Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Jai Loknath Baba Land Devlopers ... vs Shyam Yadav
2022 Latest Caselaw 3131 Chatt

Citation : 2022 Latest Caselaw 3131 Chatt
Judgement Date : 29 April, 2022

Chattisgarh High Court
Jai Loknath Baba Land Devlopers ... vs Shyam Yadav on 29 April, 2022
                                 1

                                                            NAFR
      HIGH COURT OF CHHATTISGARH, BILASPUR
                       MA No. 94 of 2017

                Judgment Reserved on : 25/02/2022
                Judgment Delivered on : 29/04/2022



     Jai Loknath Baba Land Developers Pvt.Ltd. Company, Through
      Director Smt. Jagdish Kour Peri, aged 41 years, W/o Shri Peri
      Chandrashekhar D/o Shri Atam Singh, registered under the
      Company Act 1956. Registered Office at LiG 108, Tilak Nagar,
      Gudhiyari, Raipur, Tehsil & District Raipur (C.G.)
                                                     ---- Appellant
                             Versus

  1. Shyam Yadav, W/o Late Shri Manrakhan Yadav, Aged About
     33 Years.
  2. Smt. Ranu Yadav, W/o Late Shri Ramavtar Yadav, Aged About
     28 Years.
  3. Minor Ku. Triveni Yadav, D/o Late Shri Ramavtar Yadav, Aged
     About 8 Years Through Guardian Mother Smt. Ranu Yadav,
     W/o Late Shri Ramavtar Yadav.
  4. Radha Yadav, D/o Late Shri Manrakhan Yadav, Aged About 38
     Years.
  5. Smt. Mina Yadav, D/o Late Shri Manrakhan Yadav, Aged About
     60 Years.
      All are R/o Shukrvari Bazar, Gudhiyari, Raipur, Tehsil And
      District- Raipur, Chhattisgarh.
  6. State Of Chhattisgarh, Through Collector, Raipur, Tehsil And
     District- Raipur, Chhattisgarh.
  7. M/s Reliable Infra, Through Partner Koustubh Sharma, S/o N.K.
     Sharma, R/o Shyam Dixit Complex, K.K. Road, Moudhapara,
     Raipur, Chhattisgarh.
                                                ---- Respondents

For Applicant : Mr. Anand Prakash Sharma and Mr. Manish Thakur, Advocates.

For Respondents 1 to 5 :     Mr. Mr. Prafull N. Bharat, learned Sr.
&7                           Advocate with Mr. Keshav Dewangan,
                             Advocate.
For State/R-6          :     Mr. Amit Singh Chouhan, P.L.


                Hon'ble Smt. Justice Rajani Dubey

                           CAV Order



29/04/2022

1. The appellant/plaintiff has preferred this miscellaneous

appeal being aggrieved by the judgment and order dated

18.05.2017 passed in Civil Suit No.112-A/2015 by the 4 th

Additional District Judge to the Court of 1st Additional District

Judge, Raipur (C.G.), whereby the learned Additional District

Judge dismissed the application filed by the appellant/plaintiff

under Order 39 Rule 1 and 2 read with section 151 of the

Code of Civil Procedure.

2. Briefly stated facts of the case are that the appellant/plaintiff

had filed a civil suit for specific performance of the contract

dated 10.08.2010 executed between respondents/defendants

No. 1 to 5 and appellant/plaintiff for sale of land bearing

Khasra No. 882/1 area 0.420 hectare, Khasra No.884 area

4.770 hectare, total two khasra area of which is 5.190

hectare, about 13 acres, situated at village Nakta, P.H.

No.74/13, R.I. Circle Mandir Hasoud Tehsil - Arang, District

Raipur (C.G.) (hereinafter referred to as the 'disputed land')

for sale consideration of Rs.9,00,000/- per acre. According to

the agreement, the appellant/plaintiff's company executed it

on 10.08.2010 and the same got notarized on 12.08.2010.

Thereafter, on 11.09.2010, land development agreement was

also executed between them, which was duly registered on

14.06.2010, got the possession of disputed land, completed

planning work and also constructed the boundary wall.

During this, the respondents/defendant Nos. 1 to 5 were

asked to execute the sale deed of the disputed land after

receiving balance amount of the disputed land, but the

respondent/defendant No.1-Shyam Yadav expressed that

they have to purchase another agricultural land out of the

amount of sale consideration of the disputed land. Since, the

deal to buy the land elsewhere has not been done, the

respondents/defendants do not want to sell the disputed land

and in due time, the sale deed of the disputed land would be

executed in favor of the appellant/plaintiff's company after

getting the balance amount of sale consideration. Till date

the appellant/plaintiff has made payment of Rs.45,00,000/- to

respondents/defendants as advance against the disputed

land, but excuses have been made by the

respondent/defendant No.1 for execution and registration of

the disputed land owing to non performance of deal to

purchase the land elsewhere by him. Pursuant to the sale

agreement, the appellant/plaintiff obtained the possession of

the disputed land and Rs. 25,00,000/- has been spent by him

for leveling the ground, constructed boundary wall, boring,

excavation work etc. around the land and the license was

duly obtained for the construction of the colony for

residential purpose as also obtained permission for approach

road while getting the land diverted. In the meanwhile, on

07.04.2012, a notice has been sent by the

respondents/defendants No. 1 to 5 stating therein that in

terms of the agreement dated 10.08.2010, the said

agreement has been canceled due to non execution of sale

deed of the disputed land by the appellant/plaintiff's

company within the prescribed time period of 6 months,

whereas the fact is that till 29.11.2011 an additional amount

of Rs.30,00,000/- has been taken by the

respondent/defendant No.1 for keeping the agreement in

force. The respondents/defendants No.1 to 5 were requested

several times by the appellant/plaintiff's company for

execution of sale deed. On 07.06.2012, a reminder letter was

also sent to the respondent/defendant No.1, to which the

respondent/defendant No.1, vide his letter dated 18.06.2012,

refused to execute and register the sale deed of the disputed

land. In the meanwhile, on 10.10.2012,

respondent/defendant No.1 had published a public notice in

daily news-paper with regard to illegal sale of the disputed

land, thereafter, a report was made by the appellant/plaintiff

in the police station Gol Bazar, pursuant to which, an FIR

under Section 420/34 of the IPC has been registered against

the respondents/defendants No. 1 to 5. The said case is

pending before the ACJM, Raipur as Criminal Case

No.1192/2013. The respondents/defendants are continuously

making efforts to sell the disputed land to someone else,

therefore, the appellant/plaintiff has filed the civil suit as also

filed an application under Order 39 Rule 1 and 2 of C.P.C. for

grant of interim injunction.

3. The respondents/defendants, in their written statements,

refuted all the allegations made against them and averred &

blamed the appellant/plaintiff for non execution of sale deed

stating that he is not willing to make registry of disputed land

within stipulated period of six months and plaintiff did not

pay the sale consideration. It has been also averred that the

agreement has been drafted in English and no Hindi format of

the same provided to them, therefore, the suit is not

maintainable. They have sent a notice through their advocate

for termination of agreement, thereafter, a false case has

been registered by the appellant/plaintiff against the

defendant.

4. The learned trial Court, after hearing argument of respective

parties and considering the material on record, dismissed the

application filed by the Appellant/plaintiff. Hence, this

appeal.

5. Learned counsel for the Appellant/plaintiff submits that the

learned trial Court has not considered the fact of execution of

agreement, according to which, the possession of the

disputed land was given to the Appellant/plaintiff for

development purpose and separate agreement has been

executed between the Appellant/plaintiff and

respondents/defendants No. 1 to 5. Thus, without taking back

the possession of disputed land, how it could be given to

defendant No. 7 just mentioning the fact that sale deed has

been executed on 11.12.2015, which the learned trial Court

has completely relied upon to decide the matter. He further

submits that the learned trial Court has failed to appreciate

the fact that the plaintiff is having complete possession of the

disputed land which is evident from the document that has

been admitted by the respondents/defendants No. 1 to 5.

The Appellant is always ready and willing to perform his part.

Learned counsel also submits that the Appellant/plaintiff has

carried out land development work and invested huge

amount and has prima-facie proved the case in his favour. It

has been further submitted that the learned trial Court has

completely ignored the fact that on 29.11.2011, the

respondent No. 1 has taken additional sum of Rs.30,00,000/-

to keep the agreement in force. It is next submitted that the

conduct of the respondents/defendants have not been

property appreciated which clearly show that they did not

send any kind of notice for performance of agreement. They

directly sent a notice of termination of agreement after a long

time i.e. on 07.04.2012. This very much conduct of the

respondents reflect their only objective and motive to sell the

disputed land to someone else knowing that delay on their

part is the reason of non performance of agreement. As

such, the impugned order is liable to be set aside and

injunction may be granted in favour of the appellant/plaintiff.

In addition to this, learned counsel also submits that the

respondents/defendants may be restrained to create any

third party interest of the disputed land.

6. On the other hand, learned counsel for respective

respondents supporting the impugned order submit that the

appellant/plaintiff has filed the civil suit after five years of

agreement dated 10.08.2010, which is clearly time barred

suit. As per agreement dated 10.08.2010, sale deed ought to

have been executed within six months but the

appellant/plaintiff never tried to execute the sale deed. The

petitioner company gave cheque of Rs.7,50,000/-, which was

dishonoured by the Bank and never spent Rs.25,00,000/- for

development work of the disputed land. Learned counsel

further submits that on 10.05.2011, the appellant/plaintiff

prepared Bank Development Agreement in English,

translated copy of which was not provided to them, therefore

also, the suit is not maintainable. Learned counsel also

submits that on 18.06.2012, a reminder was sent to the

appellant company for termination of agreement, thereafter,

an FIR was lodged against the respondents and filed this time

barred suit. There is no prima-facie case in favour of the

appellant/plaintiff and the learned trial Court has rightly

dismissed the application of the appellant/plaintiff.

7. I have heard learned counsel for the parties and perused the

material on record.

8. The appellant/plaintiff filed a copy of mutual agreement

dated 11.09.2016, which was executed between the

appellant/plaintiff company M/s Jai Loknath Baba Land

Developers Pvt. Ltd. and A.K. Daga. The learned trial Court,

on the basis of documents available, recorded the finding

that as per the agreement dated 10.08.2010, the

appellant/plaintiff had to pay remainder/balance amount to

the respondents/defendants within a period of six months

from the date of agreement but the appellant/plaintiff failed

to do so and, as such, the said agreement dated 10.08.2010

looses it efficacy and on 11.12.2015, respondents/defendants

No. 1 to 5 sold the entire disputed land to respondent No.7 by

registered sale deed. The appellant/plaintiff filed the civil suit

on 11.02.2015. The learned trial Court also observed that

appellant/plaintiff did not file any document showing their

possession on the disputed land, thus, prima-facie, case and

balance of convenience does not appear to be in favour of

the appellant/plaintiff.

9. The appellant/plaintiff has filed two documents one is mutual

agreement dated 11.09.2016 and agreement dated

10.09.2010 but did not file any document showing extension

of agreement dated 10.08.2010. That apart, the

appellant/plaintiff did not file civil suit for specific

performance of contract within three years from the

agreement and has filed the suit in the year 2015, and during

the pendency of suit, the disputed land was sold to

respondent No.7. As such, considering the facts and

circumstances of the present case, the finding recorded by

the learned trial Court does not appear to be illegal or

perverse and has rightly dismissed the application of the

applicant/plaintiff. The finding recorded by the learned trail

Court is in accordance with the law and basic principle of

injunction.

10. Appeal thus being devoid of merit is liable to be dismissed

and it is hereby dismissed. No order as to costs.

Sd/-

                                                                  (Rajani Dubey)
PKD                                                                   Judge
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter