Citation : 2021 Latest Caselaw 3735 Chatt
Judgement Date : 16 December, 2021
1
AFR
HIGH COURT OF CHHATTISGARH, BILASPUR
Writ Petition (C) No. 3211 of 2021
Mata Di Electricals through its Partner Devendra Jain S/o Shri Ugam
Raj Jain, aged about 35 years, R/o Near Tehsil Office Rajim, District
Gariyaband, Chhattisgarh.
---- Petitioner
Versus
1. Chhattisgarh State Ware Housing Corporation, through Managing
Director, Sector-24, Near Jhanjh Lake, Atal Nagar, Raipur, District
Raipur, Chhattisgarh.
2. Manager, Technical, Chhattisgarh State Ware Housing
Corporation, Sector 24, Near Jhanjh Lake, Atal Nagar, Raipur,
District Raipur, Chhattisgarh.
---- Respondents
(Cause Title taken from Case Information System)
For Petitioner : Mr. Anup Majumdar, Advocate.
For Respondents : Mr. Animesh Tiwari, Advocate.
Hon'ble Mr. Arup Kumar Goswami, Chief Justice Hon'ble Mr. N.K.Chandravanshi, Judge
Order on Board
Per Arup Kumar Goswami, Chief Justice
16/12/2021
Heard Mr. Anup Majumdar, learned counsel for the petitioner as
well as Mr. Animesh Tiwari, learned counsel for the respondents.
2. A notice inviting tender (NIT) dated 02.05.2020 was issued by the
respondents for supplying Power Sprayer (Petrol) in terms of the
specifications provided in the NIT. On evaluation of the tenders, the bid
of the petitioner was accepted. On 26.06.2020, the petitioner was
informed that before execution of the pre-integrity contract and
agreement, the officers of the Corporation will inspect the stores and the
Power Sprayer (Petrol) which were to be supplied. A date for inspection
within seven days of the receipt of the letter was requested.
Subsequently, in supersession of the letter dated 26.06.2020, a work
order dated 10.07.2020 came to be issued instructing the petitioner to
supply 35 numbers of Power Sprayer (Petrol) as per the NIT conditions.
Subsequent thereto, on 13.07.2020, a pre-contract integrity pact and an
agreement were executed in between the petitioner and the respondent
No. 2.
3. By a letter dated 08.10.2020, the petitioner was informed that
on an inspection being carried out on 28.08.2020, it was found that the
Power Sprayer (Petrol) available with the petitioner was not in accord
with the specifications mentioned in the work order and the NIT, and
accordingly, the petitioner was directed to rectify the Power Sprayer
(Petrol) in accordance with the specifications within seven days. It was
also indicated in the said letter that on failure to take appropriate action
within the time limit specified, appropriate action would be taken as per
clause 12(iv)(g) of the NIT.
4. It is stated by the petitioner that though a letter dated
15.10.2020 was issued by the petitioner requesting inspection of the
Power Sprayer (Petrol) procured by the petitioner, none came for
inspection of the same and thereafter, surprisingly, by an order dated
21.10.2020, the respondents cancelled the contract of the petitioner,
forfeited the earnest money deposit and disqualified the petitioner from
participating in any tender under the respondents in future.
5. The relevant portion of translated version of the order dated
21.10.2020 (translated by the petitioner) reads as follows:
"Chhattisgarh State Warehousing Corporation Head Office village Jhanjh, Sector 24, Atal Nagar, Nawa Raipur (CG) Date- 21.10.2020 To,
M/s. Mata Di Electricals Near Tahsil Office, Fingeshwar Road, Rajim, District Gariyaband (CG)
Subject: Regarding purchase of 35 Nos. Power Sprayer
(petrol)
Reference: (1) Supply Order No. 0-7068 of this office
dated 10.07.2020
(2) letter No. 9332 of this office dated
08.10.2020.
You were given order to supply 35 Nos. of Power
Sprayer (Petrol) under the referred supply order under the
subject. As per your letter No. MDE 351 dated
25.08.2020, request was made to the Corporation for
inspection. Consequent to the said letter, as per the letter
No. 8051 dated 26.08.2020 of the Headquarters,
inspection was done by the officers of the Headquarters
by visiting the specified place. In the inspection, the
officers found that the Power Sprayer (Petrol) prepared
was not as per the terms and specifications of the
agreement executed.
With reference to aforesaid, vide letter No. 2 referred
above, you were instructed to prepare the material
according to the supply order and after keeping it ready
for pre-supply inspection, you were to inform this office
within 7 days. But till date, no correspondence has been
made from your side.
Therefore, as per clause No. 12 (iv)(g) at page No.
21 of the tender sheet, and clause No. 17(iii) at page No.
25, the contract is being cancelled and to compensate the
loss incurred by the Corporation, your earnest money is
being forfeited and in future, you will be ineligible to
participate in any tender of the Corporation.
Sd/-
Managing Director 21.10.2020"
6. Mr. Majumdar submits that though prayer is made for setting
aside of the order dated 21.10.2020 in the writ petition, the petitioner is
not pressing for setting aside the order of cancellation of the contract.
The petitioner is aggrieved by forfeiture of the earnest money as well as
disqualifying the petitioner from participating in future tender. It is
submitted that in the NIT as well as in the agreement, there is no
provision for blacklisting under any eventuality and therefore, debarring
the petitioner from participating in future contract of the respondents is,
per se, illegal and arbitrary and the same cannot be countenanced in
law. It is also submitted that no notice was given to the petitioner
requiring him to show cause as to why the petitioner shall not be
disqualified from participating in the tender of the Corporation, that too,
permanently which is, in essence, blacklisting of the petitioner from
participating in future contracts.
7. Mr. Animesh Tiwari, learned counsel for the respondents
submits that it is not correct to say that no notice was issued as
contended by the petitioner. He submits that a notice was issued on
08.10.2020. Placing reliance on a judgment of the Hon'ble Supreme
Court in Kulja Industries Limited v. Chief General Manager, Western
Telecom Project Bharat Sanchar Nigam Limited & Others, reported in
(2014) 14 SCC 731, it is submitted by him that the power to blacklist a
contractor is inherent with a party allotting the contract and therefore,
merely because there was no provision of blacklisting in the NIT or the
agreement, the same will not preclude the Corporation from blacklisting
a contractor if the need arises in the interest of the Corporation. So far as
return of earnest money is concerned, it is submitted that when the
contract has been cancelled and the petitioner is not assailing the said
cancellation, no question arises for refund of the earnest money.
8. We have considered the submissions of the learned counsel for
the parties and have perused the materials on record.
9. In Kulja Industries Limited (supra), the Hon'ble Supreme Court
has observed that power to blacklist a contractor is inherent in the party
allotting the contract as 'blacklisting' signifies a business decision by
which the party affected by the breach decides not to enter into any
contractual relationship with the party committing the breach. While
between two private parties the right to take any such decision is
absolute and untrammelled by any constraints whatsoever, and the
freedom to contract or not to contract is unqualified, any such decision is
subject to judicial review when the same is taken by the State or any of
its instrumentalities. In other words, any such decision will be open to
scrutiny not only on the touchstone of the principles of natural justice but
also on the doctrine of proportionality. A fair hearing to the party being
blacklisted thus becomes an essential pre-condition for a proper exercise
of the power and a valid order of blacklisting made pursuant thereto.
10. Therefore, the argument of Mr. Majumdar that the petitioner
could not have been debarred from participating in future contracts with
the respondents in absence of any provision enabling blacklisting, is
without any merit.
11. However, a perusal of the letter dated 08.10.2020, on which
reliance is placed by Mr. Tiwari to contend that notice was given to the
petitioner with regard to proposed blacklisting, goes to show that the said
notice did not indicate that the petitioner is asked to show cause as to
why he shall not be ineligible to participate in any tender of the
respondents. The notice refers to clause 12(iv)(g) dealing with 'failures
and termination', which have no clause for disqualification in future.
12. As no order of blacklisting can be validly passed without
affording adequate opportunity of hearing, debarring the petitioner, that
too, for all times to come, from participating in contracts under the
respondent, is wholly arbitrary and illegal and therefore, such stipulation
in the order dated 21.10.2020 is set aside. The respondents are,
however, at liberty to proceed in accordance with law, if so advised.
11. So far as the prayer for return of earnest money deposit is
concerned, since the work order has been cancelled and the same is not
being questioned, issuing a direction for return of earnest money deposit
does not arise.
12. The writ petition stands disposed of in the above terms. No
cost.
Sd/- Sd/-
(Arup Kumar Goswami) (N.K.Chandravanshi)
CHIEF JUSTICE JUDGE
Amit
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!