Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Sankat Mochan Enterprises vs Union Of India
2026 Latest Caselaw 1737 Cal/2

Citation : 2026 Latest Caselaw 1737 Cal/2
Judgement Date : 11 March, 2026

[Cites 6, Cited by 0]

Calcutta High Court

M/S Sankat Mochan Enterprises vs Union Of India on 11 March, 2026

                  IN THE HIGH COURT AT CALCUTTA
                ORDINARY ORIGINAL CIVIL JURISDICTION
                           ORIGINAL SIDE

                         RESERVED ON: 04.02.2026
                         DELIVERED ON: 11.03.2026

                                    PRESENT:

                 THE HON'BLE MR. JUSTICE GAURANG KANTH

                                 AP 2 OF 2025

                    M/S SANKAT MOCHAN ENTERPRISES

                                     VERSUS

                                  UNION OF INDIA


Appearance: -

Mr. Pratip Mukherjee, Adv.
                                           ........................... for the Petitioner

Mr. Sunil Kr. Singhania, Adv.
Ms. Priti Jain, Adv.
                                                  .............. for the Respondent

                                   JUDGMENT

Gaurang Kanth, J. :-

1. The present Petition has been filed under Section 34 of the Arbitration and

Conciliation Act, 1996, challenging the Arbitral Award dated 26.06.2024

and the Corrigendum dated 06.09.2024 passed by the learned Sole

Arbitrator, Mr. Mihir Kumar Das. By the said Award, the learned

Arbitrator rejected the claims preferred by the Petitioner and allowed the

counterclaim filed by the Respondent.

2. The facts giving rise to the present Petition are briefly set out hereinbelow.

3. The Respondent issued E-Tender Notice No. 17/EL/WT/2017-18 dated

08.02.2018 for the work titled: "Part A - Provision of one additional High

Mast Tower at Coaching Yard/TATA (near S/neck at BMPR end); Part B -

Improvement of power supply arrangement at C&W sick line/ADTP." The

Petitioner, having emerged as the L-1 bidder, was awarded the said work

vide Letter of Acceptance No. 17/EL/WT/2017-18/SME dated 09.07.2018.

Thereafter, a formal Agreement being No. 03/2018-19/Agt/SME dated

09.10.2018 was executed between the parties.

4. The Petitioner commenced the work on 10.10.2018. In terms of the

Agreement, the stipulated period for completion was six months, i.e., up to

08.01.2019. Admittedly, the work was not completed within the stipulated

time. The Respondent, however, granted extension of time for completion

of the work up to 30.03.2021 without imposition of penalty. Despite such

extension, the work remained incomplete, and consequently, the

Respondent terminated the contract vide letter dated 06.04.2021.

5. By letter dated 17.05.2021, the Petitioner invoked the arbitration clause

and requested the General Manager of South Eastern Railway to appoint

an Arbitrator. As no steps were taken in this regard, the Petitioner issued a

legal notice dated 27.12.2021 furnishing the details of its alleged

outstanding dues and calling upon the Respondent to make payment

thereof.

6. Owing to the failure of the Respondent's General Manager to appoint an

Arbitrator, the Petitioner filed Arbitration Petition No. 493 of 2022 before

this Hon'ble Court under Section 11 of the Arbitration and Conciliation

Act, 1996. By order dated 12.08.2022, this Hon'ble Court appointed Mr.

Mihir Kumar Das, Advocate, Bar Association Room No. 2, High Court at

Calcutta, as the Sole Arbitrator to adjudicate the disputes between the

parties.

7. The Petitioner filed its Statement of Claim comprising ten claims

aggregating to Rs. 16,09,350/-. The Respondent contested the claims in

entirety and preferred a counterclaim amounting to Rs. 2,59,708.63/-.

8. Upon completion of pleadings, the learned Sole Arbitrator framed the

following issues for determination:

(i) Whether the agreement dated 09.10.2018 executed pursuant to the

e-tender is legal and valid?

(ii) Whether the termination of the contract by the Respondent-Railway

is legal and valid?

(iii) Whether the Claimant is entitled to the claims as prayed for in the

Statement of Claim?

(iv) Whether the Respondent-Railway suffered loss and damages due to

breach committed by the Claimant and, if so, whether it is entitled

to the counterclaim as prayed for?

(v) To what other reliefs, if any, are the parties entitled?

9. Issue No. (i) was not pressed by either party before the learned Arbitrator.

The learned Arbitrator considered the remaining issues together and came

to the finding that the Petitioner had abandoned approximately 5% of the

contractual work and, despite repeated requests from the Respondent,

failed to complete the same. On such finding, the learned Arbitrator held

that the Respondent had validly terminated the contract. Consequently,

the learned Arbitrator rejected all claims of the Petitioner, including claims

for refund of Security Deposit and Performance Bank Guarantee.

10. The learned Arbitrator further recorded that the Respondent had incurred

an additional expenditure of Rs. 2,59,708.63/- towards procurement of an

outdoor type 11/0.4 KV, 500 KVA transformer (relating to Item No. 1 of

Part B of Schedule 1-Supply) under Purchase Order No. GB225047100092

dated 10.08.2022. In view of the Petitioner's failure to complete the

balance 5% of the work, including supply and installation of the

transformer, the learned Arbitrator held that the Respondent was entitled

to recover the said amount by way of counterclaim.

11. Accordingly, by Award dated 26.06.2024, the learned Sole Arbitrator

rejected all claims of the Petitioner and allowed the Respondent's

counterclaim for Rs. 2,59,708.63/-. It was further directed that, in the

event the Petitioner failed to pay the said amount within one month from

the date of the Award, the Respondent would be entitled to interest at the

rate of 12% per annum until realisation.

12. Subsequently, upon an application filed by the Petitioner under Section 33

of the Arbitration and Conciliation Act, 1996 pointing out a typographical

error in the Award dated 26.06.2024, the learned Arbitrator issued a

Corrigendum dated 06.09.2024 rectifying the said error.

13. Being aggrieved by and dissatisfied with the Award dated 26.06.2024 and

the Corrigendum dated 06.09.2024, the Petitioner has preferred the

present Petition under Section 34 of the Arbitration and Conciliation Act,

1996.

Submission on behalf of the Petitioner

14. Mr. Pratip Mukherjee, learned Counsel for the Petitioner submits that the

impugned Award dated 26.06.2024 (as corrected by Corrigendum dated

06.09.2024) is liable to be set aside as the same is ex facie a non-speaking

and unreasoned Award in violation of Section 31(3) of the Arbitration and

Conciliation Act, 1996. The learned Sole Arbitrator has rejected all ten

claims of the Petitioner and allowed the Respondent's counterclaim

without assigning cogent reasons, without analysing the documentary

evidence on record, and without dealing with the contractual provisions

relied upon by the Petitioner. The learned arbitrator has merely recorded

conclusions without disclosing the reasoning process leading thereto

thereby rendering the award patently illegal and unsustainable under

Section 34 of the Act.

15. The finding that the Respondent validly terminated the contract is wholly

erroneous and perverse. The delay in completion of the work was

attributable to the Respondent, who failed to provide the work front and

necessary drawings in timely manner and further failed to release running

bills and legitimate payments within the contractual period. The learned

Arbitrator failed to consider that such breaches on the part of the

Respondent directly impeded execution of the work. In the absence of

consideration of these material facts, the conclusion upholding the

termination is arbitrary and contrary to the evidence on record.

16. Learned Counsel for the Petitioner further argued that the Petitioner failed

to complete 5% of the work is unsustainable, as the alleged non-

completion was a direct consequence of non-payment of legitimate dues by

the Respondent. Despite this, the learned Arbitrator mechanically rejected

all the Petitioner's claims and allowed the Respondent's counterclaim

without examining proof of loss, causation, or mitigation. The Award thus

suffers from non-application of mind, perversity, and patent illegality,

warranting interference by this Court under Section 34 of the Act.

Submission on behalf of the Respondent

17. Mr. Sunil Kr. Singhania, learned counsel for the Respondent submits that

the present Petition under Section 34 is wholly devoid of merit and is liable

to be dismissed. The impugned Award dated 26.06.2024 (as corrected by

Corrigendum dated 06.09.2024) is a detailed and reasoned Award passed

in strict compliance with Section 31(3) of the Arbitration and Conciliation

Act, 1996. The learned Arbitral Tribunal has meticulously examined the

pleadings, contractual provisions, correspondence exchanged between the

parties, extension letters, running account bills, and other documentary

evidence on record. Upon such consideration, the Tribunal has recorded a

categorical finding that the delay in execution of the work was attributable

to the Petitioner and not to the Respondent. The Award clearly reflects due

application of mind and a reasoned analysis of the material before the

tribunal, and therefore cannot be termed as non-speaking or perverse.

18. The record further demonstrates that the Respondent granted as many as

eight extensions of time to enable the Petitioner to complete the work.

Despite such indulgence and repeated opportunities, the Petitioner failed

to complete the project within the extended timelines. The Tribunal, upon

appreciation of the documentary evidence, rightly held that the

termination of the contract was valid and in accordance with the

contractual terms. These findings are pure findings of fact based on

evidence and are not open to reappreciation in proceedings under Section

34 of the Act.

19. Further, the Tribunal rightly allowed the Respondent's counterclaim upon

finding that the Respondent had incurred additional expenditure towards

procurement of the transformer, which the Petitioner was contractually

obliged to supply and install but failed to do so. The direction for refund

was passed on the basis of proved documentary evidence and contractual

liability. The scope of interference under Section 34 being limited, and

there being no patent illegality or perversity in the Award, no interference

by this Hon'ble Court is warranted.

Legal Analysis

20. This Court has heard the arguments advanced by the learned counsel for

the parties and has carefully examined the documents placed on record.

21. At the outset, it is a settled proposition that the jurisdiction of this Court

under Section 34 of the Arbitration and Conciliation Act, 1996 is

circumscribed and supervisory in character. The Court does not exercise

appellate powers over an arbitral award and cannot reassess or reweigh

the evidence as if sitting in appeal. In Dyna Technologies Pvt. Ltd. v.

Crompton Greaves Ltd., reported as (2019) 20 SCC 1, the Hon'ble

Supreme Court cautioned that while examining an arbitral award, Courts

must not adopt a hyper-technical or excessively critical approach. The

award is required to be read as a whole and in a reasonable manner. So

long as the reasoning discloses application of mind and the conclusions

are founded on material available on record, minor deficiencies in

expression or elaboration would not render the award vulnerable. The

position has been further reiterated in Gayatri Balasamy v. ISG

Novasoft Technologies Ltd., reported as (2025) 7 SCC 1, wherein the

Hon'ble Supreme Court underscored that Section 34 is not designed to

function as an appellate forum. The arbitral regime is founded upon party

autonomy and finality of adjudication. Courts are not permitted to

reappreciate evidence, revisit factual findings, or interfere merely because

a different interpretation of the material on record may also be possible.

Judicial intervention is warranted only where the award is tainted by

patent illegality, perversity, jurisdictional infirmity, or contravention of the

fundamental policy of Indian law. It is equally well established that,

particularly after the 2015 amendment, the ground of "patent illegality" is

confined to errors that strike at the root of the award and does not

encompass erroneous application of law or re-evaluation of evidence.

Where the view taken by the Arbitral Tribunal is a plausible and

reasonable one arising from the evidence on record and the contractual

terms between the parties, this Court must defer to such determination

and refrain from substituting its own interpretation.

22. Examining the Award in the light of the aforesaid settled principles, this

Court finds that the learned Arbitral Tribunal has rendered a detailed and

reasoned Award after considering the pleadings, documentary evidence,

and the relevant contractual provisions. The Tribunal specifically noted

that the Petitioner completed 95% of the contractual work, excluding

installation of the transformer which was essential to complete the power

supply arrangement at ADTP. The Tribunal took into consideration the

letters dated 05.11.2020 and 16.11.2020 extending the time for conclusion

up to 28.02.2021, as well as the communication dated 23.02.2021

informing that the third running bill (CC-3) had already been processed for

payment, and the repeated requests made to the petitioner to supply and

install the transformer. The Tribunal further recorded the issuance of a 7

days' notice dated 25.02.2021 under Clause 62 of the General Conditions

of Contract and a further 48 hours' notice calling upon the Petitioner to

complete the work. The Petitioner's own admission vide letter dated

23.10.2020 that 5% of the work remained incomplete was also duly noted.

Upon appreciation of these aforesaid documents, the Tribunal concluded

that despite eight extensions of time and repeated opportunities, the

Petitioner failed to complete the remaining work and effectively abandoned

the same. Consequently, termination of the contract vide letter dated

06.04.2021 was held to be in accordance with the contractual terms. The

forfeiture of Security Deposit, encashment of Performance Guarantee, and

denial of price variation were found to be strictly in terms of Clause 5 of

the Letter of Acceptance dated 09.07.2018 and applicable GCC provisions.

These are findings of fact based on evidence and contractual

interpretation, and in view of the law laid down by the Hon'ble Supreme

Court in Dyna Technologies Pvt. Ltd (supra) and Gayatri Balasamy

(supra), the said findings cannot be interfered with merely because another

view is possible.

23. With respect to the counterclaim, the Arbitral Tribunal found, on the basis

of documentary proof, that the Respondent had incurred an additional

expenditure of Rs. 2,59,708.63/- towards procurement of the outdoor type

11/0.4 KV, 500 KVA transformer under Purchase Order dated 10.08.2022,

necessitated by the Petitioner's failure to supply and install the same. The

Tribunal, after examining the evidence, held the Petitioner liable to refund

the said amount.

24. This Court finds no perversity in the impugned Award, nor any disregard of

the contractual provisions, nor any infraction of the fundamental policy of

Indian law or public policy. The Hon'ble Supreme Court has consistently

cautioned that judicial interference with arbitral awards must be exercised

with extreme circumspection and only in cases where the illegality is

patent, apparent on the face of the Award, and goes to the root of the

matter. An award cannot be set aside merely because another view is

possible or because the Court may have arrived at a different conclusion

on the same material.

25. Applying the aforesaid settled principles, this Court is satisfied that the

impugned Award is a well-reasoned determination rendered upon due

consideration of the evidence on record and the relevant contractual

clauses. The findings recorded by the learned Arbitral Tribunal are

plausible and fall squarely within its domain of appreciation of facts. The

present Petition, in substance, seeks a re-evaluation of evidence and

substitution of this Court's view for that of the Tribunal, which is clearly

impermissible under Section 34 of the Act. No case for interference is made

out.

26. The Petition is accordingly liable to be dismissed.

(Gaurang Kanth, J.)

SAKIL AMED (P.A)

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter