Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Mbl Infrastructure Limited vs Hooghly River Bridges Commissioners
2026 Latest Caselaw 1811 Cal/2

Citation : 2026 Latest Caselaw 1811 Cal/2
Judgement Date : 12 March, 2026

[Cites 1, Cited by 0]

Calcutta High Court

Mbl Infrastructure Limited vs Hooghly River Bridges Commissioners on 12 March, 2026

Author: Debangsu Basak
Bench: Debangsu Basak
                                       1

                                                               2026:CHC-OS:86-DB


                      IN THE HIGH COURT AT CALCUTTA
                     COMMERCIAL APPELLATE DIVISION
                                ORIGINAL SIDE
Present:
The Hon'ble Justice Debangsu Basak
           And
The Hon'ble Justice Md. Shabbar Rashidi

                               AO-COM/26/2025
                            IA No: GA-COM 1/2025
                              APOT No. 323/2025
                    (Arising out of A.P. (COM) No. 187/2024)
                             Old AP No. 340/2020)
                       MBL INFRASTRUCTURE LIMITED
                                      VS
               HOOGHLY RIVER BRIDGES COMMISSIONERS
For the Appellant         : Mr. Ratnanko Banerji, Sr. Adv.
                            Mr. Shaunak Mitra, Adv.
                            Ms. Sristi Barman Roy, Adv.
                            Ms. Pritha Basu, Adv.
                            Ms. Nairanjana Ghosh, Adv.
                            Mr. Debartha Chakraborty, Adv.
                            Mr. Sagar Dutta, Adv.

For the Respondent        : Mr. Anirban Ray, Sr. Adv.

Mr. Debanjan Mondal, Adv.

Mr. Sarvapriya Mukherjee, Adv.

Mr. Chayan Gupta, Adv.

Mr. Sandip Dasgupta, Adv.

Mr. Aviroop Mitra, Adv.

Hearing Concluded on      : January 30, 2026

Judgement on              : March 12, 2026

DEBANGSU BASAK, J.:-

1. Appellant has assailed the judgment and order dated

November 3, 2025 passed in A. P. (Com) No. 187 of 2024. By the

2026:CHC-OS:86-DB

impugned judgment and order dated November 3, 2025 learned

Single Judge has set aside the award dated June 29, 2020.

2. Learned senior advocate appearing for the appellant has

submitted that, the respondent challenged the unanimous award

dated June 29, 2020 before the learned Single Judge. He has

contended that, disputes arose out of a construction contract

dated 04th December, 2013 for construction of a basement plus

ground plus 5 storied commercial complex compass terminal. He

has pointed out that, out of 15 claims, the Arbitral Tribunal had

allowed claims 1, 3, 4, 12 (in part), 13 and 15 (in part). The

Arbitral Tribunal had rejected the counterclaim of the respondent.

3. Learned senior advocate appearing for the appellant has

submitted that, the Arbitral Tribunal found that the termination of

the contract was illegal. The Arbitral Tribunal had found the

respondent to be in material breach of the contract. The Arbitral

Tribunal had found that the respondent granted extensions of

time to complete the contract without levy of liquidated damages

being conscious of the delay on their part and that, the appellant

was not in breach or at fault.

2026:CHC-OS:86-DB

4. Learned senior advocate appearing for the appellant has

contended that, the contract contemplated a specific notice to

commence. He has contended that, despite no notice to commence

having been issued, on the instruction of the respondent,

appellant had commenced the work on February 12, 2014. He has

pointed out that, the sanctioned building plan was obtained on

January 19, 2016. As a result, the respondent had delayed several

aspects of the execution of the project including issuance of

drawings. He has contended that, non-obtaining of sanctioned

building plan had material impact and delayed the implementation

of the project. In this regard, he has drawn the attention of the

Court to the pleadings made in the statement of claim as also in

the rejoinder filed before the Arbitral Tribunal.

5. Learned senior advocate appearing for the appellant has

contended that the witness of the respondent was cross-examined

on the issue of the sanctioned plan, it's a delay and the impact of

such a delay as also delay in issuance of drawings and other

aspects.

6. Learned senior advocate appearing for the appellant has

contended that the contention of the respondent that the Arbitral

Tribunal went into the issue of no legal commencement and no

2026:CHC-OS:86-DB

sanction plan without any issue being raised by the parties is

incorrect on the face of the pleadings as also the arguments that

were advanced before the Arbitral Tribunal. He has contended that

the view taken by the Arbitral Tribunal on the aspect of no

sanction plan and its impact was within the contours of the

disputes submitted to arbitration. He has contended that, the view

taken by the Arbitral Tribunal regarding violation of municipal law

was a plausible view and was permissible to be taken by the

Arbitral Tribunal.

7. Learned senior advocate appearing for the appellant has

referred to the award. He has contended that, all relevant

provisions of the contract as also the legal position were

considered by the Arbitral Tribunal. He has contended that, since

the respondent had extended time for performance without

imposing damages for delay, the respondent was estopped from

blaming the appellant for any breach of delay. The Arbitral

Tribunal had found so by the award. He has referred to the

findings of the Arbitral Tribunal in the award in this regard.

8. Learned senior advocate appearing for the appellant has

referred to clause 27.2 of the contract which allows extension

without imposing liquidated damages in terms of the clause 28

2026:CHC-OS:86-DB

which can only be given when the contractor is not in fault. He has

contended that, since the appellant was not at fault, time was

extended till June 30, 2017 without imposing any liquidated

damages.

9. Learned senior advocate appearing for the appellant has

contended that, the respondent illegally terminated the contract on

May 17, 2017 before expiry of the extended period. Arbitral

Tribunal has rightly taken such factor into consideration. He has

referred to the relevant portion of the award in this regard.

10. Learned senior advocate appearing for the appellant has

drawn the attention of the Court to the award where the Arbitral

Tribunal has taken into consideration that, the appellant did not

suspend construction and that, the work was slow down due to

the stoppage of the payment of the respondent. The respondent

was in breach of its reciprocal obligations and that the respondent

had accepted that it was in breach of reciprocal obligations.

Arbitral Tribunal had taken into consideration non availability of

sanctioned plan before January 19, 2016 which was a breach of

the municipal law and consequently the termination was bad.

2026:CHC-OS:86-DB

11. Learned senior advocate appearing for the appellant has

referred to various paragraphs of the impugned award relating to

delay in payment, admission of default committed by the

respondent as also extension of time of the contract without

imposing liquidated damages.

12. Learned senior advocate appearing for the appellant has

contended that, impugned judgment and order dated January 03,

2025 is perverse. He has contended that there are inherent

contradictions in the impugned judgment and award. When the

learned Single Judge has held that the respondent consciously

extended time for performance without imposing delay damages,

there was no ground for the learned Single Judge to interfere as

the same was within the jurisdiction of the learned Arbitral

Tribunal.

13. Learned senior advocate appearing for the appellant has

contended that, in the impugned order the learned Single Judge

incorrectly held that the award does not differentiate and proceeds

on the basis as if there was no commencement, legal or otherwise

and that, there was no discussion or adjudication with regard to

the question of neglect, delay and default of either of the parties.

2026:CHC-OS:86-DB

He has contended that, the award in several places found the

respondent to be in breach.

14. Learned senior advocate appearing for the appellant has

contended that, learned Single Judge incorrectly held that all

breaches and counter breaches have to be adjudicated upon. He

has contended that, all major and material allegations of breach

/counter breach have been dealt with by the impugned award.

15. Learned senior advocate appearing for the respondent has

contended that, the learned Single Judge acted within the

parameters of Section 34 of the Act of 1996. He has referred to

(2025) Volume 6 Supreme Court Case 757 (Somdatt Builders-

NCC-NEC(JV) vs. National Highways Authority of India and

others) on the issue of scope of Section 37 of the Act of 1996.

16. Learned senior advocate appearing for the respondent has

contended that, the award was contrary to Section 28(3) and

34(2)(b)(ii) read with explanation 1(ii) of the Act of 1996. He has

contended that, liquidated damages were allowed contrary to

clauses 27.1 and 28 of General Condition of Contracts. He has

contended that, the Arbitral Tribunal ignored vital parts of the

letters making request for extension of time and letters granting

2026:CHC-OS:86-DB

extension. He has contended that, the respondent categorically

recorded its satisfaction and the performance of the appellant in

its letter granting extensions. He has referred to the number of

times where, extensions were granted.

17. Learned senior advocate appearing for the respondent has

contended that, issue of date of commencement of the contract

was never raised. He has contended that, in fact, both the parties

were ad idem, that although notice to commence was not issued,

the contract had commenced on and from February 12, 2014. He

has contended that, a decision on a dispute not falling within the

terms of submission to arbitration was beyond the scope of the

arbitration.

18. Learned senior advocate appearing for the respondent has

contended that, the Arbitral Tribunal proceeded to negate the

various question raised by the parties as to who were really

negligent or in default in course of performance of various items of

works, erroneously.

19. Learned senior advocate appearing for the respondent has

contended that, the finding in the award that, since

implementation of the contract did not commence in terms of the

2026:CHC-OS:86-DB

contract, there was no obligation of the appellant to complete the

project within the 18 months of the actual start of work is perverse

and patently illegal. He has contended that, commencement of

work did not require any sanctioned building plan and in any

event, the appellant was under obligation to comply with clauses

15, 16, 19 and 32 before obtaining the sanctioned building plan.

According to him, such clauses indicate that the commencement

of work does not mean actual construction work and that,

sanctioned plan was not a sine qua non, for commencement of

work.

20. Learned senior advocate appearing for the respondent has

contended that, the Arbitral Tribunal did not consider the relevant

issue and material evidence placed on record. He has contended

that, the award was beyond the terms of reference and militates

the principle laid down in Section 34(2)(a)(iv) of the Act of 1996.

21. The respondent had issued a notice inviting tender for

construction of a modern bus terminus on Grand Trunk Road near

ESI hospital with multistoried commercial complex comprising of

basement, a ground and five upper floors including sanitary,

plumbing and electrical works under Serampore Municipality,

Hooghly, West Bengal. The appellant had participated in such

2026:CHC-OS:86-DB

tender process and was successful after technical and financial

evaluation. The respondent had issued a letter of acceptance on

November 19, 2013. Parties had thereafter executed a formal

contract document dated December 04, 2013. The contract

document provided that, the work was to be completed within 18

months from the date of commencement.

22. According to him, the date of commencement of the contract

was February 12, 2014 with the date of completion being August

11, 2015. According to the respondent, the appellant had sought

extension of time to complete the contract without prejudice and

that, the respondent granted such extension again without

prejudice. According to the respondent, it had never waived the

claim for liquidated damages due to the delay occasioned in

completion of the contract.

23. According to the respondent, there was inordinate delay in

performance of the contract and that, the respondent was

compelled to terminate the contract on May 17, 2017 during the

pendency of fourth extension. According to the respondent, the

appellant had performed only 60% of the contract if value is taken

into consideration and 62% of the contract if quantity is taken into

consideration.

2026:CHC-OS:86-DB

24. The contract document dated December 04, 2013 had an

arbitration clause. Disputes and differences between the parties

had been referred to arbitration to an Arbitral Tribunal, consisting

of three arbitrators. The Arbitral Tribunal had entered into

reference and held 65 meetings between July 27, 2018 and March

13, 2020.

25. In the arbitration proceedings, the appellant had filed

statement of claim, respondent's statement of defence with counter

claim and the appellant a rejoinder. Parties had disclosed

documents.

26. In the arbitration, appellant had examined one witness while,

the respondent examined two witnesses.

27. The Arbitral Tribunal had made and published an award

dated June 29, 2019. By such award the Arbitral Tribunal had

rejected the entire counter claim of the respondent. Arbitral

Tribunal had allowed a portion of the claim of the respondent and

rejected the other portion.

28. The respondent had filed a petition under Section 34 of the

Act of 1996 assailing such part of the award by which, the counter

2026:CHC-OS:86-DB

claim of the respondent was rejected and the claims of the

appellant was allowed.

29. By the impugned judgment and order dated November 3,

2025, learned Single Judge has allowed the challenge under

Section 34 of the Act of 1996.

30. Somdatt Builders-NCC-NEC(JV) (supra) has held that, the

scope of interference under Section 37 of the Act of 1996 is

limited. Given the limited scope of interference with an Arbitral

Tribunal under Section 34 of the Act of 1996, a court exercising

jurisdiction under Section 37 of the Act of 1996, is confined to

adjudicating as to whether or not the Court acting under Section

34 of the Act of 1996 acted within limited scope of its power.

31. In the facts of the present case, disputes and differences

arose between the parties with regard to a building contract. The

pleadings of the parties did not raise any issue with regard to the

date of commencement of the contract as, in the arbitration

proceedings, both parties had accepted that, the work commenced

on February 12, 2014. It is the case of the respondent before the

Arbitral Tribunal that, it had commenced the work on February

2026:CHC-OS:86-DB

12, 2014, raised and submitted running account bills some of

which were paid.

32. The nature of the contract is for construction of a building on

an identified land. The appellant was well aware of the situation

obtaining at land in question having participated in the tender

process. The nature of work under the contract required the

appellant to carry out various other works apart from purely

constructing the building. In fact, the respondent had commenced

work under the contract on February 12, 2014 without the

sanctioned building plan.

33. Sanction of the building plan had happened later than the

actual commencement of work. In absence of the sanctioned

building plan, the appellant had commenced work on February 12,

2014 and as noted above, raised and submitted running account

bills. Preparatory work leading to the construction of the building

in terms of the sanctioned building plan did not require a

sanctioned building plan to commence the same. Parties did not

understand the contract to be that the work can only be

commenced with the obtaining of the sanctioned building plan.

Both parties had worked under the contract prior to the

sanctioned building plan being obtained.

2026:CHC-OS:86-DB

34. Learned Arbitral Tribunal had therefore, erred in holding that

the date of commencement of the contract was the date of

sanctioned building plan and cannot taken as earlier date of

February 12, 2014. Such finding of the Arbitral Tribunal is

perverse and contrary to the evidence on record. Such finding

cannot be sustained by the materials placed on record as no

reasonable person can draw such inference from the materials

placed on record.

35. Admittedly, there had been delay in execution of the contract.

Four extensions had been prayed for and granted. The respondent

had sought extension without prejudice and the same were

granted also without prejudice. The net effect of the prayers of

extension and grant thereof, both without prejudice ought to have

been decided upon by the Arbitral Tribunal before fixing the

liability inter se, between the parties.

36. Arbitral Tribunal had premised the fixation of the

responsibility on completely wrong pedestals. The first wrong

pedestal is the date of commencement of contract. The other wrong

pedestal is the extension of time to complete the contract being

done unconditionally. Findings on both such aspect, as discussed

by the learned Single Judge are perverse and not drawn out from

2026:CHC-OS:86-DB

the materials placed before the Arbitral Tribunal with no

reasonable person being able to draw the inference as recorded by

the Arbitral Tribunal.

37. In such circumstances, we find that the learned Single Judge

has rightly exercised jurisdiction under section 34 of the Act of

1996. Learned Single Judge has correctly held that the impugned

award was vitiated by patent illegality.

38. AO-COM/26/2025 is dismissed, without any order as to

costs.

[DEBANGSU BASAK, J.]

39. I agree.

[MD. SHABBAR RASHIDI, J.]

2026:CHC-OS:86-DB

Later:-

Prayer for stay made on behalf of the appellant is

considered and refused.

[DEBANGSU BASAK, J.]

I agree.

[MD. SHABBAR RASHIDI, J.]

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter