaintiff, Inder Chand Patni, and

therefore, the Plaintiff, who is not the consumer, is not entitled to institute

the suit. It is contested further on the ground that on 07.03.2002, the

Plaintiff was found guilty of tampering with the electric meter, as such,

additional fee of Rs.65,058/- was raised by the Defendants without any

undue influence or coercion, and therefore, the Plaintiff is not entitled to

any amount as claimed from the Defendants, which is even otherwise

barred by time.

4. After considering the evidence led by the parties, the trial Court arrived at

a conclusion that the Plaintiff is not the consumer of the Defendants and in

fact, his father, namely, Gulab Chand Patni was the consumer of the

Defendants. It held further that the alleged amount of Rs.65,058/- was not

recovered illegally from the Plaintiff as the electric meter, which was

inspected in his presence, was found to be tampered with by him and,

observed further that the claim of Rs.32,850/- towards damages is barred

by time. In consequence, the Plaintiff's claim has been dismissed vide

impugned judgment and decree, which has been questioned by way of this

appeal.

5. Learned counsel appearing for the Appellant submits that the finding of the

Court below holding that the alleged electric meter was inspected in

presence of the Plaintiff, is apparently contrary to law. It is contended

further that the Court below ought to have seen and held that his signature

on documentary evidence like, Panchanama (Ex.D-1) and seizure memo

(Ex.D-2) along with others were obtained by putting undue pressure on

him that if the said amount is not deposited, an FIR would be lodged

against him. Further contention of the counsel for the Plaintiff is that since

the application which was made on 10.04.2001 for reducing the load from

40 HP to 25 HP, was not decided in time, therefore, the Plaintiff's claim

with regard to damages of Rs.32,850/- ought not to have been refused.

6. On the other hand, learned counsel appearing for the Respondents has

supported the impugned judgment and decree as passed by the Court

below.

7. I have heard learned counsel for the parties and perused the entire record

carefully.

8. From perusal of the averments made in the plaint wherein, it has been

alleged that since the electric meter was inspected in his absence on

07.03.2002, and therefore, the alleged amount of Rs.65,058/- owing to

tampering of the electric meter has been recovered illegally from him by

putting undue pressure upon him that if the same is not deposited, an FIR

would be lodged against the Plaintiff. The burden to establish the said fact

is, therefore, upon the Plaintiff. However, from perusal of the documentary

evidence, particularly, Panchanama (Ex.D-1) and seizure memo (Ex.D-2),

both were executed on 07.03.2002, would reveal the fact that the alleged

meter was inspected in his presence as his signature was found in both

these documents. That apart, the Plaintiff in his evidence, particularly, at

para 21, has stated specifically that he has not lodged any complaint that

his signature has been obtained on 07.03.2002 on it by threatening and/or

by putting any undue influence upon him. In view thereof, merely on the

basis of his oral and bald statement, it cannot be said that the alleged

electric meter was inspected in his absence or the alleged amount of

Rs.65,058/- has been recovered illegally from him. The finding of the Court

below in this regard is, therefore, deserves to be and is hereby affirmed.

9. In so far as the recovery of amount of Rs.32,850/- towards damages is

concerned, the same appears to be barred by time. As it appears from the

record that an application dated 10.04.2001, made by the Plaintiff was

received by the Defendants on 24.04.2001, wherein, it was prayed for

reducing the load from 40 HP to 25 HP, was not decided within the period

of 2 months and, therefore, he is entitled to the alleged amount of

damages. It, however, appears that the requisite period of two months

expired on 23.06.2001 as such, the claim in this regard should have been

made within the period of three years from it, i.e. by 24.04.2004 but, it was

made on 05.03.2005, i.e. much beyond the prescribed period of three

years. In view thereof, the damages as claimed by the Plaintiff has rightly

been refused by the trial Court by holding it to be barred by time.

10. In view of the aforesaid background, I do not find any substance in this

appeal. The appeal being devoid of merits is accordingly dismissed.

No order as to cost(s).

            A decree be drawn accordingly.                  Sd/-


                                                     (Sanjay S. Agrawal)
                                                           JUDGE

sunita
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter