Sunday, 17, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Konarak Enterprise vs Haldia Development Authority
2025 Latest Caselaw 2777 Cal/2

Citation : 2025 Latest Caselaw 2777 Cal/2
Judgement Date : 25 September, 2025

Calcutta High Court

M/S. Konarak Enterprise vs Haldia Development Authority on 25 September, 2025

Author: Arijit Banerjee
Bench: Arijit Banerjee
                                                                          2025:CHC-OS:200-DB
                         IN THE HIGH COURT AT CALCUTTA
                         COMMERCIAL APPELLATE DIVISION
                                  ORIGINAL SIDE

     Before:
     The Hon'ble Justice Arijit Banerjee
                   And
     The Hon'ble Justice Om Narayan Rai

                                 APOT 76 of 2025
                                      WITH
                               AP-COM 229 of 2024
                               AP-COM 255 of 2024
                             IA No.GA-COM 1 of 2025

                             M/s. Konarak Enterprise
                                        Vs.
                           Haldia Development Authority
                                       WITH
                                 APOT 135 of 2025
                           Haldia Development Authority
                                        Vs.
                             M/s. Konarak Enterprise

     For the Appellant                  : Mr. Subhabrata Datta, Adv.
                                          Mr. Aranya Saha, Adv.

     For the Respondent                 : Mr. Swarajit Dey, Adv.
                                          Mr. Saptarshi Kar, Adv.
                                          Ms. Debarati Das, Adv.

     Hearing Concluded on               : 18.08.2025

     Judgment on                        : 25.09.2025

     Om Narayan Rai, J.:-

1.    These two appeals under Section 37 of the Arbitration and Conciliation

     Act, 1996 (hereafter referred to "the said Act of 1996") assail a common

     order dated January 17, 2025 passed by an Hon'ble Single Judge of this

     Court whereby two applications under Section 34 of the said Act of 1996,

     being AP-COM No. 229 of 2024 filed by Haldia Development Authority

                                     Page 1 of 39
                                                                               2025:CHC-OS:200-DB
     (hereinafter referred to as "Haldia") and AP-COM 255 of 2024 filed by M/s.

     Konarak Enterprise (hereinafter referred to as "Konarak") were disposed of.

     By the order impugned AP-COM No. 229 of 2024 has been allowed in part

     and AP-COM No. 255 of 2024 has been dismissed.

     FACTS OF THE CASE:-

2.     Summed up briefly, the undisputed facts of the case, as may be gathered

     from the material on record, are as follows:-

      a) Haldia had floated a Notice Inviting Tender (NIT) for construction of

         road from Gholpukur to Tekhali Bridge via Amdabad High School at

         Nandigram (Part- A).

      b) Konarak participated in the said tender process and emerged

         successful, whereafter the work of construction of road from Gholpukur

         to Tekhali Bridge via Amdabad High School at Nandigram (Part - A) was

         awarded to Konarak by way of a work order dated February 18, 2009.

      c) Certain disputes arose between the parties regarding payments

         (including refund of security deposit) claimed by Konarak in respect of

         the work awarded to it by Haldia.

      d) As the relevant contract governing the parties (i.e. the work order

         issued by Haldia in favour of Konarak) and the terms of the NIT

         provided for resolution of disputes through arbitration, Konarak sought

         reference of the same to a learned Arbitrator for adjudication. However,

         as the learned Arbitrator could not be appointed in terms of the

         arbitration agreement, Konarak approached this Court by filing an

         application under Section 11 of the said Act of 1996 which was

         registered as A.P. 235 of 2017.

                                       Page 2 of 39
                                                                          2025:CHC-OS:200-DB
e) The said application was disposed of by an order dated April 27, 2017

   thereby appointing a learned Arbitrator to adjudicate upon the disputes

   that had cropped up between the parties.

f) Thereafter, Konarak filed its statement of claim before the learned

   Arbitrator, thereby laying the following three claims: -

   i.    Refund of security deposit laying in the custody of the respondent

         along with interest calculated upto 30.10.2016 at the rate of 12%;

  ii.    Delayed interest on the principal amount of the Final Bill upto

         30.10.2016 at the rate of 12%;

  iii.   Further interests from 01.11.2016 till payment at the rate of 12%;

         and

  iv.    Costs.

g) The respondent contested the claim by filing its counter statement cum

   counter-claim thereby denying all the material allegations made in the

   statement of claim and laying a counter claim of Rs.73,09,922/-

   (Rupees Seventy Three Lakh Nine Thousand Nine Hundred and Twenty

   Two) on the ground that Haldia had to get the balance work left

   unfinished by Konarak, by a third party upon the payment of the said

   sum of Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand

   Nine Hundred and Twenty Two).

h) The sole learned Arbitrator disposed of the arbitral proceedings by

   making and publishing an award on February 29, 2020 thereby partly

   allowing Konarak's claim and rejecting the counter-claim filed by

   Haldia.



                                 Page 3 of 39
                                                                                2025:CHC-OS:200-DB
      i) After receiving the said award, Konarak filed an application under

         section 33 of the said Act of 1996 seeking rectification of a few mistakes

         that, according to Konarak, were apparent on the face of the award.

      j) The learned Arbitrator disposed of the said application for rectification

         by an order dated July 03, 2021 thereby effecting certain corrections in

         the award.

      k) Feeling aggrieved by the said award, both Konarak as well as Haldia

         approached this Court by filing separate applications under Section 34

         of the said Act of 1996 which were registered as AP-COM No. 255 of

         2024 and AP-COM 229 of 2024 respectively.

      l) The said applications have been disposed of by a consolidated order

         dated January 17, 2025. While Konarak's application has been

         dismissed; Haldia's application has been partly allowed. Hence the

         present appeals by both - Konarak as well as Haldia.


     ARGUMENTS ON BEHALF OF THE APPELLANT:-

3.    Mr. Datta, learned Advocate appearing for Konarak took us through the

     order impugned and submitted that the same is erroneous to the extent the

     same holds that Haldia was entitled to "risk and cost compensation". Mr.

     Datta invited our attention to the work order dated January 13, 2009 in

     order to show that the time for completion of the work awarded to Konarak

     was 180 (One Hundred Eighty) days. He thereafter invited our attention to

     Clause 1(p) of the said work order to demonstrate that the security deposit

     that had been furnished by Konarak was to be released in three phases.

4.    It was submitted by Mr. Dutta that as the release of security deposit was

     inextricably linked with the completion of work, once the learned Arbitrator

                                      Page 4 of 39
                                                                                 2025:CHC-OS:200-DB
     concluded that the security deposit should be released, he could not have at

     the same time held that the work remained unfinished.

5.     He then invited our attention to page 72 of the paper book and contended

     that the work awarded to Konarak was only restricted to construction of a

     road measuring about 6100.0 meters from Gholpukur to Tekhali near

     Nandigram and that repair work was not the scope of Konarak's work.

6.     Mr. Dutta then took us through Clause 6 of the "Conditions of Contract"

     to show that upon completion of work the contractor was to be provided a

     certificate by the Executive Engineer/Authorised Officer. Inviting our

     attention to page 316 of the Volume-III of the stay application (4th and Final

     Bill), it was submitted that officers of Haldia themselves recorded the date of

     completion of work by Konarak as September 24, 2010. He then invited our

     attention to the last page of the same document (at page 359 of the stay

     application) in order to impress that a certificate of completion of work had

     been issued in terms of Clause 6 of the "Conditions of Contract".

7.     Our attention was then drawn to the Termination Clause in the work

     order to emphasise that Haldia was obliged to issue a notice of seven days'

     calling upon the contractor (i.e. Konarak) to complete the unfinished work

     with a caution that default would attract termination of the contract.

8.     Mr. Datta submitted that it was incorrect on the part of Haldia to claim

     compensation on the basis of "risk and cost principle" by alleging that work

     had been left unfinished by Konarak.

9.     Mr. Datta then invited our attention to a notice inviting online tender (e-

     tender) dated February 08, 2016 (pages 256 to 260 of the stay application)

     and submitted that the said notice would make it evident that the work that

                                       Page 5 of 39
                                                                                2025:CHC-OS:200-DB
      had been awarded to the other contractor was different from the one

      completed by Konarak. He also invited our attention to the scope of work

      mentioned in the said notice. Referring to the several works mentioned

      under the caption "Scope of Work", in the said notice, he submitted that

      most of the works listed there were not in the list of works allotted to

      Konarak.

10.     He thereafter invited our attention to the work order issued by Haldia in

      favour of the person who had emerged successful in the aforesaid tender

      (hereafter "new contractor") (at page 276 of the stay application) to drive

      home the point that the work awarded to the new contractor was different

      from the work awarded to Konarak. He firstly stressed on the date of

      issuance of the said work order i.e. March 03, 2016 and submitted that the

      said date was six (6) years after Konarak had completed the awarded work.

      It was submitted that the fact that there was a gap of six years between the

      date of completion of the work awarded to Konarak and the issuance of new

      work order in favour of a new contractor was evidence enough to conclude

      that issuance of such tender and work order was necessitated due to the

      deterioration of the condition of road upon the same being used for six

      years.

11.     Mr. Datta then took us to the "Certificate of Final Completion" (at page

      279 of the stay application) and showed us that the said new contractor also

      did not complete the entire work as would be evident from the fact that the

      amount put to tender was Rs.78,90,364/- (Rupees Seventy Eight Lakh

      Ninety Thousand Three Hundred and Sixty Four) and the value of actual

      work done was Rs.73,09,922/- (Rupees Seventy Three Lakh Nine Thousand

                                       Page 6 of 39
                                                                              2025:CHC-OS:200-DB
   Nine Hundred and Twenty Two). Mr. Datta sought to insinuate that if the

   new contractor had completed the entire work there would not have been a

   difference in the value of the quantity of work tendered and the value of the

   quantity of work actually executed/done. He further sought to project that if

   it was the case that completion certificate would be issued only upon

   completion of the entire work then in such case, completion certificate

   would not have been issued in favour of the new contractor also. He then

   submitted that variation in the value of the quantity of quantity of work

   tendered and the value of the quantity of work actually executed/done was a

   usual feature in such contracts. It was submitted that in cases where it is

   found that completion of work is impossible given the site conditions, then

   upon execution of such quantity of work as would be possible to be executed

   final completion certificate is issued for the value of work actually upon

   drawing an excess saving statement. By making such submissions Mr.

   Datta sought to exemplify that execution of work lesser than the contracted

   work by Konarak could not be held against Konarak once completion

   certificate has been issued.

12. Mr. Datta next relied on a letter dated August 25, 2009 written by

   Konarak to Haldia in order to demonstrate that 80% of the works had been

   completed as on the date of issuance of the said letter i.e. August 25, 2009.

   He also referred to several other letters dated December 13, 2010, January

   05, 2011, February 09, 2011 and March 01, 2011 issued by Haldia and

   contended that although time had not been extended by Haldia yet Haldia

   kept on writing letters and pressing for completion of works, which in fact

   had already been completed by Konarak.

                                    Page 7 of 39
                                                                                2025:CHC-OS:200-DB
13. He also referred to a letter dated July 22, 2015 written by the Block

   Development Officer, Nandigram-II, Development Block to the District

   Magistrate, Purba Medinipur whereby the District Magistrate was informed

   about the pathetic condition of the road and he thereby sought to insinuate

   that the subsequent notice inviting tender was in fact a curative action

   aimed at repairing the damaged roads and not to complete incomplete works

   allegedly left by Konarak.

14. It was further submitted by Mr. Datta that in any event since time had not

   been extended therefore the claimant i.e. Konarak had no obligation to do

   any work after expiry of the contractual period. Mr. Datta submitted that the

   learned Arbitrator went completely wrong in deciding issue no. 6. It was

   submitted that once the learned Arbitrator held that Konarak i.e. the

   contractor was entitled to refund of the security deposit, then in the same

   breath, the learned Arbitrator could not have held that the employer i.e.

   Haldia was entitled to compensation based on the risk and cost principle.

15. It was then submitted by Mr. Datta that the Section 34 Court ought to

   have considered and appreciated that if issue no. 9 had been decided in the

   negative then security deposit could not have been directed to be refunded

   in terms of Clauses 3(a), 3(b) and 3(c) of the contract. It was then submitted

   that the learned Arbitrator had found that Haldia had not imposed any

   liquidated damages upon Konarak and that itself showed that Konarak had

   completed the work. It was submitted that both the Section 34 Court as well

   as the learned Arbitrator had failed to appreciate that the 4th and final bill

   and the certificate as regards completion of work had been prepared by the



                                     Page 8 of 39
                                                                               2025:CHC-OS:200-DB
   engineers of Haldia and the same constituted clinching evidence of Konarak

   having completed the work.

16. Mr. Datta was critical of the observations by the Hon'ble Single Judge in

   paragraph 28 of the order impugned and contented that the same suffered

   from inherent contradictions. He asserted that if the entire work had been

   completed then the question of adjusting security deposit or allowing any

   payment on the basis of risk and cost principle could not have arisen at all.

   He also took exception to the observation that "...the measurement books,

   which are documents admitted by both parties, clearly indicate that a

   substantial portion of the work was actually completed and final bills raised,

   passed and paid for such components of the work" in paragraph 29 of the

   order impugned and submitted that when the work had been completed the

   expression "substantial" could not have been used by the Hon'ble Single

   Judge without there being any basis therefor.

17. He challenged various observations as regards the contract being alive till

   October 31, 2010 and thereafter upto February 2011 made by the learned

   Arbitrator as being based on no evidence. It was further submitted the

   Conditions of Contract did not permit any unilateral extension of time and

   that extension was to be done in the manner indicated in the Conditions of

   Contract.

18. Mr. Datta submitted that no amount could have been awarded by way of

   counter claim to Haldia at all and that being so the enhancement of the

   amount awarded by the learned Single Judge in the order impugned, while

   correcting a perceived arithmetical error could also not be done. We hasten

   to put on record that although Mr. Datta challenged the very basis of

                                     Page 9 of 39
                                                                             2025:CHC-OS:200-DB
   awarding the counter claim and hence its enhancement, yet he very fairly

   steered clear of a ground taken in the Memorandum of Appeal thereby

   assailing the order impugned for the same having enhanced the counter

   claim by correcting arithmetical error, in view of the recent enunciation of

   law by a Constitution Bench of the Hon'ble Supreme Court in the case of

   Gayatri Balasamy vs. ISG Novasoft Technologies Ltd.1. It was submitted

   that in view of the law laid down by the Hon'ble Supreme Court in the

   aforesaid judgment, the Court had power to rectify computational errors

   even under Section 34 of the said Act of 1996 but in the case at hand there

   was no scope for the Court to exercise such power and enhance the counter

   claim when the counter claim itself was not allowable.

19. Mr. Datta relied on a judgment of the Hon'ble Supreme Court in the case

   of Associate Builders vs. Delhi Development Authority2 for the

   proposition that an award could be interfered with if the same was based on

   no evidence or by ignoring vital evidence.

20. Mr. Dutta pressed for setting aside that part of the order impugned

   whereby Haldia's claim for compensation was allowed by the learned

   Arbitrator and affirmed by the Hon'ble Single judge.

   ARGUMENTS ON BEHALF OF THE RESPONDENT:-

21. Mr. Dey, learned Advocate appearing for Haldia at the outset submitted

   that the scope of interference under Section 34 was very limited and that

   power of the appellate court under Section 37 of the said Act of 1996 was

   akin to that of Section 34 of the said Act of 1996. In support of his


   1(2025) 7 SCC 1

   2(2015) 3 SCC 49



                                     Page 10 of 39
                                                                               2025:CHC-OS:200-DB
   submissions he relied on the judgments of the Hon'ble Supreme Court in

   the cases of Dyna Technologies Private Limited vs. Crompton Greaves

   Limited3 and MMTC Limited vs. Vedanta Limited4.

22. Mr. Dey criticised the award by submitting that the learned Arbitrator

   erred in allowing Konarak's claim for security deposit. He submitted that the

   claim for security deposit was barred by limitation. It was submitted that in

   terms of provisions for release of security deposit contained in the work

   order, 30% of the security deposit was to be refunded one year after

   completion of a particular phase of work, the security deposit was to be

   refunded in three phases. Thus the claimant's entitlement to security

   deposit, if any, arose immediately after expiry of one year after completion of

   a given phase. He referred to the several letters issued by the claimant i.e.

   Konarak and submitted that Konarak had demanded refund of security

   deposits as early as on March 29, 2011 (Exhibit R-29 at page 236 of the stay

   application).

23. Mr. Dey took us through paragraph 51 of the Statement of Claim filed by

   Konarak i.e. the claimant and submitted that it was the claimant's own case

   that the work had been completed by the claimant on September 24, 2010,

   that the defect liability period continued till September 24, 2012 and that

   obligation as regards maintenance remained till September 23, 2013. It was

   submitted that the terms of the clause read in the light of the said

   statements made by the claimant would make it evident that the claimant's

   cause of action for 30% of the security deposit arose upon expiry of one year


   3(2019) 20 SCC 1

   4(2019) 4 SCC 163



                                     Page 11 of 39
                                                                               2025:CHC-OS:200-DB
   from the date of completion of work which would be September 24, 2011,

   then for the next 30% it arose upon expiry of two years from the date of the

   completion of work which would be September 24, 2012 and for the balance

   40% thereof, it arose upon expiry of three years from the completion of work

   which would be September 24, 2013.

24. It was then submitted that once a claim was made in the year 2011,

   limitation began to run from the said year itself and limitation set in three

   years thereafter i.e. in the year 2014 thereby barring any relief in respect of

   the security deposit. It was submitted that once limitation had set in the

   claims for security deposit could not have been entertained in an arbitral

   proceeding initiated subsequently. He invited our attention to paragraph 23

   of the order impugned and submitted that the same was based on an

   incorrect finding that the claim for refund of security deposit was made on

   November 11, 2016.

25. He then referred to the various letters written by Konarak to Haldia and

   sought to demonstrate that in none of the letters had it been written by

   Konarak that work had been completed or that the same had been

   measured up. Mr. Dey took this Court through the provisions of Clauses

   3(a), 3(b) and 3(c) of the Conditions of Contract and submitted that the

   contractor i.e. Konarak was not entitled to refund of security deposit as

   work had not been completed by it.

26. In order to demonstrate that work had not been completed by Konarak,

   Mr. Dey referred to a letter dated May 04, 2015 written by Konarak to Haldia

   (page 99 of the stay application) to demonstrate that Konarak itself admitted



                                     Page 12 of 39
                                                                             2025:CHC-OS:200-DB
   that Konarak had been unable to complete the work as its proprietor had

   met with an accident.

27. Inviting our attention to Clause 3(c) of the Conditions of Contract, it was

   submitted that while it had been argued on behalf of Konarak that the said

   Clause had not been invoked at all, there were several letters on record

   stating that the unfinished work left by Konarak would be got done by other

   agency upon failure of Konarak to complete the same and in that view of the

   matter although, Clause 3(c) was not specifically mentioned in the letters,

   yet it would be evident that the same was definitely invoked. He referred to

   the letters dated January 05, 2011 (page 232 of the stay application),

   February 09, 2011 (page 233 of the stay application) to demonstrate that

   Clause 3(c) had been invoked by Haldia. He also placed reliance on

   paragraph 44 of the order impugned and drew support therefrom as regards

   the interpretation of Clause 3(c).

28. It was submitted that the work of maintenance included the work of repair

   also. Letters dated May 04, 2015 and August 26, 2015 issued by Konarak to

   Haldia were placed to contend that the aspect that the awarded work had

   not been completed in entirety was in fact an admitted case. Mr. Dey also

   invited our attention to the cross-examination of Haldia's witnesses done on

   behalf of Konarak and placed questions 104 and 105 thereof to demonstrate

   that no suggestion was given on behalf of the claimant that the second

   contract was not pertaining to any balance work or that the entire work was

   completed.

29. In such connection paragraph 36(e) of the award passed by the learned

   Arbitrator was also placed. It was submitted by Mr. Dey that the findings of

                                        Page 13 of 39
                                                                                       2025:CHC-OS:200-DB
   the learned Arbitrator as regards the refund of security deposit and earnest

   money were not in terms of the contract governing the parties.

30. It was then submitted that both the learned Arbitrator as well as the

   Hon'ble Single Judge have failed to appreciate that even in terms of clause

   3(c) of the Conditions of Contract, forfeiture of the security deposit was

   possible and permissible. Mr. Dey submitted that by invoking clause 3(c)

   security deposit had been forfeited and as such there could not have been

   any direction to refund the same.

31. He, therefore, submitted that such part of the order impugned which

   affirms the award to the extent the same directs refund of security deposit

   and earnest money to Konarak should be set aside.

   ANALYSIS AND DECISION:-

32. We have heard the learned Counsel appearing for the respective parties

   and considered the material on record.

33. Since the twin appeals before us entail challenge thrown to an order

   passed on two applications under Section 34 of the said Act of 1996,

   therefore abiding by the law governing the field, we would only be required

   to see as to whether the Hon'ble Single Judge has exercised his jurisdiction

   under Section 34 of the said Act of 1996 properly or not. That would entail a

   limited enquiry to find out whether the award impugned before the Hon'ble

   Single Judge could pass the test of Section 34 of the said Act of 1996 or not.

   In this context we may refer to the following observations of the Hon'ble

   Supreme Court in the case of MMTC Limited (supra):-

      "11. As far as Section 34 is concerned, the position is well-settled by now that the
       Court does not sit in appeal over the arbitral award and may interfere on merits on


                                       Page 14 of 39
                                                                                        2025:CHC-OS:200-DB
 the limited ground provided under Section 34(2)(b)(ii) i.e. if the award is against the
 public policy of India. As per the legal position clarified through decisions of this
 Court prior to the amendments to the 1996 Act in 2015, a violation of Indian public
 policy, in turn, includes a violation of the fundamental policy of Indian law, a
 violation of the interest of India, conflict with justice or morality, and the existence of
 patent illegality in the arbitral award. Additionally, the concept of the "fundamental
 policy of Indian law" would cover compliance with statutes and judicial precedents,
 adopting a judicial approach, compliance with the principles of natural justice,
 and Wednesbury [Associated Provincial Picture Houses v. Wednesbury Corpn.,
 (1948) 1 KB 223 (CA)] reasonableness. Furthermore, "patent illegality" itself has
 been held to mean contravention of the substantive law of India, contravention of
 the 1996 Act, and contravention of the terms of the contract.
12. It is only if one of these conditions is met that the Court may interfere with an
 arbitral award in terms of Section 34(2)(b)(ii), but such interference does not entail a
 review of the merits of the dispute, and is limited to situations where the findings of
 the learned Arbitrator are arbitrary, capricious or perverse, or when the conscience
 of the Court is shocked, or when the illegality is not trivial but goes to the root of the
 matter. An arbitral award may not be interfered with if the view taken by the
 learned   Arbitrator    is   a   possible   view    based    on   facts.   (See Associate
 Builders v. DDA [Associate Builders v. DDA, (2015) 3 SCC 49 : (2015) 2 SCC (Civ)
 204] . Also see ONGC Ltd. v. Saw Pipes Ltd. [ONGC Ltd. v. Saw Pipes Ltd., (2003) 5
 SCC 705] ; Hindustan Zinc Ltd. v. Friends Coal Carbonisation [Hindustan Zinc
 Ltd. v. Friends Coal Carbonisation, (2006) 4 SCC 445] ; and McDermott International
 Inc. v. Burn Standard Co. Ltd. [McDermott International Inc. v. Burn Standard Co.
 Ltd., (2006) 11 SCC 181] )
13. It is relevant to note that after the 2015 Amendment to Section 34, the above
 position stands somewhat modified. Pursuant to the insertion of Explanation 1 to
 Section 34(2), the scope of contravention of Indian public policy has been modified to
 the extent that it now means fraud or corruption in the making of the award,
 violation of Section 75 or Section 81 of the Act, contravention of the fundamental
 policy of Indian law, and conflict with the most basic notions of justice or morality.
 Additionally, sub-section (2-A) has been inserted in Section 34, which provides that
 in case of domestic arbitrations, violation of Indian public policy also includes patent
 illegality appearing on the face of the award. The proviso to the same states that an
 award shall not be set aside merely on the ground of an erroneous application of the
 law or by reappreciation of evidence.




                                    Page 15 of 39
                                                                                           2025:CHC-OS:200-DB
         14. As far as interference with an order made under Section 34, as per Section 37, is
          concerned, it cannot be disputed that such interference under Section 37 cannot
          travel beyond the restrictions laid down under Section 34. In other words, the court
          cannot undertake an independent assessment of the merits of the award, and must
          only ascertain that the exercise of power by the court under Section 34 has not
          exceeded the scope of the provision. Thus, it is evident that in case an arbitral
          award has been confirmed by the court under Section 34 and by the court in an
          appeal under Section 37, this Court must be extremely cautious and slow to disturb
          such concurrent findings."
                                                              [Emphasis Supplied By Us]

34. With our boundaries thus set, we would now test the order impugned in

   the light of the material on record and the submissions made on behalf of

   the respective parties.

35. The submissions made before us raise the following issues, any of which if

   answered in the negative would call for interference with the order impugned

   and hence the award:-

    i.    Whether the finding of the learned Arbitrator that Konarak had
          not completed the work awarded to Konarak by work order dated
          January 13, 2009 which has been affirmed by the order
          impugned is correct?

   ii.    Whether the finding of the learned Arbitrator that Haldia was
          entitled to compensation in the nature of adjustment of excess
          amount paid to the new contractor (on the basis of risk and cost
          principle), which has been affirmed by the order impugned and
          then enhanced by way of correcting arithmetical error, is correct?
          This issue would include the issue as to whether the work
          awarded to the new contract was the work left unfinished by
          Konarak.




                                           Page 16 of 39
                                                                                 2025:CHC-OS:200-DB
      iii.   Whether the finding of the learned Arbitrator that Konarak was
             entitled to refund of security deposit which has been affirmed by
             the order impugned is correct? This issue subsumes the issue as
             to whether Konarak's claim of refund of security deposit was
             barred by limitation.

36.      We hasten to add that we have framed the aforesaid issues only for the

      sake of clarity of reasoning and for ease of dealing with the arguments

      advanced before us on behalf of the parties while remaining fully conscious

      that we are not sitting in appeal over the award of the arbitral tribunal. Our

      enquiry would be confined to determining as to whether upon application of

      the correct principles under Section 34 of the said Act of 1996 the award

      and the order impugned can be sustained in the light of the material before

      us.

37.      The aforesaid issues are therefore decided as under:-

      Issue No. (i) Whether the finding of the learned Arbitrator that
      Konarak had not completed the work awarded to Konarak by the
      work order dated January 13, 2009 which has been affirmed by the
      order impugned is correct?

38.      The case run by Konarak and as presented by Mr. Datta before us was

      that the contractual work had been completed by Konarak on September 24,

      2010 itself. For such purpose the noting in the 4th and Final Bill (page 316

      of the stay application) as regards the completion of the work on September

      24, 2010 and the certificate issued by the relevant engineer on July 16,

      2015 was relied on. Mr. Datta found fault with the learned Arbitrator in not

      taking into consideration the said two documents. We have noticed that the

      learned Arbitrator had relied on the various correspondences exchanged


                                        Page 17 of 39
                                                                                           2025:CHC-OS:200-DB
   between the parties to arrive at a conclusion that the work remained

   incomplete till the time of termination of the contract. The following

   observations of the learned Arbitrator are noteworthy in such context:-

        "(i) Thereafter from the end of respondent another letter dated 25 th August, 2009 is
        forthcoming (Exhibit R/4) addressed to the Chief Executive Officer, Haldia
        Development Officer issued by the claimant with prayer for extension of time upto
        31st March, 2010. In the said letter the claimant submitted that 80% of the works
        have already been completed, but culvert and bituminous work were not started
        due to rainy season. Therefore, she prayed for extension of time upto 31 st March,
        2010 to complete the entire work.

        (j) Again in her letter dated 20th April, 2010 (Exhibit C/11), the claimant prayed for
        extension of time for completion of the tender work upto 31 st August, 2010 due to
        disturbance of local people and suspension of work. In the said letter she has
        claimed that 90% of the work have already been completed, but bituminous work,
        bridge and side shouldering work cannot be started due to public disturbance at
        the road entrance of the Gholepukur Bazar. Since at the approach, structures have
        not been removed, people of the locality were not allowing her to execute any work
        and to give entry to her trucks carrying road materials for internal balance works.
        So all works will have to be closed unless the aforesaid approach is properly made
        for which the prayer for extension was made.

        (k) From the documents on record, it appears that by letter dated 13 th December,
        2010 (Exhibit R/28), letter dated 5 th January, 2011 (Exhibit R/31), letter dated 9 th
        February, 2011 (Exhibit R/31/1) and letter dated 1st March, 2011 (Exhibit R/31/2),
        the respondent was repeatedly asking the claimant to complete the work including
        repairing of the road, but no document is forthcoming from the end of the
        respondent that they have officially extended the period and disposed of both the
        aforesaid two applications of the claimant namely Exhibit R/4 and Exhibit C/11."

39. This provides ample evidence to conclude that work was still remaining

   incomplete as on March 01, 2011. In such view of the matter the recording

   of completion of work as on September 24, 2010 as reflected in the 4th and

   final bill and in the certificate referred to by Mr. Datta cannot be said to be a

   certificate as regards the completion of the entire contracted work. It is

                                          Page 18 of 39
                                                                                           2025:CHC-OS:200-DB
   therefore not in the realm of doubt that the work was not completed by

   Konarak. The learned Arbitrator has taken a plausible view of the matter.

   Non consideration of the said two documents by the learned Arbitrator

   would not have and has not affected the final conclusion reached by the

   learned Arbitrator. The letters on record including the claimant's own letters

   scream about the work remaining unfinished at least till March 01, 2011

   therefore, non-consideration of the said two documents cannot and does not

   have any effect on the learned Arbitrator's ultimate decision.

40. The matter can be angulated from another perspective as well. Clause 6 of

   the "Conditions of Contract" reads thus:-

        "Clause 6 - In completion of the work, the contractor shall be furnished with a
        certificate by the Executive Engineer/Authorised Officer (hereinafter called the
        Engineer-in-charge) of such completion but no such certificate shall be given, nor
        shall the work be considered to be completed until the contractor shall have
        removed from the premises on which the work shall be executed all scaffolding,
        surplus materials and rubbish, and cleaned of the dirt from all wood-work, doors,
        windows, walls, floors, or other parts of any building, in upon or about which the
        work is to be executed or of which he may have had possession for the purpose of
        the execution thereof nor until the work shall have been measured by the Engineer-
        in-charge/Authorised Officer whose measurements shall be binding and conclusive
        against the contractor if the contractor shall fail to comply with the requirements of
        this clause as to removal of scaffolding, surplus materials and rubbish and cleaning
        off dirt on or before the date fixed for the completion of the work the Engineer-in-
        charge/Authorised Officer may at the expense of the contractor remove such
        scaffolding, surplus materials and rubbish, and dispose off the same as he thinks
        fit and clean off such dirt as aforesaid; and the contractor shall forth with pay the
        amount of all expense so incurred and shall have no claim in respect of any such
        scaffolding or actually realised by the sole thereof."

41. Thus, in terms of the Conditions of Contract, the certificate as regards

   completion of work was to be issued by the Executive Engineer/Authorised

   Officer and the measurements were also to be done by the same authority.

                                          Page 19 of 39
                                                                               2025:CHC-OS:200-DB
   However, in the case at hand, the certificate has been signed by two officers

   designated as S.A.E. (Civil) /HDA [i.e. (Sub-Assistant Engineer) Civil] and

   A.E. (Civil)/ HDA [i.e. (Assistant Engineer) Civil]. Therefore, neither has the

   measurement been done by the Executive Engineer/Authorised Officer nor

   has the certificate of completion of works been issued by the said officer. In

   that view of the matter, the notings in the 4th and Final Bill do not qualify

   for a certificate issued in terms of Clause 6 of the Conditions of Contract.

   This aspect becomes all the more prominent in the light of the Final

   Certificate dated March 28, 2017 appearing at page 279 of the stay

   application issued in favour of the new contractor by Haldia upon

   completion of the work awarded to him. The said certificate captioned as

   "Certificate of Final Completion" has been signed by "Executive Engineer

   (Civil)" and the same clearly conforms to the requirement of Clause 6 of the

   Conditions of Contract. The aforesaid facts taken together make it evident

   that the notings in the 4th and Final Bill heavily relied upon by Mr. Datta do

   not in any manner help in proving Konarak's case that Konarak had

   completed its work and that a certificate of completion had been issued to

   that effect.

42. Now at this stage a question arises as regards the effect and purpose of

   the notings in the 4th and Final Bill heavily relied upon by Mr. Datta. The

   same can be satisfactorily answered in the light of three correspondences

   exchanged between the parties i.e. letter dated May 04, 2015 written by

   Konarak to Haldia, Haldia's reply by a letter dated August 10, 2015 and

   Konarak's counter reply by another letter dated August 26, 2015.



                                     Page 20 of 39
                                                                                           2025:CHC-OS:200-DB
43. By a letter dated May 04, 2015 (page 99 of the stay application) Konarak

   contended that the "work was completed in the year 2010 and maintenance

   period (sic was) also over......." and thereby requested Haldia "to make

   necessary arrangement for preparation of final bill....".

44. Haldia replied to the said letter by its letter dated August 10, 2015

   contending as follows:-

        "............You have executed the work leaving few stretches incomplete and with
        deviation of specified thickness of the road strata for some road stretch. You have
        rectified part of that road stretch as per instruction of this office but entire road
        rectification was not done by you. You were directed to complete the balance work
        along with rectification of the road strata for the balance stretch through several
        communications from this office but you did not execute the same mentioning the
        reason for local disturbance and work has been left unattended since
        October‟2010......"
45. Konarak replied to the said letter of Halida by a letter dated August 26,

   2015 (at page 101 of the stay application) stating as follows:-

        "..........the above mentioned work completed on date 24.09.2010 along with major
        portion of rectification work mentioned in a meeting held with HDA officials and
        local Panchayat Authority. But accidentally I fall in a major road accident and I took
        more than one year to recovery myself. But in that way I have no option to stop the
        work as was as was basis. This was mentioned by me already in my several
        letters and claimed to declare my work completed on dt. 24.69.2010 (sic
        24.09.2010). Accordingly joint measurement was taken after that period."
46. A cumulative reading of the aforementioned three letters would lead to the

   inescapable inference that the work could not be completed. Even if we

   assume that Konarak had completed the work on September 24, 2010 as

   projected by it in its letter dated August 26, 2015 then also such completion

   would only refer to the completion of construction and not of rectification

   which indeed was within the contractual scope of work awarded to Konarak

   inasmuch as Haldia's letter dated August 10, 2015 reveals that such

                                          Page 21 of 39
                                                                               2025:CHC-OS:200-DB
   rectification was necessitated because of certain deviation from the awarded

   work done by Konarak. The notings in the 4th and Final Bill heavily relied

   upon by Mr. Datta, therefore, seem to be notings pertaining to the

   measurement of the work done or competed in terms of the contract till

   September 24, 2010. The same do not mean works measured up after

   completion of entire contractual work.

47. In such view of the matter non-consideration of the notings of the 4th and

   Final Bill by the learned Arbitrator would not vitiate the award and

   consequently the order impugned would also remain unaffected.

48. Mr. Datta submitted that it is a usual feature of contracts as that of the

   present nature that a difference between the value of the quantity of actual

   work done and the value of the total contractual work awarded remains. For

   demonstrating the same he had placed the Final Completion Certificate

   issued by Haldia in favour of the new contractor and shown the relevant

   figures. He had submitted that oftentimes it happens that due to poor site

   conditions it becomes impossible to complete the awarded work in full and

   in such cases the employer measures up the work done upto the extent it

   was doable and issues completion certificate. He sought to impress upon us

   that the variation between the value of the quantity of actual work done and

   the value of the total contractual work awarded in Konarak's case was also

   explicable. We do not find this submission convincing. In the case of

   Konarak there are letters on record which show that Konarak has failed to

   deliver despite timelines being shifted from one date to other. Indeed there is

   no formal extension of time but then nothing is going to turn on that. The

   question is whether work was completed or not. We also take note of

                                     Page 22 of 39
                                                                                        2025:CHC-OS:200-DB
   Konarak's letters that hint about some local disturbances preventing

   execution of work but Konarak has not been able to establish such case

   before the learned Arbitrator that it could not do the work because of

   disturbances. On the contrary its case was that it had completed the work

   which is factually incorrect. We therefore answer Issue No. (i) in the

   affirmative.

49. We now move to the second issue.

   Issue No. (ii) Whether the finding of the learned Arbitrator that Haldia
   was entitled to compensation in the nature of adjustment of excess
   amount paid to the new contractor (on the basis of risk and cost
   principle), which has been affirmed by the order impugned and then
   enhanced by way of correcting arithmetical error, is correct? This
   issue would include the issue as to whether the work awarded to the
   new contract was the work left unfinished by Konarak.

50. The discussion as regards Issue No. (i) above has made it clear that

   Konarak had not been able to complete the contractual work awarded to it.

   The conditions of contract that governed the parties provided that Haldia

   could get unfinished work completed by another contractor. In this

   connection Clauses 3(a) to 3(c) of the Conditions of Contract may be

   noticed:-

        "Clause 3 : In any case in which under any clauses of this contract the contractor
        shall have rendered himself liable to pay compensation amounting to the whole of
        his security deposit (whether paid in lump sum or deducted by instalment). The
        Executive Engineer/Authorised officer on behalf of the Authority shall have power
        to adopt any of the following courses, as he may deem best suited to the interests
        of the Authority.

        a) To rescind the contract (of which rescission notice in writing to the contractor
        under the hand of the Executive Engineer/Authorised officer shall be conclusive


                                        Page 23 of 39
                                                                                           2025:CHC-OS:200-DB
        evidence), and in which case the security deposit of the contractor shall stand
        forfeited and be absolutely at the disposal of the Authority.

        b) To employ labour paid by the Authority and to supply materials to carry out the
        work or any part of the work debiting the contractor with the cost of the labour and
        the price of the materials (of the amount of which cost and price a certificate of the
        Executive Engineer/Authorised officer shall be final and conclusive against the
        contractor) and crediting him with the value of the work done, in all respects in the
        same manner and at the same rates as if it had been carried out by the contractor
        under the terms of his contract, the certificate of the Executive Engineer/Authorised
        officer as to value of the work done shall be final and conclusive against the
        contractor.

        c) To measure up the work of the contractor and to take such part thereof as shall
        be unexecuted out of his hands and to give it to another contractor to complete, in
        which case any expenses which may be incurred in excess of the sum which would
        have been paid to the original contractor, if the whole work had been executed by
        him (of the amount of which excess the certificate in writing of the Executive
        Engineer/Authorised officer final and conclusive) shall be borne and paid by the
        original contractor and may be deducted from any money due to him by the
        Authority under the contract or otherwise or from his security deposit or the
        proceeds of sale thereof or a sufficient part thereof."

51. The learned Arbitrator has in paragraph 36(d) of the award found that

   Haldia has invoked Clause 3(c) of the Conditions of Contract. After a

   detailed discussion under the captions "Mode of payment against tender

   work" (paragraph 35) and "Profit and loss of the parties accounted for"

   (paragraph 36) of the award the learned Arbitrator has found in paragraph

   36(c) that "on the one hand by non-payment of the entire contract value of the

   1st contractor i.e. the claimant, the respondent authorities was absolved of

   their liability to make payment of Rs.55,09,759/- which had to be paid to the

   original contractor if she did the entire work but, for doing the same by a third

   party contractor, they had to incur total expenses of Rs.73,09,922/-. As such

   the respondent had to incur extra amount of Rs.18,00,163.". The learned

                                           Page 24 of 39
                                                                               2025:CHC-OS:200-DB
   Arbitrator has then refined the aforesaid aspect further in paragraph 36(e) of

   the award where he has found that although the contract awarded to the

   new contractor was for a sum of Rs.73,09,922/- it included extra works also

   which accounted for a sum of Rs.11,74,753.44p and thus the value of the

   work left unfinished by Konarak which was completed by the new contractor

   was only Rs.61,35,168.56/- (i.e. Rs.73,09,922 - Rs.11,74,753.44). The

   learned Arbitrator has then held that the excess financial burden on Haldia

   by reason of engagement of a new contractor for completing the unfinished

   works of Konarak was to the tune of Rs.6,25,409.56/- only.

52. The learned Arbitrator's reasoning is simple and perfect. He has reasoned

   that if the contractual work was valued at Rs.1,96,49, 202/- and value of

   the total work done by Konarak upto the date of measurement was

   Rs.1,41,39,493/- then the value of the unfinished work in terms of the

   contract entered into between Haldia and Konarak would be Rs.55,09,759/-

   (i.e. Rs. 1,96,49, 202 - Rs.1,41,39,493). Since the total contracted work was

   not executed by Konarak and work valued at Rs.55,09,759/- was left

   unfinished by it (i.e. Konarak) therefore Haldia had to re-award the said

   balance work to a third party i.e. new contractor. To put it differently, the

   learned Arbitrator has reasoned that Haldia had to pay Konarak

   Rs.55,09,759/- less that it would have to pay if Konarak had completed the

   contracted work in full.

53. It has been found by the learned Arbitrator in paragraph 36(e) of the

   award that the said new contractor executed such balance work for a

   consideration of Rs.61,35,168.56/-. That being so the extra financial burden

   befalling Haldia in engaging a new contractor for doing the balance work (i.e.

                                    Page 25 of 39
                                                                                            2025:CHC-OS:200-DB
   the work left unfinished by Konarak) would be Rs.6,25,409.56 (i.e.

   Rs.61,35,168.56 - Rs.55,09,759= Rs. 6,25,409.56/-). The learned Arbitrator

   has found Konarak liable in the said sum of Rs.6,25,409.56/- which became

   the extra financial burden of Haldia due to non-completion of work by

   Konarak.

54. The learned Arbitrator has then proceeded to direct that in terms of

   Clause 3(c) of the Conditions of Contract Haldia was entitled to deduct a

   sum of Rs.6,25,409.56 from the security deposit withheld by it and release

   the balance sum of Rs.4,34,431.44 to Konarak.

55. We take note of the fact that Konarak had after passing of the award

   approached the learned Arbitrator by way of an application under Section

   33 of the said Act of 1996 whereupon the learned Arbitrator corrected the

   award by enhancing the value of the work done by Konarak to

   Rs.1,74,05,144/- (from Rs.1,41,39,493/-). However, the learned Arbitrator

   did not carry out the consequential corrections that would have been the

   natural fall out of such enhancement of the value of the work done by

   Konarak. The same was noted by the Hon'ble Single Judge and the

   necessary corrections were done in the following manner:-

    "47. The Arbitral Tribunal proceeded on the premise that it did not, since the respondent
        had not filed any such independent application under 14 Section 33 of the 1996 Act,
        and restricted its correction to the prayer made by the claimant in its application
        under the said provision.
    48. However, such view of the Arbitral Tribunal is patently illegal, being in contravention
        of Section 33(3) of the 1996 Act. The said provision empowers the Arbitral Tribunal
        to correct any error of the type referred to in Clause (a) of sub-section (1) on its own
        initiative within 30 days from the date of arbitral award.




                                          Page 26 of 39
                                                                                         2025:CHC-OS:200-DB
49. Clause (a) of sub-section (1) of Section 33 provides inter alia that the Arbitral
    Tribunal may correct any computation errors and the error pointed out by the
    respondent pertains to simple calculation.
50. Admittedly, in the present case, the Tribunal allowed the application of the claimant
    under Section 33 and altered the second component of the risk and cost claim. This
    Court is required to delve a bit more into the said aspect of the matter.
51. For considering the risk and cost counter claim, the Tribunal enumerated three
    components.
52. The first of such components was the total contract value, which was assessed at
    Rs.1,96,49,202/-, to which there is no demur from either side.
53. The second component was the work actually done by the claimant and paid for. In
    the initial award, the said amount was computed by the Tribunal to be
    Rs.1,41,39,493/-. Subsequently, on the application of the claimant, the second
    component was enhanced to Rs.1,74,05,144/-, to which the respondent did not
    have any objection.
54. Notably, the third component, that is, the unfinished work of the claimant, for which
    he was obviously not paid, was retained by the Tribunal at Rs.55,09,759/-, as
    calculated in the original award.


55. However, such approach is perverse, since, even by a logical deduction on
    application of rudimentary arithmetic, the third component ought to have
    automatically decreased upon the second component being increased, since the
    third component was the difference between the first and the second.
56. If the first component, that is the total contract value, is taken to be of value „A‟ and
    the second component, that is, work done by the claimant as "B‟, then the third
    component, that is, the unfinished work of the claimant is of value "C‟, which is
    equal to the figure: (A - B).
57. The value of „A‟ was an agreed and fixed amount and remained the same as the
    original award even after correction. However, "B‟ was increased from
    Rs.1,41,39,493/- to Rs.1,74,05,144/- after the original award was corrected under
    Section 33 at the behest of the claimant.
58. By basic mathematics, if figure C = (A - B), and "B‟ is increased, "C‟ automatically
    comes down.
59. As per the original award, C = (1,96,49,202 - 1,41,39,493) = Rs.55,09,759.
60. However, after correction of the award, „B‟ was changed to 1,74,05,144.
    Accordingly, C should have been equal to (1,96,49,202 - 1,74,05,144) = Rs.
    22,44,058.



                                        Page 27 of 39
                                                                                            2025:CHC-OS:200-DB
    61. For arriving at such figure, no further correction on merits or reappreciation of any
        legal or factual facet of the matter was 16 necessary. The said change was a logical
        and inevitable corollary of the correction effected to component „B‟ by the Tribunal.
    62. The Tribunal had proceeded to calculate the risk and cost compensation payable to
        the respondent by deducting the figure „C‟ from the total amount paid to the
        subsequent contractor that is Rs.73,09,922/-.
    63. Accordingly, the amount payable to the respondent on such count was calculated to
        be Rs.18,00,163/- = (73,09,922 - 55,09,759).
    64. However, since the figure „C‟ would have to be reduced upon the correction from
        Rs.55,09,759/- to Rs.22,44,058/-, the automatic effect of the correction would be
        that the amount payable under the head of "Risk and Cost Liability" by the claimant
        to the respondent would become Rs.(73,09,922 - 22,44,058) = Rs.50,65,864/-.
    65. Accordingly, even if the Tribunal merely allowed the Section 33 application of the
        claimant, as a logical result thereof, the risk and cost amount payable to the
        respondent would increase to Rs.50,65,864/- even without any further application
        by the respondent being necessitated."


56. The observations of the Hon'ble Single Judge are impeccably reasoned and

   unexceptionable. There is no room for interference by us and we therefore

   approve the same.

57. Mr. Datta had argued that although the Hon'ble Single Judge had power

   to correct the award under Section 34 of the said Act of 1996 but occasion

   to exercise such power could have arisen only if Haldia was entitled to any

   compensation. His submission was that the learned Arbitrator should not

   have awarded any compensation to Haldia at all. However, such argument

   lacks appeal inasmuch as the same is premised on the misconceived notion

   that the contracted work had been completed by Konarak. At the cost of

   repetition we may mention that the discussion in the preceding section of

   this judgment has made it amply clear that the contracted work was not

   completed by Konarak. In fact such position stands admitted by Konarak

   itself in its letters as already discussed hereinabove. The notings in the 4th

                                          Page 28 of 39
                                                                              2025:CHC-OS:200-DB
   and Final Bill which Konarak perceived to be a completion certificate have

   been found not to be a completion certificate issued upon completion of the

   contractual work. In such view of the matter Konarak's argument that no

   compensation could be paid to Haldia at all cannot be sustained.

58. While on the subject another argument of Mr. Datta needs to be dealt

   with. It was submitted by Mr. Datta that the contract was never terminated

   and no notice was given invoking Clause 3(c) of the Conditions of Contract.

   Such argument does not impress us. Firstly, Clause 3(c) of the Conditions of

   Contract does not require any express notice to be given by the employer (in

   this case Haldia) and secondly, even if such a meaning is ascribed to the

   said the clause, the letters dated January 05, 2011 (page 232 of the stay

   application), February 09, 2011 (page 233 of the stay application) referred to

   by Mr. Dey in his arguments and the letter dated March 01, 2011 all of

   which have been referred to by the learned Arbitrator in paragraphs 34 (m)

   and (r) of the award fulfil the same. The letters dated January 05, 2011 and

   February 09, 2011 clearly indicate that Konarak was put on notice that if it

   failed to complete the full contractual work, the "balance work" would be got

   done through some other agency.

59. Furthermore since Haldia ultimately paid all the amounts due to Konarak

   in respect of the work executed by Konarak while passing the 4th and final

   bill what remained with Haldia was only the security deposit that it had

   deducted from the bills of Konarak. The intention was therefore clear that

   Haldia intended to impose Clause 3(c) of the Conditions of Contract. This

   fact has been aptly captured by the learned Arbitrator in paragraph 36(d) of



                                    Page 29 of 39
                                                                              2025:CHC-OS:200-DB
   the award. The Hon'ble Single Judge has assigned his own reasons in

   support of such conclusion and has confirmed such finding.

60. Mr. Datta was critical of the observations by the Hon'ble Single Judge in

   paragraph 28 of the order impugned to the effect that "Secondly, completion

   certificates were issued for different phases of the work and payments were

   also made accordingly by the respondent. Thus, the respondent is estopped

   from arguing that the entire work was not done, only in which case the

   security deposit could have been forfeited". He asserted that there was an

   inherent contradiction in the observation and contended that if the entire

   work had been completed then the question of even adjusting security

   deposit and allowing any payment on the basis of risk and cost principle did

   not arise. Even if we agree with Mr. Datta that there is a seemingly apparent

   paradox in the observation of the Hon'ble Single Judge, that by itself would

   not nullify the conclusion reached.

61. Many a times and oft a judgement is a product of a dialectical process that

   involves thesis, antithesis and synthesis and the judgment ultimately

   shapes up upon a vigorous churning of conflicting ideas and arguments.

   Several reasons are assigned to prop a particular conclusion. A flaw in one

   of the several reasons given in support of a conclusion would not invalidate

   the conclusion. Upon having found that the ultimate conclusion is correct

   we need not be detained by the argument of Mr. Datta any further.

62. Mr. Datta had also argued that there was no basis for the observation that

   "substantial" work had been done by Konarak when in fact Konarak had

   completed the work. We need not devote any more time to this argument as

   we have already discussed in detail in the foregoing portion of this judgment

                                    Page 30 of 39
                                                                               2025:CHC-OS:200-DB
   that Konarak had not completed the contractual work in full. Indeed

   Konarak had done substantial work which would be reflected by the

   calculations as regards the value of work done and left unfinished by it.

   Such exercise has already been undertaken by the leaned Arbitrator and we

   have alluded to it in the previous section of this discussion.

63. Another argument advanced on behalf of Konarak was that as the learned

   Arbitrator had found that Haldia had not imposed any liquidated damages

   upon Konarak therefore it could not be said that Konarak had not completed

   the contracted work in full. The argument though attractive at face lacks

   sheen. Clauses 3(a) to 3(c) of the Conditions of Contract lists three ways in

   which Haldia can make good the losses that it suffered due to the failure of

   Konarak to complete its contractual obligation. It has invoked one of it. None

   of the said clauses make imposition of penalty/liquidated damages

   mandatory as rightly held by the Hon'ble Single Judge in paragraphs 37 and

   38 of the order impugned. We agree with the same.

64. There was yet another argument made by Mr. Datta that the work

   awarded to the new contractor was different from the work awarded to

   Konarak. He sought to differentiate between the two works by relying on the

   scope of work mentioned in the work order issued to Konarak and in the

   work order issued to the new contractor. The said issue has been

   appropriately dealt with by the arbitrator in paragraph 36 (e) of the award

   where the learned Arbitrator has found that although the contract awarded

   to the new contractor was for a sum of Rs.73,09,922/- it included extra

   works also which accounted for a sum of Rs.11,74,753.44p. The learned

   Arbitrator has then arrived at the amount that was payable/paid by Haldia

                                     Page 31 of 39
                                                                             2025:CHC-OS:200-DB
   to the new contractor for completing the work left unfinished by Konarak.

   While on this we agree with the Hon'ble Single Judge that the work of

   maintenance (which was indeed within the scope of work of Konarak)

   included the work of repair also. We also find substance in the submissions

   of Mr. Dey that during the cross-examination of Haldia's witnesses done on

   behalf of Konarak although questions were put as regards the quantity of

   works and additional works on behalf of Konarak to the said witness no

   suggestion was given on behalf of Konarak that the second contract was not

   pertaining to any unfinished work left by Konarak or that the entire work

   was completed by Konarak. Not giving such suggestion would certainly go

   against Konarak. (See: A.E.G. Carapiet vs. A.Y. Derderian5)

65. Issue No. (ii) thus also stands answered positively.

66. This takes us to the third issue.

   Issue No. (iii) Whether the finding of the learned Arbitrator that
   Konarak was entitled to refund of security deposit which has been
   affirmed by the order impugned is correct? This issue subsumes the
   issue as to whether Konarak's claim of refund of security deposit was
   barred by limitation.

67. Mr. Dey was vociferous on the point that as the claim for refund of

   security deposit was barred by limitation therefore the same could not have

   been entertained by the arbitral tribunal and affirmed by the Hon'ble Single

   Judge.

68. The learned Arbitrator has dealt with the aspect of Limitation in great

   detail. Paragraph 34 of the award is substantially devoted to it, though it



   5 AIR 1961 Cal 359


                                    Page 32 of 39
                                                                                         2025:CHC-OS:200-DB
covers certain other aspects as well. Some of the relevant snippets of the

learned Arbitrator's deliberation on the aspect of limitation may be noted:-

    "34. (m) In this connection, from the Order Book, I find that the respondent
    alongwith their Officers in Charge of the affairs made site inspection relating to the
    tender work ............ In their Minutes dated 24th December, 2009 (Exhibit R/5), 2nd
    March, 2010 (Exhibit R/6), 22nd March, 2010 (Exhibit R/7), 5th April, 2010 (Exhibit
    R/8), 30th April, 2010 (Exhibit R/9), 1st June, 2010 (Exhibit R/13), 11th June, 2010
    (Exhibit R/14), 7th July, 2010 (Exhibit R/15), 19th July, 2010 (Exhibit R/16), 27th
    July, 2010 (Exhibit R/17) and 28th August, 2010 (Exhibit R/22). .......... Another
    joint inspection in presence of the claimant was made on 28 th August, 2010 (Exhibit
    R/22) wherein the claimant was directed as follows:-

    "The contractor brought the kind knowledge of the CEO that the approach to the
    bridge has to be widen from the normal width of road. .........

    ......the agency has ....... to complete the pending rectification work .... after rainy
    season so that total completion of ...... work can be .... by 31st October, 2010..."

    Therefore, it is on record that to the knowledge of both the parties, the tenure of the
    contract was alive on the date of joint inspection upto 31 st October, 2010.

    (n) From Exhibit R/28, .... a letter dated 13th December, 2010 from the Executive
    Engineer ...... to the claimant, it will appear that though the time was running out a
    lot of work was still pending.......... unwillingness to complete the work was viewed
    seriously ............

    (o) In the .... correspondence dated 5th January, 2011 (Exhibit R/31) addressed to
    the claimant, the following directions were given:-

      "You are directed to start the work within 7 days of receipt of this letter, otherwise
    HDA will ...... get the balance work done through other agency at your risk and
    cost..... and any claim ...... from your end will not be entertained."

    (p) Such warning was not, ...... peremptory as in the ..... correspondence bearing
    No. 2666/HAD/IX-C/201 (Part I), dated 9th February, 2011 (Exhibit R/31/1) from
    the Chief Executive Officer, ........ to the claimant reflected the intention of the
    respondent regarding the tender work will be reflected as regards continuation of
    such ....... From the contents of this letter.......respondent has taken a decision ....
    to terminate the Work Order in terms of Clause 29 and Clause 16 of the General
    Conditions & Specifications and served the letter in the form of a notice to the

                                       Page 33 of 39
                                                                                    2025:CHC-OS:200-DB
claimant to start the balance work ..... within 7(seven) days from the date of issue
of letter, otherwise the contract will be terminated and balance work will be
executed by deputing other agency ...... This letter also indicates the intention of the
respondent to extend the tenure of the contract.

(q) From their ... correspondence ....vide Memo No. 2862/HAD/IX-C/201(Part 1),
dated 1st March, 2011 (Exhibit R/31/2), the last notice was served upon the
claimant to complete the work in question for 6.10 Kms construction of road.
............

(r) Therefore, in terms of above Exhibit R/31/2 due notice was served by the respondent dated 1st March, 2011 giving 7 (seven) days‟ time ... to show cause why the contract will not be terminated ......... From such document, clear intention of the respondent is explicit ......... that they allowed the claimant to continue the work upto 1st March, 2011 and thereafter finally decided to terminate the contract irrespective of the 180 days‟ time limit mentioned in the work order ..........

(s) ................ In the present case, under Clause 5, the claimant submitted written request for extension of time twice, but action taken by the Executive Engineer ........ upon consideration of such prayer has never been conveyed to the claimant ..... from the perusal of the Measurement Book, .... and recorded in the Minutes Book on periodical inspection of the site, ......... it appears that the respondent authorities kept the issue of termination of Work Order pending even after expiry of the time fixed by them as well as prayer for extension twice by the claimant.........

(t) Then it is to be decided how this Tribunal will come to a conclusion where both the parties did not strictly follow the terms of the contract in respect of the tender work ......... In such case, the intention of the parties reflecting from their conduct and action taken should be the guiding principle for the Arbitral Tribunal to arrive at a just and reasonable conclusion regarding time of completion of the present work and tenure of the Work Order beyond 180 days. ...........

(u) Therefore, ........, I hold that in the given facts and circumstances of this case, the tenure of the work order was extended upto 1st March, 2011.

(v) In the meantime the claimant wrote a letter dated 7 th March, 2011 as in Exhibit R/30 intimating her inability to continue the work in response to three letters mentioned above received by her from the respondent. ............. This letter is coming from the custody of the respondent as annexure at Page 117 of their SODCC. Therefore, the claimant expressly conveyed that she was not in a position

2025:CHC-OS:200-DB to execute any further work at the site and as such requested the respondent to terminate the contract but not to impose any penalty as she had no wilful negligence to complete the work due to public agitation and prayed for balance amount of payment for the work done by her. The consequent action taken by the Chief Executive Officer of the respondent on receipt of such intimation dated 7 th March, 2011 is not forthcoming though in the subsequent letter dated 29th march, 2011 (Exhibit R/24) the claimant reiterated her earlier grievance and ultimately requested the respondent authorities to terminate the contract honourably and arrange to pay the final bill for the "completed work done" and the Security Deposit money lying with the respondent.

(w) Therefore, the inevitable conclusion from such correspondence will reaffirm that the tenure of the contract expired on the 1st of March, 2011.

(x) If that be so, the period of limitation for the defect liability period of 3 (three) years will commence from 2nd March, 2011 i.e. upto 1st March, 2014. The period of limitation of 3 (three) years in the instant case will be upto 2 nd March, 2017. The present claimant resorted to arbitration admittedly on13th December, 2016 (Exhibit C/14) following the demand letter dated 1 st July, 2016 (Exhibit C/16) from the end of the claimant to the respondent seeking release of Security Deposit in question."

69. It is therefore clear that the learned Arbitrator has found that by conduct

the parties extended the time for completion of the work of construction till

March 01, 2011. Adding the defect liability period of three years to the date

of completion of the construction work i.e. to March 01, 2011, the learned

Arbitrator has reached the conclusion that the contractual period of the

entire work (i.e. work of construction as well as maintenance during the

defect liability period) ended on March 01, 2014. In terms of the award the

period of limitation would begin to run after March 01, 2014 and not prior to

it. We may now test the said conclusion.

70. While the limit of time that may have been fixed by a contract governing

the parties may be for the benefit of both the parties, in the case at hand

since it is Haldia's case that Konarak had failed to complete the contractual

2025:CHC-OS:200-DB work within the stipulated time and therefore Haldia is entitled to forfeit

Konarak's security deposit, we would analyse the case from the angle that

time was made the essence for the benefit of Haldia. This is all the more so

because Konarak has not made any claim for loss of profit or escalations

costs or cost overruns which are usual claims in cases where time is the

essence of contract and the employer fails the time-schedule.

71. A reading of the arbitral award, especially paragraph 34 would put it

beyond the pale of doubt that both the parties have exchanged

correspondences which manifest a clear intent to extend time. Since Haldia

itself has written letters asking Konarak to complete the work beyond the

time mentioned in the contract it cannot be gainsaid that Haldia extended

the time initially agreed for performance of the contracted work. Section 63

of the Indian Contract Act, 1872 clearly provides for such a situation. The

same reads thus:-

"63. Every promisee may dispense with or remit, wholly or in part, the performance of the promisee made to him, or may extend the time for such performance, or may accept instead of it any satisfaction which he thinks fit."

72. As stated earlier the learned Arbitrator has in paragraph 34 of the award

analysed the evidence on record and found that the parties intended to

extend the time for completion of the contract. The law of the land provides

for the same therefore there can be no hitch in accepting the conclusion that

the contract stood extended till March 01, 2011 as found by the learned

Arbitrator. The next question would be as to the effect of such extension on

the claim for security deposit. Clause (p) of the Work Order issued in favour

2025:CHC-OS:200-DB of Konarak specifies the manner in which security deposit would be

released. The same reads thus:-

"p) The bidder shall be required to properly-maintain the road including all its components for a period of 3 years from the date of completion and handing over to HDA in proper format. A Security Deposit of 10% shall be deducted from each RA bill (upto 10% in total). 2% EMD may be adjusted with the Security Deposit. The release of S.D. would be subject to quality and maintenance of the road and its components satisfactorily for entire period of 3 years.

The schedule for release would be as below:

i) Completion of 1st year from the date of completion - 30% of SD

ii) Completion of 2nd year from the date of completion - 30% of SD

iii) Completion of 3rd year from the date of completion - 40% of SD"

73. A meaningful reading of the aforementioned clause would reveal that

Konarak's right to get security deposit would mature only after completion of

the entire awarded work and not before that. The learned Arbitrator has

therefore rightly concluded that limitation would begin to run after expiry of

three years from the date of completion of the construction work. Mr. Dey

was very vocal on the point that limitation began to run from the date

Konarak firstly demanded refund of the security deposit i.e. from the date of

Konarak's letter dated March 29, 2011 (Exhibit R-29 at page 236 of the stay

application). Such submission does not impress us. It is well known that

limitation is a prescription for extinguishment of remedy for enforcement of

a right and not of extinguishment of the right itself. For the remedy to a

right to be barred by limitation, the right needs to be born first. The letter

dated March 29, 2011 relied on by Mr. Dey precedes the date when the right

of Konarak as regards release of its security deposit was born. In such view

2025:CHC-OS:200-DB of the matter, the said letter dwindles to insignificance as regards the

defence of limitation.

74. Once it is held that the claim was not barred by limitation, the only other

issue that remains to be tested was as to whether Konarak was entitled to

refund of security deposit. The discussion made while deciding Issue No. (ii)

hereinabove would reveal that it has been found by the learned Arbitrator as

well as the Hon'ble Single Judge that Haldia had invoked Clause 3(c) of the

conditions of contract. In fact it was submitted by Mr. Dey as well that the

letters dated January 5, 2011 and February 9, 2011, issued by Haldia gave

a tacit indication that in case Konarak failed to execute the unfinished work

within the time mentioned in the said notices, such work would be got done

through a third party. According to Mr. Dey the same was in fact an

invocation of Clause 3(c). Mr. Dey sought to insinuate that Clause 3(c) also

contemplated forfeiture of security deposit. A reading of Clause 3(c)

extracted hereinabove, however, does not give such impression. Clause 3(c),

read meaningfully strongly suggests about adjustment of security deposit,

which would mean refund of any excess security deposit that may be lying

due with Haldia upon the adjustments being fully made. In such view of the

matter the finding of the learned Arbitrator that the remainder of the

security deposit in the hands of Haldia after adjustment, should be refunded

does not call for any interference. The Hon'ble Single Judge has accepted the

same and as such the finding of the Hon'ble Single Judge is also beyond

question. Issue No. (iii) too therefore calls for a favourable answer and we

answer the same accordingly.

2025:CHC-OS:200-DB

75. As regards the judgment in the case of Associate Builders (supra) the

same is an authority for the proposition that an award can be interfered

with if the same is perverse, meaning that it is either based on no evidence

or on irrelevant material or if it has been passed ignoring vital evidence. We

have found that the award does not suffer from any of the aforesaid

infirmities. The only mistake which was there in the award has already been

corrected by the Hon'ble Single Judge and as such nothing further needs to

be done in the present appeal.

76. As regards the judgment in the case of Dyna Technologies Private

Limited (supra) the same instructs Courts to be cautious of their

boundaries under Section 34 of the said Act of 1996 and to respect the

finality of the award and party autonomy. The said judgment mandates that

the view taken by the arbitral tribunal should be respected even if the

reasoning provided in the award is implied unless such award portrays

perversity unpardonable under Section 34 of the said Act of 1996.

77. To conclude, we do not find any reason to interfere with the order dated

January 17, 2025 impugned before us. Both the appeals being APOT 76 of

2025 along with the connected application being GA-COM 1 of 2025 and

APOT 135 of 2025 stand dismissed. No costs.

78. Urgent photostat certified copy of this judgment, if applied for, be supplied

to the parties upon compliance of all formalities.

I agree.

   (Arijit Banerjee, J.)                                (Om Narayan Rai, J.)


 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 

LatestLaws Partner Event : IJJ

 
 
Latestlaws Newsletter