Citation : 2022 Latest Caselaw 7594 Chatt
Judgement Date : 15 December, 2022
1
AFR
HIGH COURT OF CHHATTISGARH, BILASPUR
WP(C) No. 887 of 2017
M/s. Pitambara Construction and Company, Plot No. 318, Transport
Nagar Korba, District - Korba (C.G.) through its Partnet Rakesh Kumar
Mishra, S/o late Shri R.L. Mishra, aged about 44 years, R/o Rampur,
Korba, District - Korba (C.G.)
---- Petitioners
Versus
1. The State of Chhattisgarh, through Secretary, Department of
Public Health and Engineering, Mahanadi Bhawan, Naya Raipur,
District Raipur, Chhattisgarh
2. Superintending Engineer, Department of Public Health and
Engineering, PHE Circle, Bilaspur, District - Bilaspur (C.G.)
3. Executive Engineer, Department of Public Health and
Engineering, PHE Division, Korba, District - Korba
---- Respondents
(Cause Title taken from Case Information System) ________________________________________________________ For Petitioner : Mr. A. K. Prasad, Advocate
For Respondents : Ms. Astha Shukla, Government Advocate
Date of Hearing : 24.11.2022 Date of Judgment : 15.12.2022 ________________________________________________________ Hon'ble Mr. Arup Kumar Goswami, Chief Justice
Hon'ble Mr. Sanjay Agrawal, Judge
C A V Judgment
Per Arup Kumar Goswami, Chief Justice
Heard Mr. A.K. Prasad, learned counsel for the petitioner. Also
heard Ms. Astha Shukla, learned Government Advocate, appearing for
the respondents.
2. The petitioner is a partnership firm and is engaged in construction
work as well as general work order supply.
3. The petitioner had participated in response to a Notice Inviting
Tender (NIT) dated 28.05.2016 floated by the respondent No. 3, i.e.,
Executive Engineer, bearing No. 15/SAC for construction of RCC
elevated service reservoir 100 K.L. capacity 12 meter staging
(including providing and fixing of all pipes, specials and fitting etc.) at
Livelihood College and ITI Rampur, Korba for an estimated cost of Rs.
11.97 lacs. The period of completion of the work was stipulated to be
six months including rainy season.
4. The petitioner having emerged as the successful tenderer, a work
order dated 20.10.2016 was issued to the petitioner for an amount of
Rs. 14.468 lacs. It is pleaded that while 90% of the work of water tank
had been completed, on 01.04.2017, the petitioner came to learn that
an NIT dated 25.03.2017 for the very same work, for which the work
order was issued to the petitioner, was floated and on enquiry, the
petitioner further came to learn that the respondent No.3, i.e. Executive
Engineer, Department of Public Health and Engineering, is going to
forfeit the term deposit amount deposited by it. It is also pleaded that
the authorities had earlier assured that bill submitted by the petitioner
would be finalized after execution of the complete work and, in the
process, not a single penny was paid to the petitioner.
5. On the above factual background, the writ petition was filed for
quashing the NIT dated 25.03.2017.
6. The writ petition came to be filed on 03.04.2017 and this Court
passed an order on 11.04.2017 providing that if the work awarded to
the petitioner has not been terminated, he will be permitted to continue
with the work for the time being. Subsequently, the petitioner filed an
amendment application on 02.10.2017, which was allowed by an order
dated 03.12.2019. By the said amendment, the petitioner pleaded that
during the pendency of the petition, the petitioner had completed the
work within the prescribed period of time. However, final measurement
of the constructed water tank had not been done. An additional prayer
was made praying for a direction to the respondents to take final
measurement of the constructed water tank and to pay final bill amount
to the petitioner.
7. The respondent Nos. 1 to 3 filed a return on 04.10.2017, wherein
preliminary objections were also raised. It is pleaded that a letter dated
20.09.2016 was issued to the petitioner informing him that his bid was
accepted and that he should report to the Office within seven days of
receiving the letter for signing the agreement. However, the petitioner
did not turn up. A letter dated 01.10.2016 was thereafter issued stating
that as the petitioner did not appear, as directed, the bid of the
petitioner was cancelled and the earnest money was forfeited.
However, in view of an apology letter being received from the petitioner
on 07.10.2016, by a letter dated 14.10.2016, a further period of seven
days was granted to the petitioner for signing the agreement. The
agreement having been signed on 20.10.2016, the work order was
issued to the petitioner on 20.10.2016 itself. It is stated that though
directed by letter dated 20.10.2016, the petitioner had not submitted
the Soil Bearing Capacity (SBC) test report. Letters dated 30.11.2016
and 09.12.2016 were issued in that context and it is stated that by the
letter dated 09.12.2016, the petitioner was directed to submit the SBC
test report and thereafter, to obtain approval of the design and drawing
and then to commence work of construction of the water reservoir as
per the approved drawing and design. However, without submitting
any SBC test report, the petitioner submitted drawing and design for
approval as per Clause 6.0 of the Annexure E-I of the NIT. As the SBC
test report was not submitted, the drawing and design report submitted
for approval was rejected and returned to the petitioner in original. As
thereafter also the SBC test report was not submitted, invoking
Clauses 13 and 14 of the Conditions of Contract, the work awarded in
favour of the petitioner was terminated by letter dated 25.03.2017
forfeiting the earnest money deposit and informing the petitioner that
a fresh NIT would be initiated and the work would be completed
through a different agency and that difference of amount would be
recovered from the petitioner as recovery of land revenue and
thereafter, on the very next date, fresh NIT was issued for the work in
question.
8. With regard to the claim of the petitioner that 90% work has been
completed, it is stated that such work cannot be certified as the
construction was made without furnishing the SBC test report and
without approval of the drawing and design, as also for not having been
constructed under the supervision of the respondents. The allegation
of submitting SBC test report, as stated in paragraph 8.4 of the writ
petition, was specifically denied.
9. The petitioner filed another application being I.A. No. 03 of 2017,
praying to add paragraphs 8.19 to 8.31 after proposed paragraph 8.18
of the earlier application for amendment, paragraphs 9.14 to 9.28 after
proposed paragraph 9.13 of the earlier application for amendment and
also a prayer as paragraph 10.5 after proposed paragraph 10.4 of the
earlier application for amendment. The first application for amendment
dated 02.10.2017 was registered as I.A. No. 02 of 2017 and the
second application for amendment dated 25.11.2017 was registered as
I.A. No. 03 of 2017. Order-sheet of the Court does not indicate that
any order was passed on I.A. No. 02 of 2017. However, by the order
dated 03.12.2019, I.A. No. 03 of 2017 was allowed. Consolidated writ
application was filed by the petitioner also incorporating the
amendment sought for vide I.A. No. 02 of 2017, though not allowed by
the Court, presuming that I.A. No. 2 of 2017 was also allowed by this
Court. Be that as it may.
10. By the I.A. No. 03 of 2017, the petitioner had pleaded that after
filing of the return of the respondents on 04.10.2017, the petitioner had
come to learn about the order dated 25.03.2017. It is pleaded that the
same was never communicated to the petitioner. It is asserted that the
petitioner had submitted SBC test report before the Department before
commencement of the work alloted to him and the said SBC test report
was approved by Superintending Engineer by letter dated 17.02.2017.
It is pleaded that when the Executive Engineer sought approval from
Superintending Engineer for issuance of a fresh NIT for construction of
the water tank at the risk and cost of the petitioner, the Superintending
Engineer by a letter dated 11.04.2017 disapproved the issuance of NIT
and cancellation of the tender. Nonetheless, the Executive Engineer
went ahead to issue the NIT on 25.03.2017. It is pleaded that the
respondents had inspected the construction work from time to time and
had not raised any objection with regard to the quality of the work and
accordingly, had denied the allegation made that the petitioner had
constructed the water tank without SBC test report and without
approval of drawing and design. The petitioner had also enclosed a
SBC test report. An additional prayer for quashing the termination
order dated 25.03.2017 was also made.
11. On the date of filing of I.A. No. 03 of 2017, the petitioner had also
filed a rejoinder to the return filed by the respondents. In the said
rejoinder, it is stated by the petitioner that the petitioner had filed
application for SBC test report before Engineering College, Bilaspur.
But, as the authority expressed inability to give the report within a short
time and stated that they would require three months time to visit the
site, petitioner wrote a letter to the respondent No.3 for testing to be
conducted by the Public Health and Engineering Department, upon
which, the petitioner was verbally instructed to get the SBC test report
from Chhattisgarh Water Resources Department, Minimata Bango
Quality Control Central Laboratory and accordingly, the petitioner had
made an application, based on which, soil was tested on 29.12.2016
and report was given on 13.01.2017. The petitioner had not only given
SBC test report, but had also submitted material testing report and that
it had also submitted drawing and design, which was duly approved by
the respondent No.3. The construction work of the petitioner was
inspected by the Sub Divisional Officer and the Sub-Engineer and they
had expressed their satisfaction and had not raised any objection in
respect of the work done, which was completed on 19.04.2017.
12. An additional return came to be filed by the respondents on
04.04.2018. In the said additional return, it is categorically denied that
any SBC test report was submitted to the office of the respondent No.3
or in the office of Assistant Engineer, PHE, Korba. It is stated that the
cost of construction of the overhead tank was provided by the office of
the Collector and District Magistrate, Korba under the head of DMFT
and when a visit was made by the Collector to the work site on
25.03.2017, no work was found to be done by the petitioner and
therefore, the contract was terminated. Accordingly, it is stated that the
plea taken by the petitioner that he has completed work on 19.04.2017,
when work was not even started on 25.03.2017, is without any basis.
Even if any construction was raised, no sanctity can be given to such
construction as the same has been constructed without any SBC test
report and without approval of drawing and design. It is stated that
staircase of a similar overhead tank constructed by another contractor
without SBC test report at Village - Basibar, Block - Pali had collapsed
during the testing of the overhead tank and the tank also was tilted.
13. The petitioner filed a covering memo dated 07.01.2020 without
any affidavit showing that one M/s. S.K. Enterprises, Korba has been
granted final bill for construction of RCC overhead tank at Village -
Rampur based upon testing report of Assistant Research Officer, Mini
Mata Hasdev Bango Quality Control Sub Unit, Darri.
14. Noticing from the pleadings of the petitioner that two authorities,
i.e., Executive Engineer and Superintending Engineer seem to take
different stands, this Court required the Secretary of the Public Health
and Engineering Department to file an affidavit and, accordingly, the
Secretary had filed an affidavit on 04.11.2022. It is stated that as per
Clause 3.1 of Annexure-E of the NIT, the petitioner was under an
obligation to submit the plate load bearing test report conducted by
Government Engineering College, Bilaspur and under Clause 6.0 of
Annexure-E-1 of the NIT, after obtaining approval of the design and
drawings from the competent authority, the petitioner was to
commence the work. In the said affidavit, the Secretary, while
reiterating the stand taken in the return submitted on 04.10.2017, has
stated that the order dated 05.03.2017 was duly communicated to the
petitioner through registered post. The postal receipt dated 27.03.2017
was enclosed. With regard to the letter dated 17.02.2017, it is stated
that SBC test report was approved by the Superintending Engineer in
respect of another work, namely, construction of RCC elevated service
reservoir 50 KL capacity at village Rampur and not for the work related
to the petitioner. It is stated that competent authority for grant of
technical sanction for the work in question is the Executive Engineer.
15. A rejoinder-affidavit dated 20.11.2022 was filed by the petitioner
to the aforesaid affidavit of the Secretary. In the said affidavit, the
petitioner reiterated that the Superintending Engineer had considered
the SBC test report given by the petitioner as well as M/s. S.K.
Enterprises and that both the test reports were approved.
16. Mr. A.K. Prasad, learned counsel for the petitioner, submits that
SBC test report and the drawings and design were duly approved by
the Superintending Engineer and that the construction was undertaken
under the supervision of the officials of the respondents and therefore,
when the petitioner has completed the work within the stipulated period
of time, the respondents had acted illegally and arbitrarily in issuing the
cancellation of the work order dated 25.03.2017 as well as in issuing
the second NIT. It is submitted that without any justification the
payment of the petitioner is held up on the specious plea that the
petitioner had constructed the water tank without SBC test report and
without approval of the drawing and design. It is submitted that as the
Government Engineering College, Bilaspur had expressed its inability
to furnish the SBC test report for which they said that they would
require three months, on the oral instructions of the respondent No.3,
the SBC test report was obtained from the Chhattisgarh Water
Resources Department, Minimata Bango Quality Control Central
Laboratory and the same was also duly got approved by the
Superintending Engineer alongwith designs and drawings on
17.02.2017.
17. On the other hand, Mr. Gagan Tiwari, learned Deputy
Government Advocate, appearing for the respondents, submits that
the SBC test report, drawings and designs were not approved by the
Superintending Engineer as alleged and whatever construction was
made by the petitioner was without the same and therefore, the order
dated 25.03.2017 was issued cancelling the work order of the
petitioner. The construction raised by the petitioner cannot be certified
in absence of the drawing and design not being approved and also the
construction having not been supervised by the officials of the
respondents. It is submitted by him that it is also not understood why
the petitioner had allegedly submitted the SBC test report to the
Superintending Engineer when the Executive Engineer is the
competent authority in respect of the work in question. In the
circumstances of the case, it is submitted by him that no case is made
out for granting reliefs to the petitioner, as prayed for.
18. We have considered the submissions of the learned counsel for
the parties and have perused the materials on record.
19. Perusal of the work order dated 20.10.2016 goes to show that the
petitioner was asked to submit SBC test report along with test report of
metals and steel etc. Clause 3.1 of Annexure-E of the tender document
provides that the plate load bearing test should be conducted by
Government Engineering College, Bilaspur for safe bearing capacity at
proposed site below 3 m from ground level. Clause 30.0 lays down
that the tenderer shall have to produce the complete design and
working drawing of each component of structure before starting of
work. Clause 6.0 of Annexure-E-I dealing with special conditions
provides that the contractor will submit the detail design and drawings
of the R.C.C. elevated reservoirs within 30 days from the date of issue
of written order to commence the work for approval of the competent
authority of the Department in five copies.
20. Clauses 13 and 14 of the conditions of contract read as follows :
"13. The works comprised in this tender are to be
commenced immediately upon receipt of the order
commencement given in writing by the E.E. when
possession of aforesaid (but excluding such if any as
may have been postponed by an order from the E.E.)
shall be completed in every respect within 04 months
excluding rainy season from the date of issue of the
aforesaid order and if from any cause whatever other
than wilful obstruction or defaults, on the part of E.E.
or his staff and except as hereinafter provided the
whole of such work shall not be finished to the
satisfaction of the E.E. within the said period, the
contractor(s) shall forfeit to the Governor of C.G. from
his/their security deposit by way of ascertained and
liquidated damages for each defaults and not by way
of penalty, the sum of Rs.3,500/- (Rupee Three
Thousand Five Hundred only) per day for every
completed day of such default provided that the entire
amount of damage to be forfeited under the provisions
of this clause shall not exceed 10% on the whole work
as shown in the tender.
Provided nevertheless that if the contractor(s) shall
be of the opinion that he/they is/are entitled to any
extension of time on account of the works being
altered, varied or added to or on account of any delay
by reason of any inclement whether or causes not
under the control of the contractor(s) in consequence
of orders to that effect from the E.E. himself which
orders, the such cases it shall be competent for E.E.
by an order in writing to extend the aforesaid period
for final completion by such period or periods as he
shall deem reasonable and the contractor(s) is/are to
complete the works within such extended period or
periods as aforesaid. Provided that the contractor(s)
shall not be entitled to any extension of time unless
he/they shall consider himself/themselves entitled to
any extension to the E.E. giving written notice of such
claim to any extension of time and of the ground or
grounds and of the amount thereof unless in any case
the E.E. shall in his discretion dispense with such
notice and certify for a extension of time. Nevertheless
and in case of any extension of time, the aforesaid
provision with amount for damage in defaults in due
completion shall apply in case of non completion of
the works within the extended time. Provided that the
Contractors shall be entitled to any extension of time
in respect of the extra work involved in extra depth of
foundation mentioned in clause 5.
14. If the contractor(s) shall become bankrupt or
compound with or make any assignment for the
benefit of his/their creditors or shall suspend or delay
the performance of his/their part of the contract
(Except on account of causes mentioned in clauses
13 or in consequence of not having proper instructions
for which the contractor(s) shall have dully applied).
The E.E. may give to the Contractor(s) or his/their
assignee or trustee, as the case may be, notice
requiring the work to be proceeded with."
21. The order dated 25.03.2017 reads as follows :
**dk;kZy; dk;Zikyu vfHk;ark yksd LokLF; ;kaf=dh foHkkx] [k.M & dksjck (N-x-) I.T.I. Chowk, Rampur, Korba (C.G.) Contact No. : 07759-228663 (O), Toll Free No. 18002330008, E-mail : [email protected] _____________________________________________________________________________ i= [email protected]@ys-'[email protected]@yks-Lok-;[email protected] dksjck fnukad 25&3&17 izfr] esllZ firkEcjk daLVªD'ku ,.M daiuh IykV ua- 318] Vh-ih- uxj dksjck ftyk dksjck ¼N-x-½ eksckbZy ua- & 09977153939
fo"k; %& ykbZOgyhgqM dkyst ,oa vkbZ-Vh-vkbZ- jkeiqj dkyst dksjck esa 100 fd-yh- {kerk ,oa 12 eh- ÅapkbZ ds vkj-lh-lh- mPp Lrjh; dk tykxkj fuekZ.k dk;Z dk vuqca/k lekIr djus ckcr~ lwpuk A lanHkZ %& ¼1½ vuqca/k dzekad [email protected],y- 2016&17 ykbZOgyhgqM dkyst ,oa vkbZ-Vh-vkbZ jk;iqj dkyst dksjck A ¼2½ dk;kZns'k dzekad [email protected]'[email protected] 01-10-2016 ¼3½ bl dk;kZy; dk i= dz- [email protected]'[email protected] 20-10-2016 ¼4½ bl dk;kZy; dk i= dz- [email protected]'[email protected] 30-11-2016 ¼5½ lgk;d vfHk;ark] dksjck dk i= dz- [email protected] 02-12-2016 ¼6½ bl dk;kZy; dk i= dz- [email protected]'[email protected] 09-12-2016 ¼7½ dysDVj dksjck ls nwjHkk"k ij ppkZ fnukad 25-03-2017 &&&&&00&&&& mijksDr lanfHkZr vuqca/k ds rgr~ vkidks ykbZOgyhgqM dkyst ,oa vkbZ-Vh-vkbZ- jkeiqj dkyst dksjck esa 100 fd-yh- {kerk ,oa 12 eh- ÅapkbZ ds vkj-lh- lh- mPp Lrjh; dk tykxkj fuekZ.k dk;Z dk dk;kZns'k fn;k x;k Fkk] ijUrq vR;ar [ksn dk fo"k; gS fd v/kksgLrk{kjdrkZ }kjk vusdks ckj fyf[kr ,oa ekSf[kr funsZ'k nsus ds i'pkr~ Hkh vkids }kjk vkt fnukad rd vuqca/k vuqlkj SBC Test Report izLrqr ugha fd;k gS A ftls ,slk izrhr gksrk gS fd vki mDr dk;Z djus gsrq bPNqd ugha gS A vr% vuqca/k dh /kkjk 13 ,oa 14 ds rgr~ vuqca/k fujLr fd;k tkrk
gS ,oa tek tekur jkf'k 'kklu ds i{k esa jktlkr fd;k tkrk gS A iqu% fufonk vkea=.k djus dh dk;Zokgh dh tkosxh ,oa vU; ,tsalh ds ek/;e ls dk;Z iw.kZ djk;k tkosxk A ftl ij vkus okyh varj dh jkf'k vkil Hkw&jktLo lafgrk ds rgr~ olwyh dh tkosdh A lkFk gh foHkkx }kjk vkeaf=r fufonk esa Hkkx ysus gsrq 01 o"kZ ds fy, i`Fkd fd;k tkrk gS A [email protected] dk;Zikyu vfHk;ark yksd LokLF; ;kaf=dh foHkkx [k.M&dksjck ¼N-x-½
ia-i= [email protected]@ys-'[email protected]@yks-Lok-;[email protected] dksjck fnukad 25&3&17 izfrfyfi %& 1- eq[; vfHk;ark] yksd LokLF; ;kaf=dh foHkkx] fcykliqj ifj{ks= fcykliqj ¼N-x-½ dh vksj lknj lwpukFkZ lEizsf"kr A 2- dysDVj] ftyk&dksjck dh vksj nwjHkk"k ij gqbZ ppkZuqlkj fnukad 25-03-2017 ds lanHkZ esa lknj lwpukFkZ laizsf"kr A 3- v/kh{k.k vfHk;ark] yksd LokLF; ;kaf=dh foHkkx] fcykliqj e.My fcykliqj dh vkj lknj lwpukFkZ laiszf"kr A 4- lgk;d vfHk;ark] yksd LokLF; ;kaf=dh] mi[k.M dksjck dh vksj lwpukFkZ A
[email protected] dk;Zikyu vfHk;ark yksd LokLF; ;kaf=dh foHkkx [k.M&dksjck ¼N-x-½**
22. Though Clauses 13 and 14 aforesaid do not prescribe termination
of contract, it appears that since SBC test report was not produced, it
was opined that the petitioner was not interested to do the work. It is
also relevant to note that by that time, almost five months had elapsed
from the date of issuance of the work order. The order of this Court
dated 11.04.2017 provided that the petitioner would be permitted to
continue with the work if the work awarded to the petitioner has not
been terminated. The work order was cancelled on 25.03.2017 and
therefore, the order dated 11.04.2017 will not enure to the benefit of
the petitioner and it is the own case of the petitioner that during the
pendency of the writ petition only he had completed the work. How
the petitioner could continue with the work after the work order was
terminated is not understood.
23. In the letter dated 17.02.2017 of the Superintending Engineer,
though there is reference to the presence of a representative of the
petitioner, it does not appear that SBC test report of the petitioner was
approved. In the said letter dated 17.02.2017, there is reference of
letter No. 6588 dated 20.10.2016 of the Executive Engineer. The letter
No. 6588 dated 20.10.2016 relates to M/s. S.K. Enterprises. In the
said letter dated 17.02.2017, there is also a reference to a letter No. 22
dated 08.12.2016. The date 08.12.2016 is wrongly recorded there and
it should have been 08.11.2016. The said letter was issued by M/s.
S.K. Enterprises and the same is available at page 90 of the reply-
affidavit filed by the Secretary. Therefore, it does appear to the Court
that approval contained in the said letter dated 17.02.2017 relates to
the SBC test report of the petitioner. Even assuming that there was a
SBC test report of another Government organization, though the
petitioner was required to submit such report from Government
Engineering College, Bilaspur, materials on record do not demonstrate
that the drawing and design was approved by the Executive Engineer
as required in terms of Clause 6.0 of Annexure-E-I. There is also no
material on record to indicate that the construction work was done
under the supervision of the officials of the Department.
24. In view of the materials on record, as obtaining, we are of the
considered opinion that the petitioner has failed to make out a case for
granting reliefs, as prayed for, in exercise of powers under Article 226
of the Constitution of India.
25. Taking that view, the writ petition is dismissed.
Sd/- Sd/-
(Arup Kumar Goswami) (Sanjay Agrawal)
CHIEF JUSTICE JUDGE
Chandra
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!