Sunday, 10, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Arss - Sips (Jv) A Joint Venture vs Union Of India
2021 Latest Caselaw 3790 Chatt

Citation : 2021 Latest Caselaw 3790 Chatt
Judgement Date : 20 December, 2021

Chattisgarh High Court
Arss - Sips (Jv) A Joint Venture vs Union Of India on 20 December, 2021
                                                                           Arb. Appeal No.33/2020

                                           Page 1 of 27

                                                                                                AFR

                  HIGH COURT OF CHHATTISGARH, BILASPUR

                             Arbitration Appeal No.33 of 2020

                              Order reserved on: 25-11-2021

                              Order delivered on: 20-12-2021

   {Arising out of order dated 4-7-2020 passed in M.J.C.No.9/2020 by the
  Judge, Commercial Court (District Level), Nava Raipur, Atal Nagar, Distt.
                                    Raipur}

    1. ARSS - SIPS (JV), a Joint Venture, having its registered office at 129,
       Transport Center, Rohtak Road, Punjabi Baag, New Delhi

    2. M/s ARSS Infrastructure Projects Ltd., having its registered office at
       Plot No.38, Sector A, Zone D, Mancheswar Industrial Estate,
       Bhubaneswar, Odisha

    3. Shyam Indus Power Solutions Pvt. Ltd., having its registered office at
       Building No.16A, Najafgarh Road, Moti Nagar, Shivaji Marg, New
       Delhi - 110015
                                                              ---- Appellants

                                              Versus

    1. Union of India, through the Secretary, Ministry of Railways, Rail
       Bhawan, 1, Raisina Road, New Delhi

    2. South East Central Railway, through                           its     General     Manager,
       Headquarter, Bilaspur, Chhattisgarh

    3. Chief Administrative Officer (Construction), South East Central
       Railway, Bilaspur, Chhattisgarh

    4. Chief Engineer (Construction - I), South East Central Railway,
       Bilaspur, Chhattisgarh
                                                     ---- Respondents

------------------------------------------------------------------------------------------------------
For Appellants: Mr. Vijay Dubey and Mr. Amrito Das, Advocates.
For Respondents: Mr. H.S. Ahluwalia, Advocate.
------------------------------------------------------------------------------------------------------

                          Hon'ble Shri Sanjay K. Agrawal and
                         Hon'ble Shri Arvind Singh Chandel, JJ.

C.A.V. Order

Sanjay K. Agrawal, J.

1. Invoking the appellate jurisdiction of this Court under Section 37 of the Arb. Appeal No.33/2020

Arbitration and Conciliation Act, 1996 (for short, 'the AC Act'), the

appellants herein have called in question the impugned order dated 4-

7-2020 passed by the learned Judge, Commercial Court (District

Level), Nava Raipur, Atal Nagar, District Raipur, whereby the learned

Commercial Court has rejected the application filed by the appellants

herein seeking interim injunction under Section 9(1) of the AC Act

finding no merit and refused to restrain the respondents herein from

encashing the performance bank guarantee (PBG) to the extent of ₹

6,77,26,553/-.

2. Respondent No.2 South East Central Railway issued a notice inviting

tender for work in Lajkura-Raigarh Section for construction of 4 th line

between Jharsuguda and Bilaspur. The scope of the said work was

widening, including soil investigation, design of bridges, execution of

earthwork, minor bridges, major bridges, RUB, extension of FOB, staff

quarter and other service buildings, supply of ballast and other

miscellaneous works in which the appellants participated and were

declared successful bidders and consequently, letter of acceptance

(LOA) was issued in their favour on 21-9-2016. Accordingly,

agreement dated 13-6-2017 came to be executed between the parties

with a stipulation that the work will be completed within 24 months

from the date of issuance of LOA dated 21-9-2016 and accordingly,

the appellants submitted bank guarantee worth ₹ 6,77,26,553/- in

shape of performance bank guarantee (PBG) with the respondents as

per the terms and conditions of the NIT. However, thereafter, in the

course of execution of work, dispute arose between the parties

regarding laxity in performance and dissatisfaction with progress of

work, and when the work in question could not be completed within Arb. Appeal No.33/2020

the stipulated time despite several extensions given to the appellants,

ultimately, respondent No.2 terminated the contract on 2-1-2020 which

was called in question by the appellants herein before this Court by

filing W.P.(C)No.31/2020 and which was dismissed by this Court

(Division Bench) on 24-2-2020 giving liberty to the appellants to

invoke the arbitration clause, if any.

3. It is the case of the appellants that since arbitrator was not appointed

despite making application, thereafter, they filed application under

Section 9(1) of the AC Act on 28-2-2020 before the District Judge,

Bilaspur for grant of interim injunction, which was returned to the

appellants to file before the Commercial Court (District Level) after

coming into force of the Commercial Courts Act, 2015. In the said

application, it was pleaded that the contract period for completion of

the said contract was extended by the respondents herein up to 31-3-

2020 invoking clause 17-A of the general conditions of contract

without any penalty and without any liquidated damages, but the

contract in question has been terminated on 2-1-2020 prior to last date

of completion of work i.e. 31-3-2020, which is ex facie illegal and bad

in law and by which the appellants have prima facie case and are

entitled to obtain interim injunction under Section 9(1) of the AC Act.

4. The respondents filed reply to the said application filed under Section

9(1) of the AC Act before the Commercial Court opposing the said

application stating inter alia that the appellants have neither prima

facie case in their favour nor balance of convenience lies in their

favour and there is no irreparable loss to the appellants if the

application for interim injunction is rejected and as such, the

application is liable to be rejected.

Arb. Appeal No.33/2020

5. The learned Commercial Court by its impugned order rejected the

application holding that invocation of bank guarantee and payment

thereunder can be restrained only on three grounds namely, fraud,

irretrievable injury and special equity, but the appellants have not

setup any such ground out of the aforesaid three grounds for obtaining

injunction against invocation of bank guarantee and accordingly,

rejected the application which has been sought to be questioned by

way of this arbitration appeal.

6. Mr. Vijay Dubey and Mr. Amrito Das, learned counsel appearing for

the appellants herein, would submit that the learned Commercial

Court is absolutely unjustified in rejecting the application under

Section 9(1) of the AC Act. They would further submit that invocation

of bank guarantee in the present case is per se unjust, illegal and bad

in law because the respondents themselves extended the contract

under clause 17-A and they have not invoked clause 17-B of the

general conditions of contract meaning thereby that extension was not

because of any fault on the part of the contractor. However, even

before that, the contract was terminated on 2-1-2020 without

specifying under which clause the contract was found to be violated

either in terms of progress of work or otherwise. Relying upon the

decisions of the Supreme Court in the matters of Hindustan

Construction Co. Ltd. v. State of Bihar and others 1, Standard

Chartered Bank v. Heavy Engineering Corporation Ltd. and another 2

and Hindustan Steelworks Construction Ltd. v. Tarapore & Co. and

another3, they would submit that in such circumstances, the

respondents be restrained from invocation of performance bank 1 (1999) 8 SCC 436 2 (2020) 13 SCC 574 3 (1996) 5 SCC 34 Arb. Appeal No.33/2020

guarantee furnished by the appellants. Mr. Das, learned counsel,

would also submit that extension of contract period for completion of

work by virtue of clause 17-A of the general conditions of contract

would amount to "special equity" and that would furnish a ground for

grant of interim injunction restraining encashment of performance

bank guarantee and as such, the appeal deserves to be allowed and

the order of the Commercial Court deserves to be set-aside.

7. Mr. H.S. Ahluwalia, learned counsel appearing for the respondents,

would take preliminary objection stating inter alia that since now, the

Arbitral Tribunal has been constituted by the respondents by order

dated 23-11-2021, therefore, by virtue of sub-section (3) of Section 9

of the AC Act, arbitration appeal would not be maintainable and

remedy of the appellants, if any, is to approach the Arbitral Tribunal so

constituted for seeking any interim injunction. He would further submit

that earlier, when the appellants had approached this Court by filing a

writ petition challenging the order of termination of contract and

invocation of bank guarantee, an order was passed by the Division

Bench on 24-2-2020 in W.P.(C)No.31/2020 wherein, though, liberty

was granted to the petitioners to take remedy of seeking adjudication

of dispute by way of arbitration, observations were made on prima

facie consideration that the progress of work was not satisfactory. He

would also submit that such observation shows that prima facie

progress of work by the appellants was not found satisfactory,

therefore, the contract was terminated. Relying upon the decisions of

the Supreme Court in the matters of Gujarat Maritime Board v. Larsen

and Toubro Infrastructure Development Project Limited and another 4

4 (2016) 10 SCC 46 Arb. Appeal No.33/2020

and Andhra Pradesh Pollution Control Board v. CCL Products (India)

Limited5, learned counsel would submit that in such circumstances,

this Court would not normally interfere with invocation of bank

guarantee and as such, the learned Commercial Court has rightly

rejected the application for interim injunction filed by the appellants

and the instant appeal deserves to be dismissed.

8. Replying to the submission of learned counsel for the respondents

relating to applicability of Section 9(3) of the AC Act, Mr. Das, learned

counsel for the appellants, would submit that it is a case where

jurisdiction under Section 9(1) of the AC Act has been invoked by the

appellants on 28-2-2020 and Arbitral Tribunal has been constituted

only on 23-11-2021, therefore, sub-section (3) of Section 9 would not

be applicable and he would rely upon the decision of the Supreme

Court in the matter of Arcelor Mittal Nippon Steel India Ltd. v. Essar

Bulk Terminal Ltd.6 to buttress his submission.

9. We have heard learned counsel for the parties and considered their

rival submissions made herein-above and also went through the

record with utmost circumspection.

10. Upon hearing learned counsel for the parties and after going through

the record, following two questions emerge for consideration: -

1. Whether upon constitution of Arbitral Tribunal by respondent

No.2 on 23-11-2021, the instant arbitration appeal arising out of

rejection of application under Section 9(1) of the AC Act would

not be maintainable by virtue of Section 9(3) of the AC Act?

2. Whether the learned Commercial Court (District Level) is

5 (2019) 20 SCC 669 6 2021 SCC OnLine SC 718 Arb. Appeal No.33/2020

justified in rejecting the application filed by the appellants under

Section 9(1) of the AC Act seeking interim injunction against

revocation of bank guarantee to the extent of ₹ 6,77,26,553/-?

Answer to Question No.1: -

11. It is vehemently submitted by Mr. Ahluwalia, learned counsel for the

respondents herein, that during the pendency of appeal, Arbitral

Tribunal has been constituted on 23-11-2021, therefore, arbitration

appeal would not be maintainable and is hit by sub-section (3) of

Section 9 of the AC Act, whereas in reply to this, it is submitted by Mr.

Vijay Dubey and Mr. Amrito Das, learned counsel for the appellants

herein, that since application under Section 9(1) of the AC Act has

already been entertained by the learned Commercial Court on 4-3-

2020 and it has finally been decided by that Court on its merit on 4-7-

2020 against which this appeal has already been entertained by this

Court on 30-7-2020 by granting interim order in favour of the

appellants, therefore, Section 9(3) of the AC Act would not be a bar

for finally adjudicating this arbitration appeal and it is not hit by Section

9(3) of the AC Act.

12. The question is, what would be the effect of constitution of Arbitral

Tribunal by respondent No.2 on 23-11-2021 upon this arbitration

appeal in view of sub-section (3) of Section 9 of the AC Act?

13. This question is no longer res integra and it has authoritatively been

adjudicated by the Supreme Court in Arcelor Mittal Nippon Steel India

Ltd. (supra) in which in paragraph 2, the following questions were

framed for adjudication and determination:

"2. The short question of law raised in this appeal is, whether the Court has the power to entertain an application Arb. Appeal No.33/2020

under Section 9(1) of the Arbitration and Conciliation Act, 1996, hereinafter referred to as "the Arbitration Act", once an Arbitral Tribunal has been constituted and if so, what is the true meaning and purport of the expression "entertain" in Section 9(3) of the Arbitration Act. The next question is, whether the Court is obliged to examine the efficacy of the remedy under Section 17, before passing an order under Section 9(1) of the Arbitration Act, once an Arbitral Tribunal is constituted."

14. Their Lordships of the Supreme Court considered the above-stated

questions and in paragraph 95 held that the bar of Section 9(3) would

not operate, once an application has been entertained and taken up

for consideration. It was further held that it has never been the

legislative intent that even after an application under Section 9 of the

AC Act is finally heard, relief would have to be declined and the

parties have to be relegated to their remedy under Section 17 of the

AC Act. Finally, in paragraphs 107 and 108, their Lordships have held

that the bar of Section 9(3) operates where the application under

Section 9(1) had not been entertained till the constitution of the

Arbitral Tribunal, and observed as under: -

"107. It is reiterated that Section 9(1) enables the parties to an arbitration agreement to approach the appropriate Court for interim measures before the commencement of arbitral proceedings, during arbitral proceedings or at any time after the making of an arbitral award but before it is enforced and in accordance with Section 36 of the Arbitration Act. The bar of Section 9(3) operates where the application under Section 9(1) had not been entertained till the constitution of the Arbitral Tribunal. Ofcourse it hardly need be mentioned that even if an application under Section 9 had been entertained before the constitution of the Tribunal, the Court always has the discretion to direct the parties to approach the Arbitral Tribunal, if necessary by passing a limited order of interim protection, particularly when there has been a long time gap between hearings and the application has for all practical purposes, to be heard afresh, or the hearing has just commenced and is likely to consume a lot of time. In this case, the High Court Arb. Appeal No.33/2020

has rightly directed the Commercial Court to proceed to complete the adjudication.

108. For the reasons discussed above, the appeal is allowed only to the extent of clarifying that it shall not be necessary for the Commercial Court to consider the efficacy of relief under Section 17, since the application under Section 9 has already been entertained and considered by the Commercial Court. The judgment and order under appeal does not, otherwise, call for interference."

15. Reverting to the facts of the case in the light of the principles of law

laid down by their Lordships of the Supreme Court in Arcelor Mittal

Nippon Steel India Ltd. (supra), it is quite vivid that in the instant case,

application under Section 9(1) of the AC Act has been filed and

entertained by the Commercial Court and finally dismissed on merits

by order dated 4-7-2020 against which arbitration appeal has been

preferred on 10-7-2020 and entertained by granting interim order in

favour of the appellants herein on 30-7-2020 and therefore

constitution of Arbitral Tribunal by respondent No.2 on 23-11-2021

would not prevent this Court to decide this arbitration appeal filed

under Section 37 of the AC Act, calling in question the order rejecting

application under Section 9(1) of the AC Act finally on merits, which is

a continuation of proceeding under Section 9(1) of the AC Act. As

such, the preliminary objection raised on behalf of the respondents

that this arbitration appeal is not maintainable in view of constitution of

Arbitral Tribunal in terms of Section 9(3) of the AC Act, is hereby

overruled.

Answer to Question No.2: -

16. The question is, whether the learned Commercial Court (District Level)

is justified in rejecting the application under Section 9(1) of the AC Act Arb. Appeal No.33/2020

filed by the appellants restraining revocation of bank guarantee by the

Bank in favour of the respondents?

17. The appellants have furnished bank guarantee on 10-10-2016 in

favour of the respondent SECR to the extent of ₹ 6,77,26,553/-. It is

the performance bank guarantee by which the Bank has unequivocally

undertaken to pay the said amount to the respondents

notwithstanding any dispute or disputes raised by the contractor in

any suit or proceeding pending before any court or Tribunal relating

thereto to discharge their liability and the said amount is payable. As

such, the bank guarantee is an unconditional bank guarantee. Clause

1.35 of the Special Conditions of Contract relates to performance

guarantee payable wherever the contract is rescinded.

18. At this stage, before entering into the merits of the matter, it would be

appropriate to refer to the provisions contained in Section 126 of the

Indian Contract Act, 1872 which provides and which defines "Contract

of guarantee" as under: -

"126. "Contract of guarantee", "surety", "principal debtor" and "creditor".--A "contract of guarantee" is a contract to perform the promise, or discharge the liability, of a third person in case of his default. The person who gives the guarantee is called the "surety"; the person in respect of whose default the guarantee is given is called the "principal debtor", and the person to whom the guarantee is given is called the "creditor". A guarantee may be either oral or written."

19. Section 126 of the Indian Contract Act, 1872 defines a contract of

guarantee as "a contract to perform the promise, or discharge the

liability, of a third person in case of his default". A guarantee is an

undertaking to be collaterally responsible for the debt, default, or

miscarriage of another. The essentials of a contract of guarantee are:

Arb. Appeal No.33/2020

• The contract of guarantee must have all the essentials of a contract.

• There must be an existing debt, which should be recoverable.

• Existence of three parties in a contract of guarantee, ie, principal debtor, creditor, and surety.

• There must be a distinct promise by the surety to pay the debt in case of default by the principal debtor.

• The principal debtor must be primarily liable.

• The liability must be legally enforceable.

20. A bank guarantee is an independent and distinct contract between the

bank and the beneficiary and is not qualified by the terms of the

underlying transaction, or the primary contract between the person at

whose instance the bank guarantee is given and the beneficiary. The

nature of obligation of the bank is absolute, and not dependent upon

the inter se disputes or proceedings (see Hindustan Steel Works

Construction Ltd. v. Tarapore & Co.7). The bank is liable to pay as

soon as the demand is made by the creditor (see National Thermal

Power Corpn. Ltd. v. Flowmore Pvt. Ltd.8).

21. In the matter of Himadri Chemicals Industries Ltd. v. Coal Tar Refining

Co.9, the Supreme Court has held that in the matter of invocation of a

bank guarantee or letter of credit, a bank guarantee is an independent

and a separate contract and is absolute in nature. The existence of

disputes between the parties to the contract is not a ground for issuing

an order of injunction to restrain enforcement of a bank guarantee, or

letter of credit. In the matter of invocation, it is not open to a bank to

rely upon the terms of the underlying contract between the parties.

7 (1996) 5 SCC 34 8 (1995) 4 SCC 515 9 (2007) 8 SCC 110 Arb. Appeal No.33/2020

Their Lordships of the Supreme Court have enunciated the following

principles in the matter of injunction for restraining encashment of a

bank guarantee or a letter of credit: -

(i) While dealing with an application for injunction in the course of

commercial dealings, and when an unconditional bank guarantee or

letter of credit is given or accepted, the beneficiary is entitled to

realize such a bank guarantee or a letter of credit in terms thereof

irrespective of any pending disputes relating to the terms of the

contract.

(ii) The bank giving such guarantee is bound to honour it as per its

terms, irrespective of any dispute raised by its customer.

(iii) The courts should be slow in granting an order of injunction to

restrain the realization of a bank guarantee or a letter of credit.

(iv) Since a bank guarantee or a letter of credit is an independent

and a separate contract and is absolute in nature, the existence of

any dispute between the parties to the contract is not a ground for

issuing an order of injunction to restrain enforcement of bank

guarantee or letter of credit.

(v) Injunction against encashment may be granted if there is fraud

of an egregious nature which would vitiate the very foundation of

such a bank guarantee or letter of credit, and the beneficiary seeks

to take advantage of the situation.

(vi) Allowing encashment of an unconditional bank guarantee or a

letter of credit would result in irretrievable harm or injustice to one of

the parties concerned.

22. The principle laid down in Himadri Chemicals Industries Ltd. (supra) Arb. Appeal No.33/2020

was followed by the Supreme Court in the matter of Vinitec

Electronics Pvt. Ltd. v. HCL Info Systems Ltd. 10 and it has been held

that in the case of an unconditional bank guarantee, the same are

payable by the guarantor on demand. When in the course of

commercial dealings, unconditional guarantees have been given or

accepted, the beneficiary is entitled to realise such a bank guarantee

in terms thereof, irrespective of any pending disputes. The bank

guarantee is an independent contract between the bank and the

beneficiary thereof. For a party to claim that the case falls under the

exception of fraud or special equities, proper pleadings must be made

out which lay down the factual foundation of the allegation of fraud or

special equities.

23. In the matter of NHAI v. Ganga Enterprise11, the Supreme Court has

held that a bank guarantee has to be strictly construed as per the

terms of the guarantee. The invocation must be in accordance with

the terms of the bank guarantee, and any deviation therefrom, would

render the invocation bad in law. If the enforcement is in terms of the

guarantee, the courts would normally refrain from interfering with the

enforcement of the bank guarantee. Interference would be justified if

the invocation is contrary to the terms of the guarantee, or in the case

of fraud.

24. In the matter of State of Maharashtra v. National Construction Co.

Bombay12, the Supreme Court analysed the law relating to bank

guarantees, and laid down the general rule in the following term:

"The rule is well established that a bank issuing a guarantee is not concerned with the underlying contract 10 (2008) 1 SCC 544 11 AIR 2003 SC 3823 12 (1996) 1 SCC 735 Arb. Appeal No.33/2020

between the parties to the contract. The duty of the bank under a performance guarantee is created by the document itself. Once the documents are in order, the bank giving the guarantee must honour the same and make payment. Ordinarily, unless there is an allegation of fraud or the like, the courts will not interfere, directly or indirectly, to withhold payment, otherwise trust in commerce, national and international, would be irreparably damaged. But that does not mean that the parties to the underlying contract cannot settle their disputes with respect to allegations of breach by resorting to litigation or arbitration as stipulated in the contract. The remedy arising ex contractu is not barred, and the cause of action for the same is independent of enforcement of the guarantee."

Exceptions to Grant of Injunction of a Bank Guarantee: -

25. A bank guarantee must be honoured strictly in accordance with the

terms of the guarantee, subject to two exceptions. The first is in a

clear case of fraud, which the bank has notice of, and the beneficiary

seeks to take advantage of.

26. The Supreme Court in the matter of General Electric Technical

Services Company Inc. v. M/s. Punj Sons (P) Ltd. and another 13 held

that by interim injunction under Order 39 Rule 1 of the CPC, bank

guarantee cannot be interdicted by Court in the absence of fraud or

special equities in the form of preventing irretrievable injustice

between the parties. It was further held that it is the fraud of

beneficiary, not the fraud of somebody else.

27. In the matter of Svenska Handelsnbanken v. Indian Charge Chrome14,

their Lordships of the Supreme Court have held that fraud in

connection with the bank guarantee would vitiate the very foundation

of the bank guarantee. The fraud must be of an egregious nature

such as to vitiate the entire underlying transaction.

13 AIR 1991 SC 1994 14 (1994) 1 SCC 502 Arb. Appeal No.33/2020

28. The second exception to the general rule of non-intervention is if there

are 'special equities' in favour of injunction, such as when 'irretrievable

injury' or 'irretrievable injustice' would occur if such an injunction was

not granted {see B.S.E.S. Ltd. (Now Reliance Energy Ltd.) v. Fenner

India Ltd.15}.

29. In the matter of Dwarikesh Sugar Industries Ltd. v. Prem Heavy

Engineering Works (P) Ltd.16 the Supreme Court has held that in

respect of the second exception to the rule of granting injunction in

case of a bank guarantee, the resulting irretrievable injury has to be

such that it would make it impossible for the guarantor to reimburse

himself, if he ultimately succeeds, and the same shall have to be

decisively established. The Supreme Court has further held that it

must be proved to the satisfaction of the court that there would be no

possibility whatsoever of the recovery of the amount from the

beneficiary by way of restitution.

30. The Supreme Court in the recent past in Andhra Pradesh Pollution

Control Board (supra) while taking note of its earlier decisions in the

matters of Ansal Engg. Projects Ltd. v. Tehri Hydro Development

Corpn. Ltd.17, SBI v. Mula Sahakari Sakhar Karkhana Ltd. 18 and

Hindustan Construction Co. Ltd. v. State of Bihar19 and relying upon

the same, held that absent a case of fraud, irretrievable injustice and

special equities, the Court should not interfere with the invocation or

encashment of a bank guarantee so long as the invocation was in

terms of the bank guarantee.

15 (2006) 2 SCC 728 16 (1997) 6 SCC 450 17 (1996) 5 SCC 450 18 (2006) 6 SCC 293 19 (1999) 8 SCC 436 Arb. Appeal No.33/2020

31. Thereafter, in Standard Chartered Bank (supra), the Supreme Court

again noticed its earlier decision in Himadri Chemicals Industries Ltd.

(supra) and held that bank guarantee is an independent contract

between bank and the beneficiary and the bank is always obliged to

honour its guarantee as long as it is unconditional and irrevocable

one. It has been further held that the dispute between the beneficiary

and the party at whose instance the bank has given the guarantee is

immaterial and is of no consequence, however, exceptions to this rule

are when there is a clear case of fraud, irretrievable injustice or

special equities. It was also held that the Court ordinarily should not

interfere with the invocation or encashment of the bank guarantee so

long as the invocation is in terms of the bank guarantee. Their

Lordships finally held that once the demand was made in due

compliance with bank guarantees, it was not open for the bank to

determine as to whether the invocation of the bank guarantee was

justified so long as the invocation was in terms of the bank guarantee.

32. In the matter of U.P. State Sugar Corporation v. Sumac International

Ltd.20 the Supreme Court has held that the exception of irretrievable/

irreparable injury, exceptional circumstances which make it impossible

for the guarantor to reimburse himself if he ultimately succeeds, will

have to be decisively established. A mere apprehension that the

other party will not be able to pay is not a sufficient ground to establish

irretrievable injury.

33. The Delhi High Court also in the matter of Intertoll ICS Cecons O&M

Company P. Ltd. v. National Highways Authority of India21, speaking

through A.K. Sikri, J. (as His Lordship then was) after analysing the

20 (1997) 1 SCC 568 21 ILR (2006) I Delhi 196 Arb. Appeal No.33/2020

judgments of the Supreme Court on the point, has laid down the

principles in paragraph 10 of the report as under: -

"10. The principles which may be distilled from the aforesaid judgments and the observations made therein, would be the following:

(a) The bank guarantee is an independent contract between the bank and the beneficiary.

(b) When there is an unconditional bank guarantee and the bank has agreed to make payment without demur or protest, on beneficiary invoking the said bank guarantee, the bank is under obligation to honour the said demand. It is based on the rationale that otherwise trust in commerce, national and international, would be irreparably damaged.

(c) The bank, or for that matter, the person at whose instance the bank guarantee is given [and as a sequitter even the court] will not go into the pending disputes or nature thereof between the contractor and the employer/beneficiary. The duty of the bank under a performance guarantee is created by the document itself. Once the documents are found to be in order, the bank has to honour the same.

(d) The courts, at this stage, cannot even go into the question as to whether the beneficiary has suffered any damages or not. Therefore, the ground that in India only a reasonable amount can be awarded by way of damages even when the parties to the contract have provided for liquidated damages, is not available in such proceedings.

(e) The court is also precluded from embarking on the enquiry in encashment of bank guarantee the beneficiary is trying to take undue enrichment.

(f) In so far as dispute between the parties to the underlying contract is concerned, that has to be settled by resorting to litigation or arbitration, as the case may be.

(g) The courts should, therefore, be slow in granting the injunction to restrain the realization of such a bank guarantee.

(h) However, there are two well recognized exceptions to this rule which are:

Arb. Appeal No.33/2020

(1) A fraud of egregious nature.

(2) The invocation/encashment of bank guarantee would result in irretrievable harm or injustice to one of the parties.

(i) In some cases third exception is also carved out viz. when there are special equities in favour of the person seeking injunction.

(j) In case the bank guarantee is not invoked in terms thereof, the bank can refused to honour the bank guarantee as in that case it would not be in accordance with the agreed stipulation and invocation would be improper. This can be treated as the fourth exception as in such a case injunction can be granted."

34. In the matter of State Trading Corporation of India Ltd. v. Jainsons

Clothing Corporation and another22, their Lordships of the Supreme

Court have clearly held that it is settled law that the court, before

issuing the injunction under Order 39, Rules 1 and 2, CPC should

prima facie be satisfied that there is triable issue strong prima facie

case of fraud or irretrievable injury and balance of convenience is in

favour of issuing injunction to prevent irremedial injury. It was further

held that the court should normally insist upon enforcement of the

bank guarantee and the court should not interfere with the

enforcement of the contract of guarantee unless there is a specific

plea of fraud or special equities in favour of the plaintiff. He must

necessarily plead and produce all the necessary evidence in proof of

the fraud in execution of the contract of the guarantee, but not the

contract either of the original contract or any of the subsequent events

that may happen as a ground for fraud.

35. Coming to the facts of the present case in the light of the aforesaid

principles laid down for issuance of injunction against encashment or

22 (1994) 6 SCC 597 Arb. Appeal No.33/2020

invocation of bank guarantee that are in case of fraud of an egregious

nature as to vitiate the entire underlying transaction or special equity

in favour of person seeking interim injunction for preventing

irretrievable harm or injustice to one of the parties, it is appropriate to

mention here that the learned Commercial Court has noticed the

parameters for invocation of bank guarantee and thereafter in

paragraph 33 of the order has rightly held that invocation of bank

guarantee can be interdicted on three grounds i.e. "fraud",

"irretrievable injury" and "special equity", and also held that the

appellants herein have not setup any such ground out of the said

three grounds to seek restraint order against the invocation of bank

guarantee and proceeded to reject the application. The present

appellants have filed copy of the application filed by them under

Section 9 of the AC Act before the Commercial Court along with this

appeal memo. A careful perusal of the application filed under Section

9 seeking injunction against encashment or invocation of bank

guarantee would show that it is the case of the appellants herein that

though the respondents have extended the period of completion of

contract under clause 17-A of the general conditions of contract till 31-

3-2020, but terminated the contract in question on 2-1-2020, which is

arbitrary and illegal and therefore the appellants have prima facie

case for grant of injunction in their favour and balance of convenience

is also in their favour. As such, no specific ground of fraud or special

equity in favour of the appellants has been pleaded while seeking

interim injunction against encashment of bank guarantee. However,

learned counsel for the appellants have emphasized that the pleading

made in paragraph 19 of the application under Section 9 of the AC Act Arb. Appeal No.33/2020

extending their contract under clause 17-A of the general conditions of

contract, would amount to the plea of "special equity" which is an

exception for granting interim injunction in favour of the appellants

restraining encashment of bank guarantee.

36. Now, the question is, whether the ground of special equity which is

one of the established grounds for injunction against invocation of

bank guarantee has been pleaded by and on behalf of the appellants?

37. Learned counsel for the appellants have emphasized that in

paragraphs 17, 18, 19 and 20 of the application under Section 9 of the

AC Act, the appellants herein have pleaded the ground of special

equities in their favour. Paragraphs 17, 18, 19 and 20 of the said

application are reproduced herein-below for the sake of convenience:

17/ यह कक अनावेदकगण दावा 2/1/2020 को संकवदा कनवस् कवने के इस आदेश को अनावेदकगण की मनमानेपन से की गई कायर वाही होने के कावण रवि याचचिका क्रमांक (सी) नं. 31/2020 माननीय छतीसगढ उच चयायालय मे पस्स् ककया औव कदनांक 2/1/2020 के इस आदेश को चिसनौ्ी कदया था । माननीय छतीसगढ चयायालय ने इस वीि याचचिका पव कदनांक 24/2/2020 को आदेश पारव् कव्े हसए आदेश की कंचडका 11 एवं 12 मे यह पच्पाकद् ककया है कक "अनावेदकगण के कथनानससाव संकवदा मे काल 1.38 सपेशल कंडीशन लो कक काल 63 लनवल कंडीशन ऑफ काचि्ैकि के साथ पढा लायेगा । समे पककावा के बीचि आरबि्ेशन से कववाद के कनवाकवण का पबंध है । इसललये वीि याचचिका मे इसका कनवाकवण नही हो सक्ा , कयाकक कववाद के कनवाकवण कवने के ललए भय पक के साकय देने हागे । इसललये पककाव अने अचधकावा के संबंध मे अचय पचिाव कवचध अनससाव पाप कवने के ललए कायर वाही कव सक्े है । इसकी ससकवधा दी गई ।"

18/ यह कक माननीय उच चयायालय के कदनांक 24/2/2020 के आदेश के ्सव् ं बाद अनावेदकगण ने आवेदकगण दावा संकवदा के अं्र्र की गई "पवफामरश गावंिी की वाशश" का नगदीकवण कवने के ललए ्तकाल ही संबंचध् बैक को संपकर ककया, जलसकी लानकावी होने आवेदकगण ने कदनांक 26/2/2020 को बैक को औव अनावेदकगण को पत देकव यह सूचचि् कव कदया कक माननीय उच चयायालय की अनसमच् अनससाव आवेदकगण संकवदा मे पबंचध् वीच् से कवववाद को मधयसथ को सौपने की कायर वाही पावंभ कव वहे है । इसललए बैक गावंिी का नकदीकवण अनावेदकगण न कवाये । आवेदकगण काे आबंकि् कायर को ककसी अचय को पूणर कवने के ललए अगव अनावेदक 2 से 4 पदान कव दे्े है ्ो अनावेदकगण को अपूवणीय कच् होगी । इसललए अं्रवम पाय के ललए यह आवेदन माननीय Arb. Appeal No.33/2020

चयायालय मे पस्स् कव्े है ।

19/ यह कक अनावेदकगण दावा आवेदकगण को कायर पूणर कवने के ललए कदनांक 31/3/2020 ्क की अवचध कवस्ारव् ककया गया है, (कबना ककसी ललकवीडेिेि डैमेल कवथ पी.वही.सी. अण्डव काल -17 (ए) आफॅ ली.सी.सी., कबना ककसी पेनालिी के कायर अवचध कवस्ारव् ककया है । ऐसी दशा मे कवस्ारव् अवचध के समाप होने के पूवर 2/1/2020 को संकवदा कनवस् कवने का आदेश अवैध ्था मनमाना है । इसललए पथम दकष मे यह मामला आवेदक के पक मे है । आवेदक के पक मे ससकवधा का सं्सलन भी है ।

20/ यह कक आवेदन पत पस्स् कवना अलरचि है कयाकक अनावेदक बैक गावंिी को इनकेश कवाने औव आवेदक के ठे का कायर को अचय को देने ्था आवेदक कंचडका को अचय बीड मे भाग लेने से भी अयोरय होना आदेशश् ककया है । अ्ः आरबि्ेशन मे अगसव होने के पूवर माननीय चयायालय मे "अं्रवम पाय" पाप कवने लायक वाद कावण कदनांक 2/1/2020 को औव माननीय उच चयायालय के आदेश कदनांक 24/2/2020 को आवेदक कंचडका को पाप हसआ है ।

38. Clause 17-A of the general conditions of contract deals with extension

of time in contracts, sub-clauses of which deal with extension due to

modification, extension for delay not due to Railway or contractor, and

extension for delay due to Railways.

39. True it is that the appellants' contract period has been extended by the

respondents by invoking clause 17-A of the Standard General

Conditions of Contract and the appellants' contract in question was

extended relying upon clause 17-A, which relates to extension of time

in contracts in terms of extension due to modification, extension for

delay not due to Railway or contractor and extension for delay due to

Railways, and the contract in question has not been extended under

clause 17-B, which provides for extension of time for delay due to

contractor.

40. At this stage, it would be appropriate to notice the bank guarantee

furnished by the appellants on 10-10-2016 to the extent of ₹

6,77,26,553/-. It states as under: -

"In consideration of the President of India (hereinafter called "the Government") having agreed to exempt M/s Arb. Appeal No.33/2020

ARSS - SIPS (JV) at 129, Transport Centre, Rohtak Road, Punjabi Bagh, New Delhi - 110035 (hereinafter called "the said Contractor"(s)/Supplier(s)") from the demand, under the terms and conditions of this Agreement No. CEC/BSP/ ER/T/15-16/127 Lajkura-Raigarh/4th line JSG-BSP/538 dated 21.09.2016 made between The President of India, Acting through the Chief Engineer(C) or his successor, South East Central Railway, Bilaspur, of the Ministry of Railways, Railway Board and M/s ARSS - SIPS (JV) at 129, Transport Centre, Rohtak Road, Punjabi Bagh, New Delhi - 110035 for Soil Investigation, design of bridges, execution of earth work, minor bridges, major bridges, RUBs, extension of FOB, Staff Quarters and other service buildings, supply of ballast and other miscellaneous works in Lajkura-Raigarh section in connection with the construction of 4th line between Jharsuguda - Bilaspur (hereinafter called "the said Agreement"), of performance guarantee for the due fulfillment by the said Contractor(s) of the terms and conditions contained in the said Agreement, on production of a Bank Guarantee for Rs.6,77,26,553/- (Rupees Six Crore Seventy Seven Lacs Twenty Six Thousand Five Hundred Fifty Three Only) we, ICICI Bank Limited, having its Registered Office at Near Chakli Circle, Old Padra Road, Vadodara, Gujarat, Pin -

390 007, India and amongst other places, a branch at 9A, Connaught Place, New Delhi - 110001, India (hereinafter referred to as "the Bank") at the request of M/s ARSS - SIPS (JV) at 129, Transport Centre, Rohtak Road, Punjabi Bagh, New Delhi - 110035 (contractors) do hereby undertake to pay to the Government an amount not exceeding Rs. 6,77,26,553/- (Rupees Six Crore Seventy Seven Lacs Twenty Six Thousand Five Hundred Fifty Three Only) against any loss or damage caused to or suffered or would be caused to or suffered by the Government by reason of any breach by the said Contractor(s) of any of the terms or conditions contained in the said Agreement.

2. We, ICICI Bank Limited at 9A, Connaught Place, New Delhi - 110001, India do hereby undertake to pay the amounts due and payable under this guarantee without any demur, merely on a demand from the Government (Railways) stating that the amount claimed is due by way of loss or damage caused to or would be caused to or suffered by the Government (Railway) by reason of breach by the said contractor(s) of any of the terms or conditions contained in the said Agreement or by reason of the Arb. Appeal No.33/2020

contractor(s) failure to perform the said agreement. Any such demand made on the Bank shall be conclusive as regards the amount due and payable by the Bank under this Guarantee. However, our liability under this Guarantee shall be restricted to an amount not exceeding Rs. 6,77,26,553/- (Rupees Six Crore Seventy Seven Lacs Twenty Six Thousand Five Hundred Fifty Three Only).

3. We undertake to pay to the Government any money so demanded notwithstanding any dispute or disputes raised by the contractor(s)/supplier(s) in any suit or proceeding pending before any court or Tribunal relating thereto our liability under this present being absolute and unequivocal.

The payment so made by us under this bond shall be a valid discharge of our liability for payment there under and the contractor(s)/supplier(s) shall have no claim against us for making such payment."

41. A careful perusal of the aforesaid terms of the bank guarantee would

show that the performance guarantee is an autonomous and

independent contract and that is independent in character. The

obligation arising under the bank guarantee is independent of the

obligation arising out of the main contract between the parties. The

performance guarantee imposes an absolute obligation on the banks

to pay irrespective of any dispute which may have arisen between the

parties and pending before any such court or tribunal, the liability

being absolute and unequivocal. It is independent of the primary

contract between the appellants and the respondents. The bank is

not concerned with the rights regardless of the underlying disputes,

but only with the performance of the obligation. The letter of

guarantee was addressed to the SECR in unqualified terms. The

liability of the bank is absolute and unequivocal.

42. Now, at this stage, it would be appropriate to notice clause 1.35 of the

subject contract which states as under: -

Arb. Appeal No.33/2020

"1.35 Performance Guarantee:

                                xxx   xxx    xxx

                                xxx   xxx    xxx

                               xxx    xxx    xxx

(f) Wherever the contract is rescinded, the Security Deposit shall be forfeited and the Performance Guarantee shall be encashed. The balance work shall be got done independently without risk and cost of the failed contractor. The failed contractor shall be debarred from participating in the tender for executing the balance work. If the failed contractor is a JV or a partnership firm, then every member/partner of such a firm shall be debarred from participating in the tender for the balance work either in his/ her individual capacity or as a partner of any other JV/ partnership firm.

                                xxx   xxx    xxx

                                xxx   xxx    xxx

                               xxx    xxx    xxx"

43. A careful perusal of clause 1.35 of the subject contract would show

that whenever the contract is rescinded, the security deposit shall be

forfeited and the performance guarantee shall be encashed. As such,

the unequivocal and absolute term of performance bank guarantee is

invokable as per clause 1.35 of the subject contract. Their Lordships

of the Supreme Court in their decisions as noticed herein-above

including U.P. State Sugar Corporation (supra) have held that "when

in the course of commercial dealings an unconditional bank guarantee

is given or accepted, the beneficiary is entitled to realise such a bank

guarantee in terms thereof irrespective of any pending disputes. The

bank giving such a guarantee is bound to honour it as per its terms

irrespective of any dispute raised by its customer". As such, it was

further held that "the very purpose of giving such a bank guarantee Arb. Appeal No.33/2020

would otherwise be defeated. The courts should, therefore, be slow in

granting an injunction to restrain the realization of such a bank

guarantee".

44. In view of the discussion made herein-above, we are of the

considered opinion that Courts' interference under Order 39 Rules 1 &

2 of the CPC while granting interim injunction in enforcing bank

guarantees must be minimal. In case of fraud or special equities to

prevent irretrievable injustice to the parties seeking injunction, Courts

interfere to prevent enforcement of bank guarantees. If the terms of

the bank guarantee are unconditional and absolute, the bank has to

pay the amount of bank guarantee without demur. The payment of

bank guarantee cannot be made subject to the claims and counter-

claims arising out of the main contract between the parties. In the

instant case, the terms of the performance bank guarantee are

absolute and unconditional, and none of the grounds of fraud or

irretrievable injustice or special equity have been specifically pleaded,

except the pleading that the period of contract in favour of the

appellants has been extended by the respondents invoking clause 17-

A of the general conditions of contract which is not relatable to the

default of the appellants / contractor and the contract has been

rescinded on 2-1-2020 prior to the date of completion of contract i.e.

31-3-2020, that would not per se constitute the ground of special

equity for seeking interim injunction, as the exception carved out for

invocation of bank guarantee and same would remain in the realm of

the contractual dispute between the parties, which would fall outside

the ground of special equity and as such, the appellants have failed to

plead and establish any of the ground(s) noticed herein-above for Arb. Appeal No.33/2020

seeking interim injunction against the invocation of bank guarantee.

Accordingly, we hold that the learned Commercial Court (District

Level) has rightly held that the appellants have failed to plead and

establish the grounds of "fraud", "special equity" and "irretrievable

injustice" to the appellants for seeking interim injunction against the

enforcement of bank guarantee.

45. We accordingly hereby dismiss the arbitration appeal and

consequently the interim order dated 30-7-2020 is hereby vacated.

No order as to cost(s).

              Sd/-                                                    Sd/-
       (Sanjay K. Agrawal)                                   (Arvind Singh Chandel)
             Judge                                                   Judge

Soma
                                                               Arb. Appeal No.33/2020



               HIGH COURT OF CHHATTISGARH, BILASPUR



                         Arbitration Appeal No.33 of 2020

                          ARSS - SIPS (JV) and others

                                       Versus

                             Union of India and others


                                     Head Note

The Bank can be restrained from enforcement of unconditional and absolute

performance bank guarantee by interim injunction only in case of fraud and

special equities to prevent irretrievable injustice.

cSad dks dsoy /kks[kk/kMh ,oa fo'ks"k bZfDoVh ds ekeys esa] vifjorZuh; vU;k; dks jksdus

gsrq varfje O;kns'k }kjk fcuk 'krZ ,oa iw.kZ izn'kZu cSad xkjaVh dks ykxw djus ls jksdk

tk ldrk gSA

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter